Lipton Soft Drinks Ireland Ltd.
Client: Lipton Soft Drinks Ireland Ltd
Engineer: RPS Consulting Engineers,
Ballincollig, Cork
Value: €980,000
Timeframe: 9 months Completed: 2010
Project Description:
Construction of an extension to a pharmaceutical facility, including construction of new office
block & internal refurbishment of existing continuously live production facility within a 'clean'
environment, where we had to adhere to strict environmental control procedures to ensure no
cross contamination of the product occurred. Also as this facility provided a specific product
required by all the other plants in Europe no down time apart from planned shutdowns was
allowed.
Lipton Soft Drinks Ireland Ltd.
Intel Ireland
Client: M+W Group 1A Sussex Terrace, Dublin4 (working on behalf
of Intel Ireland)
Engineer: M+W Group
Value: €3.3million
Timeframe:20weeks Completed: 2012
Project Description:
Site Enabling Works for 3 extensions to the existing buildings & associated site
works in a live manufacturing facility.
Safety Milestone achieved on Site at 35,835 accident free hours.
Carrigaline Library, Carrigaline, Co. Cork.
Client: Cork County
Council
Engineer: Cork County
Council
Value: €226,117
Timeframe:3 months
Completed: 2010
Project Description:
Refurbishment and fit out works
to Carrigaline Library . This
Project was delivered on budgetProject was delivered on budget
& time. Works were carried out
in a Town centre based works
involving strict safety
management.
Mitchelstown Library, Mitchelstown, Co. Cork.
Client: Cork County
Council
Engineer: Cork County
Council
Value: €194,891
Timeframe:3 months
Completed: 2010
Project Description:
Conversion of existing
Commercial/Retail units into
new Library at Sutton Court.new Library at Sutton Court.
This Project was delivered on
budget & time. Works were
carried out in a Town centre
based works involving strict
safety management.
Ozolaid House, Camden Quay, Cork.
Client: Murray Properties
Ltd.
Quantity Surveyor: James
Sheehan &
Associates
Value: €380,000
Timeframe:4 months
Completed: 2009
Project Description:
Refurbishment & Alterations to
‘Ozolaid House’,1 Camden‘Ozolaid House’,1 Camden
Quay, Cork.(Listed Building).
The building consists of five
storeys including one retail unit
and 18 residential units. This
project consists of the strip out
of the existing mechanical and
electrical of the existing listed
building. Refurbishment of
original Sash windows. The
removal of existing internal
doors, floors walls and ceiling
finishes and the installation of
new, to achieve a fire rating for
the fire cert Compliance. City
Centre location required very
tightly managed safety and
construction procedures
Bowens Menswear, Bandon. Co. Cork
Client:
Bandon Menswear
Quantity Surveyors: Unique
Fit out
Value: €315,000
Timeframe: 7 months
Completed: 2010
Project Description:
Refurbishment, Strip Out &
Complete fit out of Bowens
Menswear including some Menswear including some
roof/structural works on Main
St. Bandon. Town Centre
location required very tightly
managed safety and construction
procedures. Traffic Management
plans fully operational during
night time works and for
deliveries
Kerry Foods, Wallingstown, Little Island, Cork
Client: Kerry Food Group
Engineer: Thomas O Brien
Architect: Wilson Architecture
Value: €2.5million
Timeframe: 16week (turnkey project)
Completed: 2008
Project Description:
Design & Build of complete Turnkey Package 25,000sqft Light Industrial Units with Substantial Civil
Elements. Phase 1 consisting of a steel structure with in-situ concrete slab floors of high tolerance.
Office space (fit out) accounted for 7000sqft of the total space.
An Post DSU, Ballincollig, Cork
Client: An Post
Architects: Jack Coughlan & Associates
Value: €120,000
Timeframe:2 months Completed: 2011
Project Description:
Refurbishment, fit out works and construction of extension to the existing sorting
post office in Ballincollig. Ancillary site works include fit out of office space &
creation of new opens and associated works.
Woodlands Depot, Killarney, Co. Kerry.
Client: Killarney Town Council (Kerry)
Engineer: Malone O’Regan McGillicuddy
Value: €2.4million
Timeframe: 11 months Completed: 2009
Project Description:
GFA 960m2 –Construction of energy efficient offices and fit out of same(Mechanical 7% &
Electrical 9%) & loading areas on a Greenfield site for Killarney Town Council. Works also
included a 450m NRA spec link road with extensive Traffic Management works.
