Date post: | 25-Mar-2018 |
Category: |
Documents |
Upload: | nguyenduong |
View: | 221 times |
Download: | 4 times |
PLUMBING GENERAL NOTES1. ALL INFORMATION SHOWN ON THESE DRAWINGS INCLUDING
LOCATION AND SIZES ARE BASED ON THE BEST INFORMATION
AVAILABLE. INFORMATION SHOWN IS TO INDICATE THE INTENT OF
THE PLUMBING SYSTEM WORK BUT MAY NOT REFLECT THE
EXACT ROUTING AND LOCATION. IT IS THE RESPONSIBILITY OF
THE CONTRACTOR TO FIELD VERIFY EXISTING EQUIPMENT,
PIPING, CONNECTIONS, STRUCTURE, ELECTRICAL, LIGHTING AND
ARCHITECTURAL INFLUENCES PRIOR TO INSTALLATION OF THE
NEW WORK TO AVOID ANY CONFLICTS WITH SYSTEMS
REQUIRING MODIFICATIONS. NOTIFY ENGINEER OF ANY
CONFLICTS, PRIOR TO PERFORMING WORK.
2. OFFSET ALL PIPING AS REQUIRED TO AVOID STRUCTURAL
MEMBERS, FLASHING, MECHANICAL AND ELECTRICAL EQUIPMENT.
3. DO NOT SCALE DRAWINGS, SEE ARCHITECTURAL DRAWINGS FOR
FINAL LOCATIONS OF ALL PLUMBING FIXTURES, GENERAL
PURPOSE FLOOR DRAINS, AND ADDITIONAL EQUIPMENT
REQUIRING PLUMBING CONNECTIONS.
4. COORDINATE SANITARY DRAINAGE UTILITY LOCATIONS AND
INVERT ELEVATIONS PRIOR TO COMMENCING WORK, NOTIFY
ARCHITECT IMMEDIATELY IF CONDITIONS DISCOVERED WILL NOT
ALLOW SYSTEM INSTALLATION AS DESIGNED.
5. SEE ISOMETRICS AND DIAGRAMS FOR BRANCH PIPE SIZES NOT
INDICATED IN PLAN.
6. COORDINATE PLACEMENT OF SLEEVES THROUGH FLOORS,
WALLS AND ROOF CONSTRUCTION PRIOR TO COMMENCING
WORK.
7. SEE ARCHITECTURAL PLANS AND DETAILS FOR MOUNTING
ELEVATIONS OF ALL PLUMBING FIXTURES.
8. MOUNT WALL HYDRANTS AND HOSE BIBBS AT 18" ABOVE
SURROUNDING GRADE OR FINISHED FLOOR ELEVATIONS UNLESS
SPECIFICALLY NOTED OTHERWISE.
9. FIELD VERIFY EXACT LOCATION OF ALL EXISTING UTILITIES AND
EQUIPMENT PRIOR TO COMMENCING WORK.
10. PROTECT EXISTING UTILITIES AND EQUIPMENT TO REMAIN
DURING ENTIRE CONSTRUCTION PERIOD; REPLACE DAMAGED
MATERIALS IMMEDIATELY AT NO ADDITIONAL COST TO THE
OWNER.
11. COORDINATE EXACT ROUGH-IN CONNECTION LOCATIONS AND
SIZES WITH EQUIPMENT SUPPLIER PRIOR TO COMMENCING
WORK ASSOCIATED WITH EQUIPMENT BEING FURNISHED BY
OTHERS.
12. SEE HVAC PLANS FOR FINAL LOCATION OF ALL HVAC EQUIPMENT,
COORDINATE PIPING SYSTEM CONNECTION PRIOR TO
INSTALLATION.
13. ALL WORK SHALL COMPLY WITH IPC 2015 AND IFGC 2015.
14. ALL MATERIALS IN THE PLENUM SPACE SHALL MEET THE FLAME
SPREAD AND SMOKE DEVELOPMENT INDEX PER
IMC/2015-SECTION 602.2.1. AND SHALL BE LISTED AND LABELED
FOR INSTALLATION WITHIN A PLENUM.
15. ALL EQUIPMENT AND MATERIALS USED IN THE DISTRIBUTION OF
DOMESTIC POTABLE WATER SHALL BE APPROVED AND TESTED
FOR SUCH APPLICATION WITH DOCUMENTED LISTINGS AND
LABELING IN ACCORDANCE WITH THE LATEST EDITION OF THE
INTERNATIONAL PLUMBING CODE, PUBLIC LAW 111-380 AND
ANSI/NSF-61, ANNEX G.
16. EXTEND ALL VENT TERMINATIONS THROUGH THE ROOF A
MINIMUM OF 20' FROM ALL OUTSIDE AIR INTAKES, AND OTHER
BUILDING OPENINGS.
DESCRIPTIONSYMBOL
PLUMBING ABBREVIATIONS
ABOVEABV
AMERICANS WITH DISABILITIES ACTA.D.A.ABOVE FINISHED FLOORAFF
ABOVE FINISHED GRADEAFG
ACID NEUTRALIZATION TANKANT
ACCESS PANELAPARCHITECT, ARCHITECTURALARCH
ACID VENT THROUGH ROOFAVTR
BACK FLOW PREVENTERBFP
BELOWBLWBALL VALVEBV
COMMONC
CUBIC FEET PER HOURCFH
CAST IRON PIPINGC.I.CEILINGCLG
COLUMNCOL
CONCRETECONC
CONNECTCONNCONTINUECONT
CONSTRUCT, CONSTRUCTIONCONST
COORDINATECOOR
CRAWLSPACECSCHECK VALVECV
DOWNDN
DISHWASHERDW
EXISTING(E)EACHEA
ELECTRICAL CONTRACTOREC
ELECTRIC, ELECTRICALELEC
ELEVATIONELEVELECTRIC WATER COOLEREWC
FAHRENHEITF
FLOORFLR
GENERAL CONTRACTORGCGALLONS PER MINUTEGPM
HEADERHDR
HORIZONTALHORIZ
HORSEPOWERHPINVERT ELEVATIONIE
INDIRECT WASTEIW
INTEGRALINT
JOIST(S)JST(S)KITCHEN EQUIPMENT CONTRACTORKEC
LOCATIONLOC
MANUFACTUREMANUF
MAXIMUMMAXTHOUSAND BRITISH THERMAL UNIT PER HOURMBH
MECHANICAL CONTRACTORMC
MEDIUM PRESSURE GASMG
MINIMUMMINMEMORY STOPMS
NEW(N)
NORMALLY CLOSEDNC
NORMALLY OPEN / NUMBERNONOT TO SCALENTS
OUTSIDE AIROA
PLUMBING CONTRACTORPC
PHASEPHPOINT OF CONNECTIONP.O.C.
PROVIDEPROV
PRESSURE REDUCING VALVEPRV
PRESSURE PER SQUARE INCH GAUGEPSIGPRESSURE AND TEMPERATURE RELIEFPTR
POLYVINYL CHLORIDE PIPINGPVC
RELOCATED(R)
RETURN AIRRAREFERENCERE
REQUIREDREQD
SUPPLY AIRSA
SANITARY PIPINGSANSHEETSHT
SQUARESQ
SIMILARSIM
SAFETY RELIEF VALVESRVSTAINLESS STEELSS
TEMPERATURE CONTROLTCC
TYPICALTYP
VENT PIPINGVVERTICALVERT
VACUUM BREAKERVB
VENT THROUGH ROOFVTR
WITHW
DESCRIPTIONSYMBOL
PLUMBING ABBREVIATIONS
ABOVEABV
ABOVE FINISHED FLOORAFFARCHITECT, ARCHITECTURALARCH
BACK FLOW PREVENTERBFP
BELOWBLW
CAST IRON PIPINGC.I.CEILINGCLG
COLUMNCOL
CONCRETECONC
CONSTRUCT, CONSTRUCTIONCONSTCOORDINATECOOR
DOWNDN
DISHWASHERDW
EXISTING(E)EACHEA
ELECTRICAL CONTRACTOREC
ELECTRIC, ELECTRICALELEC
ELEVATIONELEVFLOORFLR
GENERAL CONTRACTORGC
GALLONS PER MINUTEGPM
INVERT ELEVATIONIEINDIRECT WASTEIW
MAXIMUMMAX
MECHANICAL CONTRACTORMC
MINIMUMMINNEW(N)
NORMALLY CLOSEDNC
NORMALLY OPENNO
NOT TO SCALENTSOUTSIDE AIROA
POINT OF CONNECTIONP.O.C.
PRESSURE REDUCING VALVEPRV
POLYVINYL CHLORIDE PIPINGPVCRETURN AIRRA
SUPPLY AIRSA
SIMILARSIM
STAINLESS STEELSSTEMPERATURE CONTROLTCC
TYPICALTYP
DESCRIPTIONSYMBOL
GENERAL
CONNECT NEW TO EXISTING
REFERENCE BUBBLE
REVISION NUMBER
SECTION OR ELEVATION BUBBLE
DRAWING NOTE
DEMOLITION NOTE
* SECTION NUMBER# SHEET NUMBER#
*
#
#*
* SECTION OR ELEVATION LETTER
*#
ISOMETRIC OR ELEVATION BUBBLE
# REFERENCE DRAWING NUMBER
* ISOMETRIC OR ELEVATION LETTER# REFERENCE DRAWING NUMBER
#
#
DEMOLITION NOTE, ALTERNATEX
DRAWING NOTE, ALTERNATE#
NOTES:
1. REFER TO PROJECT SPECIFICATIONS FOR ADDITIONAL INSULATION REQUIREMENTS.
2. (ASTM E84) ALL INSULATION MATERIALS INSTALLED WITHIN THE PLENUM SHALL MEET THE FLAME/SMOKE REQUIREMENTS OF 25/50.
REMARKS:
1. FOR PIPING SMALLER THAT 1-1/2" INSTALLED WITHIN A BUILDING PARTITION WITHIN A CONDITIONED SPACE WITHIN A CONDITIONED SPACE. INSULATION
REDUCTION OF UP TO 1" BUT NOT LESS THAN 1" PER IECC TABLE C403.2.1, NOTE A.
DOMESTIC
COLD WATER
DOMESTIC
COLD WATER
DOMESTIC
COLD WATER
DOMESTIC
HOT WATER & RECIRC.
DOMESTIC
HOT WATER & RECIRC.
DOMESTIC
HOT WATER & RECIRC.
DOMESTIC
HOT WATER & RECIRC.
DOMESTIC
HOT WATER & RECIRC.
DOMESTIC
HOT WATER & RECIRC.
STORM & OVERFLOW
DRAINAGE
ROOF & OVERFLOW
DRAIN BOWLS
CONDENSATE
DRAINAGE
CONDENSATE DRAINAGE
WITH HEAT TRACING
INTERIOR
INTERIOR
(WITHIN PARTITION)
EXTERIOR
INTERIOR
INTERIOR
(WITHIN PARTITION)
EXTERIOR
INTERIOR
INTERIOR
(WITHIN PARTITION)
EXTERIOR
INTERIOR
INTERIOR
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
WITH ASJ-SSL
GLASS FIBER
GLASS FIBER
FLEXIBLE
ELASTOMERIC
YES
YES
YES
NONE
NONE
NONE
NONE
NONE
NONE
YES
YES
NONE
NONE
NONE
NONE
ALUMINUM
NONE
NONE
ALUMINUM
NONE
NONE
ALUMINUM
PVC
NONE
ALUMINUM
NONE
40 - 60
120 - 140
180
180
180
NA
NA
NA
NA
0.21 - 0.27 75
0.21 - 0.27 75
0.21 - 0.27 75
0.21 - 0.28 100
0.21 - 0.28 100
0.21 - 0.28 100
0.25 - 0.29 125
0.25 - 0.29 125
0.25 - 0.29 125
0.21 - 0.27 75
0.21 - 0.27 75
0.21 - 0.27 75
0.21 - 0.27 75
0.5 1 1 1 -
0.5 1 1 1 1
0.5 1 1 1 -
1 1.5 1.5 1.5 -
1 1.5 1.5 1.5 1
1 1.5 1.5 1.5 -
1.5 2 2 2 -
1 2 2 2 1
1.5 2 2 2 -
1 1 1 1 -
1 1 1 1 -
0.5 0.5 0.5 0.5 -
0.5 0.5 0.5 0.5 -
0.5
0.5
0.5
1
1
1
1.5
1
1.5
1
1
0.5
0.5
INTERIOR
INTERIORFLEXIBLE
ELASTOMERIC
40 - 60
40 - 60
120 - 140
120 - 140
SERVICE
INSULATION CONDUCTIVITY
CONDUCTIVITY BTU * IN / (H * FT * °F )
LOCATIONINSULATION
MATERIAL
VAPOR
BARRIERJACKET
OPERATING
TEMPERATURE( ° F )
MEAN TEMP RATING ( ° F )
NOMINAL PIPE SIZE (IN)REMARKS
< 1 1 TO < 1-1/2 1-1/2 TO < 4 4 TO < 8 ≤ 8
PIPE INSULATION SCHEDULE
F
P
PLUMBING LEGENDALL SYMBOLS MAY NOT BE USED
DESCRIPTIONSYMBOL
NOTE:
1. COORDINATE AND SCHEDULE WITH GAS SERVICE AND METER PROVIDER PRIOR TO COMMENCING WORK. MEDIUM PRESSURE GAS (2PSI) REQUIRED
FROM THE METER TO THE BUILDING. CONTACT XCEL BUILDERS CALL LINE @ 1.800.628.2121 PRIOR TO COMMENCING WORK.
