+ All Categories
Home > Documents > Construction and Environment Note Sode

Construction and Environment Note Sode

Date post: 03-Apr-2018
Category:
Upload: gunjan-jaiswal
View: 230 times
Download: 2 times
Share this document with a friend

of 96

Transcript
  • 7/29/2019 Construction and Environment Note Sode

    1/96

    By Prof SACHIN JAIN 1

    Construction and environment

    By

    Prof SACHIN JAIN

  • 7/29/2019 Construction and Environment Note Sode

    2/96

    2

    Climate change Ozone layer depletion Acidification

    Eutrophication

    Depletion ofrenewable resources

    Depletion of non-renewable resources

    Winter and summer smog

    Eco-Toxicity

    Generationof waste

    Environmental impacts

  • 7/29/2019 Construction and Environment Note Sode

    3/96

    3

    A significant part of these impactscome from the construction sector(construction, use and maintenanceof infrastructures).

    The impact of use and maintenancecan be significantly more importantthan the impact of construction.

    Examples: roads or buildings.

  • 7/29/2019 Construction and Environment Note Sode

    4/96

    4

    Quantitative assessment

    of all measurable effects

    Maintenance of buildings

    Production of goods

    Transport of goods

    Examples of processes or products

  • 7/29/2019 Construction and Environment Note Sode

    5/96

    5

    E

    xamplesofparametersa

    ssessed

    Production of goods(for a specific process in a specific factory)

    Consumption of raw materials andproducts (quantity/product)

    Emission of gases, and of

    solid and liquid wastes(quantity/product)

    Transport(for a specific truck in a specific trip)

    Emission of different gases(quantity/km or trip)

    Consumption of fuel,oil, tyres, etc.

    (quantity/km or trip)

  • 7/29/2019 Construction and Environment Note Sode

    6/96

    By Prof SACHIN JAIN 6

    Any processExample: production of1 kg of clinker in a kiln

    Products

    1 kg of clinker

    (Energy)(MJ of heat)

    Raw materialskg of limestone,

    of clay, etc.

    Wastes

    Solid - Liquid Gaskg of dust, contaminated water, NOx, SOx, ...

    EnergyMJ (fuels,electricity)

    Productskg of explosives, of

    admixtures, etc.

  • 7/29/2019 Construction and Environment Note Sode

    7/96

    By Prof SACHIN JAIN 7

    To be defined:- functional unit

    - cradle-grave, cradle-gate- system boundaries

  • 7/29/2019 Construction and Environment Note Sode

    8/96

    8

    Examples

    A badly isolated building may have a lower environmental

    impact up until construction is completed (fewer materials

    required) but will have a much higher impact during usebecause of thermal conditioning.

    A material can have an important impact in production (for

    instance high energy consumption) but very low afterwards

    (low maintenance and recyclable) or vice versa.

  • 7/29/2019 Construction and Environment Note Sode

    9/96

    By Prof SACHIN JAIN 9

    What if function changes?

    RecyclingLandfill

    Abandonment

    Repairing,renovating,transforming...

    Functional unit to be redefined !(new life cycle)

