COMITÉ PANAMEÑO DE PRESAS FORO: SEGURIDAD DE PRESAS 17 DE NOVIEMBRE DE 2012 Hans Schwarzweller
Transcript
Page 1: COMITÉ PANAMEÑO DE PRESAS

COMITÉ PANAMEÑO DE PRESAS

FORO: SEGURIDAD DE PRESAS

17 DE NOVIEMBRE DE 2012

Hans Schwarzweller

Page 2: COMITÉ PANAMEÑO DE PRESAS

Center Hill Dam Foundation Remediation BAUER Spezialtiefbau – Bauer Foundation Corp.

Page 3: COMITÉ PANAMEÑO DE PRESAS

3

Center Hill Dam Foundation Remediation Project Location

Page 4: COMITÉ PANAMEÑO DE PRESAS

4

Wolf Creek Dam Foundation Remediation Project Location

Wolf Creek Dam

Center Hill Dam

Page 5: COMITÉ PANAMEÑO DE PRESAS

5

Center Hill Dam Foundation Remediation Project Overview

- Concrete Dam approx. 420m long- Main Dam is 69m high above stream bed- Embankment Dam is approx. 300 m long- Diff. U/S to D/S Water Level approx. 50m

Page 6: COMITÉ PANAMEÑO DE PRESAS

6

Center Hill Dam Foundation Remediation The basic problem

Page 7: COMITÉ PANAMEÑO DE PRESAS

7

Center Hill Dam Foundation Remediation The basic problem

1959 2007

Page 8: COMITÉ PANAMEÑO DE PRESAS

8

Center Hill Dam Foundation Remediation The basic problem

Page 9: COMITÉ PANAMEÑO DE PRESAS

9

Center Hill Dam Foundation Remediation Sink holes

Page 10: COMITÉ PANAMEÑO DE PRESAS

10

Center Hill Dam Foundation Remediation Sink holes

Page 11: COMITÉ PANAMEÑO DE PRESAS

11

Center Hill Dam Foundation Remediation Sink holes

Page 12: COMITÉ PANAMEÑO DE PRESAS

12

Center Hill Dam Foundation Remediation Sink holes / Existing Condition

Sink hole

Page 13: COMITÉ PANAMEÑO DE PRESAS

13

Center Hill Dam Foundation Remediation Cut off trench works

Page 14: COMITÉ PANAMEÑO DE PRESAS

14

Center Hill Dam Foundation Remediation Solution

Barrier Wall

Encasement Wall

Page 15: COMITÉ PANAMEÑO DE PRESAS

15

Center Hill Dam Foundation Remediation Geology

1000Psi ~ 7Mpa

Page 16: COMITÉ PANAMEÑO DE PRESAS

USA - Center Hill Dam Foundation Remediation Geology

16

Page 17: COMITÉ PANAMEÑO DE PRESAS

USA - Center Hill Dam Foundation Remediation Geology

17

Formation Rock Type Approximate Thickness Character

Unconfined Compressive

Strength

Catheys Limestone 56 - 116 ftfinely crystalline shaley Limestone bands medium to thin bedded hard to moderately hard

108 MPa

Cannon Limestone 110 - 120 ftfinely crystalline shaley Limestone bands massive bedded hard to moderately hard

36 – 220 MPa

Hermitage 4 beds of Shale and Limestone 50 - 55 ft

dense to finely crystalline thin bedded soft to moderately hard

35 – 200 MPa

Upper Carters Limestone 25 - 27 ftdense to finely crystalline shale stringers/bands medium to thin bedded hard to very hard

55 – 195 MPa

T3 Bentonitesandy volcanic weak

shaleShale 1-1/4 to 2 ft

dense to fine grained sandy at top, shale at bottom thin bedded soft

Lower Carters Limestone 55 - 85 ftfine to medium crystalline shaley LS bands/stringers massive to thick bedded hard to very hard

120 – 180 MPa

Page 18: COMITÉ PANAMEÑO DE PRESAS

18

Center Hill Dam Foundation Remediation Geology

UCS 72 MPa

Page 19: COMITÉ PANAMEÑO DE PRESAS

100f

t ~ 3

0m

Center Hill Dam Foundation Remediation Encasement & Barrier wall layout

Page 20: COMITÉ PANAMEÑO DE PRESAS

20

Center Hill Dam Foundation Remediation Site Works Overview

E- & B- Wall

Extended Working Platform

Staging Area

Water Access

Page 21: COMITÉ PANAMEÑO DE PRESAS

21

Center Hill Dam Foundation Remediation Previous Works

Page 22: COMITÉ PANAMEÑO DE PRESAS

22

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 23: COMITÉ PANAMEÑO DE PRESAS

23

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 24: COMITÉ PANAMEÑO DE PRESAS

24

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 25: COMITÉ PANAMEÑO DE PRESAS

25

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 26: COMITÉ PANAMEÑO DE PRESAS

26

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 27: COMITÉ PANAMEÑO DE PRESAS

27

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 28: COMITÉ PANAMEÑO DE PRESAS

Center Hill Dam Foundation Remediation Todays Scope of Work

Page 29: COMITÉ PANAMEÑO DE PRESAS

Center Hill Dam Foundation Remediation Scheduled Small Drilling Equipment

Precision tool for Pilot Hole Drilling Verticality Control by Laser at a Coal Mine in Belgium Drilling depth: 626 ft – Laser beam confirms a total deviation of 1 inch = 0.01%