2. GAS PIPE SIZING BASED UPON 70 LINEAR FEET OF GAS PIPING, LOW PRESSURE GAS (2PSI) AT 831 BTU/CF.
CONNECTED GAS LOAD SCHEDULE
1 B-1 2,500,000 2,500,000 2PSI/7"W.C. MECHANICAL ROOM -
9,162,000TOTAL CONNECTED LOAD
NO OF UNITS EQUIPMENT LOAD EACH (BTU/H) TOTAL LOADPRESSURE REQUIRED
MIN. / MAX.LOCATION REMARKS
1 B-2 -
1 B-3 -
1 MAU-1 170,000 170,000 14"W.C./7"W.C. ROOF -
1 GWH-1 800,000 800,000 -
1 GWH-2 300,000 300,000 -
2 OVENS 160,000 320,000 10.5"W.C./7"W.C. KITCHEN -
12 TURRETS 6,000 72,000 7"W.C. SCIENCE ROOMS -
2,500,000 2,500,000
2,500,000 2,500,000
MECHANICAL ROOM
MECHANICAL ROOM
MECHANICAL ROOM
MECHANICAL ROOM
2PSI/7"W.C.
2PSI/7"W.C.
14"W.C./7"W.C.
14"W.C./7"W.C.
STORM DRAIN, RAINWATER DRAINSD
OVERFLOW STORM DRAINOSD
SUBSOIL DRAIN, FOOTING DRAINSSDSOIL, WASTE, OR SANITARY SEWERSAN
STORM / RAINWATER DRAIN BELOW FLOORSD
SOIL / WASTE / SANITARY SEWER BELOW FLRSAN
GREASE DRAINGDVENT
ACID WASTEAW
ACID VENTAV
INDIRECT DRAINDPUMP DISCHARGE LINEPD
COLD WATER
HOT WATER SUPPLY (140° F)
HOT WATER RECIRCULATING (140° F)TEMPERED HOT WATER (110° F)TW
TEMPERED HW RECIRCULATING (110° F)TWR
(CHILLED) DRINKING WATER SUPPLYDWS
(CHILLED) DRINKING WATER RECIRCULATINGDWRSOFT WATERSW
CONDENSATE DRAINCD
DISTILLED DRAINDI
DEIONIZED WATERDELAWN SPRINKLER SUPPLYLS
FIRE PROTECTION WATER SUPPLYF
GAS, LOW-PRESSUREG
GAS, MEDIUM-PRESSUREMGGAS, HIGH-PRESSUREHG
GAS VENTGV
IRRIGATION WATERIR
ISOLATION VALVE
GLOBE VALVE
ANGLE VALVE
BALL VALVE
BUTTERFLY VALVE
GAS COCK, GAS STOP
COMBINATION FLOW MEASURINGDEVICE AND BALANCING VALVE
CHECK VALVE
PLUG VALVE
SOLENOID VALVE
S
MOTOR-OPERATED VALVE [SPECIFY TYPE]
M
PRESSURE REDUCING VALVE
PRESSURE-RELIEF VALVEP
TEMPERATURE-PRESSURE-RELIEF VALVET
HOSE BIBB
VALVE IN YARD BOX (VALVE TYPE SYMBOLAS REQUIRED FOR VALVE USE)
RECESSED-BOX HOSE BIBB ORWALL HYDRANT
UNION (SCREWED)
UNION (FLANGED)
STRAINER
PIPE ANCHOR
PIPE GUIDE
EXPANSION JOINT
FLEXIBLE CONNECTOR
TEE
CONCENTRIC REDUCER
ECCENTRIC REDUCER
AQUASTAT
FLOW SWITCH
PRESSURE SWITCH
WATER HAMMER ARRESTER
PRESSURE GAUGE WITH GAUGE COCK
THERMOMETER
VALVE IN RISER
RISER DOWN (ELBOW)
RISER UP (ELBOW)AIR CHAMBER
RISE OR DROP
BRANCH-TOP CONNECTIONBRANCH-BOTTOM CONNECTION
BRANCH-SIDE CONNECTION
CAP ON END OF PIPE
CLEANOUT PLUG
CIRCULATION PUMP
FLOOR CLEANOUT
WALL CLEANOUT
YARD CLEANOUT OR CLEANOUT TO GRADE
FLOOR DRAIN
FLOOR SINK
CONDUCTOR NOZZLE
DIRECTION OF FLOW
INDICATES PIPE SLOPE DOWN
NEW TO EXISTING CONNECTION
INDICATES ITEMS TO BE REMOVED
GAS TURRET
M
4"
TO GASTURRETS( 72 MBH)
1-1/4"
OVEN (160 MBH)
OVEN (160 MBH)
1-1/4"
1-1/4"
MAU-1 170 MBH
1-1/4"
GWH-1 (800 MBH)
B-1 (2500 MBH)
B-2 (2500 MBH)
B-3 (2500 MBH)
GWH-2 (300 MBH)
METER BY OTHERS
GPR-2GPR-1
1-1/2"
GAS DIAGRAM
1-1/2"
2-1/2"
4"
4"
5"
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:0
1 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-001
PLUMBING CODESHEET, LEGENDS ANDNOTES
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JJR
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
05.25.2016
SAN
4"
SAN
I.E.=96'-2"
5' - 0
"
I.E.=96'-2"
I.E.=96'-2"
5' - 0
"
6"
6"
6"
I.E.=96'-2"
5' -
0"
6"
SD
SD
SD
SD
I.E.=96'-2"
SD5' - 0"
I.E.=96'-2"
SD
8"
SAN SAN SAN SAN
?
3
F
9
7n
A
10n
4.9 8
EE
DD
CC
BB
4 5
I.E.=91'-6"
5' - 0"
SAN
SA
N
SA
N SA
N
SA
N
SAN
SAN
2
7
4
22
1
4
2
2
2"
2"
2"
2"
4"2"
4"
4"4"4"
2"
4"2"
4"
4"
4"
2"
2"
2"
4"
4"
2"
4"
4"
4"
2"
4"
2"4"
4"
4"
2"
4"
4"
4"
4"
4"
4"
2"
4"4"4"
4"
4" 4"
4"
2"
4"
2"
2"
1
2"
6"
10
1
22
3
8
6
8
3
7
5
4
3
11
12
8
4
34
7
7
4
3
8
5
3
121
21
11
11
8
4
3 4
5
7
7
2
8
3
4
9
10
2
10
11
2
12
11
7
7
3
8
3 5
2
4
3
8
4
78
3
7
88
4
7
4
3
3
5
5
3
2
5
RE:MATCHLINE
MATCHLINE
P-110B
RE:MATCHLINE
MATCHLINE
P-110B
92
2"
4"
2
2"
10
10
SUMP PUMP
I.E.=96'-4"
16
16
16
16
16
16
15
14
(SP-2)
100'-0"FINISHED FLOOR ELEVATION
6139.00' USGS100'-0"
FINISHED FLOOR ELEVATION
6139.00' USGS
I.E.=96'-2"
13 SD
3"
2"
2"
2
2
2
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" SANITARY UP TO FLOOR ABOVE.
2. 2" SANITARY UP TO SINK ABOVE.
3. 2" VENT UP TO FLOOR ABOVE.
4. 4" SANITARY UP TO WALL CLEANOUT.
5. 2" SANITARY UP TO LAVS.
6. 2" SANITARY UP TO EWC.
7. 2" SANITARY UP TO FLOOR DRAIN.
8. 4" SANITARY UP TO WATER CLOSET.
9. 4" SANITARY UP TO FLOOR ABOVE.
10. 4" SANITARY UP TO FLOOR CLEAN OUT.
11. 6" STORM DRAIN UP TO FLOOR ABOVE.
12. 8" STORM DRAIN UP TO FLOOR ABOVE.
13. 3" STORM DRAIN UP TO FLOOR ABOVE.
14. 2" SUMP PUMP DISCHARGE RISE UP TO FLOOR ABOVE.
15. 4" SANITARY RISE UP FOR TWO WAY GRADE CLEANOUT.
16. 4" STORM RISE UP TO GRADE CLEANOUT.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:0
3 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-110A
PLUMBINGUNDERGROUND -AREA A
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1UNDERGROUND PLUMBING PLAN - AREA A
05.25.2016
SAN
5' - 0"
4"
I.E.=93'-8"
5' - 0"
I.E.=93'-4"
I.E.=96'-2"
SD
4"
5' - 0"
I.E.=96'-2"
SD
6"
I.E.=96'-2"
SD
I.E.=96'-2"
SD
4"
I.E.=96'-2"
SD
4"
I.E.=96'-2"
SD6"
SD
I.E.=96'-2"
6"
3
F
G
H
J
K
L
94.9 8
M
4
7
SANSANSANSAN
SAN SAN
SA
N
SA
N
SA
N
SA
N
SAN
SA
N
SA
N
SA
N
SA
N
SA
N
2
2
2
2
6
22
5
14
5
8
2
1
7
2
5
8
1
5
2
4"
2"
2"
4"
4"
2" 2"
4"
4"
2"
2"
4"
2
6
4"
4"
2"
2"
4"
2"
4"
2"
2"
2"4"
2"
4"
2"
4"
4"4"
2"
4"
4"
2"
4"
3"
4"
4"4"
2"
4"
2"
2"
2"
4"
10
22
5
5
5
4
5
84
14
8
4
5
5
5
4
8
8
8
1
1
5
5
5
5
3
8 8
8
8
8
5
5
5
5
14
1411
11
13
1311
1311
RE:MATCHLINE
MATCHLINE
P-110A
RE:MATCHLINE
MATCHLINE
P-110C
RE:
MATCHLINE
MATCHLINE
P-110C
FUTUREEXPANSION
RE:MATCHLINE
MATCHLINE
P-110A
7
7
3"
4"
2
7
7
I.E.=95.33'
15
2"
3
6"
2"
2"
100'-0"FINISHED FLOOR ELEVATION
6139.00' USGS
100'-0"FINISHED FLOOR ELEVATION
6139.00' USGS
19
18
17
17
17
17 17
1717
77
2
2
9
3
4
3
8
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" SANITARY UP TO FLOOR ABOVE.
2. 2" SANITARY UP TO SINK ABOVE.
3. 2" VENT UP TO FLOOR ABOVE.
4. 4" SANITARY UP TO WALL CLEANOUT.
5. 2" SANITARY UP TO LAVS.
6. 2" SANITARY UP TO EWC.
7. 2" SANITARY UP TO FLOOR DRAIN.
8. 4" SANITARY UP TO WATER CLOSET.
9. 4" SANITARY UP TO FLOOR ABOVE.
10. 4" SANITARY UP TO FLOOR CLEAN OUT.
11. 6" STORM DRAIN UP TO FLOOR ABOVE.
12. 8" STORM DRAIN UP TO FLOOR ABOVE.
13. 4" STORM DRAIN UP TO FLOOR ABOVE
14. 2" SANITARY UP TO URINAL ABOVE.
15. 4" SANITARY RISE TO GRADE CLEAN OUT, PLUGFOR FUTURE EXTENSION.
16. 2" SANITARY UP TO FLOOR CLEAN OUT.
17. 4" STORM RISE UP TO GRADE CLEANOUT.
18. 4" SANITARY RISE UP TO TWO WAY GRADE CLEANOUT.
19. 2" SANITARY UP TO MSB.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:0
4 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-110B
PLUMBINGUNDERGROUND -AREA B
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/8" = 1'-0"A1UNDERGROUND PLUMBING PLAN - AREA B
0
PROJECTNORTH
2' 4' 8' 16'
05.25.2016
SAN SAN
GD
GD
GD
3"
3"
6"
F
SA
NS
AN
SA
N
SAN
6"
4"
6"
4"
PRECAST CONCRETEGREASE INTERCEPTOR2500 GALLON CAPACITY
5' -
0"
I.E.=94'-7"
I.E.=95'-8"
I.E.=95'-6"
5' -
0"
I.E.=96'-2"
SD
6"
I.E.=96'-2"
SD
5' -
0"
I.E.=96'-2"
6"
31
N
M
P
Q
4 7
6
10
3
25
23
26
6"
4"
2"
3"
4"
2"
2"
4"
2"
6"
4"
4"
4"
4"
2"
3"
2"
2"
RE:
MATCHLINEMATCHLINE
P-110B
25
3
23
25
4
3
23
24
3
23
10
2
8
7
3
16
2
15
2
2"
5
7
10
12
3
8
7
7
12
11
10
P-530
10
P-530
10
P-530
6"
6"21
21
22
8
5
3
16
8
7
7
7
5
8
4
4"
2"
2" 4"
4"
2"
2"
316
8"
19
20
17
23
23
23
35
10
10
23
2"
2"
2"
2"
SAN
SA
N
23
25
23
25
3
3
3
233
27
27
23
28
5' -
0"
SD
3"
29
4"
2" 2"
18
16
P-530
6"
100'-0"FINISHED FLOOR ELEVATION
6141.17' USGS
100'-0"FINISHED FLOOR ELEVATION
6139.00' USGS
6
631
30
30
30
30
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" SANITARY UP TO SHOWER ABOVE.
2. 3" SANITARY UP TO FLOOR SINK ABOVE.
3. 2" VENT UP TO FLOOR ABOVE.
4. 4" SANITARY UP TO WALL CLEANOUT.
5. 2" SANITARY UP TO LAVS.
6. 2" SANITARY UP TO EWC.