    Demolition

  • 7/29/2019 Construction and Environment Note Sode

    10/96

    By Prof SACHIN JAIN 10

    Construction waste management

    for better environment

  • 7/29/2019 Construction and Environment Note Sode

    11/96

    By Prof SACHIN JAIN 11

    Construction and demolition waste overview

  • 7/29/2019 Construction and Environment Note Sode

    12/96

    By Prof SACHIN JAIN 12

    Typical composition of waste

    Hardcore recycling rates

  • 7/29/2019 Construction and Environment Note Sode

    13/96

    By Prof SACHIN JAIN 13

    Best practice targets for longer term

  • 7/29/2019 Construction and Environment Note Sode

    14/96

    By Prof SACHIN JAIN 14

    C&D waste possible routes

  • 7/29/2019 Construction and Environment Note Sode

    15/96

    By Prof SACHIN JAIN 15

    Causes of waste on site

  • 7/29/2019 Construction and Environment Note Sode

    16/96

    16

    Hacking off concrete becomes concrete waste

    Broken bag of crush stone Improper stacking of tiles

  • 7/29/2019 Construction and Environment Note Sode

    17/96

    17

    Left over mortar becomes waste Wooden package disposed

    Cutting waste of reinforcement

    Waste materials are not

    segregated from useful material

  • 7/29/2019 Construction and Environment Note Sode

    18/96

    18

    Damage of drywall panels

    Cutting wasteof dry wall

    Lost of plaster while applyingCutting waste of tiles

  • 7/29/2019 Construction and Environment Note Sode

    19/96

    By Prof SACHIN JAIN 19

  • 7/29/2019 Construction and Environment Note Sode

    20/96

    20

    Percentage wastage of materials in public housing

  • 7/29/2019 Construction and Environment Note Sode

    21/96

    21

    Percentage wastage of materials for various trades for private residential

    building

  • 7/29/2019 Construction and Environment Note Sode

    22/96

    By Prof SACHIN JAIN 22

    Wastage management

  • 7/29/2019 Construction and Environment Note Sode

    23/96

    By Prof SACHIN JAIN 23

    Waste Management Hierarchy

  • 7/29/2019 Construction and Environment Note Sode

    24/96

    By Prof SACHIN JAIN 24

    Resource Optimization

    (Rethink Design)

    Reduce Packaging

    Implement efficient,material saving

    construction technique

    Source Reduction

    (Accurate Estimating

    & ordering)Prevention

    Prevention of waste generation in construction

  • 7/29/2019 Construction and Environment Note Sode

    25/96

    By Prof SACHIN JAIN 25

  • 7/29/2019 Construction and Environment Note Sode

    26/96

    By Prof SACHIN JAIN 26

    Reuse

  • 7/29/2019 Construction and Environment Note Sode

    27/96

    By Prof SACHIN JAIN 27

    Selective Demolition Methodology

  • 7/29/2019 Construction and Environment Note Sode

    28/96

    28

    Flow Chart for

    Recycling Process

  • 7/29/2019 Construction and Environment Note Sode

    29/96

    By Prof SACHIN JAIN 29

  • 7/29/2019 Construction and Environment Note Sode

    30/96

    By Prof SACHIN JAIN 30

  • 7/29/2019 Construction and Environment Note Sode

    31/96

    By Prof SACHIN JAIN 31

    Various types of crushers

  • 7/29/2019 Construction and Environment Note Sode

    32/96

    By Prof SACHIN JAIN 32

    Uses of recycled material

    Secondary aggregates for road (capping layer and sub base)

    construction Top soil Drainage media Capillary break layers on contaminated land

    Metal (steel reinforcement)

    Large timber sections Wood for fuel and kindling and use as a filler material in the

    manufacture of medium density fiber board Paving slabs

    Bricks

  • 7/29/2019 Construction and Environment Note Sode

    33/96

    By Prof SACHIN JAIN 33

    Concrete the non waste in waste stream

  • 7/29/2019 Construction and Environment Note Sode

    34/96

    By Prof SACHIN JAIN 34

    What is Recycled Concrete?

  • 7/29/2019 Construction and Environment Note Sode

    35/96

    By Prof SACHIN JAIN 35

    Concrete to be Recycled

  • 7/29/2019 Construction and Environment Note Sode

    36/96

    By Prof SACHIN JAIN 36

    Where Does Recycled Concrete

    Come From?

    Local Sources

    CRD Construction, Renovation & Demolition

    Buildings

    Road/Parking Lot Reconstruction

  • 7/29/2019 Construction and Environment Note Sode

    37/96

    By Prof SACHIN JAIN 37

    Concrete Crushing

  • 7/29/2019 Construction and Environment Note Sode

    38/96

    By Prof SACHIN JAIN 38

    Benefits of Recycling Concrete

    Local Product Local Sources

    Reduces Truck Traffic

    Alternative to a Non-Renewable Resource

    Cost Savings

    No Disposal Fees

    Better Trucking Utilization (Reduced Costs)

    Allow up to 10% Deleterious Materials

  • 7/29/2019 Construction and Environment Note Sode

    39/96

    By Prof SACHIN JAIN 39

    Processed Concrete

    Plasma Gasification Cupola for energy production from wastage

  • 7/29/2019 Construction and Environment Note Sode

    40/96

    By Prof SACHIN JAIN 40

    Plasma Gasification Cupola for energy production from wastage

  • 7/29/2019 Construction and Environment Note Sode

    41/96

    By Prof SACHIN JAIN 41

    This method is used in St Lucie Country which contains more than 4million tons of MSW.