High Street, Killarney, Co. Kerry
Client: High Street Development s(Niall Fleming)
Architect: O Sullivan Campbell & Associates
Engineer: Malone O'Regan McGillicuddy, 4 Day Place, Tralee,Co Kerry
M&E Specialist: Martin Buckley & Associates, Tramway House, Albert Road, Cork
Value: €3.5million
Timeframe: 12 months Completed: 2008-Fit Outs are ongoing
Project Description:
A Design Build Fixed Price Project- Construction of a 4 Storey Steel Commercial & Residential
Units & Fit Out- Apartment / Duplex Apartments with extensive Mechanical(8%) & Electrical(20%)
Works. These works were completed on a part brownfield town centre site(located in the heart of
Killarney). Careful sequencing of works was vital due to access only from the site as adjacent
properties on 3sides. The fit out of the different floors has been carried out over the last number of
years as required by different longterm clients. Facilities include: Canteen/tea rooms/large scale
board room/studios. Open plan and closed plan workspace/office space. A large storage back house
facility was developed for the ground floor 'Daybreak Shop'. Installation of a lift serving all floors.
High Street, Killarney, Co. Kerry
High Street, Killarney, Co. Kerry
Television Mobiles Ltd. (TVM)
Client: Television Mobiles Ltd. Bartlemy, Co. Cork
Engineer: Malachy Walsh & Partners
Value: €1,951,847
Timeframe: 17 months Completed: 2012
Project Description:
Demolition of existing derelict cottage and construction of new centralised office building with
attached truck workshop. The office building comprises of offices- constructed to a passive standard,
meeting rooms, production rooms, editing suites(strict dust regulatory guidelines to abide by),
storage rooms, roof garden, Canteen, Kitchen, large reception area, truck workshop comprising of
3no. bays and large scale plant room (editing/production purposes) and associated works.
Television Mobiles Ltd. (TVM)
The Framemaker Artist Studios
Client: The Framemaker
Architect: Wilson Architecture
Value: €765,000
Timeframe: 5 months
Completed: 2006
Project Description:
Construction of a retail
warehouse facility which
included the provision of artist
studios and office areas. Works
included the fitting out of the included the fitting out of the
unit, artist studios and office
areas.
Killarney Areas Services Centre
Client: Kerry County Council
Engineer: Kerry County Council
Value: €148,000
Timeframe:2 months
Completed: 2010
Project Description:
Construction of internal office
development for a primarily open
plan office for local authority
functions in an existing new
building shell of approximatelybuilding shell of approximately
241m2. Installation of self
contained aero-thermal heating
system c/w heat recovery
ventilation for above office
development.
Installation of electrical power,
security system, fire alarm system,
CCTV system as well as providing
conduits for IT and
communications requirements by
others.
Bandon Town Council Offices.
Client: Bandon Town Council
Engineer: Cork County Council
Value: €50,000
Timeframe:1 month
Completed: 2011
Project Description:
Refurbishment and fit out to Bandon
Town Council offices. Works
comprised of removal of existing
office fitting and re-establishment of
office space with new furniture.office space with new furniture.
Work was carried out also to remove
and replace a subsiding floor and all
associated refurbishment works.
Goleen Coast Guard Station, Cork
Client: The Office of Public
Works (OPW)
Engineer: The Office of Public
Works (OPW)
Value: €644,757
Timeframe:11 month
Completed: 2011
Project Description:
Goleen Coast Guard Station
Demolition of existing Rocket Cart
Shed; the realignment of existing slip Shed; the realignment of existing slip
road adjacent to the shed;
construction of new slip road;
construction of two storey Coast
Guard Station of 326 sq metres; and
associated landscaping and other
ancillary works
Goleen Coast Guard Station
Cascade Carrigtowhill, Cork
Client: Castlelake Partnership
Engineer: Denis O Sullivan & Associates (DOSA)
Architects: PRC Architects, Morrisons Island, Cork City
M&E Specialist:Martin Buckley & Associates, Tramway House, Albert Road, Cork
Value: €14million
Timeframe:11 month Completed: 2008
Project Description:
Cascade is Design Build(fixed price) project constructed on a greenfield development &
fit out of 95 Luxury Apartments in Carrigtwohill, Co. Cork. Phase 1. This development
was 10,000sqm in size and 4-6 floors high. It is located just on the outskirts of
Carrigtwohill town in close proximity to existing residential and commercial units.
Works included extensive piling and the construction of footbridge over a lake on the
site.