7. 2" SANITARY UP TO FLOOR DRAIN.
8. 4" SANITARY UP TO WATER CLOSET.
9. 4" SANITARY UP TO FLOOR ABOVE.
10. 4" SANITARY UP TO FLOOR CLEAN OUT.
11. 6" STORM DRAIN UP TO FLOOR ABOVE.
12. 8" STORM DRAIN UP TO FLOOR ABOVE.
13. 4" STORM DRAIN UP TO FLOOR ABOVE
14. 2" SANITARY UP TO URINAL ABOVE.
15. 3" VERTICAL DRY VENT UP TO ABOVE FLOOR.
16. 2" SANITARY UP TO MSB.
17. 4" METERED COLD WATER SERVICE, 3" IRRIGATION SUPPLY AND 6" FIRE SERVICE, ENTERBUILDING BELOW GRADE, RE: SITE UTILITY AND IRRIGATION PLANS FOR CONTINUATION.
18. 4" CW UP TO ABOVE FLOOR, SEE PLAN B1 ON P-410 FOR CONTINUATION.
19. 3" IR UP TO ABOVE FLOOR, SEE PLAN B1 ON P-410 FOR CONTINUATION.
20. 6" FIRE SERVICE UP TO ABOVE FLOOR. SEE FIRE SPRINKLER PLANS FOR CONTINUATION.
21. 3" V UP IN WALL ABOVE.
22. (2) 4" SAN RISERS UP TO 2-WAY GRADE CLEANOUT ABOVE.
23. 2" SANITARY UP TO FLOOR SINK.
24. 2" SANITARY UP TO DISPOSAL.
25. 2" SANITARY UP TO HAND SINK.
26. 2" SANITARY DN. TO 6" SANITARY.
27. 2" SANITARY DN. TO 4" SANITARY.
28. 2" SANITARY UP TO WASHER WALL BOX.
29. 3" STORM DRAIN UP TO FLOOR ABOVE.
30. 4" STORM RISE UP TO GRADE CLEANOUT.
31. 2" SANITARY UP TO SINK ABOVE.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:0
6 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-110C
PLUMBINGUNDERGROUND -AREA C
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1UNDERGROUND PLUMBING PLAN - AREA C
05.25.2016
REF.
DW
R.
FD
FD
FD
FD
FD
FD
FD
P-410
A2
P-411
B2
EWC-2
4"
WH-1
WH-1
2 1/2"
1 1/2"2 1/2"1 1/2"
3"
3"
OD
SD
8"
WH-1
P-410
B2
P-410
A4
S-1 W/TMV-2
P-411
B4
S-1S-1
S-1
S-1 W/TMV-2
S-1 W/TMV-2
EWC-1
S-1
S-1
S-1
S-1
3/4"
WH-1
FCO-1
4" FCO-1
3/4"
3/4"
1"
2"
KINDERGARTEN
106
STAIR
ST.C
KINDERGARTEN
107
CIRC.
100B
T.
108A
T.
107A
ST.
107B
KINDERGARTEN
108
KINDERGARTEN
105
T.
106A
T.
105A
BREAKOUT
100B.2
PRE-K
110
FLEX
104
T.
103A
ST.
103B
T.
104A
T.
110A
ST.
110B
PRE-K
111
BREAKOUT
100C.1
RES. RM.
112
CIRC.
100C
MULTI-PURPOSE
103
ELEM.READING
102E
LMC
102
SEM.
102D
ST.
102CSEM.
102B
OFF.
102A
VEST.
100
ADMIN.
101
OFFICE
101R
OFFICE
101Q
OFFICE
101N
OFFICE
101M
PRIN. OFFICE
101K
CONF.
101J
STOR.
101H
LOUNGE
101G
WORK ROOM
101L
101L.1
CLINIC
101B
CLINIC T.
101C
T.
101D
T.
101E
IDF
101F
ELEC.
113
WK. RM.
114
CONF.
101P
CIRC.
101.2
CIRC.
101.1
M.S. ART
146
S-1
WCB-1
1
P-510
2
P-510
3
P-510
4
P-510
3
F
9
7n
A
10n
4.9 8
EE
DD
CC
BB
4 5
22
1
1/2"1/2"
3/4"3/4"
1/2"1/2"
3/4"3/4"3/4"
3"2"
1"3/4"3/4"3/4"
1 1/2"1 1/4"
3/4"
1/2"1/2"
2 1/2"1 1/2"
1"1"
3"
2"
1"
3"2"1"
2"
1 1/2"
S-2
12
S-2
2 1/2"
2"
2"1"
3/4"
3/4"3/4"3/4"
4"
2 1/2"2"
3/4"3/4"3/4"
IMB-1
DW-1
1"3/4"2"
2"
1 1/4"
3/4"
RE:MATCHLINE
MATCHLINE
P-111B
RE:MATCHLINE
MATCHLINE
P-111B
2
1
12
5
1
3/4"
1
2
1
1
1
22
2
1
1
1
5
1 1
1
1
10
9
11
3
8
2
4"
2
15
14
2
2"
2"
2
GG
G
16
3/4"
3/4" 3/4"
1 1/4"
1"
3/4"
OD
4" FCO-1
4" FCO-1
2"
1"
2"
SD
WH-1CN-1
CN-1
CN-1CN-1
CN-1 CN-1
S-2
S-1 W/TMV-2
S-1 W/TMV-2
S-1 W/TMV-2
4" GCO-2
4" GCO-1
4" GCO-1
4" GCO-1
4" GCO-1
4" GCO-1
4" GCO-1
CN-1
4" GCO-1
18
19
20
21
3"
3"
21
3/4"
3/4"3/4"3/4"
4"
2"4"
4"
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" VENT, 1/2" CW & HW DROP TO SINK.
2. 2" SANITARY, 1/2" CW & HW UP TO SINK ABOVE.
3. 2" VENT & 1/2" CW DROP TO EWC.
4. 2" VENT & 1/2" CW DROP TO DF.
5. 3/4" CW DN TO WALL HYDRANT.
6. 4" SD & 4" OD RISE TO RD-1 & OD-1.
7. 6" SD & 6" OD RISE TO RD-1 & OD-1.
8. 4" SANITARY DOWN IN WALL.
9. 4" SANITARY RISE UP TO FLOOR ABOVE.
10. 1" HW RISE UP TO FLOOR ABOVE.
11. 2" CW AND 3/4 HWC RISE UP TO FLOOR ABOVE.
12. 8" SD & 8" OD RISE UP TO RD-1 & OD-1.
13. 2" VENT RISE UP TO FLOOR ABOVE.
14. 6" STORM DOWN IN CHASE.
15. 2" SANITARY DOWN IN CHASE.
16. GAS PIPING TO EXTEND TO SECOND FLOOR SCIENCE ROOM GAS TURRETS.
17. 4" STORM DOWN.
18. 3/4" CW ROUTED UNDER STRUCTURAL BEAM.
19. 2" SUMP PUMP DISCHARGE RISE FROM ELEVATOR SUMP PUMP.
20. 2" SUMP PUMP DISCHARGE UP TO DISCHARGE INTO MOP BASIN ON FLOOR ABOVE.
21. 2" SANITARY UP TO FLOOR DRAIN ABOVE.
22. 3" SD AND 3" OD RISE TO 3" RD-1 & 3" OD-1.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:1
1 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-111A
PLUMBING FIRSTFLOOR - AREA A
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1FIRST FLOOR PLUMBING PLAN - AREA A
05.25.2016
FD
FD
FD
P-410
D1
P-410
B1
FCO-1
WH-1
WH-1
WH-1
P-410
D2
S-4SI-1
SI-1S-4
EWC-2
S-1 W/TMV-2
S-1 W/TMV-2
FCO-1
3
2
1
1
2
1
2
1
2
1
2
2
1
2
1
4
EWC-3
S-1
2"1"3/4"
2"1 1/4"1"
2"2 1/2"4"
3/4"3/4"
1/2"
1/2"1/2"1/2"
3/4"3/4"1/2" 2"
2"2 1/2"4"
2 1/2"4"
2 1/2"4"
3/4"3/4"
3/4"3/4"
3/4"3/4"
3/4"3/4"
3/4"3/4"
3/4"
3/4"
3/4"
3/4"
1" 3/4"
3/4"3/4"
3/4"3/4"
3/4"
3/4"3/4"3/4"
3/4"
4"2 1/2"
4"2 1/2"
2
STAIR
ST.D
CLASSROOM
120
CIRC.
100D
CLASSROOM
121
CLASSROOM
122
IDF
100D.1
CLASSROOM
119
BREAKOUT
100D.2
CLASSROOM
118
CLASSROOM
123
CLASSROOM
124
CLASSROOM
117
CIRC.
100C
J.
115
WK. RM.
114
M.S. ART
146
KILN
145B
ART ST.
145A
E.S. ART
145
SPED/FLEX
127
M.S. MUSIC
144
BREAKOUT
100C.2
PR.
144D
PR.
144C
PR.
144B
ST.
144A
VEST.
100C.4
3
F
G
H
J
K
L
94.9 8
M
4
FUTUREEXPANSION
2"2 1/2"
1/2"
FCO-1
17
1417
14
14
6
7
2"
1 1/2"3/4"
1"
1"3/4"
2 1/2"
RE:MATCHLINE
MATCHLINE
P-111A
RE:MATCHLINE
MATCHLINE
P-111A
RE:MATCHLINE
MATCHLINE
P-111C
RE:
MATCHLINE
MATCHLINE
P-111C
S-1 W/TMV-2
S-1 W/TMV-2
S-1 W/TMV-2
S-1 W/TMV-2
S-1 W/TMV-2
S-1 W/TMV-2
S-1 W/TMV-2
SI-2
S-1 W/TMV-2
SI-2
S-1 W/TMV-2
SI-2
S-1 W/TMV-2
SI-2
CN-1
CN-1 CN-1
3/4"1/2"
3/4"
3/4"
CN-1
CN-1 CN-1
PT-1
TD-1
CN-1
4" GCO-1 4" GCO-1
4" GCO-14" GCO-1
4" GCO-1
4" GCO-1
4" GCO-1
1"
1"
1"
1"
1"1"
1"
G
GG
GG
23
BUILDINGEXPANSION JOINTRE: ARCH
ES-1
ES-1
23
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" VENT, 1/2" CW & HW DROP TO SINK.
2. 2" SANITARY, 1/2" CW & HW UP TO SINK ABOVE.
3. 2" VENT & 1/2" CW DROP TO EWC.
4. 2" VENT & 1/2" CW DROP TO DF.
5. 3/4" CW DN TO WALL HYDRANT.
6. 4" SD & 4" OD RISE TO RD-1 & OD-1.
7. 6" SD & 6" OD RISE TO RD-1 & OD-1.
8. 4" SANITARY DOWN IN WALL.
9. 4" SANITARY RISE UP TO FLOOR ABOVE.
10. 1" HW RISE UP TO FLOOR ABOVE.
11. 2" CW AND 3/4 HWC RISE UP TO FLOOR ABOVE.
12. 8" SD & 8" OD RISE UP TO RD-1 & OD-1.
13. 2" VENT RISE UP TO FLOOR ABOVE.
14. 6" STORM DOWN IN CHASE.
15. 2" SANITARY DOWN IN CHASE.
16. GAS PIPING TO EXTEND TO SECOND FLOOR SCIENCE ROOM GAS TURRETS.
17. 4" STORM DOWN.
18. 3/4" CW ROUTED UNDER STRUCTURAL BEAM.
19. 2" SUMP PUMP DISCHARGE RISE FROM ELEVATOR SUMP PUMP.
20. 2" SUMP PUMP DISCHARGE UP TO DISCHARGE INTO MOP BASIN ON FLOOR ABOVE.
21. 2" SANITARY UP TO FLOOR DRAIN ABOVE.
22. 3" SD AND 3" OD RISE TO 3" RD-1 & 3" OD-1.
A
B
C
23. PROVIDE EXPANSION LOOP FOR CW, HW, HWC, AND GAS AT EXPANSION JOINT TO ALLOWSETTLING.
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:1
5 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-111B
PLUMBING FIRSTFLOOR- AREA B
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/8" = 1'-0"A1FIRST FLOOR PLUMBING PLAN - AREA B
0
PROJECTNORTH
2' 4' 8' 16'
05.25.2016
DN3084
Trash
Trash
Trash
2472
2472
2472
2472
2442
2472
2472
2472
2472
2460 2460
2472
2472
2442
2442
2472
3072
3072
3072
2460
3060
2448
2448
24362436
3048
P-410
A1
P-410
B3
WH-1
EWC-1
EXT. EQ. ST.
138
VEST.
136B
LOCKER ROOM
136C
OUT. EQ. ST.
139
FM. OFFICE
140BVEST.
140C
ELEC.
141D
DRY ST.
141F
FM REC.
142A
FM. ST.
142
COMMONS
140
E.S. MUSIC/STAGE
143
1519 SF
IDF
140D
T.
141A.1
FM T. / LR
140B.1
TABLE STOR.
140A
OFFICE
136D
SHOWER
136D.1
LOCKER ROOM
136E
JANITOR
136E.2
EQUIP. STOR.
136F
MULTIPURPOSE
137
GYM
136
VEST.
136A
CIRC.