    The MSW will be conveyed to one of of six cupolas that will have aceramic interior and a steel exterior, the latter immersed in water

    Six plasma torches will create arcs of artificial lightening in eachcopula that will heat the space to temperatures greater than thoseon the surface of sun, changing the municipal waste to a gaseous orliquid state.

    The gas formed will exit the chamber at a temperature ofapproximately 2300oF (1260oC) and will be transported to a gascleaning facility, where wet scrubbers and a wet electrostaticprecipitator will extract sulfur, chlorines, dust and such volatilemetals as mercury and cadmium.

    After the gashes been cleaned it will enter a gas turbine electricgenerator with a capacity of 160 MW per day.

  • 7/29/2019 Construction and Environment Note Sode

    42/96

    By Prof SACHIN JAIN 42

    40 MW of which will be used to power the gasification plant andremaining 120 MW is supplied to grid.

    Supper heated liquid by product will be cooled to from a solidvitreous slag that will be broken to small granules.

    These granules can be used as aggregate in asphalt or concrete.

    The new plant will be capable of processing 3000 tones (2700metric tones)of MSW per day.

    Some of 2000 tones of new MSW will be taken from existing

    Landfills. Plant is capable of processing dewatered sludge and can take up to

    15% of 3000 tones daily load as sludge.

  • 7/29/2019 Construction and Environment Note Sode

    43/96

    By Prof SACHIN JAIN 43

    Construction of Dry Tomb Land fill

  • 7/29/2019 Construction and Environment Note Sode

    44/96

    By Prof SACHIN JAIN 44

    Leave it Alone

  • 7/29/2019 Construction and Environment Note Sode

    45/96

    By Prof SACHIN JAIN 45

    Environment Impact Assessment

  • 7/29/2019 Construction and Environment Note Sode

    46/96

    By Prof SACHIN JAIN 46

    Environmental Impact Assessment (EIA) is an instrument ofreconciliation.

    The Council on European Economic Committee, in their directive tothe member states, highlights the objectives of EIA.

    The effects of a project on the environment must be assessed inorder to take account of

    The concerns to protect human health,

    To contribute by means of a better environment to the quality of life,

    To ensure maintenance of the diversity of species and to maintainthe reproductive capacity of the ecosystem as a basic resource of

    life.

  • 7/29/2019 Construction and Environment Note Sode

    47/96

    By Prof SACHIN JAIN 47

    Prevention Rather Than Cure

    It is essential that consequences of projects, plans or policies

    at different levels be assessed before they are executed.

    EIA examines these consequences and predicts future

    changes in the environment.

    It guides administrative agencies in balancing conflicting social

    values and environmental quality.

    It helps them to make the best choice among various available

    options.

    EIA foresees and avoids potential dangers.

  • 7/29/2019 Construction and Environment Note Sode

    48/96

    By Prof SACHIN JAIN 48

    The Mandatory Model

    Power coupled with duty is the most salient feature of the mandatorymodel of impact assessment.

    The decision-making agency is obliged to study the impact of adevelopment proposal before it is approved.

    The EIS serves as a guarantee of the right to information and abasis for proper impact assessment.

  • 7/29/2019 Construction and Environment Note Sode

    49/96

    By Prof SACHIN JAIN 49

    Pleas Against And In Favor

    The EIS on which assessment is made is often too lengthy,

    Environmentalists may try to delay development by raisingfalse pleas of defects in impact statements.

    EIS may impose procedural burden rather than afford anopportunity to improve decision-making.

    Public participation and judicial review play key roles asintegral parts of mandatory model.

    They make EIA into a reasoned and objective process andmake it an important tool in protecting and managing theenvironment.