Page 30: COMITÉ PANAMEÑO DE PRESAS

Center Hill Dam Foundation Remediation Scheduled Large Drilling Equipment

Page 31: COMITÉ PANAMEÑO DE PRESAS

Center Hill Dam Foundation Remediation Scheduled Large Drilling Equipment

Page 32: COMITÉ PANAMEÑO DE PRESAS

Center Hill Dam Foundation Remediation Scheduled Large Drilling Equipment

Page 33: COMITÉ PANAMEÑO DE PRESAS

33

Center Hill Dam Foundation Remediation Scheduled Cutter Equipment

320to

Page 34: COMITÉ PANAMEÑO DE PRESAS

34

Center Hill Dam Foundation Remediation Scheduled Cutter Equipment

2,25m

3,2 m

70to

Page 35: COMITÉ PANAMEÑO DE PRESAS

35

Center Hill Dam Foundation Remediation Scheduled Slurry Equipment

Page 36: COMITÉ PANAMEÑO DE PRESAS

36

Center Hill Dam Foundation Remediation Scheduled Submittals & Reporting

Page 37: COMITÉ PANAMEÑO DE PRESAS

37

Center Hill Dam Foundation Remediation Scheduled Survey & Monitoring

Page 38: COMITÉ PANAMEÑO DE PRESAS

38

Center Hill Dam Foundation Remediation Scheduled Survey & Monitoring

Page 39: COMITÉ PANAMEÑO DE PRESAS

39

Center Hill Dam Foundation Remediation Scheduled Survey & Monitoring by CIS

Page 40: COMITÉ PANAMEÑO DE PRESAS

40

Center Hill Dam Foundation Remediation Scheduled Survey & Monitoring by CIS

Page 41: COMITÉ PANAMEÑO DE PRESAS

WallTrackerDokumentation und Visualisierung von Projektdaten

41

Page 42: COMITÉ PANAMEÑO DE PRESAS

WallTrackerDokumentation und Visualisierung von Projektdaten

Zweck und Ziele

1. Zeitnahe Qualitätskontrolle / -überwachung (z.B. erreichte Tiefen,

Überschnitte, Testergebnisse, …)

2. Zeitnahe Datenanalyse (Tiefe-Soll-Ist, Überschnitt-soll-Ist, …)

3. Zeitnahes Produktions-Controlling (Massen, Soll-Ist-Vergleiche)

4. Visualisierung der erbrachten Leistung

5. Übersichtliche Dokumentation von geographisch zugeordneten Daten

(geocoded data)

42

Page 43: COMITÉ PANAMEÑO DE PRESAS

WallTrackerVisualisierung und Dokumentation von Projektdaten

Software-Hintergrund1.Visualisierung von verschiedenen Daten aus verschiedenen Datenbanken über die ArcGIS-Software von Esri (ArcGIS: GeoInformationssystem)

2.ArcGIS-Reader ist kostenlos und wird bei Bedarf von IT installiert

Info aus Wikipedia:GeoinformationssystemGeoinformationssysteme (GIS), Geographische Informationssysteme oder Räumliche Informationssysteme (RIS) sind Informationssysteme zur Erfassung, Bearbeitung, Organisation, Analyse und Präsentation geografischer Daten. Geoinformationssysteme umfassen die dazu benötigte Hardware, Software, Daten und Anwendungen.

43

ArcGis Explorer Online

Page 44: COMITÉ PANAMEÑO DE PRESAS

WallTrackerDokumentation und Visualisierung von Projektdaten

44

Page 45: COMITÉ PANAMEÑO DE PRESAS

WallTrackerDokumentation und Visualisierung von Projektdaten

45

Page 46: COMITÉ PANAMEÑO DE PRESAS

WallTrackerVisualisierung und Dokumentation von Projektdaten

46

Page 47: COMITÉ PANAMEÑO DE PRESAS

WallTrackerVisualisierung und Dokumentation von Projektdaten

47

Page 48: COMITÉ PANAMEÑO DE PRESAS

WallTrackerVisualisierung und Dokumentation von Projektdaten

WallTracker ©

for

Center Hill Dam Seepage Rehabilitation

48

Page 49: COMITÉ PANAMEÑO DE PRESAS

CHD – Data Flow: Principles and Concepts

Single comprehensive data structure– Described in Data Management Plan to be submitted to Government– Master database serves as single authoritative repository of all project data– Relational database structure

Balance between automation and QC– Data flow is automated to eliminate transcription, but transparent to allow

QC at all steps

Page 50: COMITÉ PANAMEÑO DE PRESAS

CHD – Data Flow: Principles and Concepts

Data integrity built into each stage of process:– Raw data uploaded to Government FTP site immediately on generation– All data are verified on appending to database:

• Checks for completeness• Checks for compliance with valid values

– Normalization within database allows for efficient management:• All locations related by coordinates and stations• Consistent unit nomenclature across entire database

Government and QCS can remotely view operator screens and access all data with WallTracker

Page 51: COMITÉ PANAMEÑO DE PRESAS

CHD – Data Flow: Instrumentation and Survey

Inputs

Argus ADAS

Government’s or QCS’s Tablet PC:• Mirror of Argus data view• WallTracker view

Argus data view

Master Site Database

WallTracker

FTP(raw data;

submittals)

Page 52: COMITÉ PANAMEÑO DE PRESAS

CHD – Data Flow: Wall Installation

Bauer equipment with B-Tronics

Operator’s Control Screen

Wireless router

B-Tronics.dat file

Master Site Database

FTP(raw data;

submittals)

WallTrackerGovernment’s or QCS’s Tablet PC:• Mirror of Operator’s Control

Screen (within 1,000m)

Page 53: COMITÉ PANAMEÑO DE PRESAS

53