33 Oliver Plunkett St. Cork
Client: Murray Properties Ltd
Thompson
House, 55 McCurtain St.
Cork
Engineer: Dan Mulvihill &
Associates.
Value: €244,461
Timeframe:11 month Completed:
2011
Project Description:
Structural Stabilization Works and Structural Stabilization Works and
complete refurbishment/renovation
works to No. 33 Oliver Plunkett Street
located in Cork City. This 4storey
building required careful monitoring
and sequencing of works to ensure
minimal disruption to the residents,
businesses and pedestrians of the city
centre location.
Swimming Pools-Bishopstown, Churchfield, Douglas,
Cork City
Client: Cork City Council
Engineer: JODA Engineers, Model Farm Road, Cork
Value: €742,290
Timeframe: 1 month Completed: 2011
Project Description:
Douglas Swimming Pool, Bishopstown Leisureworld & Churchfield Leisureworld.-Live Operational
Public Environment
Energy upgrade and disability works including associated site works. Electrical works(35%) &
Mechanical works(31%).
OS Sheet Metals, Tramore Road, Cork City
Client: OS Sheet Metals
Engineer: Watermans Consulting Engineers
Value: €1.6million
Timeframe: 11months Completed: 2008
Project Description:
Refurbishment, alterations and fit out to Industrial Unit. Including extensive site works.
Works included a large scale Electrical element including the provision of a new
substation to supply fabrication machinery.
Nyhan Motors, Midleton, Co. Cork
Client: Nyhan Motors
Architect: Joe O’ Sullivan Architectural Design & Planning, Unit 8, Airways Technology Park,
Farmer’s Cross, Cork
Engineer: Gearoid Hayes & Associates, 13 Oliver Plunkett. St. Bandon. Co. Cork
M&E Specialist:Martin Buckley & Associates, Tramway House, Albert Road, Cork
Value: €2million
Timeframe: 2month
Completed: 2008
Project Description:
A Design Build Fixed Price Contract-Construction of a Car Showrooms with Offices and extensive
parking facilities for both stock cars and customer cars. A mechanics full fitted garage and all
associated site works including extensive tarmac works and landscaping to car show areas.
Cobh Community Centre, Cobh, Co. Cork
Client: Cobh Community Centre
Engineer: O'Brien Thomas J Consulting Engineers Ltd, Discovery House U22Airport East
Business pk,Farmers Cross, Cork
Architect: Stephen Kowalski Architects.
M&E Specialist:Martin Buckley & Associates, Tramway House, Albert Road, Cork
Value: €2.3 million
Timeframe: 9 month
Completed: 2008
Project Description:
A Design Build Fixed Price Contract- Construction of a Community Centre in Cobh Co. Cork for
Cobh Parish to include area assigned to COPE, theatre and 3 floors of workshops, kitchen/servery
and entrance lobby & Fit out of same. Extensive piling to ground works, tarmac car park facilities,
playing court areas & perimeter boundaries
St. Patricks GRD School, Whitechurch, Co. Cork
Client: St. Patrick's NS Whitechurch / Department of Education
Architect: KOBW Architects, Heron House, Blackpool Park, Blackpool, Co. Cork ..
Value: €2.3 million
Timeframe: 11 month
Completed: 2012
Project Description:
Phased demolition of existing school building, provision of 1 no. temporary classroom and the
construction of a new 16 classroom Generic Repeat Design school of 2,268m2 including
construction of a fully equipped PE Hall, activity areas including Ball courts etc. with associated site
works.
Cork University Hospital – All Works
Client: Health Service Executive –Cork University Hospital
Architect: Health Service Executive
Value: €676,996
Timeframe: 2011-2012 (over the space of the 2years)
Completed: ongoing
Project Description:
-Ultrasound room -GI Clinic
-Concourse Room -Medical Records -Fire Door Refurbishment
-Pergola -X-Ray room -Acroyvn Wall
-Ward 2C,3A,5B -CAT Lab -Phlebotomy Unit
-Fire Door Compartmentation -Water Filtration
Cork University Hospital – All Works
Cork University Hospital – All Works
Prosys Industrial Unit, Carrigtwohill, Co. Cork
Client: Prosys Sampling Systems Ltd.