100C
31
N
M
P
Q
4 7
WH-1
P-412
C4
P-412
D4
4"2 1/2"
1/2"
P-412
C1
RE:MATCHLINE
MATCHLINE
P-111B
RE:
MATCHLINE
MATCHLINE
P-111B
FUTUREEXPANSION
EWC-1
EWC-3
DF-1
G
GG
G
GG
CN-1 CN-1
CN-1
4"2 1/2"
2"
7
1"
2"
4"
2 1/2"
1 1/2" 3/4"3/4" 1/2"
2"
1"
3/4"
4" GCO-1
4" GCO-14" GCO-1
4" GCO-1
2"
1/2"
3/4"
3/4"3/4"3/4"
1/2"
3/4"3/4"3/4"
1/2"
1/2"
2"
2"
2"
22
3"
3"
12
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" VENT, 1/2" CW & HW DROP TO SINK.
2. 2" SANITARY, 1/2" CW & HW UP TO SINK ABOVE.
3. 2" VENT & 1/2" CW DROP TO EWC.
4. 2" VENT & 1/2" CW DROP TO DF.
5. 3/4" CW DN TO WALL HYDRANT.
6. 4" SD & 4" OD RISE TO RD-1 & OD-1.
7. 6" SD & 6" OD RISE TO RD-1 & OD-1.
8. 4" SANITARY DOWN IN WALL.
9. 4" SANITARY RISE UP TO FLOOR ABOVE.
10. 1" HW RISE UP TO FLOOR ABOVE.
11. 2" CW AND 3/4 HWC RISE UP TO FLOOR ABOVE.
12. 8" SD & 8" OD RISE UP TO RD-1 & OD-1.
13. 2" VENT RISE UP TO FLOOR ABOVE.
14. 6" STORM DOWN IN CHASE.
15. 2" SANITARY DOWN IN CHASE.
16. GAS PIPING TO EXTEND TO SECOND FLOOR SCIENCE ROOM GAS TURRETS.
17. 4" STORM DOWN.
18. 3/4" CW ROUTED UNDER STRUCTURAL BEAM.
19. 2" SUMP PUMP DISCHARGE RISE FROM ELEVATOR SUMP PUMP.
20. 2" SUMP PUMP DISCHARGE UP TO DISCHARGE INTO MOP BASIN ON FLOOR ABOVE.
21. 2" SANITARY UP TO FLOOR DRAIN ABOVE.
22. 3" SD AND 3" OD RISE TO 3" RD-1 & 3" OD-1.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:1
8 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-111C
PLUMBING FIRSTFLOOR - AREA C
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1FIRST FLOOR PLUMBING PLAN - AREA C
05.25.2016
R.
DW
P-411
D1
S-3
S-3
S-3S-3
S-3S-3S-3S-3S-3
S-3
P-411
A1
3
F
9
7n
A
10n
4.9 8
EE
DD
CC
BB
4 5
RE:MATCHLINE
MATCHLINE
P-112B
RE:MATCHLINE
MATCHLINE
P-112B
3
5
5
5
5
111
3
1. PROVIDE (1) DUAL GT-1 & AT-1 AT EACH WORKSTATION.
2. PROVIDE (1) ANT-1 AT EACH SINK.
3. PROVIDE GAS VALVE AND GAS CONTROLS STATION FOR EACH ROOM.
4. EXTEND 2" G TO BOILER ROOM, TO SERVE ALL THREE CLASSROOMS
1. PROVIDE (1) DUAL GT-1 & AT-1 AT EACH WORKSTATION.
2. PROVIDE (1) ANT-1 AT EACH SINK.
3. PROVIDE GAS VALVE AND GAS CONTROLS STATION FOR EACH ROOM.
4. EXTEND 2" G TO BOILER ROOM, TO SERVE ALL THREE CLASSROOMS
1. PROVIDE (1) DUAL GT-1 & AT-1 AT EACH WORKSTATION.
2. PROVIDE (1) ANT-1 AT EACH SINK.
3. PROVIDE GAS VALVE AND GAS CONTROLS STATION FOR EACH ROOM.
4. EXTEND 2" G TO BOILER ROOM, TO SERVE ALL THREE CLASSROOMS
S-3 W/TMV-2
S-3 W/TMV-2
S-3 W/TMV-2
S-3 W/TMV-2
CLASSROOM
206
STAIR
ST.C
CLASSROOM
207
CIRC.
200B
CLASSROOM
208
CLASSROOM
205
ST.
200B.3
RES. RM.
209
IDF
200B.1
BREAKOUT
200B.2
CLASSROOM
210
SCIENCE
204
CLASSROOM
211
ST.
204A
ST.
203A
?
?
SCIENCE
203
ELEV.
VV
T.
213
T.
212
ELEC
249
J.
248
T.
247
WORK ROOM
246
SCIENCE
214
MDF
245
SCI. ST.
244
BREAK- OUT
D
CIRC.
200A
WORK RM.
200B.2
READINGROOM
202E
CSE-1
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" VENT RISE, 1/2" CW & HW DOWN TO FLOOR BELOW.
2. 2" VENT RISE & 1/2" CW DOWN TO FLOOR BELOW.
3. 2" VENT RISE UP FROM FLOOR BELOW.
4. 4" ROOF DRAIN DOWN.
5. 6" ROOF DRAIN DOWN.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:2
3 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-112A
PLUMBING SECONDFLOOR - AREA A
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1SECOND FLOOR PLUMBING PLAN - AREA A
05.25.2016
P-411
D2
P-411
D4
P-411
B1
1
EWC-2
2
EWC-1 2
S-3 W/TMV-2
3
F
G
H
J
K
L
94.9 8
M
4
7
4
54
5
5
RE:MATCHLINE
MATCHLINE
P-112A
RE:MATCHLINE
MATCHLINE
P-112A
FUTURE EXPANSION
S-1 W/TMV-2
S-3 W/TMV-2
S-3 W/TMV-2
CLASSROOM
220
CLASSROOM
221
STAIR
ST.D
STAIR
ST.D
CLASSROOM
222
IDF
200D.1
CLASSROOM
219
BREAK OUT
200D.2CLASSROOM
223
CLASSROOM
218
CLASSROOM
217
?
?
CIRC.
200D
T.
216
SCIENCE
214
BREAK- OUT
D
SCI. ST.
244
CIRC.
200A
T.
225
FLEX
227
ELEC
243
IDF
242
ST.
241
WK. RM.
240
ST.
228
J.
239
T.
238
ST.
237
BREAKOUT
D
CIRC.
140E
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 2" VENT RISE, 1/2" CW & HW DOWN TO FLOOR BELOW.
2. 2" VENT RISE & 1/2" CW DOWN TO FLOOR BELOW.
3. 2" VENT RISE UP FROM FLOOR BELOW.
4. 4" ROOF DRAIN DOWN.
5. 6" ROOF DRAIN DOWN.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:2
6 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-112B
PLUMBING SECONDFLOOR - AREA B
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/8" = 1'-0"A1SECOND FLOOR PLUMBING PLAN - AREA B
0
PROJECTNORTH
2' 4' 8' 16'
05.25.2016
3
F
9
7n
A
10n
4.9 8
EE
DD
CC
BB
4 5
8" RD-17,616 SQ. FT.
6" RD-1 3,402 SQ. FT.
6" RD-1 3,674 SQ. FT.
6" RD-1 3,520 SQ. FT.
3" RD-11,096 SQ. FT.
6" RD-13,171 SQ. FT.
6" RD-13,281 SQ. FT.
RE:MATCHLINE
MATCHLINE
P-131B
RE:MATCHLINE
MATCHLINE
P-131B
3" VTR
3" VTR
6" OD-1 3,520 SQ. FT.
6" OD-13,171 SQ. FT.
6" OD-13,281 SQ. FT.
6" OD-13,674 SQ. FT.
6" OD-1 3,402 SQ. FT.
8" OD-17,616 SQ. FT.
3" OD-11,096 SQ. FT.
3" RD-21,815 SQ. FT.
3" OD-21,815 SQ. FT.
GENERAL NOTES1. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDE
AIR.
2. ROOF DRAIN WILL BE OUTLINED AS DESINED BY ARCHITECT DURING DESIGN DEVELOPMENT. OVERFLOW WILLUTILIZE PARAPET SCUPPERS.
DRAWING NOTES #
1. 1-1/4" GAS DOWN THRU ROOF IN TO CEILING SPACE OF FLOOR BELOW.
2. 1-1/4" GAS CONNECTION TO MAU-1. RE: GAS CONNECTION DETAIL 11/P-530.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:2
9 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-131A
PLUMBING ROOFPLAN - AREA A
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1ROOF PLUMBING PLAN - AREA A
05.25.2016
3
F
G
J
K
L
94.9 8
M
4
7
4" RD-11,571 SQ. FT.
6" RD-1 2,555 SQ. FT.
4" RD-1 2,138 SQ. FT.
6" RD-12,518 SQ. FT.
4" RD-1 2,224 SQ. FT.
6" RD-12,876 SQ. FT.
6" RD-16,587 SQ. FT.
FUTUREEXPANSION
RE:MATCHLINE
MATCHLINE
P-131A
RE:MATCHLINE
MATCHLINE
P-131A
RE:MATCHLINE
MATCHLINE
P-131C
RE:
MATCHLINE
MATCHLINE
P-131C
4" OD-1 2,138 SQ. FT.
6" OD-12,518 SQ. FT.
4" OD-1 2,224 SQ. FT.6" OD-1
2,555 SQ. FT.
6" OD-12,876 SQ. FT.
4" OD-11,571 SQ. FT.
6" OD-16,587 SQ. FT.
3" VTR.
6" RD-12,538 SQ. FT.
6" OD-12,538 SQ. FT.
3" RD-22,500 SQ. FT.
3" OD-22,500 SQ. FT.
GENERAL NOTES1. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDE
AIR.
2. ROOF DRAIN WILL BE OUTLINED AS DESINED BY ARCHITECT DURING DESIGN DEVELOPMENT. OVERFLOW WILLUTILIZE PARAPET SCUPPERS.
DRAWING NOTES #
1. 1-1/4" GAS DOWN THRU ROOF IN TO CEILING SPACE OF FLOOR BELOW.
2. 1-1/4" GAS CONNECTION TO MAU-1. RE: GAS CONNECTION DETAIL 11/P-530.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:3
2 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-131B
PLUMBING ROOFPLAN - AREA B
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/8" = 1'-0"A1ROOF PLUMBING PLAN - AREA B
0
PROJECTNORTH
2' 4' 8' 16'
05.25.2016
31
N
M
P
Q
4 7
6" RD-1 3,446 SQ. FT.
4" RD-1 2,012 SQ. FT.
8" RD-1 10,462 SQ. FT.
FUTUREEXPANSION
RE:MATCHLINE
MATCHLINE
P-131B
RE:
MATCHLINE
MATCHLINE
P-131B
4" RD-1 2,012 SQ. FT.
G
4" OD-1 2,012 SQ. FT.
4" OD-1 2,012 SQ. FT.
8" OD-1 10,462 SQ. FT.
6" OD-1 3,446 SQ. FT.
3" VTRW/ VC-1
3" VTRW/ VC-1
3" VTRW/ VC-1
3" VTRW/ VC-1
8" RD-1 374 SQ. FT.
3" OD-1 374 SQ. FT.
3" VTRW/ VC-1
3" VTRW/ VC-1
3" VTRW/ VC-1
RTU-6
RTU-8
RTU-7
KEF-1
DEF-1
EF-14
EF-15
1
2
GENERAL NOTES1. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDE
AIR.
2. ROOF DRAIN WILL BE OUTLINED AS DESINED BY ARCHITECT DURING DESIGN DEVELOPMENT. OVERFLOW WILLUTILIZE PARAPET SCUPPERS.
DRAWING NOTES #
1. 1-1/4" GAS DOWN THRU ROOF IN TO CEILING SPACE OF FLOOR BELOW.
2. 1-1/4" GAS CONNECTION TO MAU-1. RE: GAS CONNECTION DETAIL 11/P-530.
A
B
C
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:3
4 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-131C
PLUMBING ROOFPLAN - AREA C
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
PROJECTNORTH
0 2' 4' 8' 16' 1/8" = 1'-0"A1ROOF PLUMBING PLAN - AREA C
05.25.2016
L-1 W/TMV-2
UR-2
UR-1
WC-1
WC-2
L-2 W/TMV-2
WC-2L-2 W/TMV-2
2"FD-1
2"FD-1W/ TG-1
H
J
3/4"
3/4"
3/4"
2"
2"
2"
2"
1 1/2"
3/4"
3/4"
3/4"
3/4"
T.
125
T.
126
H
J
L-1 W/TMV-2
S-1 W/TMV-2
MSB-1
WC-2
WC-1
WC-1
WC-1
2"FD-1W/ TG-1
L-1 W/TMV-2
L-2 W/TMV-2
F
G
3/4"
1"
2"
1"3/4"
1"
2"
3/4"
1/2"
3/4"
1"
1 1/2"
2"
4"
J.
115
T.
116
F
G
BUILDING WATERHEATING SYSTEMGWH-1
KITCHEN WATERHEATING SYSTEMGWH-2
Q
2
Q
3"FS-3
3"FS-3
4"FCO-14"
MECH.
141B
3"FS-2
2"FS-2
2"FS-2
4"FCO-1
B-3
B-2
B-1
CWP-2 CWP-1
HWP-1HWP-2
PUMPSRE: HVAC
BOILERSRE: HVAC
6
B-3
B-2
B-1
G
G
8
7
7
7
23
DET-24
6
P-530
15
P-530
1
P-531
GPR-2, VENTTO EXTERIOR
4
P-531
GPR-1, VENTTO EXTERIOR
4
P-531
5
MASTERMIXING VALVE
TMV-1
12
P-530
4"
9
11 10
G
3/4"3/4"
1/2"
G
G
2" PLUGGED BYPASSVALVE, COORDINATEWITH XCEL
2
Q
1
4"
3"
6"FS-1
6"FS-1WATER ENTRY
141E
1
4"
3"
3"BFP-1
FIRE SERVICEENTRY, RE: FP-111
4" METERED CW ENTRY
3" MASTER IRRIGATIONVALVE BY IRR.