  • 7/29/2019 Construction and Environment Note Sode

    50/96

    50

    The Discretionary Model

    Merits

    It depends on the discretionary powers of the administration.

    This model exhibits flexibility and maintains a harmony betweendevelopmental needs and environmental values;

    experts can make a choice from available alternatives.

    Quick, expert and timely decision-making is the advantage of thismodel.

    Public participation is not allowed as a matter of routine,

    Demerits

    Experts within the government may go wrong,

    Reasons for decisions may not be disclosed;

    Interests of weaker or vulnerable groups and regions could beneglected;

    Alternative opinions, expressed outside the realms ofadministration, may be overlooked or disregarded;

  • 7/29/2019 Construction and Environment Note Sode

    51/96

    By Prof SACHIN JAIN 51

    METHODOLOGY OF EIA

  • 7/29/2019 Construction and Environment Note Sode

    52/96

    By Prof SACHIN JAIN 52

    The EIA can be broadly divided into the following steps,

    basics,

    environmental setting,

    impact prediction and assessment.

  • 7/29/2019 Construction and Environment Note Sode

    53/96

    By Prof SACHIN JAIN 53

    Basics

    One must have a fair understanding and knowledge of thestudy.

    Starting with the need for the project one must identifyalternative solutions to meet this need.

    Also with these solutions a no-project alternative should be

    included.

    Since impacts due to alternative solutions may widely differdepending upon the alternative itself it is necessary to broadlyexamine each alternative and the factors that are most

    affected.

    Environmental Setting

  • 7/29/2019 Construction and Environment Note Sode

    54/96

    By Prof SACHIN JAIN 54

    Environmental Setting

    It provides baseline information against which predictions andassessments of the impacts for each alternative can be compared.

    The factors can be classified under physical-chemical (e.g. air andwater quality, soil fertility, etc.) biological (flora and fauna), cultural(archaeological sites, recreation, etc.) and socio-economic (populationcharacteristics, economic state, etc.).

    Impact Prediction and Assessment

    This is a complex task involving widely different techniques in differing

    disciplines.

    As measurement techniques vary, interpretation varies, and therefore a

    number of methodologies have been developed for presentation of theseimpacts to decision makers and the general public public.

  • 7/29/2019 Construction and Environment Note Sode

    55/96

    By Prof SACHIN JAIN 55

    Methodologies for Environmental Impact

    Assessment

    Adhoc

    Checklists

    Matrices

    Networks

    Overlay techniques

    Adh

  • 7/29/2019 Construction and Environment Note Sode

    56/96

    By Prof SACHIN JAIN 56

    Adhoc

    These were the first methods to be used in the preparation of EIA.

    The procedure involves the bringing together of various experts in

    particular fields to identify impacts in their area of expertise.

    The environment is generally divided into broad categories, the

    assessment of which could be intuitive or subjected to qualitativeinterpretation of quantitative results.

    The adhoc approach has little or no formal analytical structure and

    at most provides only a preliminary review.

    Ch kli t

  • 7/29/2019 Construction and Environment Note Sode

    57/96

    By Prof SACHIN JAIN 57

    Checklists

    Checklists can be of various types ranging from simple to fairlysophisticated.

    Simple checklists have no guidelines on how to measure andinterpret environmental impacts.

    Descriptive checklists are more structured with identification ofenvironmental parameter and guidelines on how parameterdata is to be measured.

    Scaling checklists go a step further by providing information onhow the parameter values are scaled.

    Lastly, there are scaling-weighting checklists that provideadditional information on relative weights of importance ofeach parameter.

  • 7/29/2019 Construction and Environment Note Sode

    58/96

    By Prof SACHIN JAIN 58

    Interaction Matrices

    This method develops on the checklist method byincorporating a list of project activities to a checklist of potentialimpact environmental characteristics.

    Developed by Leopold et al. (described in Canter, 1977) themethod involves the use of a matrix with 100 specified actionsand 88 environmental items.

    Each cell represents an impact that is a result of interactionbetween an action and an environmental item.

    As with the EES two aspects of each impact needs to bedetermined, namely, magnitude and importance.

    Both of these are assigned a numerical scale from one to ten.