Engineer: David Kelly Partnership, Nelson House, Emmet Place, Youghal, Co. Cork
Value: €930,000
Timeframe: 11months
Completed: 2011
Project Description:
Construction of a New Light Industrial Building with ancillary office accommodation and parking
facilities including associated site works at IDA Business Park
Youghal Hospital, Youghal, Co. Cork
Client: Youghal Hospital -Live Operational Environment
Engineer: HSE South, Estates Department, Block B, St. Finbarrs Hospital,
Douglas Road, Cork
Value: €307,885
Timeframe: 2months
Completed: 2012
Project Description:
Fire upgrade works, ceilings, partitions, electrical works(15%), mechanical works
(20%) including doors and flooring etc. Works included an upgraded access roadway
& site services. Works carried out over 6phases in a very tight project programme.
Salt Barn, Ballincollig, Co. Cork
Client: Cork County Council
Engineer: Cork County Council, ref. National Roads Office, Richmond, Glanmire,
Co. Cork
Value: €235,000
Timeframe: 4months
Completed: 2012
Project Description:
Construction of a salt storage barn and a machinery storage area in Ballincollig.
Works included building works, construction of concrete aprons, installation of
services and all associated works
Salt Barn, Skibbereen, Co. Cork
Client: Cork County Council
Engineer: Cork County Council, ref. National Roads Office, Richmond, Glanmire,
Co. Cork
Value: €230,000
Timeframe: 4months
Completed: 2012
Project Description:
Construction of a salt storage barn and a machinery storage area in Skibbereen. Works
included building works, construction of concrete aprons, installation of services,
extensive piling and all associated works
AOC Iron Mountain, Carrigtwohill, Co. Cork
Client: AOC Commercials, Carrigtwohill, Co. Cork
Engineer: Denis O Sullivan & Associates (DOSA), Barrack Square, Ballincollig,
Co. Cork
Value: €2.6million
Timeframe: Phased Development over 3 years
Completed: 2008
Project Description:
Large industrial Building for Iron Mountain Paper Storage, Carrigtwohill, Co. Cork
including the provision of extensive car parking spaces and associated works
Cobh Cross, Carrigtwohill, Co. Cork
Client: James Fenton & John Cahill, Killacloyne, Carrigtwohill, Co. Cork
Engineer: Tony Dunlea
Value: €2.8million
Timeframe: 9months
Completed: 2008
Project Description:
Phase one. Six Industrial/ Warehouse Units, associated car parking spaces, machinery
storage unit with ancillary two storey offices, including Road works & other Civil
Elements
North Monastery Secondary School, Cork
Client: North Monastery Secondary School Board of Management
Engineer: O Connell Harley O Dwyers
Value: €616,584
Timeframe: 4months
Completed: 2009
Project Description:
Complete Upgrading of Electrical Works, Fire upgrading & Associated Building to 32
classrooms & Refurbishment Works including the installation of an underground,
waterproofed reinforced concrete structure.
Before After
Cork Institute of Technology – Shop & Handrails
Client: Cork Institute of Technology (CIT)
Architect: Neff Design, Liberty Bridge, Kilmurriheen, Spur Hill Cork
Engineers: Horgan Lynch Engineers, Blackrock, Cork
Value: €74,684
Timeframe: August 09-September 09 & February ‘10 – June ‘10
Completed: 2009 & 2010
Project Description:
Refurbishment & Upgrade to Cork Institute of Technology Main Campus Shop. Also
the Make up & installation of handrails & balustrades for Cork Institute of
Technology Athletic Track
Bandon Co-op Kinsale, Co. Cork
Client: Bandon Co-operative Society Ltd.
Engineers: Murphy, McCarthy Consulting Engineers. Ltd. Centre Park Road, Cork
Value: €729,876
Timeframe: 11months
Completed: 2011
Project Description:
Construction of a new detached store and yard entrance; provision of new wall and
roof sheeting to existing building; internal alterations to convert existing building
store into a retail shop area. These works were carried out in 3 phases.
Cork Institute of Technology – Block A Works
Client: Cork Institute of Technology (CIT)
Architect: Neff Design, Liberty Bridge, Kilmurriheen, Spur Hill Cork
Value: €1,078,250
Timeframe: 11months
Completed: 2012
Project Description:
Construction of an extension to the rear (North) of A Block of Cork IT. It will
comprise of a generally single storey build with part mezzanine and a new first floor
over room A183 in the existing A Block including 3 new workshops
Shanakiel Hospital, Cork City
Client: Board of Management- Shanakiel Hospital
Architect: HBK Architects, Lisburn, Co. Antrim
Value: €110,000
Timeframe: 3months
Completed: 2009
Project Description:
Refurbishment and Removal/Demolition of a section of 600mm thick structural wall
and the shuttering and pouring of an insitu concrete structural lift shaft to facilitate the
Installation of a Lift and all associated site works.