3" BFP-2 (IRRIGATION)
3" IR DOWN TOBELOW SLAB
3" V. FROM BELOWFLOOR, UP TO 3" VTR
3" BFP-1 (DOMESTIC)
4" CW UP, OFFSET ATSTRUCTURE TODISTRIBUTION SYSTEM
2"
2"
2"
2"
WC-3
WC-3
L-1 W/TMV-2
L-1 W/TMV-2
2" FD-1W/ TG-1
2" FD-1W/ TG-1
S-1
T.
110A
T.
111A
PRE-K
110
D1 1/2"
3/4"
3/4"
1 1/2"
3/4"
3/4" 2"
3/4"
3/4"
3/4"
1"
1" 1/2"
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
3
2" FD-1W/ TG-1
2" FD-1W/ TG-1
2" FD-1W/ TG-1
WC-2
WC-4
WC-4
L-2 W/TMV-2
L-2 W/TMV-2
L-2 W/TMV-2
S-1 W/TMV-2
WORK ROOM
101L
CLINIC T.
101C
IDF
101F
T.
101D
T.
101E
3
C
2"
2"
2"
2"
2"1"
3/4"
2" FD-1W/ TG-1
2" FD-1W/ TG-1
WC-4
WC-4L-2 W/TMV-2
L-2 W/TMV-2
S-1 W/TMV-2
T.
103A
T.
104A
FLEX
104
C
WC-2WC-2
WC-1WC-1
WC-1WC-1
WC-1
WC-1
L-2 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-2 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
UR-2
UR-1
2"FD-1W/ TG-1
EWC-1
K
L
4
2"
2 1/2"
3/4"1"
3/4"
3/4"
1/2"
3/4"
1"
1 1/2"
1"2"
2"2"
2"2"
3/4"
1/2"
3/4"
1"
1 1/2"
1"
1 1/2"
3/4"
1"
1/2"
3/4"
4"
4"
4" 2"FD-1W/ TG-1
2"FD-1W/ TG-1
2"FD-1W/ TG-1
2"
2"
T.
128
T.
129
2
P-530
K
L
4
DRAWING NOTES #
1. 2"HWC, 2-1/2"HW, 4"CW & 1-1/4"MG TO KITCHEN AND 2-1/2"G TO COOKLINE AND SCIENCEDISTRIBUTION.
2. 1-1/2" 140° HW & 140° HWC TO KITCHEN.
3. 1" 140° HWC DROP AND CONNECT TO CP-2.
4. 1-1/2" 140° HW AND 1-1/2" CW TO GWH-2.
5. 1"G DROP AND CONNECT TO GWH-1 WITH GAS VALVE AND UNION.
6. 3" VERTICAL DRY VENT FROM BELOW, PROVIDE CLEANOUT PLUG AND RISE TO 3" VTR.
7. 1-1/2"MG CONNECT TO BOILER WITH GAS VALVE.
8. 4"MG RISE TO STRUCTURE ABOVE.
9. CORE DRILL AND PROVIDE SEAL AT WALL PENETRATION.
10. GAS SERVICE, METER, SERVICE REGULATOR AND VALVING BY XCEL.
11. GAS METER BY XCEL, SEE TOTAL CONNECTED GAS LOAD.
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:4
1 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-410
ENLARGED PLUMBINGGROUPS
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/4" = 1'-0"D1First Floor - Area B - T. - 125
1/4" = 1'-0"B1First Floor - Area B - T. - 116
1/4" = 1'-0"B3First Floor - Area C - Mechanical Room - 141B
1/4" = 1'-0"A1First Floor - Area C - Water Entry - 141E
1/4" = 1'-0"A2First Floor Area A - T. - 110A and 111A
1/4" = 1'-0"B2First Floor - Area A - Callout Clinic - 101C
1/4" = 1'-0"A4First Floor - Area A - T. - 103A and 104A
1/4" = 1'-0"D2First Floor - Area B - T. - 128 and 130
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
NATURAL GAS PIPING SIZED AS MG 2.0 PSIG FOR 600' WITH A TOTAL LOAD OF 11,259 CFHLOW PRESSURE SYSTEM SIZED FOR 6" WC FOR 600' WITH A LOAD OF 1260 CFH (KITCHEN1200 CFH 100' FROM METER)SCIENCE LOAD 60 CFH AT 600 FEET FROM METER
05.25.2016
D
E
EWC-2
L-2 W/TMV-2
L-1 W/TMV-2
UR-2
WC-1
WC-2 WC-2
WC-1
WC-1
HB-1HB-1
WCO-1
WCO-1
L-1 W/TMV-2
L-2 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
CIRC.
200A
T.
212
T.
213
FD-1 W/TG-1
FD-1 W/TG-1
2"
D
E
H
J
H
J
EWC-1
L-1 W/TMV-2
L-2 W/TMV-2
UR-2
UR-1
WC-1
WC-1
WC-2
HB-1
WCO-1
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
CIRC.
200A
T.
225
FD-1 W/TG-1
H
J
S-1 W/ TMV-2
F
G
F
G
WC-2
WC-1
WC-1
WC-1
WC-1
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-1 W/TMV-2
L-2 W/TMV-2
T.
216
F
G
33
WC-2
L-2 W/TMV-2
J.
239
T.
2382" FD-1W/ TG-1
3
1 10
6 7
4 5
MSB-1
WC-3L-1 W/TMV-2
FD-1 W/TG-13/4"
S-1
WC-3FD-1 W/TG-1
EWC-1
2"1"
3/4"
1 1/2"
2"2"
1"
2"
1"
2"
2"
1 1/2"
2"
3/4"
L-1 W/TMV-2
T.
106A
T.
105A
CIRC.
100B
DD
WC-3
WC-3L-1 W/TMV-2
FD-1 W/TG-1
FD-1 W/TG-1
WCO-1
WCO-1
WCO-1
2"
3/4"3/4"1 1/2"
1/2"1/2"
3/4"3/4"
2"
WCO-1
2"
1"
2"
DD
L-1 W/TMV-2
T.
108A
T.
107A
ST.
107B
S-1 W/TMV-2
DD
33
WC-2
L-2 W/TMV-22" FD-1
W/ TG-1
WCO-1
WCO-1
T.
247
3
MSB-16 7
1 10 4 5
3
DRAWING NOTES #
1. 1" CW UP TO WATER CLOSET FROM BELOW.
2. 2" VENT RISE TO 3" VTR.
3. 2" VENT RISE FROM FLOOR DRAIN.
4. 2" VENT RISE FROM LAV.
5. 1/2" CW & HW UP TO LAV FROM BELOW.
6. 2" VENT RISE FROM MOP BASIN.
7. 1/2" CW & HW UP TO MOP BASIN FROM BELOW.
8. 3/4" CW TO URINAL UP FROM BELOW.
9. 2" VENT RISE UP FROM URINAL.
10. 2" VENT RISE UP FROM WATER CLOSET.
11. 3/4" CW TO HOSE BIB UP FROM BELOW.
12. 2" VENT RISE UP FROM WATERCOOLER.
13. 1/2" CW TO WATER COOLER FROM BELOW.
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:4
8 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-411
ENLARGED PLUMBINGGROUPS CONTINUED
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/4" = 1'-0"D1Second Floor - Area A - T. - 212 and 213
1/4" = 1'-0"D2Second Floor - Area B - T. - 225
1/4" = 1'-0"D4Second Floor - Area B - T. - 216
1/4" = 1'-0"B1Second Floor - Area B - T. and J. - 238 and 237
PROJECTNORTH
0 1' 2' 4' 8'
1/4" = 1'-0"B2First Floor - Area A - T. - 105A and 106A
1/4" = 1'-0"B4First Floor - Area A - T. - 107A and 108A
1/4" = 1'-0"A1Second Floor - Area A - T. - 245
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
PROJECTNORTH
0 1' 2' 4' 8'
05.25.2016
#
REMARKS:
1. P.C. TO EXTEND IW FROM EVAPORATOR COILS TO FLOOR SINK.
2. P.C. TO EXTEND IW FROM SINK TO NEAREST FLOOR SINK.
3. P.C. TO EXTEND IW FROM KETTLE TROUGH TO FLOOR SINK. P.C. TO TEE HW AND CW TO KETTLE FAUCET. TEE CW TO COND. FEED AND BOILER FEED.
4. P.C. TO TEE WATER TO (2) FAUCETS.
5. P.C. TO EXTEND IW FROM BOOSTER HEATER TO NEAREST FLOOR SINK P.C. TO INTERCONNECT HW FROM BOOSTER HEATER TO DISH MACHINE.
6. P.C. TO EXTEND IW TO NEAREST FLOOR SINK.
7. P.C. TO TEE HW TO PRE-RINSE, TEE CW TO PRE-RINSE, DISPOSER AND TO SOILED DISH TABLE TROUGH NOZZLES.
8. P.C. TO EXTEND IW FROM STEAMER TO NEAREST FLOOR SINK P.C. TO TEE CW TO (2) STEAMER CONNECTIONS.
9. P.C. TO CONNECT 2"SAN AND 2" VENT TO DISPOSER.
10. P.C. TO PROVIDE WB-1 FOR WASHER/DRYER FOR HW, CW, SAN, AND VENT CONNECTIONS.
11. P.C. TO CONNECT HW,CW TO MOP SINK FAUCET AS SCHEDULED ON P600.
4
5
6
WASTEIN
VENTIN
HOTIN
COLDIN
INDIRECTWASTE IN
GASIN
KITCHEN EQUIPMENT ROUGH-IN SCHEDULE
DESCRIPTION REMARKS
STEAMER, 6 PAN
10 GALLON TILT KETTLE
CONVECTION OVENS, DOUBLE STACK
8- - - 1/2 2 -
3- - 1/2 1/2 - -
-- - - - - 3/4
12 HAND SINK -2 2 1/2 1/2 - -
17 VEGETABLE PREP SINK 2- - 1/2 1/2 2 -
24 HOT FOOD TABLE 6- - 1/2 - 1 -
33 WALK IN FREEZER 1- - - - 1 -
36 WALK IN COOLER 1- - - - 1 -
43 DISH TABLE 6- - - - 1 -
45 DISH MACHINE 5- - 3/4 - 2 -
51 DISPOSAL 92 2 - - - -
52 SPRAY RINSE 7- - 1/2 1/2 - -
54 3-COMPARTMENT SINK 2,4- - 1/2 1/2 2 -
57 WASHER/DRYER STACKED 102 2 1/2 1/2 2 -
60 MOP SINK 112 2 1/2 1/2 2 -
3084
Trash
Trash
Trash
2472
2472
2472
2472
2442
2472
2472
2472
2472
2460 2460
2472
2472
2442
2442
2472
3072
3072
3072
2460
3060
2448
2448
24362436
3048
1
P GG
G
GG
KITCHEN
141
DRY ST.
141F
KIT. ST./LOCKER
141A
OFFICE
141C
ELEC.
141D
FM. ST.
142
FM REC.
142A
1 1/4" 1 1/4"
G G
GG
FCO-1
1 1/4"
1 1/4"
G
G
3/4"
1/2"
1"
1"
WB-1
2"
3/4"1 1/2"1"3/4"
7
X
14
11
12 10
3/4"
3/4"
1"
1 1/4"
1 1/4"
2 1/2"
2"
1
2
WH-1
39
137
FS-X
3/4"
1 1/4"
1 1/2"
4"
2 1/2"2"
3/4"
4"
4"
1"
3/4"
1"
2"
2 1/2"
4"
2"
7
7
6
D
D
5
4
7
8
8
1/2"
1
2
P
N
WC-2
2"FD-1W/ TG-1
L-2 W/TMV-2
L-2 W/TMV-2
2"FD-1W/ TG-1
MSB-1
JANITOR
136E.2
LOCKER ROOM
136E
2"
2 1/2"
4" 1"
2"
2"
1 1/2"
3/4"3/4"
3/4"
1/2"
3/4"
2" 3/4"
1"
2"
1 1/4"
3/4"
N
21
18
19
15
15
20
P
SH-1
WC-2
WC-2
2"FD-1W/ TG-1
2"FD-1W/ TG-1
L-2 W/TMV-2
L-2 W/TMV-2
2"FD-1W/ TG-1
WC-2
MSB-1
L-2 W/TMV-2
L-2 W/TMV-2
2"FD-1W/ TG-1
4"FCO-1
SHOWER
136D.1
FM T. / LR
140B.1
FM T. / LR
140B.1
TABLE STOR.
140A
FM. OFFICE
140B
LOCKER ROOM
136C2"
3/4"3/4"
3/4"
3/4"
3/4"3/4"
1 1/2"
1"
2"
2" 2"
4"
2 1/2"
2"
3/4"
1"
2"
2"2"
P815
3
15
15
16
17
18
19
1516
11
19
18
20
1920
11
21
21
GENERAL NOTES1. ISOLATION VALVES WILL BE SPECIFIED AT ALL MAIN/SUBMAIN TAKE-OFFS AND BRANCH CONNECTIONS.
