+ All Categories
Home > Documents > Consenting Under s36 of The Electricity Act

Consenting Under s36 of The Electricity Act

Date post: 24-Jan-2016
Category:
Upload: fran
View: 49 times
Download: 0 times
Share this document with a friend
Description:
Consenting Under s36 of The Electricity Act. Lesley McNeil Energy Consents and Deployment Unit. The Energy Consents and Deployment Unit. Responsibility for applications for onshore generating stations over 50 MW Team of 14 members of staff Unprecedented level of applications - PowerPoint PPT Presentation
Popular Tags:
12
Lesley McNeil Energy Consents and Deployment Unit
Transcript
Page 1: Consenting Under s36 of The Electricity Act

Lesley McNeilEnergy Consents and Deployment Unit

Page 2: Consenting Under s36 of The Electricity Act

Responsibility for applications for onshore generating stations over 50 MW

Team of 14 members of staff Unprecedented level of applications 9 month target determination for new

applications 41 determinations with 36 consents (2163

MW) in the last 36 months

Page 3: Consenting Under s36 of The Electricity Act
Page 4: Consenting Under s36 of The Electricity Act

Its never too early to call Energy Consents! Guidance for developers on our website at

http://www.scotland.gov.uk/Topics/Business-Industry/Energy/Infrastructure/Energy-Consents/Guidance

The team is available to discuss your project and our requirements as early as pre-scoping.

Engaging with ECDU and other consultees early = better applications = quicker determinations

Page 5: Consenting Under s36 of The Electricity Act
Page 6: Consenting Under s36 of The Electricity Act

Draft press notices and consultation list available on ECDU website

Consultation period for all consultees (except the Planning Authority) is at least 28 days.

Consultation period for Planning Authorities is 4 months

Consultation period for members of the public is two stage – 28 days followed by an additional 28 days after the first statutory consultation response.

Page 7: Consenting Under s36 of The Electricity Act

For the purposes of EIA SEI is entirely new information submitted in support of the application.

An SEI is an addendum to the application and requires a press notice and a further 28 days consultation period.

Page 8: Consenting Under s36 of The Electricity Act

An objection from the Local Planning Authority automatically triggers a Public Inquiry

Scottish Ministers also reserve the power to call a Public Inquiry where there is no objection from the LPA but they consider it appropriate to do so.

On average, referral to a PLI will add approximately 9-12 months to a determination timeframe.

Page 9: Consenting Under s36 of The Electricity Act
Page 10: Consenting Under s36 of The Electricity Act

S36 Conditions Deemed Planning Conditions

Discharged By

Scottish Ministers Planning Authority

With input from....

Page 11: Consenting Under s36 of The Electricity Act

Can we work better?Main considerations for large-scale applications under…

The Electricity Act 1989 The Electricity Works (Environmental Impact

Assessment)(Scotland) Regulations 2000 The Electricity (Applications for Consent)

Regulations 1990

Can all be found in full on Office of Public Service Information website (http://www.opsi.gov.uk/)

Page 12: Consenting Under s36 of The Electricity Act

Lesley McNeilThermal Consents and PolicyEnergy Consents and Deployment Unit0300 244 [email protected]

http://www.scotland.gov.uk/Topics/Business-Industry/Energy/Infrastructure/Energy-Consents


Recommended