  • 7/29/2019 Construction and Environment Note Sode

    59/96

    By Prof SACHIN JAIN 59

    It is possible to expand or contact the matrix, i.e. action or

    environmental items not included can always be added and vice-

    versa i.e. items or action having no relevance he project underquestion can be deleted.

    It is also possible to represent cell entries as qualities estimates of

    the cause effect relationships.

    Networks

  • 7/29/2019 Construction and Environment Note Sode

    60/96

    By Prof SACHIN JAIN 60

    Networks

    Network approaches can expand on the matrix theme byintroducing a cause condition effect network, which allowsidentification of cumulative or indirect effects.

    The network is depicted in the form of a tree, called arelevance or impact tree, and is used to relate and recordsecondary, tertiary and higher order effects.

    To understand this technique considers the impact tree.

    Activity A has two primary impacts, three secondary impactsand four tertiary impacts.

    There are ten branches of the tree.

    O l T h i

  • 7/29/2019 Construction and Environment Note Sode

    61/96

    By Prof SACHIN JAIN 61

    Overlay Techniques

    This methodology essentially consists of developing a set of

    maps of environmental characteristics such as physical, social,etc. for a project area and overlaying these maps

    (transparencies) to create a composite map, which shows the

    spatial distribution of the selected impacts.

    The overlay approach is generally effective in its ability to set aproposed project within a geographical context and to indicate

    spatial relationships between the environmental factors that

    are regarded as relevant to the assessment of the project.

    However it cannot be used to identify impacts or identifysecondary and tertiary relationships.

  • 7/29/2019 Construction and Environment Note Sode

    62/96

    By Prof SACHIN JAIN 62

    The method has been used to identify the optimal routing fortransmission lines and site selection processes for coal and oilrelated developments (Codoni et al., 1985).

    The method was also applied on the Huasai- Thale- Noi RoadProject in Thailand where the project was halted due toenvironmental concern.

    An alternative route was determined by using rough overlays of theenvironmental site selection parameters (lohani and Halim, 1986).

  • 7/29/2019 Construction and Environment Note Sode

    63/96

    By Prof SACHIN JAIN 63

    Conceptual EIA of large

    scale electric power plants

    India produces electricity mainly from coal hydro and from nuclear

  • 7/29/2019 Construction and Environment Note Sode

    64/96

    By Prof SACHIN JAIN 64

    India produces electricity mainly from coal, hydro, and from nuclearalbeit in a limited way.

    The environmental impacts from each of these modes are widely

    different. Also within each type, differences in magnitude arise due to location

    features, type of inputs, equipments, etc.

    The setting up of a power plant leads to growth and development inthat area.

    These benefits would arise irrespective of the type of power plant.

    The negative impacts occur through the air water and land mediaand are type and location-specific.

    The issues/methodology for quantification of the impacts and theirrelative weighting for different type of power plants are brieflydiscussed below.

  • 7/29/2019 Construction and Environment Note Sode

    65/96

    By Prof SACHIN JAIN 65

    Coal based thermal power

    generation

  • 7/29/2019 Construction and Environment Note Sode

    66/96

    By Prof SACHIN JAIN 66

    Air Pollution

    Air pollution occurs as a result of the emission of

    Particulates (SPM),

    Oxides of Sulphur (SOx),

    Oxides of Nitrogen (NOx),

    Fly ash

  • 7/29/2019 Construction and Environment Note Sode

    67/96

    By Prof SACHIN JAIN 67

    Air pollution control

    SPM Control

    SOx Control

    NOx Control

    SPM C t l

  • 7/29/2019 Construction and Environment Note Sode

    68/96

    By Prof SACHIN JAIN 68

    SPM Control

    Pre and post combustion control measures exist for all the majorpollutants.

    At present, the installation of electrostatic precipitators (ESP) for thecontrol of SPM emissions are mandatory in India

    The average cost of SPM control by ESPs is approximately 1 % of thecost of generation.

    ESP usually operate at efficiencies of 99 percent and above, theefficiencies generally being relatively insensitive to particle size butgrade efficiency curves indicate a minimum in the 0.2-2 micrometerrange (Wall 1986).