2. VENT PIPE ROUTING TO BE OUTLINED DURING DESIGN DEVELOPMENT TO MAINTAIN CLEARANCES TO OUTSIDEAIR.
3. DOMESTIC WATER DISTRIBUTION TO BE ROUTED ABOVE CEILING. THE WATER PIPING WILL BE ROUTED UP TOFIXURES ON THE SECOND FLOOR ABOVE AND DOWN TO FIXTURES ON THE FIRST FLOOR.
DRAWING NOTES #
1. 4" CW, 2-1/2" HW, AND 2" HWC ROUTED ABOVE CEILING TO COMMONS AREA. SEE SHEET P-111C FORCONTINUATION.
2. 1-1/2" GAS LINE ROUTED ABOVE CEILING TO COMMONS AREA. SEE SHEET P111C FOR CONTINUATION.
3. 3/4" CW DROP IN WALL TO WH-1.
4. 4" CW FROM WATER SERVICE ENTRY ROOM. SEE SHEET P-111C FOR CONTINUATION.
5. HEAT TRACE CONDENSATE IN FREEZER COORDINATE WITH KE CONSULTANT.
6. 1-1/4" GAS (14" W.C.) UP TO MAKE-UP AIR UNIT ON ROOF. SEE SHEET P-131C FOR CONTINUATION.
7. 1/2" CW & HW RUN DOWN IN WALL TO HAND SINK IN KITCHEN.
8. 2" VENT RISE INTO STRUCTURE AND TRANSITION TO A 3" VTR IN STRUCTURE SPACE.
9. 1/2 CW& HW DOWN IN WALL TO SERVE SCULLERY HAND SPRAYER.
10. 1/2 CW & HW DOWN IN WALL TO SERVE HAND SPRAYER.
11. 2" VENT RISE IN WALL TO ABOVE CEILING.
12. 1/2" HW DOWN IN WALL TO SERVE DISH TABLE.
13. 2" SANITARY FROM FLOOR SINK. SEE P-110C FOR CONTINUATION.
14. 3" SANITARY UP FROM BELOW TO WALL CLEAN-OUT.
15. 2" VENT, 1/2" CW & HW TO LAV.
16. 3/4" HWC DOWN IN WALL & CONNECT TO HW WITHIN 2'-0" OF THE LAV.
17. 2" VENT, 1/2" CW & HW TO SHOWER.
18. PROVIDE WATER HAMMER ARRESTOR WHA-1 WITH ACCESS PANEL.
19. 2" VENT & 1" CW TO WATER CLOSET.
20. 2" VENT, 1/2" CW & HW TO MOP BASIN.
21. CIRCUIT SETTER, BALANCE TO 0.5 GPM.
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:5
2 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-412
ENLARGED PLUMBINGGROUPS CONTINUED
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JJR
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
1/4" = 1'-0"C1First Floor - Area C - Kitchen - 141
PROJECTNORTH
0 1' 2' 4' 8'
1/4" = 1'-0"D4First Floor - Area C - North Locker Room - 136E
PROJECTNORTH
0 1' 2' 4' 8'
1/4" = 1'-0"C4First Floor - Area C - South Locker Room - 136C
PROJECTNORTH
0 1' 2' 4' 8'
05.25.2016
2"2"
2"
2"
2"
2"
2"
2"
2"
2"
4"2"
2"
4"
2"
4"
2" 4"
FD-1
FD-1
WC-1
WC-1
S-1
L-1
S-1
WCO-1
2"
2"
2"2"
2"
4"
4"
2"
2"
4"
4"
2"
2"
4"
FD-1
WC-1
L-1WCO-1
WCO-1
FD-1
WC-1
2"
2"
2"
2"
2"
2"
2"
4"
2"4"
4"
2"
2"
2"
4"
2"
2"
2"
4"
4"
4"
4"
4"
2"
4"
2"
2"
2"
2"2"
2"
2"
4"
2"
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:5
3 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-510
PLUMBINGISOMETRICS
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
NTS1
ISOMETRIC - TOILET 105A & 106ANTS
2ISOMETRIC - TOILET 107A & 108A
NTS3
ISOMETRIC - TOILET 103A & 104ANTS
4ISOMETRIC - TOILET 110A & 111A
05.25.2016
S
INTERCEPTOR NOTES
12"
DIELECTRIC UNION (TYP.)
G
2"
RELIEF VALVE, PIPE
DISCHARGE TO FLOOR SINK
GWH-1
THERMOMETER
1"HW, SEE PLAN
FLUE, SEE HVAC
DRAWINGS
1-1/2"CW, 3/4"HWC SEE
PLAN
1-1/2"
3/4"
CP-1
CHECK VALVE IN HORIZONTAL
BALL VALVE (TYP.)
1"
DET-1
CONCRETE HOUSEKEEPING
PAD, SEE ARCH.FINISHED FLOOR
6" LONG DRIP LEG
DRAIN VALVE
UNION
MANUAL GAS VALVE
SWAY BRACING SWAY BRACING
NOTE: PROVIDE FOR PIPING
2-1/2" AND SMALLER WHERE
APPLICABLE
WASHER & DOUBLE HEX
NUTS
UNI-STRUT TYPE CHANNEL
20 GA. GALV. SHIELD 12"
LONG
RIGID 360°INSULATION
INSERT
VAPOR BARRIER
PIPE CLAMP
1/2"Ø HANGER ROD
1/2" INLET CONNECTION
3/8" OUTLET CONNECTION
1/4 TURN STOP VALVE
INTEGRAL WATER HAMMER
ARRESTORMETAL BOX FASTEN TO
STUDS OR WALL
PRIMARY CHAMBER
4"EXTEND TO GCO-1
GRADE ADJUSTMENT RINGS
AS REQUIRED
6" THICK REINFORCED PRECAST
CONCRETE TOP W/ LIFT RINGS
SEALANT AT ALL JOINTS
4" OUTLET, SEE PLAN
GASKET AT ALL PIPE
PENETRATIONS
SECONDARY CHAMBER
BAFFLE WALL WITH
BAFFLE FITTINGS
STATIC WATER LEVEL
4" INLET, SEE PLAN
4" OPEN ENDED PIPE
SECTIONS (TYP.)
24"Ø GAS TIGHT RING AND
COVER (TYP. OF 2)
3"V TO BUILDING, SEE PLAN
ALL PIPING INDICATED SHALL BE 4" CAST IRON UNLESS SPECIFICALLY NOTED OTHERWISE.
PIPING AND FITTINGS INSTALLED SHALL MEET THE REQUIREMENTS OF THE LATEST EDITION OF THE
INTERNATIONAL PLUMBING CODE.
INLET AND OUTLET BAFFLE FITTINGS SHALL EXTEND A MINIMUM OF 4" ABOVE THE STATIC WATER
LEVEL AND TO WITHIN 12" OF THE FLOOR.
SECONDARY CHAMBER VOLUME SHALL BE EQUAL TO 13 TOTAL CAPACITY.
TANK SHALL MEET ASTM C-913-79 SPECIFICATIONS FOR USE AS A WASTEWATER STRUCTURE, ALL
SEALANTS SHALL MEET FEDERAL SPECIFICATION SS-S-210A AND SHALL BE PROVIDED WITH THE
TANK.
TANK AND LID SHALL BE DESIGNED FOR H-20 TRAFFIC LOADING.
TOTAL TANK HOLDING CAPACITY SHALL BE 2500 GALLONS. COORDINATE EXACT DIMENSIONAL DATA
WITH EQUIPMENT SUPPLIER PRIOR TO INSTALLATION.
CLEANOUT COVER, SEE
PLUMBING EQUIPMENT
SCHEDULE
FINISHED GRADE
SEWER, RE: PLANS
CONCRETE RETAINING PAD
MIN. 6" THICK & EXTEND 4"
BEYOND CLEANOUT HOUSING
ALL AROUND
SEWER FROM BUILDING,
RE: PLANS
BEDDING
4" CAST IRON EXTENSION
(TYPICAL)
TWO-WAY CLEANOUT
P-TRAP
COUNTER
INSIDE CABINET
SINK (RE: SCHEDULE)
FINISHED FLOOR
THERMOSTATIC MIXING VALVE
W/ WALL BRAKET
HOT WATER SUPPLY
TEMPERED WATER SUPPLY
COLD WATER SUPPLY
COLD WATER SUPPLY
FAUCET (RE: SCHEDULE)
NOT TO SCALE
ROOFTOP GAS CONNECTION DETAIL
ICE MAKER BOX DETAIL
TRAPEZE HANGER DETAIL
VACUUM RELIEF
NOT TO SCALE
GREASE INTERCEPTOR DETAIL
GAS VALVE
1'-0" MINIMUM
GAS PIPE SUPPORT
STANDARD TYPE
6" DIRT LEG
ROOF LINE
UNION @ CONNECTION
FOR SLAB ON GRADE OR EXPOSED
APPLICATIONS P-TRAP
DRAINAGE PIPING, SEE PLAN
FOR SIZE AND CONTINUATION
EXISTING OR NEW CONCRETE
FINISHED FLOOR W/ NEW
TOPPING RE: ARCH
FLOOR SINK, SEE PLAN
FOR DESIGNATION
QUICK SET MORTAR RE: SPECIFICATIONS
CHIP CONCRETE AS REQUIRED FOR FLUSH
INSTALLATION
FINISHED FLOOR
MIXING VALVE WITHIN RECESSED
ENCLOSURE (EXCEPT IN BOILER
ROOM WHERE THE UNIT IS
EXPOSED)
CW AND HW SUPPLY
RE: PLANS
EW-1
P-TRAP
EXPOSED PIPING TO
FLOOR IN BOILER RM.
RE: ARCH FOR
MTD HEIGHT
EW-1
WASTE IN WALL RE:
PLANS
VENT IN WALL RE:
PLANS
6"
1-1/2" P-TRAP
SECURE TO CABINET BACK
1-1/2" WYE FITTING
DISHWASHER DRAIN TUBE, SECURE TO STANDPIPE
W/ HOSE CLAMP
PROVIDE GROMMET AT TUBE PENETRATION THRU
BASE CABINET
PROVIDE ESCUTCHEON AT WALL
PENETRATION
CONNECT TO 2"W AT SINK, SEE
PLAN
2"PD, SEE PLAN
MULTI-PIN CONNECTOR
JUNCTION BOX PROVIDED W/ MULTI-PIN
CONNECTOR & CORD IN LENGTHS AS
REQUIRED
OIL-MINDER POWER CABLE,
PROBE CABLE & FLOAT CABLE
GATE VALVE
COVER
SUMP PUMP
SUMP PIT CAST IN PLACE COOR. W. G.C.
CHECK VALVE
HIGH LIQUID ALARM FLOAT W/ CLAMP DEVICE TO
MOUNT TO PUMP DISCHARGE PIPING
FLOOR
MULTI-PIN CONNECTOR & CORD IN
CONDUIT LENGTHS AS REQUIRED
MULTI-PIN CONNECTOR
POWER
SUPPLY
ELECTRICAL
OUTLET
STANCOR OIL-MINDER 115V, 1Ø CONTROL SYSTEM W/ BUILT IN AUDIBLE AND VISUAL
ALARM WHEN PUMP DOESN'T RUN DUE TO OIL IN PIT, HIGH AMPERAGE OR HIGH
LIQUID CONDITION. PROVIDE SILENCING BUTTON FOR AUDIBLE ALARM BUILT INTO
PANEL. PANEL SHALL HAVE ADDITIONAL CONTACT FOR A REMOTE ALARM LOCATION.
3" BFP-1, EXTEND FUNNEL
DRAIN TO FLOOR SINK
IR
4" METERED CW SERVICE, SEEPLAN FOR CONTINUATION
EXTEND FUNNEL DRAIN TOFLOOR SINK SEE PLAN
4" MAIN BUILDING ISOLATIONVALVE, PROVIDE SIGN ON WALL
3" MASTER IRRIGATION CONTROLVALVE, FURNISHED BY IRRIGATIONCONTRACTOR, INSTALLED BY P.C.
REDUCE TO 3" CW.
3" IR DROP TO BELOW FLOOR,SEE PLAN FOR CONTINUATION.
FINISHED FLOOR
3/4" DRAIN VALVE
3" ISOLATION VALVE
SUPPORT VERTICALPIPING FROM WALL.
4" CW TO STRUCTUREAND EXTEND TO SYSTEM
3" IRRIGATION BACKFLOW
PREVENTION DEVICE BFP-2.
3" PRESSURE REDUCING VALVE PRV-1
1" PRESSURE REDUCING VALVE PRV-2
PRESSURE GAUGE (TYP)
2" BYPASS WITH BYPASS VALVE(NC)
STRUT FRAMING VERTICALSUPORT SYSTEM (TYP)
GRADE CLEANOUTNOT TO SCALE10
11
NOT TO SCALE7
NOT TO SCALE8
THERMOSTATIC MIXING VALVE DETAILNOT TO SCALE12
GAS FIRED WATER HEATER PIPING DIAGRAMNOT TO SCALE15
POINT OF USE NEUTRALIZATION TANK DETAILNOT TO SCALE5
FLOOR SINK DETAILNOT TO SCALE3
CABINET MIXING VALVE DETAILNOT TO SCALE2
ELEVATOR SUMP PUMP DETAILNOT TO SCALE4
CIRCULATION PUMP DETAILNOT TO SCALE6
CLEVIS HANGER DETAILNOT TO SCALE9
EWH-1 PIPING DETAILNOT TO SCALE13
DISHMACHINE STANDPIPE DETAILNOT TO SCALE14
REDUCE TO INLET
CONNECTION (TYP.)
