+ All Categories
Home > Documents > Closing a Project in EPM 2010 - University Services · Closing a Project in EPM 2010 ... 1. Open MS...

Closing a Project in EPM 2010 - University Services · Closing a Project in EPM 2010 ... 1. Open MS...

Date post: 05-Jun-2018
Category:
Upload: trinhminh
View: 219 times
Download: 0 times
Share this document with a friend
2
© 2010 Regents of the University of Minnesota. All rights reserved. Closing a Project in EPM 2010 The project close process brings the project to an official completion. The project needs to be closed out in EPM 2010 after it is completed and no further work will be performed by team members. Before closing out a project in EPM 2010, notify team members that they must submit all of their project time updates in EPM. For more information, refer to the Tracking Time in EPM 2010 Project Web App Quick Reference. BECOMING THE STATUS MANAGER FOR THE PROJECT PLAN These steps only need to be done if you are not the project manager set-up originally in MS Project Professional. If you are unsure, follow the steps to verify that you are listed as the status manager for all tasks in the plan. 1. Open MS Project Professional 2010 on your desktop and open the project plan. 2. From the Task menu, open the Gantt Chart view. 3. Expand the summary level tasks by clicking on the + (plus) sign. 4. In the Status Manager column, change the Status Manager from the current status manager to yourself for all tasks (not just the summary level tasks). 5. Save the project and publish it to the server. 6. Close and check-in the project. ACCEPTING PROJECT UPDATES IN PWA 1. Open IE and sign in to PWA (us.project.umn.edu\pwa). 2. Under Projects on the left-hand menu, select Approval Center. 3. Select the check box next to any project updates or click the drop- down arrow on the selection column to accept all updates. 4. Click the Accept button to accept the updates and click OK. 5. Exit PWA. CLOSING OUT THE PROJECT PLAN IN MS PROJECT PROFESSIONAL 1. Sign in to Microsoft Project 2010 and open the project. 2. Verify that each task in project has zero remaining hours on all resource assignments and is 100% Complete. Refer to Tips for Closing Tasks for more information. 3. Verify your project has an Actual Finish Date and that your project is marked 100% complete at Row Zero (don't change % complete or end dates directly! This might change the actual hours which will give you errors when saving and publishing).
Transcript

© 2010 Regents of the University of Minnesota. All rights reserved.

Closing a Project in EPM 2010 The project close process brings the project to an official completion. The project needs to be closed out in EPM 2010 after it is completed and no further work will be performed by team members. Before closing out a project in EPM 2010, notify team members that they must submit all of their project time updates in EPM. For more information, refer to the Tracking Time in EPM 2010 Project Web App Quick Reference.

BECOMING THE STATUS MANAGER FOR THE PROJECT PLAN

These steps only need to be done if you are not the project manager set-up originally in MS Project Professional. If you are unsure, follow the steps to verify that you are listed as the status manager for all tasks in the plan.

1. Open MS Project Professional 2010 on your desktop and open the project plan.

2. From the Task menu, open the Gantt Chart view.

3. Expand the summary level tasks by clicking on the + (plus) sign.

4. In the Status Manager column, change the Status Manager from the current status manager to yourself for all tasks (not just the summary level tasks).

5. Save the project and publish it to the server.

6. Close and check-in the project.

ACCEPTING PROJECT UPDATES IN PWA

1. Open IE and sign in to PWA (us.project.umn.edu\pwa).

2. Under Projects on the left-hand menu, select Approval Center.

3. Select the check box next to any project updates or click the drop-

down arrow on the selection column to accept all updates.

4. Click the Accept button to accept the updates and click OK.

5. Exit PWA.

CLOSING OUT THE PROJECT PLAN IN MS PROJECT PROFESSIONAL

1. Sign in to Microsoft Project 2010 and open the project.

2. Verify that each task in project has zero remaining hours on all resource assignments and is 100% Complete. Refer to Tips for Closing Tasks for more information.

3. Verify your project has an Actual Finish Date and that your project

is marked 100% complete at Row Zero (don't change % complete or end dates directly! This might change the actual hours which will give you errors when saving and publishing).

© 2010 Regents of the University of Minnesota. All rights reserved.

4. Remove all tasks from resource time sheets to prevent any additional time from being recorded to this project in the future. Go to the Gantt Chart view and verify that all tasks have been expanded. In the Publish Y/N column, change all tasks to No.

5. Go to Project Project Information and confirm that all outline

codes are filled in completely, specifically the following:

a. Update the Project State outline code to ‘4 – Completed’; b. Update the Overall Health outline code, if necessary. c. Update the Scope outline code, if necessary. d. Update all the Checklist outline codes; e. Update all other outline codes that are required or have

been left blank.

6. Save the project and publish it to the server.

7. Close and check-in the project.

RENAMING A CLOSED PROJECT

Once the project is closed, it is recommended that it be renamed so the project name displays at the bottom of any project list. The naming convention for completed projects is to add a z_ before the project name (e.g., z_project name).

1. Open Project Professional and select Open.

2. Locate the completed project file name and click on it twice to change the file name to edit mode.

3. Type in the new name for the completed project (e.g., z_project name).

4. Click OK at the rename job successful message.

5. Click the Open button to open the project.

6. Save the project and publish it to the server.

7. Close and check-in the project.

TIPS FOR CLOSING TASKS

Closing out Fixed Units and Fixed Work Tasks

1. Select the combination view with the Task Form on the bottom; 2. In the top pane, select the task to be closed out; 3. In the bottom pane, right click and select Work; 4. Change resource remaining work hours to zero (do not change the

% Complete directly).

Closing out Fixed Duration Tasks

1. Select the task to be closed out; 2. Change Fixed Duration to either Fixed Work or Fixed Units; 3. Change resource remaining work hours to zero and % Complete

will calculate to 100%.

Closing out Milestones

1. Select the milestone task; 2. Change % Complete to 100 (Project milestone tasks are the only

tasks where it is acceptable to change % Complete).


Recommended