St. Stephens Hospital, Glanmire, Co. Cork
Client: Health Service Executive –Cork University Hospital
Architect: Health Service Executive
Value: €114,000
Timeframe: 2 months
Completed: 2012
Project Description:
Fire Safety Upgrading works to Unit 8, St. Stephens Hospital Glanmire- works carried
out in a live hospital environment working within strict Hospital Health & Safety
guidelines with an emphasis on Aspergillus Control.
Nurture Creche, Fairylawn, Western Road, Cork
Client: Nurture Creche Ltd.
Architect: QDM Architecture, Cork
Value: €1.6m
Timeframe: 6months
Completed: 2007
Project Description:
Renovation & Refurbishment of existing 3 storey Building(protected façade) in a city
environment. Development & Construction of an Assembly Area, Provision of a Lift
Shaft, Lift & Access Ramp & associated site works- comprising of Crèche Facility,
external specialized play areas & Apartment Duplex & associated site works including
extensive piling and hard landscaping.
Fota House, Co. Cork
Client: Irish Heritage Trust
Q. Surveyors:Bill Feehely & Associates
Value: €785,000
Timeframe: 6months
Completed: 2010
Project Description:
Development of Road Network & Extensive Car Parking facilities at Fota House,
Cobh, Co. Cork . These works included lighting, road alignment, widening and re-
surfacing and all works carried out to ensure minimum disruption to the ongoing
work/activities of Fota House
Cullen NS, Cullen, Co. Cork
Client: Cullen NS –Board of Management
Architect: Joe O Sullivan Architects
St. Marys NS, Carrigaline, Co. Cork
Construction of a single storey, including an Autism Spectrum
Disorder unit
Client: Board of Management- St. Marys
NS
Architect: Declan O Sullivan Architects
Blue Haven Hotel-Hamlets- Old Fish Market Wall
Restoration Complete restoration of original Old Fish Market Wall & internal
structure upgrading works(value of works and timeframe includes all three projects Blue Haven Hotel/Oz
Haven & Hamlets Bar)
Client: Fitzgerald & Partners
Contract Value: €515,000
Quantity Surveyors: James Sheehan & Associates
Timeframe: 6months
Blue Haven Hotel-Hamlets- Old Fish Market Wall
Restoration (value of works and timeframe includes all three projects Blue Haven Hotel/Oz
Haven & Hamlets Bar)
Client: Fitzgerald & Partners
Contract Value: €515,000
Quantity Surveyors: James Sheehan & Associates
Timeframe: 6months
Oz Haven-Blue Haven Food Company
Complete stripout & fit out of Oz Haven Café
(value of works and timeframe includes all three projects Blue Haven Hotel/Oz
Haven & Hamlets Bar)
Client: Fitzgerald & Partners
Contract Value: €515,000
Quantity Surveyors: James Sheehan & Associates
Timeframe: 6months
Cobh Cross, Carrgtwohill, Co.
Cork
Light weight Industrial/ Warehouse
Units with Ancillary Two- Storey
Offices.
Iron Mountain Development @
Carrigwohill, Co. Cork
Development consisting of a
Comerical Unit which took place
over two phases.
Client: Mr. James Fenton &
Mr. John Cahill
Architect: Tony Dunlea
Consulting Engineer
Engineer: Tony Dunlea
Consulting Engineer
Client: Iron Mountain
Engineer: Denis O’ sullivan
Christy Kearney, Little Island, Co.
Cork
Commercial retail unit located within Euro Business Park Little Island.
Client: Christy Keanrey
Architect: Concept Design
Engineer: Concept Design
OS Sheet Metals, Tramore Rd,
Cork Refurbishment & Alterations to Industrial Unit & associated site works.
Client: OS Sheet Metals Contract
Value: €1,700,000
Engineer: Waterman Consulting Engineer’s Time
Frame: 10months
Toss Bryan, Fermoy, Co. Cork
Commercial Unit located in Fermoy
Client: Toss Bryan
Engineer: Sean McCarthy Consulting
Engineers
Greenstar Recycling Ltd.
Construction of an commercial recycling unit with underground
waterproof concrete structures , in Glanmire, Co. Cork
Client: Greenstar Recycling Ltd.
Architects: O Riordan Staehli Architects