THERMOSTAT
(TYP.)
THERMOSTAT
UNION
1-1/4" HW (140°)
3" HW (120°) TO SYSTEM
1-1/4" CW
INCREASER
3/4"HWC FROM FROM
CP-1TMV-1
CHECK VALVE
BALANCING VALVE W/
MEMORY STOP.
16
GCO-X
HANGER ROD
HEAVY DUTY CLEVIS HANGER
VAPOR BARRIER INSULATION, RE:SPEC
180° INSERT CALCIUM SILICATE INSULATION OF
SAME THICKNESS AS PIPE INSULATION
180° GALVANIZED SHEET STEEL
SADDLE MIN. 9" LONG, RE: SPEC.
NUT AND BOLT
SUPPORT NUT
LOCKING NUT
5 PIPEDIAMETER
MINIMUM
BALL VALVE
CHECK VALVE
UNION
NEOPRENE ISOLATED CLAMP
IN-LINE CIRCULATION PUMP,
SEE PLAN FOR DESIGNATION
UNI-STRUT MOUNTED ON WALL
UNION
BALL VALVE
3/4" HWC FROM SYSTEM
ACID NEUTRALIZATION TANK
(ANT), SEE PLAN FOR SPECIAL
DESIGNATION
THREADED CONNECTIONS
(TYP.)
1-1/2"AW
FINISHED FLOOR
BASE CABINET FLOOR
2"SAN & VENT WITHIN WALL
2"AW TO WALL W/
ESCUTCHEON
SERVICE CLEANOUT PLUG-IN LID
2"AV TO WALL W/ ESCUTCHEON
SINK, SEE PLANS
FOR DESIGNATION
WATER SERVICE DETAILNOT TO SCALE1
ANCHOR STRUT TO WALL
WALL WASHER & DOUBLE HEX NUTS
BACKING ASREQUIRED FORFRAMED WALL
VERTICAL PIPE MOUNTING DETAILNOT TO SCALE17
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:5
4 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-530
PLUMBING DETAILS
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
05.25.2016
R
3
GAS VALVECONTROL ONOFFON
GAS VALVE CONTROLSTATION
GAS AND COMPRESSED AIR SHUT OFF PANELNOT TO SCALE2
POTTER-ROEMER FIG. #1812-FSSEMI-RECESSED CABINET W/ SOLIDMETAL DOOR & FIG. #1901 CAM CATCHLOCK. PROVIDE SPECIAL CABINETPUNCHING FOR GAS, COMPRESSED AIRAND ELECTRICAL CONDUIT. PROVIDEDECAL AS NOTED (MIN. 1" HIGH) W/CLEAR BACK- GROUND & BLACKLETTERING
TO SYSTEM,RE: PLAN
AUTOMATIC GASVALVEINSTALLED BYPC., RE:SPEC
POTTER-ROEMER FIG. #1812-CSEMI-RECESSED CABINET W/ SOLIDMETAL DOOR & FIG. #1901 CAMCATCH LOCK. PROVIDE SPECIALCABINET PUNCHING FOR GAS PIPINGSHOWN & ELEC. CONDUIT. PROVIDEDECAL AS NOTED (MIN. 1" HIGH) W/CLEAR BACK- GROUND & BLACKLETTERING' (TYP.)
WIRING FROMCONTROL PANELTO VALVE BY E.C.
WARRICK CONTROLS, INC.GAS VALVE CONTROLPANEL MODEL SA4006A
FROM POWERSOURCE, RE:ELEC
UNION(TYP.)
DIRT LEG(TYP.)
MANUAL GASCOCK (TYP.)
PROVIDE DECAL ON ACCESSDOOR READING: "AUTOMATIC GAS
VALVE SHUT-OFF VALVE" (TYP.)
GAS SUPPLY,RE: PLAN
GAS VALVE CONTROL PANELNOT TO SCALE
COMPRESSED AIR TO SYSTEM
NATURAL GAS TO SYSTEM
ISOLATION VALVE (TYPICAL)
COMPRESSED AIR FROM SYSTEM
NATURAL GAS FROM SYSTEM
GAS SOLENOID VALVE
MG
1 NOT TO SCALE
GAS FIRED WATER HEATER PIPING DETAIL
MAINTAIN A REGULATED 8.5" W.C. PRESSURE AT MAX. BTU/H INPUT
1-1/2"HWC, SEE PLAN AND CIRC. PUMP PIPING
DIAGRAM
RELIEF VENT EXTEND
FULL SIZE THROUGH
EXTERIOR WALL
1"MG, SEE PLAN
6"
2'-0"
FINISHED FLOOR
HOUSEKEEPING PAD, RE: ARCH
DRAIN VALVE
X" TO DET
2"CW, SEE PLAN
GWH-1
6" (TYP.)
2"HW, SEE PLAN
RELIEF VALVE
ROLLER SUPPORT
PLASTIC BASE
NOTE:
1. GAS PIPING SHALL BE A MINIMUM OF 7" ABOVE ROOF LINE.
2. GAS PIPE SUPPORT MIRO 3-RAH-7 SERIES.
ROOF
ROOFING FELT
ALL THREAD ROD
ADJUSTMENT NUTS
SPINDLE
GAS PIPING, SEE PLAN
GAS PIPE GUIDE DETAILNOT TO SCALE5
MEDIUM PRESSUREGAS, SEE PLAN FORCONT.
MANUAL GAS VALVE
SERVICE UNION
6" LONG DIRT LEG
NOTE: SEE PLAN FOR PIPE SIZES NOT INDICATED HERE.
GAS PRESSURE REGULATOR(GPR) SEE PLAN AND SCHEDULEFOR REQUIREMENTS
LOW PRESSURE GAS, SEEPLAN FOR CONTINUATION
INCREASER AS REQUIRED
PRESSURE GUAGE
(4) PIPE DIAMETERS
VENT TO ROOF FULL SIZEOF UNIT DISCHARGE W/GOOSENECK
GAS PRESSURE REGULATOR PIPING DETAILNOT TO SCALE4
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:5
4 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-531
PLUMBING DETAILS(CONT.)
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JJR
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
05.25.2016
DOMESTIC WATER PRESSURE REDUCING VALVE SCHEDULE
SYMBOL SERVES MANUF. MODEL NUMBERINLETSIZE
OUTLETSIZE
INLETPRESSURE
PSIG
OUTLETPRESSURE
PSIG
FALL-OFFPRESSURE
REMARKS
PRV-1 X X XX X" X" XX XX XX XX XX
SYMMONS S-6080
1,4
3/4"-- -- -- 3/4" 1S19-314BRADLEYCOMBO SHOWER EYEWASH
CSE-1
S-3SCIENCE SINK
FAUCETELKAY
CHICAGO 201AGN2BVBE7317LRAD3122
1-1/2" 2" 2" 1/2"1/2"
DRAIN STRAINER ELKAY LK-35
LK-35ELKAYDRAIN STRAINER
1,31/2" 1/2"2"2"1-1/2"LRAD-1919
100-GN2AE3-317CPCHICAGOELKAY
FAUCET1-COMPT. SINK
S-1
1,21/2"--2"2"1 1/4"0355.012
0700J.R. SMITH
AM. STD.
SUPPORT CARRIERFAUCET
WALL HUNG LAVATORYL-2
HWCWCWVWREMARKS
TRAP
ROUGH-IN CONNECTIONSMODEL NOMANUFACTURERTAG DESCRIPTION
PLUMBING FIXTURE SCHEDULE
8
L-1 1 1/4" 2" 2" -- 1/2" 2
--1"2"2"INT.TUE1LN12CP0637
6601.012
J.R. SMITHTOTO
AM. STD.
CARRIERFLUSH VALVEUR-1
WALL HUNG URINAL
S-42-COMPARTMENT SINK
FAUCETELKAY
CHICAGO SI-1 2" 2" 1/2"1/2" 5
1/2"1-1/4" 2" 2" -- 1EWC-1J.R. SMITH
ELKAY VRCGRNTL8C0830
SS8248LR640-L12E35-317YAB
1-117-FS-X-B30SH-1 SHOWER VALVE SYMMONS -- -- -- 1/2"1/2" 6
ELECTRIC WATER COOLERSUPPORT CARRIER
1/2" 1/2" -3" 3"FIAT
CHICAGOMSB-2424MOP SERVICE BASIN
MSB-1FAUCET
2"
BADGER 5ISEDISPOSER
1,31/2" 1/2"2"2"1-1/2"LRAD-3122
100-GN2AE3-317CPCHICAGOELKAY
FAUCET1-COMPT. SINK
S-2
1,8--1"2"2"INT.TUE1LN12CP6541.132
TOTOAM. STD.
CARRIERFLUSH VALVEUR-2
WALL HUNG URINAL
WALL. MTD. WATER CLOSET TOTO CT708EWC-1 FLUSH VALVE
SEATINT. 2"4" --1"TOTO TET1LN32#CP 9
WALL. MTD. WATER CLOSET TOTO CT708EWC-2 FLUSH VALVE
SEATINT. 2"4" --1"TOTO TET1LN32#CP 1,9
2"FLUSH VALVEWC-3FLR. MTD. WATER CLOSET 2234.015
TOTOTOTO
4"INT. 9--1"SEAT
FLR. MTD. WATER CLOSET TOTO
TET1LN32#CP
CT705ELNWC-4 FLUSH VALVE
SEATINT. 2"4" --1"TOTO TET1LN32#CP 1,9
BRADLEY S19-2100TEMPERING VALVE
445897SRCXKCP
CHURCH 9500SSC
CHURCH 9500SSC
CHURCH 9500SSC
CHURCH 9500SSC
0637J.R. SMITH
SYMMONS S-60800355.012
0700J.R. SMITH
AM. STD.
SUPPORT CARRIERFAUCET
WALL HUNG LAVATORY
SP-2 12"ELEVATOR 20 FT. 1/2 HP
1. ONE (1) 2" SUBMERSIBLE WASTEWATER PUMP MODEL 1411; CAST IRON CASE AND IMPELLER, 1/2" SOLIDS HANDLING MAX; 1750 RPM; 15' POWER CABLE;
ONE (1) TYPE 4X SIMPLEX CONTROL PANEL MODEL 8111 - ISOLATED CONTACT FOR HWA; THREE (3) TETHERED FLOAT SWITCHES MODEL 8233K1006.
PROVIDE 30" DIAMETER BASIN 36" DEEP WITH OPEN GRATED COVER, COORDINATE LOCATION WITH ELEVATOR HOIST EQUIPMENT.
1-110-XSH-2 SHOWER VALVE SYMMONS -- -- -- 1/2"1/2" 7
LOCATED IN MECHANICAL
ROOM475 CFH1-1/2"1"7"WC2PSI
COOKLINE,
TURRETSGPR-2
REMARKSCAPACITYOUTLET SIZEINLET SIZEOUTLET
PRESSURE
INLET
PRESSURESERVICETAG
LOCATED IN MECHANICAL
ROOM10,566 CFH5"2"14"WC2PSI
B-1, B-2, B-3,
GWH-1, GWH-2, MAU-1GPR-1
GAS PRESSURE REGULATOR SCHEDULE
1015115/150 GPM1411-09DLWEIL
1, 296%349 GPH @ 100°F140°F300119 GAL.SUF 119 300 NE(A)STATEKITCHENGWH-2
REMARKSMOCPMCAV/PH
ELECTRICALHP/ WATTSHEAD
FLOWRATE
OUTLET
SIZE
MODEL
NUMBERMANUF.SERVICETAG
SUMP PUMP SCHEDULE
REMARKS
1, 296%924 GPH @ 100°F140°F80024 GAL.INN 800AERCOBUILDINGGWH-1
REMARKSEFFICIENCYRECOVERY RATE
@ DEGREE RISEOUTLET WATERTEMPERATURE
MBH
INPUT
STORAGE
CAPACITY
GALLONS
MODEL NUMBERMANUFACTURERSERVICETAG
FUEL-FIRED WATER HEATER SCHEDULE
REMARKS:
1. EFFICIENCY BASED ON 2XXX IECC TABLE 504.2.
2. INLET GAS PRESSURE REQUIREMENTS; 4" MINIMUM, 14" MAXIMUM.
NOTES:
1. REFER TO ARCHITECTURAL DRAWINGS AND ELEVATIONS FOR EXACT LOCATION AND MOUNTING HEIGHT ELEVATIONS OF ALL PLUMBING FIXTURES PRIOR
TO INSTALLATION.
2. PROVIDE ALL FIXTURES WITH CHROME PLATED CAST BRASS, ADJUSTABLE 'P' TRAPS WITH CLEANOUT PLUGS, TUBING OUTLETS AND WALL FLANGES
UNLESS FIXTURE IS FURNISHED WITH AN INTEGRAL TRAP OR IS PROVIDED ONE AS A STANDARD ACCESSORY.
3. PROVIDE ALL FIXTURES WITH CHROME PLATED SUPPLIES WITH ANGLE OR STRAIGHT PATTERN LOOSE KEY 1/4 TURN STOPS UNLESS FIXTURE IS
FURNISHED WITH INTEGRAL STOPS OR STOPS ARE PROVIDED AS STANDARD ACCESSORIES.
4. ALL LAVATORIES AND SINKS DESIGNATED TO BE IN COMPLIANCE WITH ANSI-A117.1 SHALL BE PROVIDED WITH OFFSET TAILPIECE CONNECTIONS AND
PROTECTIVE TRAP AND SUPPLY WRAPPING KITS, REFER TO SPECIFICATIONS FOR ADDITIONAL INFORMATION.
