+ All Categories
Home > Documents > Constructing a network diagram

Constructing a network diagram

Date post: 17-Nov-2014
Category:
Upload: nelramlawy
View: 44,777 times
Download: 3 times
Share this document with a friend
Description:
hftyhty
Popular Tags:
45
BUSINESS DECISION BUSINESS DECISION ANALYSIS ANALYSIS Constructing a Network Diagram Click function key F5 to run this lecture as a Slide Show
Transcript
Page 1: Constructing a network diagram

BUSINESS DECISION BUSINESS DECISION ANALYSISANALYSIS

Constructing a Network Diagram

Click function key F5 to run this lecture as a Slide Show

Page 2: Constructing a network diagram

Are there any pre-requisites for this topic?

NO. You may have come across

terms like “critical path”

but no knowledge is

pre-supposed.

Page 3: Constructing a network diagram

Project management is also referred to as:

network analysis

critical path analysis

PERT - program evaluation & review technique

Page 4: Constructing a network diagram

OK, so what’s a project?

Well any managerial

activity can be represented as

a project.

For example:

• developing a new product or service

• marketing a new product or service

• breaking into a new market

• building a new plant

• installing a new computer system

• planning a training programme

• re-locating head office.

Page 5: Constructing a network diagram

What do your example

projects have in common?

Each can be decomposed into its

constituent parts, called ACTIVITIES.

We can then define a project as a collection

of related activities.

Three things are important:

• each activity takes time

• each activity uses up resources

• activities are structured.

Page 6: Constructing a network diagram

What gives activities

structure?

Precedence:

some activities have to be completed before others

can be started.

But that’s too vague. A roof cannot be erected unless the foundations have been dug. Obviously

true! So digging foundations must precede erecting the roof! But what about the walls?

So we refer to the immediately preceding activities.

Page 7: Constructing a network diagram

The first step for any project is to:

• list the constituent activities

• arrange them into a Precedence Table.

Activity Description Preceding TimeActivity (weeks)

A Survey site - 6

BDevelop initial proposal

- 8

CObtain approval of governors

A,B 12

D Choose architect C 4E Work out budget C 6F Finalise design D,E 15G Agree financing E 12H Hire contractor F,G 8

The project is to build an extension to the Recreation Centre. The table lists the activities

and their immediate

predecessors – up to the point of starting

construction.

Page 8: Constructing a network diagram

And here’s another project …………. “purchase of a new car”.

Activity DescriptionPreceding Activity

Duration (days)

A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3

Page 9: Constructing a network diagram

Is activity B a pre-condition for starting activity I?

NO

Activity DescriptionPreceding Activity

Duration (days)

A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3

Page 10: Constructing a network diagram

Is activity A a pre-condition for starting activity K?

YES

Activity DescriptionPreceding Activity

Duration (days)

A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3

Page 11: Constructing a network diagram

Can activities E and F take place at the same time?

YES

Activity DescriptionPreceding Activity

Duration (days)

A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3

Page 12: Constructing a network diagram

Precedence tables aren’t that easy to use. Is there

some other way of representing a project?

Y E S

A useful visual representation of a project is obtained by

drawing a network diagram.

Page 13: Constructing a network diagram

This is how we represent an activity.

activityevent of starting

an activityevent of ending

an activity

get out of bed

So somewhere in the project “Get to University Monday Morning” will be:

Page 14: Constructing a network diagram

Err .. but we’ll need to link activities together,

won’t we. That’s correct.

Sometimes we might want to show:

ActivityPreceding Activity

A -B AC B

A B C

Page 15: Constructing a network diagram

Err .. but we’ll need to link activities together,

won’t we. That’s correct.

Sometimes we might want to show:

ActivityPreceding Activity

M K,L

MK

L

Page 16: Constructing a network diagram

ActivityPreceding Activity

B AC A

Err .. but we’ll need to link activities together,

won’t we. That’s correct.

Sometimes we might want to show:

AB

C

Page 17: Constructing a network diagram

Are there any rules to follow when drawing network diagrams? YES

1. Must be drawn from left to right.

2. Must have a single starting point.

3. Also a single ending point.

4. One arrow (only) per activity.

5. Must correctly reflect the precedence table.

Page 18: Constructing a network diagram

There is one complication that we need to allow for.

OK, tell me the worst!!

Sometimes we have to use Dummy activities.

We use a dashed arrow to record these.

A dummy activity may be needed:

• to prevent 2 or more activities sharing the same starting and ending events.

• to maintain network logic – i.e. to ensure that the network abides by the precedence table.

