+ All Categories
Home > Documents > Concepts and best practices for the risk register in primavera risk analysis

Concepts and best practices for the risk register in primavera risk analysis

Date post: 16-Aug-2015
Category:
Upload: p6academy
View: 33 times
Download: 3 times
Share this document with a friend
Popular Tags:
34
1
Transcript
Page 1: Concepts and best practices for the risk register in primavera risk analysis

1

Page 2: Concepts and best practices for the risk register in primavera risk analysis

<Insert Picture Here>

Concepts and Best Practices for the Risk Register in Primavera Risk Analysis

Matt CandelaSenior Technical Support Engineer

Page 3: Concepts and best practices for the risk register in primavera risk analysis

3

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions.

The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.

Page 4: Concepts and best practices for the risk register in primavera risk analysis

4

Agenda

• Demo of primary Risk Register functionality in Primavera Risk Analysis (PRA)

• Detailed look at functionality

• Other options and considerations

• Overview of risk functionality in P6 R8

Page 5: Concepts and best practices for the risk register in primavera risk analysis

5

• Uncertainty is inherent to a task.– Example: digging a trench is scheduled for 10 days. It may only

take 8, or could take up to 12.

• Risks are events that may or may not occur and could affect a task.– Example: there is a 5% chance of flooding, which could delay

the digging of the trench by 5 to 8 days.

Risk vs. Uncertainty

Page 6: Concepts and best practices for the risk register in primavera risk analysis

6

• Risk scoring– Thresholds, scoring criteria

• Create risks and assign to tasks– Qualitative, quantitative probabilities and impacts

– Risk scores generated

• Mitigation– Post-mitigated probabilities, impacts and risk scores

• Build impacted risk plans

Primary Risk Register Functionality

Page 7: Concepts and best practices for the risk register in primavera risk analysis

7

Risk Scoring

• Scores are calculated using Probability and Impact Scoring Diagram

• Determined by intersection of the probability and impact

Page 8: Concepts and best practices for the risk register in primavera risk analysis

8

Qualitative and Quantitative Risks

• Risks have both qualitative and quantitative values– Quantitative used in impacted risk plan

– Qualitative used to determine risk scores

• Qualitative risks: quantitative values from thresholds– For probability, low and high are averaged

– For impacts, low is min and high is max

• Quantitative risks: qualitative values determined by average of min, max, and most likely impacts

Page 9: Concepts and best practices for the risk register in primavera risk analysis

9

Qualitative Risks - Example

• Risk HAZ is assigned a high schedule impact

• High schedule threshold is defined as 20 to 40 days in the risk scoring options

Page 10: Concepts and best practices for the risk register in primavera risk analysis

10

Qualitative Risks - Example

• Risk is assigned to a task on Quantitative tab

• Schedule impact is min 20 days and max 40

Page 11: Concepts and best practices for the risk register in primavera risk analysis

11

Quantitative Risks - Example

• Risk ACC is quantified and assigned to task 3

• Cost impact is min $50,000 and max $100,000, average is $75,000

Page 12: Concepts and best practices for the risk register in primavera risk analysis

12

Quantitative Risks - Example

• $75,000 is within medium cost threshold

• Qualitative cost impact is medium

Page 13: Concepts and best practices for the risk register in primavera risk analysis

13

Qualitative and Quantitative Risks Assigned to Multiple Tasks

• Qualitative: impacts spread across the tasks, per following Risk Register options:– “Spread the risk duration across multiple impacts”

– “Spread the risk costs across multiple impacts”

• Quantitative: impact averages will be summed to determine qualitative value

Page 14: Concepts and best practices for the risk register in primavera risk analysis

14

Mitigation

• Mitigation Response of Avoid, Transfer, or Reduce allows for post-mitigation values and score.