5. FURNISH ALL BATTERY POWERED FAUCETS AND FLUSH VALVES WITH NEW SET OF BATTERIES FOLLOWING FINAL ACCEPTANCE OF THE PROJECT,
COORDINATE WITH THE OWNER'S DESIGNATED REPRESENTATIVE.
6. REFER TO SPECIFICATIONS FOR ADDITIONAL INFORMATION WHICH MAY NOT BE NOTED HERE.
7. ALL EQUIPMENT AND MATERIALS USED IN THE DISTRIBUTION OF DOMESTIC POTABLE WATER SHALL BE APPROVED AND TESTED FOR SUCH APPLICATION
WITH DOCUMENTED LISTINGS AND LABELING IN ACCORDANCE WITH THE LATEST EDITION OF THE INTERNATIONAL PLUMBING CODE, PUBLIC LAW 111-380
AND ANSI/NSF-61, ANNEX G .
REMARKS:
1. FIXTURE DESIGNATED TO BE IN COMPLIANCE WITH ANSI-A117.1.
2. BATTERY POWERED SENSOR FAUCET, 0.5 GPM, 4" CENTERS, PROVIDE WITH TMV-2.
3. MANUAL FAUCET, 8" CENTERS, RIDGID GOOSENECK FAUCET, 2.2 GPM, WRISTBLADE HANDLES. PROVIDE WITH TMV-2.
4. SINGLE HOLE DRILLING, PROVIDE BLANK OFF FOR REAR CENTER HOLE, DECK MOUNTED FAUCET ON LEFT SIDE (COORDINATE WITH ARCHITECTURAL
CASEWORK), 8"CENTERS, RIDGID GOOSENECK VACUUM BREAKER, SERRATED NOZZLE, WRISTEBLADE HANDLES, 2.2 GPM.
5. RIGHT AND LEFT DRAIN BOARDS, 32"RIM HEIGHT(SPECIAL ORDER LEGS), REAR MOUNTED FAUCET, 8"CENTERS, 1.5 GPM, WRISTBLADE HANDLES.
6. ADA SHOWER SYSTEM, 5"HOSE WITH HAND HELD SHOWER, DIVERTER VALVE, PRESSURE BALANCING MIXING VALVE, 30"SLIDE BAR IN PLACE OF WALL
HOOK.
7. 2.5 GPM SHOWER HEAD, PRESSURE BALANCING MIXING VALVE.
8. BATTERY POWERED SENSOR FLUSH VALVE, 0.5GPF.
9. BATTERY POWERED SENSOR FLUSH VALVE, 1.28 GPF.
1/2"1-1/4" 2" 2" -- 1EWC-2J.R. SMITH
ELKAY VRCGRN8WSK0830
ELECTRIC WATER COOLERSUPPORT CARRIER
1/2"1-1/4" 2" 2" -- 1EWC-3J.R. SMITH
ELKAY VRCGRN80830
ELECTRIC WATER COOLERSUPPORT CARRIER
DRAIN STRAINER ELKAY LK-35
3/4"-- -- -- 3/4" 1S19-270BBRADLEYCOUNTER MOUNTED EYEWASH
EW-1BRADLEY S19-2000TEMPERING VALVE
REMARKS:
1. SURFACE MOUNTED, PROVIDE COMPLETE WITH WALL MOUNTING BRACKET; LEAD FREE DESIGN, INLET STRAINER CHECKSTOPS, INTEGRAL DIAL
THERMOMETER.
2. MINIMUM FLOW OF 0.5 GPM WITH OPERATIONAL CIRCULATION.
3. SINK AND LAVATORY TO MEET ASSE 1070.
TMV-1 BUILDING BRADLEY S59-3080-B 1" 1-1/4" 40 140 110 2.0 1,2
REMARKSMINIMUM FLOW
GPM
OUTLET
TEMPERATURE°FHWCW
INLET
TEMPERATURE °FOUTLET
SIZE INCH
INLET SIZE
INCHMODEL NUMBERMANUF.SERVICETAG
WATER MIXING VALVE SCHEDULE
1140115 VOLT/ 1 PHASE32501/8 HP27.0 FT.4.0 GPM3/4"3/4"009-SF5TACOCP-2
1120115 VOLT/ 1 PHASE32501/8 HP20.0 FT.10.0 GPM1-1/2"1-1/2"011-SF4TACOCP-1
REMARKSSERVICEELECTRICAL
CHARACTER.RPMHPHEADFLOW RATE
OUTLET
SIZE
INLET
SIZEMODEL NUMBERMANUF.TAG
DOMESTIC WATER CIRCULATION PUMP SCHEDULE
REMARKS:
1. STAINLESS STEEL CASING, SEALLESS, REPLACEABLE CARTRIDGE STYLE, FLANGED INLET AND OUTLET CONNECTIONS. PROVIDE COMPLETE WITH 24 HOUR
TIMER/ AQUASTAT COMBINATION CONTROLLER.
LM495-1POWERSTEMPERATURE MIXING VALVETMV-21/2" THREADED INLETS. PROVIDE WITH PAINTED WALL
MOUNTED CABINET AND CHECK STOPS.
J.R. SMITHTRAP GUARDTG-1
2" = 2692-02
3" = 2692-03
4" = 2692-04
BARRIER TRAP SEAL GUARD (ASSE 1072). PROVIDE SIZE
AS REQUIRED.
MM-500MIMBPPPWCB-1
STEEL BOX WITH STEEL FACEPLATE, SUPPORT
BRACKETS, SUPPLY PIPE OPENING. PROVIDE WATER
HAMMMER ARRESTOR ON SUPPLY LINE.
DISHWASHER BOX/
ICE MAKER BOX
982-VR909CAGCPCHICAGODECK MTD. DBL GAS/AIR TURRETGT-1 / AT-1
DUAL 90° TURRET W/VANDAL RESISTANT PIN, BALL
VALVE, ET7 SERRATED NOZZLE W/ CHECK VALVE AND
INDEX LEVER HANDLE.
SC-1250DPPPWATER HAMMER ARRESTORWHA-4
SC-1000CPPPWATER HAMMER ARRESTORWHA-3
SC-750BPPPWATER HAMMER ARRESTORWHA-2
SC-500APPPWATER HAMMER ARRESTORWHA-1
B67WOODFORDWALL HYDRANTWH-1
4710-UJ.R. SMITHWALL CLEANOUTWCO-1
MM-500MLBPPPWASHER BOXWB-1
Z-1180ZURNSOLIDS INTERCEPTORSI-1
1010Y-C-CIDJ.R. SMITHROOF DRAINRD-1
Z1181-E-SSZURNPLASTER TRAPPT-1
1070Y-C-CIDJ.R. SMITHOVERFLOW ROOF DRAINOD-1
998-RCFCHICAGOHOSE BIBBHB-2
B75WOODFORDHOSE BIBBHB-1
4880-UJ.R. SMITH2-WAY GRADE CLEANOUTGCO-2
4880-UJ.R. SMITHGRADE CLEANOUTGCO-1
3100Y-PDBS-12J.R. SMITHFLOOR SINK (ICE/FREEZERS)FS-5
9693-DBSJ.R. SMITHFLOOR SINK (DISHWASHER)FS-4
9693-DBSJ.R. SMITHFLOOR SINK (BOILERS)FS-3
3430Y-PDBS-12J.R. SMITHFLOOR SINK (KITCHEN)FS-2
3200Y-PDBS-12J.R. SMITHFLOOR SINK (WATER ENTRY)FS-1
2005Y-P050-F37J.R. SMITHFLOOR DRAIN (ICE/CONDENSATE)FD-3
2330Y-FBSJ.R. SMITHFLOOR DRAIN (HVAC PUMPS)FD-2
2005YJ.R. SMITHFLOOR DRAIN (GENERAL)FD-1
4220J.R. SMITHFLOOR CLEANOUTFCO-1
1770J.R. SMITHCONDUCTOR NOZZLECN-1
510FEBCOBACKFLOW PREVENTERBFP-3
975XLWILKINSREDUCED PRESSURE BACKFLOW
PREVENTERBFP-2
375WILKINSREDUCED PRESSURE BACKFLOW
PREVENTERBFP-1
STYLE 9ORIONACID NEUTRALIZATION TANKANT-1
REMARKSMODEL NOMANUFACTURERDESCRIPTIONTAG
PLUMBING EQUIPMENT SCHEDULE
COMPLETE WITH SERVICE ISOLATION VALVE
COMPLETE WITH SERVICE ISOLATION VALVE
COMPLETE WITH SERVICE ISOLATION VALVE
COMPLETE WITH SERVICE ISOLATION VALVE
BOX TYPE, 3/4" INLET, POLISHED CHROME
1-1/2" INLET AND OUTLET CONNECTIONS COMPOSITE
MAT'L., TOP ACCESS TYPE
ON FLOOR TYPE 2" INLET/OUTLET CONNECTIONS
REMOVABLE SEDIMENT BUCKET, ALLOW 14-1/2" ABOVE
UNIT FOR BASKET REMOVAL
VACUUM BREAKER SPOUT W/ HOSE THREAD OUTLET,
1/2"FPT INLET LOOSE KEY HANDLE
BOX TYPE, 1/2" INLET, POLISHED CHROME
1/2" INLINE DUAL CHECK VALVE ASSEMBLY. NSF-61.
1-1/2" MECHANICAL JOINTS ON INLET & OUTLET, TOP
INLET AND VENT, 6" CLEANOUT IN LID, 5 GALLON. DIP
TUBE
STAINLESS STEEL, 12" SQ. 10" DEEP WITH 1/2 GRATE
AND FLASHING FLANGE, DOME STRAINER. PROVIDE
WITH TRAP GUARD.
EXTEND FUNNEL DRAIN FULL SIZE TO FLOOR SINK.
NSF-61.
EXTEND FUNNEL DRAIN FULL SIZE TO FLOOR SINK.
NSF-61.
STAINLESS STEEL SHALLOW COVER, ROUND FACE W/
VANDAL RESISTANT CENTER SCREW.
3/4" INLETS, 2" OUTLET CONNECTIONS, RECESSED BOX
W/ SERVICE STOPS AND INTEGRAL WATER HAMMER
ARRESTORS.
NO HUB BOTTOM OUTLET, UNDER DECK CLAMP, CAST
IRON DOME STRAINER.
NO-HUB BOTTOM OUTLET, PVC OVERFLOW STANDPIPE
WITH UNDER DECK CLAMP, CAST IRON DOME STRAINER
(2) REQ'D. PROVIDE TYLER #003519 2-WAY CLEANOUT
FITTING, VANDAL RESISTANT SCREWS.
GALVANIZED FLANGED HOUSING WITH HEAVY DUTY
COVER, VANDAL RESISTANT SCREWS.
8.5" SQ. 6" DEEP W/ ALUMINUM DOME BOTTOM
STRAINER AND 1/2 NICKEL BRONZE GRATE. PROVIDE
WITH TRAP GUARD.
12" SQ. 8" DEEP W/ 1/2 DEPRESSED
STAINLESS STEEL GRATE AND STAINLESS STEEL
BOTTOM DOME STRAINER. PROVIDE WITH TRAP GUARD.
12" SQ. 8" DEEP W/ ALUMINUM DOME BOTTOM STRAINER
AND 1/2 A.R.C. GRATE. PROVIDE WITH TRAP GUARD.
16.5" SQ. 12" DEEP W/ ALUMINUM DOME BOTTOM
STRAINER AND 1/2 NICKEL BRONZE GRATE. PROVIDE
WITH TRAP GUARD.
6"Ø STRAINER W/ EXTENDED RIM AND VANDAL
RESISTANT SCREWS. PROVIDE WITH TRAP GUARD.
12" Ø BAR GRATE AND BOTTOM STRAINER. PROVIDE
WITH TRAP GUARD.
6" Ø STRAINER W/ VANDAL RESISTANT SCREWS.
PROVIDE WITH TRAP GUARD.
CAST IRON ADJUSTABLE CLEANOUT WITH ROUND
BRONZE TOP AND ABS PLUG.
BRONZE FINISH WITH WALL FLANGE.
TD-1 TRENCH DRAIN ZURN Z-806
ENVISIONMECHANICAL ENGINEERS INC.
9777 Pyramid Court, Suite 120Englewood, CO 80112Tel- 303-688-0223Fax- 303-688-3584envisionengrs.comProject #
CONSULTANT:
ISSUE:
OWNER:
PROJECT:
DRAWING INFORMATION:
DRAWN BY:
PROJECT NO:
SHEET TITLE:
APPROVED BY:
CHECKED BY:
SHEET OF
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
P 303.607.0977www.hcm2.com
1331 Nineteenth StreetDenver, CO. 80202
hord|coplan|macht
015-078
5/2
4/2
016 9
:46:5
5 P
M
C:\U
sers
\pfo
x.E
NV
ISIO
N.0
00\D
ocum
ents
\015-0
78 -
JeffC
O K
-8 -
PLU
MB
ING
CE
NT
RA
L_pfo
x.r
vt
P-610
PLUMBINGSCHEDULES
Jefferson County SchoolDistrict
CANDELAS K-8
JKB
JAL
11576.000
JKB
19486 WEST 94th AVENUEARVADA, CO 80007
1829 DENVER WEST DRIVEGOLDEN, CO 80401
05/25/16 WORK PACKAGE # 2 ISSUE FORCONSTRUCTION
05.25.2016