+ All Categories
Home > Documents > Colfax Corridor Connections - January 2016 public … consistent with economic development ......

Colfax Corridor Connections - January 2016 public … consistent with economic development ......

Date post: 30-Mar-2018
Category:
Upload: hakhuong
View: 217 times
Download: 2 times
Share this document with a friend
60
Public Meetings January 2016
Transcript

Public Meetings January 2016

Agenda Welcome and Introductions

Project update Process

Project definition

Key environmental findings

Key traffic analysis findings

Related activities Bike/pedestrian projects

15L Short-Term Improvements

Passenger stop visual preference survey

Q&A

Open House

Moving People: Proposed Bus Rapid Transit (BRT)

3

What is the purpose of this project?

To identify and provide a package of multi-modal transportation improvements in the East Colfax corridor that:

Meet current and future person-trip demand

Improve mobility, connectivity, safety, and accessibility

Help to mitigate congestion

Encourage a shift of auto trips to alternative modes

Interact seamlessly, efficiently, and safely with other transportation corridors, systems, and modes

Are consistent with economic development components of federal sustainability & livability plans and principles

Key Challenge:

Adding person-trip capacity to East Colfax without adding roadway lanes or taking property

5

Maximum number of cars on a street

Distribution of people served by these cars

The same number of people on a bus

The same number of people on a ped-bike friendly street

Previous Studies and Plans

6

CCD Strategic Transportation Plan, 2008 Identified 20-30% increased person trip demand in

corridor by 2025

CCD Colfax Streetcar Feasibility Study, 2010 Identified four transit routes in study area, with current

use ~30,000 riders per day

Determined all four routes at capacity during peak

Routes 15 and 15L at capacity throughout day, with ~22,000 riders per day

Colfax Corridor Connections Study Recommendation: Bus Rapid Transit in exclusive lanes

during peak periods

7

Stakeholders and Public Involvement

8

Project Stakeholders & Team Lead Agency

o City and County of Denver

Partner/Coordinating Agencies

o City of Aurora

o Regional Transportation District (RTD)

o Denver Regional Council of Governments (DRCOG)

o Colorado Department of Transportation (CDOT)

o Federal Transit Administration (FTA)

Stakeholders

o Regulatory Agencies

o Auraria and Anschutz Campuses

o Registered neighborhood organizations

o Businesses and property owners

o Community leaders

o Residents and travelers along the corridor

Consultant Team: Steer Davies Gleave (lead)

9

Public Involvement Activities

Technical Working Group Meetings

Community Task Force Meetings

Four sets of Public Meetings in Denver & Aurora

Printed Materials

o Available at 100+ local businesses on Colfax

o Info sent to a network of nearly 150 organizations

o RTD ridership survey/meeting info available on 15/15L buses

Digital Resources

o Website, Facebook and Twitter sites

o Email database of nearly 1,000 stakeholders

10

Initial Feedback on BRT Concept

City of Aurora:

o Supportive of the BRT project

o Agencies are working together on additional technical analysis

Technical Working Group:

o Supportive of the BRT recommendation

Community Leadership Group:

o Supportive of the BRT recommendation

RTD:

o Supportive of Enhancing Transit on Colfax; Fiscally Constrained with FasTracks, which is their current priority

11

Public Meeting Feedback:

12

Several hundred comments submitted o Majority have been supportive of BRT concept Most cited benefits of BRT were: o Faster travel times

o Transit schedule reliability

o Increased corridor capacity

o Economic development potential

Most cited areas where more information was desired were: o Traffic operations

o Interaction of bicycle/pedestrian facilities

o Economic activity

o Social/community effects

13

• More detailed project definition • Continued discussion and review on

specifics of project with partners • Additional ridership forecasting • Additional in-depth traffic analysis

• Initiation of environmental clearance

What’s Happened Since the Last Public Meetings?

How Did We Get Here?

What’s the study area for this project?

10 miles

Why is This Project Needed?

(2010 to 2035) (2010 to 2035)

*ridership includes 10, 20, and 15 & 15L (2010 to 2035) (2010 to 2035)

* *

Why is This Project Needed?