Page 19: Constructing a network diagram

DETAILS

OK. Let’s have a go at drawing a network.

We’ll draw the one for the extension to

the recreation centre.

Page 20: Constructing a network diagram

DETAILS

Where do I

start?

Well, a network must have a single starting point – a circle or node.

Once the project has started which activities can be begun?

A Survey site

B Develop initial proposal

Page 21: Constructing a network diagram

DETAILS

A

B

So we draw arrows for activities A & B running from the starting event. Make sure that you label

the activities as you include them in the network.

What comes next?

Activity Preceding Activity

C A,B

Page 22: Constructing a network diagram

DETAILS

Well is this correct. Does it abide by the rules for drawing network diagrams?

That’s no problem. Just do

this.

Activity Preceding Activity

C A,B

A

BC

RULES

NO Two or more activities may not share the same starting and ending event.

Page 23: Constructing a network diagram

DETAILS

Use a dummy activity. Here’s one way in which it can be done. It prevents A & B from sharing the same starting and ending event.

So how do I remedy

this error?

RULES

A

B

C

Page 24: Constructing a network diagram

DETAILSRULES

A

B

C

Activities D & E can start when C is finished.

E

D So we’ll add these to the network.

Page 25: Constructing a network diagram

DETAILSRULES

The table says that F can start when D & E are

completed.

So can we do this?

A

B

CE

D

F

Page 26: Constructing a network diagram

DETAILSRULES

No. We’ve broken the rules again.

A

B

CE

D

F

So another dummy activity

is needed.

Page 27: Constructing a network diagram

DETAILSRULES

This will

work.

A

B

C

E

D

F

Page 28: Constructing a network diagram

RULES

Now we can add

activity G.

A

B

C

E

D

F

DETAILS

G

G can be started once E is

completed.

Page 29: Constructing a network diagram

RULES

That leaves

activity H.

A

B

C

E

D

F

DETAILS

G

The start of H requires the

completion of F and G.

Page 30: Constructing a network diagram

RULES DETAILS

A

B

C

E

D

F

G

H

So we bring the arrows for F & G into the starting event for activity H.

And this is the finished

network.

Page 31: Constructing a network diagram

RULES DETAILS

A

B

C

E

D

F

G

H

Always check the network against the

precedence table before continuing.

Page 32: Constructing a network diagram

RULES DETAILS

Right, now we’ll draw the network for the project of

buying a new car.

For this project there’s only one starting activity,

namely A

Page 33: Constructing a network diagram

RULES DETAILS

A

Activities B & C can be started

once A is completed.

B

C

Page 34: Constructing a network diagram

RULES DETAILS

A

And D, E & F can be started

when C is completed.

B

C

D

E

F

Page 35: Constructing a network diagram

RULES DETAILS

Activity G requires

completion of D, E & F.

So two dummy activities are needed to prevent D, E & F having the same

starting and ending events.

A B

C

D

E

F

G

Page 36: Constructing a network diagram

RULES DETAILS

Activity H can now be added to the

network.

A B

C

D

E

F

GH

Page 37: Constructing a network diagram

RULES DETAILS

I & J can now

start.

A B

C

D

E

F

GH

IJ

Page 38: Constructing a network diagram

RULES DETAILS

Since the start of K needs completion of I & J we need another dummy

activity.

A B

C

D

E

F

GH

IJ

K

Page 39: Constructing a network diagram

RULES DETAILS

Now we add

activity L

A B

C

D

E

F

GH

IJ

K

L

Page 40: Constructing a network diagram

RULES DETAILS

A B

C

D

E

F

GH

IJ

K

L

M

N

Activities M & N can now be

started.

Page 41: Constructing a network diagram

RULES DETAILS

A B

C

D

E

F

GH

IJ

K

L

M

N

That leaves

activity O.

It can be started when activities B, M & N are completed.

Page 42: Constructing a network diagram

RULES DETAILS

A B

C

D

E

F

GH

IJ

K

L

M

N

That leaves

activity O.

A dummy activity will be needed to separate activities M and N.

Page 43: Constructing a network diagram

RULES DETAILS

A

C

D

E

F

GH

IJ

K

L

M

N

The network is

now completed.

OB

But remember to

check it against the precedence

table.

Page 44: Constructing a network diagram

What should I now be able to do?

Given the precedence table for a project, you should be able to draw

its network diagram.

Page 45: Constructing a network diagram

That’s the end of this lecture. You should now explore the problems, on drawing networks, that

are available within Blackboard.


Recommended