Consolidation and Upgrade of the SPS Electrical NetworksCurrent StatusJP. Sferruzza, on behalf of EN/EL
JP. Sferruzza 2
Content of the Presentation
• Introduction on the SPS electrical networks;
• Problem statement;
• Current status of the project;
• Next steps;
• Collection of user requirements.
LIU-SPS 22/07/2015
JP. Sferruzza 3
Content of the Presentation
• Introduction on the SPS electrical networks;
• Problem statement;
• Current status of the project;
• Next steps;
• Collection of user requirements.
LIU-SPS 22/07/2015
JP. Sferruzza 4
The SPS Electrical Networks
Stable Network
• General services
• Lights• Ventilation• Racks,
etc…
Pulsed Network
• Power converters
Safety Network
• Lifts• Lights• Access• Fire
Detection• Ventilation
and smoke extraction
Different 400 kV transformersAssured by generators
LIU-SPS 22/07/2015
JP. Sferruzza 5
18 kV and 400 V Pulsed Network
EMD1/BE
SMB
x6
SQF SQD
18 kV EMD2/BE
SMB
x8
BA3BB3
400 kV
18 kV
BA4BA2
BA1
BA7 BA6
BA5
BB3
Build. 861
LIU-SPS 22/07/2015
JP. Sferruzza 6
18 kV and 400 V Stable Network
EMD1/E9
66 kV
18 kV
BA2
BA1
BA7
BA6
BA5
BB3
BA4
BA3
BB6
Build. 958
LIU-SPS 22/07/2015
JP. Sferruzza 7
BK1
3.3 kVBE91
Generators
BK2 BK3
BK4BB4
BB5BK5
Nominal Supply from EMD2/E91
18 kVSEM11
Generators
BK7
BK6
Nominal Supply from EMD2/E91ME9 18 kV
18kV, 3.3 kV and 400 V Safety Network
BK1 to BB5 : 3.3 kV feeders from BE91 (Building 791)
BK6 et BK7 : 18 kV feeders from SEM11 (Building 2160)
BK1
3.3 kVBE91
Generators
BK2 BK3
BK4BB4
BB5BK5
Nominal Supply from EMD2/E91
18 kVSEM11
Generators
BK7
BK6
Nominal Supply from EMD2/E91ME9 18 kV
LIU-SPS 22/07/2015
JP. Sferruzza 8
Content of the Presentation
• Introduction on the SPS electrical networks;
• Problem statement;
• Current status of the project;
• Next steps;
• Collection of user requirements.
LIU-SPS 22/07/2015
JP. Sferruzza 9
BK1
3.3 kV
Generators
BK2 BK3
BK4BB4
BB5BK5
Nominal Supply from EMD2/E91
18 kVSEM11
Generators
BK7
BK6
Nominal Supply from EMD2/E91ME9 18 kV
Consolidation Done – Safety Network & UPSBK substations installed in 2000
LIU-SPS 22/07/2015
JP. Sferruzza 10
Consolidation Done – High Voltage Cables
High voltage cables replaced during LS1
LIU-SPS 22/07/2015
JP. Sferruzza 11
Status of the other Equipment
20351970 200020232024
SPS Installation
LS2 LS3
Foreseen run of HL-LHC
2015
Today
LIU-SPS 22/07/2015
Mid 20182019
JP. Sferruzza 12
Status of the other Equipment
20351970 200020232024
Installationof the
electrical networks
LS2 LS3
Foreseen run of HL-LHC
2015
Today
Decreasing reliability
High voltage switchgears, transformers;Auxiliary power supply;Low voltage switchboards;Underground power distribution;
BK substations;Uninterrupted Power Supplies (UPS)
UPS lifetime
Recommended lifetime of the electrical equipment
LIU-SPS 22/07/2015
Mid 20182019
JP. Sferruzza 13
Example of Failure
LIU-SPS 22/07/2015
• Blast in EMD5/B3 on 22/09/2013 (during LS1);
• The switchgear had to be replaced (>6 months);
• During a run, such a failure would stop the SPS for several
weeks in the best case (with a temporary solution).