    Fabric filters are preferred for their high overall collection efficiency,which is maintained over a wide range of particle sizes.

    For submicron particles, bag filter systems in terms of collectionefficiencies are superior to all other control technologies.

    SO C l

  • 7/29/2019 Construction and Environment Note Sode

    69/96

    By Prof SACHIN JAIN 69

    SOx Control

    Given the low levels of sulphur in most Indian coals, the emissionsof SOx in most cases are likely to fall within ambient standards

    Only those areas that are already having high sulphur emissionssuch as the Singrauli area or in certain metropolitan cities wouldrequire Flue Gas Desulphurisation (FGD) equipment.

    Damage from SOx emissions are maximum in areas which alreadyhave heavy particulate loading.

    FGDs typically operate at efficiencies around 90 percent andcontribute to a 25-30 percent increase in the cost of generation.

    NOx Control

  • 7/29/2019 Construction and Environment Note Sode

    70/96

    By Prof SACHIN JAIN 70

    NOx Control

    NOx emissions were never considered significant contributorsto environmental degradation.

    However, in recent years increasing attention is being paid tothe environmental damage from NOx emissions and methodsto reduce it.

    Low NOx burners provides an inexpensive way with operatingefficiencies below fifty percent.

    Selective Catalytic Reduction (SCR) equipment operate atefficiencies of approximately 85 percent but increase the costsof generation by approximately 7- 10 percent

    Quantification of environmental damage

  • 7/29/2019 Construction and Environment Note Sode

    71/96

    By Prof SACHIN JAIN 71

    Quantification of environmental damage

    The damage caused due to air pollution from a power plantwould depend upon the dosage received by the surroundingpopulation, as well as their physiological, socio- economic andhealth characteristics.

    The dosage received by the population is a function of both theground level concentrations as well as the period over whichthe population is exposed.

    Concentrations are generally computed on a short term (lessthan 24 hours), seasonal and on an annual basis.

    Their levels depend upon both the technical features of theplant (quantity and characteristics of the fuel used, type ofplant and state of operation, height of stacks, etc. andatmospheric conditions (wind directions, atmospheric stability,etc.).

    These can be computed using several approaches, the mostcommonly used one being the Gaussian Dispersion Model.

  • 7/29/2019 Construction and Environment Note Sode

    72/96

    By Prof SACHIN JAIN 72

    In order to determine the exposure, the seasonal/annual concentrationsfrom the plant will need to be determined added to the backgroundconcentrations, the sum of which when mapped the surrounding populationwould give the total exposure.

    The mapping of pollutants onto the recipient population, requires dose-response curves of the population

    Therefore the estimate of damage is based on air quality standards.

    A value function curve for air would be used to ascertain the deterioration inair quality.

    Figure below shows the short term and long term concentration for differentwind speeds.

  • 7/29/2019 Construction and Environment Note Sode

    73/96

    By Prof SACHIN JAIN 73

    No Typical emissions from a power plant : Scenario 1 (down wind ad unstable

    conditions).

    Ash Disposal

  • 7/29/2019 Construction and Environment Note Sode

    74/96

    By Prof SACHIN JAIN 74

    Ash Disposal

    Given the high percentage of ash in Indian coals (averaging 40

    percent), significant quantities of both fly and bottom ash aregenerated (80:20 respectively).

    The ash can be disposed or utilized in a number of ways

    Disposal

    Ash Utilization

    Disposal

  • 7/29/2019 Construction and Environment Note Sode

    75/96

    By Prof SACHIN JAIN 75

    Disposal

    There are two types of disposal

    Wet disposal system

    Dry disposal system

  • 7/29/2019 Construction and Environment Note Sode

    76/96

    By Prof SACHIN JAIN 76

    Wet disposal system

    The most common disposal method is the wet disposal system.

    In this System, the ash is transported by slurry pipelines and

    deposited at the disposal site in a fluid state.

    Every tone of fly ash requires approximately 8-10 liters of water to

    convert it to slurry System differences arise in terms of how the

    transport water and supematent are handled in terms of treatment

    and discharge, recycle, evaporation or impoundment.

    Land requirements are roughly 0.4 ha per MW installed capacity.