Mode/Technology Options Considered

Roadway Expansion Enhanced Bus Bus Rapid Transit

Light Rail Modern Streetcar

Automated Guideway Transit Monorail MagLev

Commuter Rail

Heavy Rail (Metro)

Gondola Personal Rapid Transit

Route/Alignment Options

• Greatest number of activity centers

• Fewest on-street parking spaces • Shortest alignment • Fewest roadway intersections • Most consistent with locally

adopted plans • Blueprint Denver ‘area of

change’ • Urban character is primarily

commercial & mixed-use • Economic development

opportunities

Colfax Avenue - Route Recommended to Advance

13th/14th

Colfax

17th

20th/

Montview

Enhanced Bus

Bus Rapid Transit

Modern Streetcar

Light Rail

* Other transportation improvements (bike, pedestrian, etc.) are components of all options

End of Screen 2 - Results

21

Locally Preferred Alternative: Bus Rapid Transit in Exclusive Lanes During Peak Hours

23

• Most stops are at existing 15L stops • 2 stops proposed at different locations

• Glencoe to Eudora • Tamarac to Uinta

Project definition

Project definition

24

Exclusive lanes (replacing general purpose lanes) during peak periods between Broadway (and the Civic Center Station) in downtown Denver and Syracuse Street in east Denver, a distance of 4.7 miles.

Exclusive lanes would continue to allow right-turns for autos and would also allow crossing for parking adjacent to the lanes.

25

Project definition

Extent of improved service frequencies and stop enhancements: I-25 to I-225

26

Project definition

Extent of peak-period exclusive lanes: Broadway to Syracuse

Project definition

27

Branded service with low-floor articulated buses the 10-mile length of the corridor.

Project definition

28

Five-minute peak-period headways the entire length of the 10-mile corridor.

Project definition

29

Twenty enhanced passenger stations throughout the corridor with real-time passenger information, off-vehicle ticketing, and other passenger amenities.

Stops will consist of curb extensions where appropriate (primarily in current bus stop location with minimal parking loss) and on-sidewalk curbside enhancements where curb extensions are not appropriate.

BUS RAPID TRANSIT

BUS A new type of

RAPID It should be

Example BRT Before/After Concept 35

TRANSIT Focused on

Bus Rapid Transit: How It Addresses Corridor Needs

More than doubles ridership of current bus service…

Up to 50,000 Daily Riders

2035 BRT

Bus Rapid Transit: How It Addresses Corridor Needs

Increases person-trips potential by 25%…

40

Bus Rapid Transit: How It Addresses Corridor Needs

End-to-end transit travel time change

Already heavily used urban transportation corridor Minimal to no impacts (and many benefits) in most

federal resource areas Categorical exclusion document being prepared

under guidance of Federal Transit Administration Anticipated completion spring 2016

Key environmental issues and findings

Bus Rapid Transit: Traffic Takeaways

Congestion occurs today and will get worse in the future with or without the project

Traffic diversion occurs today and will get worse in the future with or without the project

Some shift from autos to transit due to improved travel times and convenience

Appropriate operational improvements at hot spots as necessary

BRT increases person-trip capacity by up to 25%

Bus Rapid Transit: Traffic Methodology

Traffic Analysis used two separate types of models FOCUS travel demand model for traffic growth and

ridership forecasting VISSIM / Synchro capacity analysis models for more

specific intersection analysis

VISSIM evaluated specific intersection operations along Colfax

Synchro evaluated select intersections adjacent to Colfax (such as 13th, 14th, etc.)

Analysis conducted with and without the project

Bus Rapid Transit: Traffic Findings

Many streets see only a minor increase in delay/congestion Regardless of project, some intersection hot spots become

apparent For corridor hot spots, we have identified potential operational

improvements: Signal optimization New and/or lengthened turn lanes/pockets Minimal capacity improvements through re-striping or minor curb/gutter

relocation (all within ROW)

Currently developing package of operational improvements using Synchro model to see which are most effective to meet the goals of the project

Bike/Pedestrian Access

Bike/Ped access has been a key component of the BRT project from the beginning.

We are identifying short term opportunities for pedestrian and bicycle improvements that support the larger Colfax bus rapid transit (BRT) project

Short-term opportunity to improve transit on Colfax while still working toward long-term goal of implementing BRT

15L Improvements

Stop/Shelter Visual Preference Survey

How BRT Meets Project Goals:

Meets person trip demand

Better serves existing users and attract new users

Conforms with livability principles and promotes economic development

New transportation capacity without new ROW

Accommodates intra-corridor trips

Improves connectivity and mobility options

Affordable and fiscally sustainable

Where Do We Go From Here?

Spring 2016: Bicycle/pedestrian improvement

coordination Complete detailed traffic analysis Complete details on short-term 15L

enhancements Complete environmental clearance

Questions?


Recommended