EDMS 1314867
JP. Sferruzza 14
Content of the Presentation
• Introduction on the SPS electrical networks;
• Problem statement;
• Current status of the project;
• Next steps;
• Collection of user requirements.
LIU-SPS 22/07/2015
JP. Sferruzza 15
Current Status
• Preliminary study started in February 2015;
• Overview of the current status of the SPS electrical networks;
• Identification of the risks on the project;
• Project roadmap, priorities.
LIU-SPS 22/07/2015
JP. Sferruzza 16
Work Packages Definition and Priority
Network Equipment Quantity to be replacedObsolescence
degreeImpact of a failure Priority
Work
Package
Stable and pulsed
networks
-
Primary distribution
HV transformers 22
High
Shutdown of the
SPS
Possible impact on other sites
High WP1
HV cubicles 84
HV cables 1-2 km
LV primary switchboards 34
Auxiliary power supply systems 18
Stable and pulsed
networks
-
Secondary distribution
LV secondary switchboards 71
HighComplete or partial
shutdown of the
SPS, depending on
the circuit
Mediu
m
WP2
UPS 17
Underground power
distribution and lights
Underground power distribution 370 boxes, 70 km cablesHigh
WP3Normal lights 1100 lights, 14 km cables LowLow
Safety network
Backup lights 350 lights, 14 km cables High Safety - low impact
Emergency lights 310 lights, 14 km cables Very High Safety - high impact
Very
High
WP4
HV transformers 4
HighAccess, safety of
personnelWP5HV cubicles 2
LV secondary switchboards 3
LIU-SPS 22/07/2015
JP. Sferruzza 17
Risks - Interaction with other Projects
Electrical Networks
Consolidation
Identification & De-cabling of Obsolete
Equipment in the Injectors
LIU Project
LIU-SPS 22/07/2015
Upgrade
It is also a chance!
JP. Sferruzza 18
Risks - Interaction with non-EL Users
Electrical Network Consolidation Project
Non-EL Users
Some works planned by non-EL users will require the availability of some parts of the networks concerned by the EL consolidation
Some new needs will have to be taken into account by an “upgrade” part of the project
LIU-SPS 22/07/2015
COORDINATION MEETINGS
JP. Sferruzza 19
Content of the Presentation
• Introduction on the SPS electrical networks;
• Problem statement;
• Current status of the project;
• Next steps;
• Collection of user requirements.
LIU-SPS 22/07/2015
JP. Sferruzza 20
Next Steps
• Beginning of the study phase in June;
• The study phase will require the collection of user needs for upgrade;
• Objective of the study phase: define a general strategy for all SPS sites, end 2015.
LIU-SPS 22/07/2015
JP. Sferruzza 21
Project Costing
• A detailed cost breakdown for the consolidation works will be provided after completion of the study phase;
• Funding for the consolidation will be covered by EL-SPS & ACC-CONS;
• The cost of dedicated upgrades for projects such as LIU shall be covered by the project concerned.
LIU-SPS 22/07/2015
JP. Sferruzza 22
Content of the Presentation
• Introduction on the SPS electrical networks;
• Problem statement;
• Current status of the project;
• Next steps;
• Collection of user requirements.
LIU-SPS 22/07/2015
JP. Sferruzza 23
Collection of User Requirements - Timeline
LIU-SPS 22/07/2015
June Dec.July Aug. Sept. Oct. Nov.
Memo
Identification of concerned projects and
project leaders
For each project, electrical load schedule to be studied with the
help of EN/ELValidation
End Study Phase Beginning Design Phase Objective: first installation
works during EYETS 2016
2016
JP. Sferruzza 24
Collection of User Requirement - Parameters
• List of electrical loads, location;
• Rated power;
• Absorbed power;
• Power factor;
• Nominal voltage;
• Load profile;
• Load criticality;
• Space required;
• Planning of installation and commissioning.LIU-SPS 22/07/2015
JP. Sferruzza 25
Conclusion
• A wide project for EN/EL, able to ensure the reliability of the SPS electrical supply for the next 30 years;
• Good opportunity to coordinate upgrade and consolidation works in a single project;
• The Study Phase requires the collection of user needs for upgrade (for end of October 2015);
• General strategy for all SPS site to be determined by the end of the year.
LIU-SPS 22/07/2015