  • 7/29/2019 Construction and Environment Note Sode

    77/96

    By Prof SACHIN JAIN 77

    Control of leachates (discussed below) and prevention of groundwater contamination IS more The primary advantage of wet systemsare that they are simple, relatively inexpensive to operate andnormally unobtrusive (quiet, no fugitive dust, no transport traffic).

    They are also flexible with respect to short-term variability

    The main disadvantages are associated with the disposal site.

    A large disposal area is required due to the large volume of effluents.

    Preparation of the disposal site requires dams and dykes whichincrease the cost.

    difficult to ensure, and liners are required. Flexibility to long termchanges are less.

    D di l t

  • 7/29/2019 Construction and Environment Note Sode

    78/96

    By Prof SACHIN JAIN 78

    Dry disposal system

    The dry disposal system transports and deposits the waste in the

    landfill as a solid.

    Bottom ash is transported hydraulically to a dewatering bin or pond;

    Fly ash is collected in silos for transport to the disposal site.

    They are generally transported and disposed separately.

    Ash is typically trucked to the landfill, dumped, spread and

    compacted with the use of water.

  • 7/29/2019 Construction and Environment Note Sode

    79/96

    By Prof SACHIN JAIN 79

    Advantages of dry disposal techniques lie in a lower requirement forland and water and often lower capital costs.

    Control of leachates and ground water protection is easier. Site closure and revegetation is simpler and cheaper.

    The most important positive aspect is the ease of reclamation infuture use of ash

    The primary disadvantages centre on greater quantities of dust,noise and traffic, and higher operating costs.

    Water Pollution due to thermal plant

  • 7/29/2019 Construction and Environment Note Sode

    80/96

    By Prof SACHIN JAIN 80

    Water Pollution due to thermal plant

    Both thermal and chemical discharges are responsible for waterpollution.

    Thermal pollution of the water bodies occur with boiler blowdownand/or when condenser cooling occurs.

    This could affect the aquatic system in a number of lays.

    For some fish species, warmer water spells disaster in the form ofincreased mortality rates and increased susceptibility to disease.

    For some other species, warmer water could imply a higher metabolicrate, which leads to shorter maturing periods and shorter reproductioncycles.

  • 7/29/2019 Construction and Environment Note Sode

    81/96

    By Prof SACHIN JAIN 81

    The cooling systems fall mainly into two categories,

    Once through systems: These systems circulate water through

    the plant condensers and return it to the environment

    Closed cycle systems: These systems circulate water from the

    condenser to another device in which the flow is cooled,generally by evaporation to he atmosphere.

    Common used cooling devices are cooling towers, cooling

    ponds and spray systems.

  • 7/29/2019 Construction and Environment Note Sode

    82/96

    By Prof SACHIN JAIN 82

    For regulatory purposes, the discharge streams from power plants aredivided into several point source categories of

    Cooling water, i.e. once through and cooling tower blowdown,

    Ash transport water, i.e. fly ash and bottom ash transport water,

    Metal cleaning wastes,

    Low volume wastes,

    Material storage run off i.e. coal pile and ash pile run off

  • 7/29/2019 Construction and Environment Note Sode

    83/96

    By Prof SACHIN JAIN 83

    Hydro

  • 7/29/2019 Construction and Environment Note Sode

    84/96

    By Prof SACHIN JAIN 84

    Building of a dam or formation of a reservoir leads to the

    submergence of large areas If land.

    The two major issues therefore are

    large-scale displacement and rehabilitation of the people and

    loss of large areas of land under forest cover.

    Large Scale Displacement

  • 7/29/2019 Construction and Environment Note Sode

    85/96

    By Prof SACHIN JAIN 85

    Large Scale Displacement

    Displacement and consequently the rehabilitation of people from the landthey have occupied for centuries is a tough task.

    People are emotionally attached not only to the land but also to theirlifestyles.

    Although in recent years rehabilitation packages offered have been veryliberal but their implementation is not perfect.

    This leads to a large degree of discontent amongst the oustees.

    Often tribal who are displaced from their forest homeland and have tochange their way of life.