• Title and Total Cost optional for simple mitigation plan

Page 15: Concepts and best practices for the risk register in primavera risk analysis

15

Mitigation - Detailed Actions

• Qualitative tab > Mitigation tab > Use Detailed Actions

• Multiple mitigation actions with additional fields available

Page 16: Concepts and best practices for the risk register in primavera risk analysis

16

Mitigation - Detailed Actions

• Total Cost calculated as sum of details actions costs– Excluding actions set to Rejected

• Post-mitigated values taken from an action– Rejected actions are not considered

– Action with latest finish date is used

– Tie goes to action with the lowest score

Page 17: Concepts and best practices for the risk register in primavera risk analysis

17

• Mitigation Response set to Accept: any other response allows for mitigation

• Use Detailed Actions is selected: post-mitigated values taken from an action

• Risk is quantified: post-mitigated values must be set on Quantitative tab

Post-Mitigated Options Grayed Out

Page 18: Concepts and best practices for the risk register in primavera risk analysis

18

Building an Impacted Plan

• (Task ID):B is the original task with no risk impact– Duration and duration uncertainty of the original task

Page 19: Concepts and best practices for the risk register in primavera risk analysis

19

Building an Impacted Plan

• (Task ID):(Risk ID) is the risk event– Task existence for probability, duration uncertainty for schedule

impact, resource uncertainty (ZCRI) for cost impact

– Zero remaining duration

Page 20: Concepts and best practices for the risk register in primavera risk analysis

20

Building an Impacted Plan

• (Task ID) is the summary for base task and risk event– Logic from original task

– Resource assignments from original task, unless “Cost Impacts include duration costs” is selected in Risk Register options

Page 21: Concepts and best practices for the risk register in primavera risk analysis

21

Correlation

• Available on Risk View tab when a risk is assigned to multiple tasks

• Impact Ranges 90% correlation, Event Existence 100%

Page 22: Concepts and best practices for the risk register in primavera risk analysis

22

Link in Series

• Available on Task View tab when a task has multiple risks assigned

• When unchecked, risks are in parallel

Page 23: Concepts and best practices for the risk register in primavera risk analysis

23

Link in Series - Example 1

• Risks are linked in series

• Cumulative effect, both impact schedule

Page 24: Concepts and best practices for the risk register in primavera risk analysis

24

Link in Series - Example 2

• Risks are not linked in series, occur in parallel

• Only longest duration affects schedule

Page 25: Concepts and best practices for the risk register in primavera risk analysis

25

Assigning a Risk to a Summary Task

• Risk will impact sub task with latest finish date

• Potential for confusion over which task risk will impact and/or unexpected impact

Page 26: Concepts and best practices for the risk register in primavera risk analysis

26

Assigning a Risk to a Hammock Task

• Crash may occur or impacts may be incorrect

• Ability to do so has been removed in version 8.7.0029

Page 27: Concepts and best practices for the risk register in primavera risk analysis

27

Other Considerations and FAQs

• Opportunity on task near Data Date– Opportunities work by pulling back start date, impact may be

incorrect

• What do risk start and finish dates affect?– Proximity, exposure plan

• Is there a way to quickly assign a risk to a large number of tasks?– Filter on Risk View tab or use “Impacted Task ID(s)” column:

IDs separated by comma, no space

Page 28: Concepts and best practices for the risk register in primavera risk analysis

28

• Web only

• Risk scoring– Thresholds, scoring criteria

• Create risks and assign to tasks– Qualitative probabilities and impacts

– Risk scores generated

• Mitigation– Post-mitigated probabilities, impacts and risk scores

Primary P6 R8 Risk Functionality

Page 29: Concepts and best practices for the risk register in primavera risk analysis

29

Primary P6 R8 FunctionalityDefine risk scoring under “Administer…Enterprise Data”

Page 30: Concepts and best practices for the risk register in primavera risk analysis

30

Primary P6 R8 FunctionalitySelect “Risks” on Projects View to create and assign risks

Page 31: Concepts and best practices for the risk register in primavera risk analysis

31

Primary P6 R8 FunctionalityUse “Response Plans” tab for mitigation

Page 32: Concepts and best practices for the risk register in primavera risk analysis

32

Importing a Project from P6 R8 into PRA

• Requires Primavera Risk Analysis 8.7.0029 or later

• Requires Web Services Utility with appropriate settings– See “Using Web Services to connect” in PRA help

• Run Connection Wizard in PRA

• Use “File…Primavera…Import Primavera P6 Project” from PRA, no option from P6 R8 Web

• Risks only included in single project import

Page 33: Concepts and best practices for the risk register in primavera risk analysis

33

Page 34: Concepts and best practices for the risk register in primavera risk analysis

34


Recommended