18
CONFIRMATION REPORT Use transaction:CO28 Preferred profiles:Z00001-ECE Order Header confirmations Z00002-ECE Confirmations per count point
Transcript
Page 1: Confirmation report - murali krishna nookella

CONFIRMATION REPORT

Use transaction:CO28

Preferred profiles:Z00001-ECE Order Header confirmationsZ00002-ECE Confirmations per count point

Page 2: Confirmation report - murali krishna nookella

Enter the transaction code:CO28

Page 3: Confirmation report - murali krishna nookella

Select confirmations

Choose display

Page 4: Confirmation report - murali krishna nookella

You will see this screen

Page 5: Confirmation report - murali krishna nookella

Select the profile

Page 6: Confirmation report - murali krishna nookella

Enter the plant number

Page 7: Confirmation report - murali krishna nookella

Enter the dates. This is to filter the searchcriteria within the period.If you leave this field, system will search all the prod orders

Page 8: Confirmation report - murali krishna nookella

You can use above any one of them for your search.

Page 9: Confirmation report - murali krishna nookella

Click on execute icon

Page 10: Confirmation report - murali krishna nookella

You will find the report on the basis of everyindividual production order

Page 11: Confirmation report - murali krishna nookella

Scroll down to see the other production order confirmations

Page 12: Confirmation report - murali krishna nookella

You can change the fields by selecting fields tab

Page 13: Confirmation report - murali krishna nookella

Choose the ones you want

Page 14: Confirmation report - murali krishna nookella

Click continue to see the change

Page 15: Confirmation report - murali krishna nookella

Find the new column here

Page 16: Confirmation report - murali krishna nookella

Enter the profile and plant to see the confirmations with respect to work center with respect to work center

Click on execute button

Page 17: Confirmation report - murali krishna nookella

This is the report with respect to work center and operation

Page 18: Confirmation report - murali krishna nookella

Scroll down to see the confirmations with respectto operation and work center

This report can be downloaded to excel