    Therefore there are two features that need to be looked at in the designstage.

    the rehabilitation package

    the scale of displacement

    Quantification of displacement

  • 7/29/2019 Construction and Environment Note Sode

    86/96

    By Prof SACHIN JAIN 86

    Quantification of displacement

    Value function graphs would need to be drawn.

    Rehabilitation packages would range from 0 to 10 starting from the

    worst to the best.

    The scale of displacement would range from 0 (for large number of

    people displaced, say > 100,000) to 10 (none, or a very small

    number of people displaced).

    Forest Loss

  • 7/29/2019 Construction and Environment Note Sode

    87/96

    By Prof SACHIN JAIN 87

    Forest Loss

    Often, with the construction of a darn, large areas of forest are lost.

    Here timber and other minor forest products lost also environmentalservices like prevention of soil erosion, climate regulation,production of oxygen, absorption of carbon-dioxide and mostimportantly a provision of a habitat for birds and animals is

    damaged.

    In addition, tribal and other communities have their lives deeplywoven around forests.

    Therefore this is a major issue and should be included in theevaluation

    Q tifi ti f F t l

  • 7/29/2019 Construction and Environment Note Sode

    88/96

    By Prof SACHIN JAIN 88

    Quantification of Forest loss

    This is difficult to quantify.

    The scale would be similar to the scale of displacement

    graph, i. e. 0 for large forest loss and 10 for no forest

    loss.

    Others

  • 7/29/2019 Construction and Environment Note Sode

    89/96

    By Prof SACHIN JAIN 89

    Others

    These losses are

    Siltation,

    Diseases (malaria, encephalitis, schistosomiasis, Fluorosis, etc.)

    Risk of enhanced earthquakes in the area.

    Although these are of relatively less importance than the two majorissues, value function graphs can be made for each impact.

  • 7/29/2019 Construction and Environment Note Sode

    90/96

    By Prof SACHIN JAIN 90

    Nuclear

    The setting up of a nuclear plant may pose radiological dangers toth l l l ti i th f f l l l di ti f d

  • 7/29/2019 Construction and Environment Note Sode

    91/96

    By Prof SACHIN JAIN 91

    the local population in the form of low-level radiation, surface andground water radio-active contamination, and from waste disposal atplant site.

    As part of the plant design radioactive discharges are kept muchbelow threshold (safe) levels, and therefore based on designoperating features, the normal operation of a nuclear plant will causeno radiological threat to the neighboring population and countryside.

    In the event of an accident (due to internal or external causes) alarge release of radioactivity may result in catastrophicconsequences.

    Non radiological threat includes 'thermal cooling' of the typedescribed in the case of coal plants but with a higher degree of

    magnitude.

  • 7/29/2019 Construction and Environment Note Sode

    92/96

    By Prof SACHIN JAIN 92

    Finalizing the EIA

  • 7/29/2019 Construction and Environment Note Sode

    93/96

    By Prof SACHIN JAIN 93

    Value function graphs provide a way of quantifying the majorimpacts.

    These impacts need to be weighted in terms of their relativeimportance.

    Since this is a value judgment, the value assigned is arrived at byconducting a survey.

    The sample group needs to be carefully chosen over the cross-section of society.

    It is important that the representative sample be truly representativeof the population, and not just the policy makers.

  • 7/29/2019 Construction and Environment Note Sode

    94/96

    By Prof SACHIN JAIN 94

    This will ensure the value of the weights are unbiased towards anygroup and therefore would reflect an objective result.

    Issues such as displacement would probably attract a wide range ofvalues which is major cause for protest in Hydro projects.

    Once the weight and scores are all' obtained, the EIU with andwithout the power plant can be calculated.

    If the result is positive then the setting up of the power plant isenvironmentally acceptable

    Reference

  • 7/29/2019 Construction and Environment Note Sode

    95/96

    By Prof SACHIN JAIN 95

    Reference

    Construction and Environment by NICMAR

    Developing a strategic approach to construction waste

    by Gilli Hobbs

    Construction and demolition waste management A hand

    book for contractors and site managers by A FAS &

    construction industry federation initiative

  • 7/29/2019 Construction and Environment Note Sode

    96/96

    THANKYOU


Recommended