Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | gunjan-jaiswal |
View: | 230 times |
Download: | 2 times |
of 96
7/29/2019 Construction and Environment Note Sode
1/96
By Prof SACHIN JAIN 1
Construction and environment
By
Prof SACHIN JAIN
7/29/2019 Construction and Environment Note Sode
2/96
2
Climate change Ozone layer depletion Acidification
Eutrophication
Depletion ofrenewable resources
Depletion of non-renewable resources
Winter and summer smog
Eco-Toxicity
Generationof waste
Environmental impacts
7/29/2019 Construction and Environment Note Sode
3/96
3
A significant part of these impactscome from the construction sector(construction, use and maintenanceof infrastructures).
The impact of use and maintenancecan be significantly more importantthan the impact of construction.
Examples: roads or buildings.
7/29/2019 Construction and Environment Note Sode
4/96
4
Quantitative assessment
of all measurable effects
Maintenance of buildings
Production of goods
Transport of goods
Examples of processes or products
7/29/2019 Construction and Environment Note Sode
5/96
5
E
xamplesofparametersa
ssessed
Production of goods(for a specific process in a specific factory)
Consumption of raw materials andproducts (quantity/product)
Emission of gases, and of
solid and liquid wastes(quantity/product)
Transport(for a specific truck in a specific trip)
Emission of different gases(quantity/km or trip)
Consumption of fuel,oil, tyres, etc.
(quantity/km or trip)
7/29/2019 Construction and Environment Note Sode
6/96
By Prof SACHIN JAIN 6
Any processExample: production of1 kg of clinker in a kiln
Products
1 kg of clinker
(Energy)(MJ of heat)
Raw materialskg of limestone,
of clay, etc.
Wastes
Solid - Liquid Gaskg of dust, contaminated water, NOx, SOx, ...
EnergyMJ (fuels,electricity)
Productskg of explosives, of
admixtures, etc.
7/29/2019 Construction and Environment Note Sode
7/96
By Prof SACHIN JAIN 7
To be defined:- functional unit
- cradle-grave, cradle-gate- system boundaries
7/29/2019 Construction and Environment Note Sode
8/96
8
Examples
A badly isolated building may have a lower environmental
impact up until construction is completed (fewer materials
required) but will have a much higher impact during usebecause of thermal conditioning.
A material can have an important impact in production (for
instance high energy consumption) but very low afterwards
(low maintenance and recyclable) or vice versa.
7/29/2019 Construction and Environment Note Sode
9/96
By Prof SACHIN JAIN 9
What if function changes?
RecyclingLandfill
Abandonment
Repairing,renovating,transforming...
Functional unit to be redefined !(new life cycle)
Demolition
7/29/2019 Construction and Environment Note Sode
10/96
By Prof SACHIN JAIN 10
Construction waste management
for better environment
7/29/2019 Construction and Environment Note Sode
11/96
By Prof SACHIN JAIN 11
Construction and demolition waste overview
7/29/2019 Construction and Environment Note Sode
12/96
By Prof SACHIN JAIN 12
Typical composition of waste
Hardcore recycling rates
7/29/2019 Construction and Environment Note Sode
13/96
By Prof SACHIN JAIN 13
Best practice targets for longer term
7/29/2019 Construction and Environment Note Sode
14/96
By Prof SACHIN JAIN 14
C&D waste possible routes
7/29/2019 Construction and Environment Note Sode
15/96
By Prof SACHIN JAIN 15
Causes of waste on site
7/29/2019 Construction and Environment Note Sode
16/96
16
Hacking off concrete becomes concrete waste
Broken bag of crush stone Improper stacking of tiles
7/29/2019 Construction and Environment Note Sode
17/96
17
Left over mortar becomes waste Wooden package disposed
Cutting waste of reinforcement
Waste materials are not
segregated from useful material
7/29/2019 Construction and Environment Note Sode
18/96
18
Damage of drywall panels
Cutting wasteof dry wall
Lost of plaster while applyingCutting waste of tiles
7/29/2019 Construction and Environment Note Sode
19/96
By Prof SACHIN JAIN 19
7/29/2019 Construction and Environment Note Sode
20/96
20
Percentage wastage of materials in public housing
7/29/2019 Construction and Environment Note Sode
21/96
21
Percentage wastage of materials for various trades for private residential
building
7/29/2019 Construction and Environment Note Sode
22/96
By Prof SACHIN JAIN 22
Wastage management
7/29/2019 Construction and Environment Note Sode
23/96
By Prof SACHIN JAIN 23
Waste Management Hierarchy
7/29/2019 Construction and Environment Note Sode
24/96
By Prof SACHIN JAIN 24
Resource Optimization
(Rethink Design)
Reduce Packaging
Implement efficient,material saving
construction technique
Source Reduction
(Accurate Estimating
& ordering)Prevention
Prevention of waste generation in construction
7/29/2019 Construction and Environment Note Sode
25/96
By Prof SACHIN JAIN 25
7/29/2019 Construction and Environment Note Sode
26/96
By Prof SACHIN JAIN 26
Reuse
7/29/2019 Construction and Environment Note Sode
27/96
By Prof SACHIN JAIN 27
Selective Demolition Methodology
7/29/2019 Construction and Environment Note Sode
28/96
28
Flow Chart for
Recycling Process
7/29/2019 Construction and Environment Note Sode
29/96
By Prof SACHIN JAIN 29
7/29/2019 Construction and Environment Note Sode
30/96
By Prof SACHIN JAIN 30
7/29/2019 Construction and Environment Note Sode
31/96
By Prof SACHIN JAIN 31
Various types of crushers
7/29/2019 Construction and Environment Note Sode
32/96
By Prof SACHIN JAIN 32
Uses of recycled material
Secondary aggregates for road (capping layer and sub base)
construction Top soil Drainage media Capillary break layers on contaminated land
Metal (steel reinforcement)
Large timber sections Wood for fuel and kindling and use as a filler material in the
manufacture of medium density fiber board Paving slabs
Bricks
7/29/2019 Construction and Environment Note Sode
33/96
By Prof SACHIN JAIN 33
Concrete the non waste in waste stream
7/29/2019 Construction and Environment Note Sode
34/96
By Prof SACHIN JAIN 34
What is Recycled Concrete?
7/29/2019 Construction and Environment Note Sode
35/96
By Prof SACHIN JAIN 35
Concrete to be Recycled
7/29/2019 Construction and Environment Note Sode
36/96
By Prof SACHIN JAIN 36
Where Does Recycled Concrete
Come From?
Local Sources
CRD Construction, Renovation & Demolition
Buildings
Road/Parking Lot Reconstruction
7/29/2019 Construction and Environment Note Sode
37/96
By Prof SACHIN JAIN 37
Concrete Crushing
7/29/2019 Construction and Environment Note Sode
38/96
By Prof SACHIN JAIN 38
Benefits of Recycling Concrete
Local Product Local Sources
Reduces Truck Traffic
Alternative to a Non-Renewable Resource
Cost Savings
No Disposal Fees
Better Trucking Utilization (Reduced Costs)
Allow up to 10% Deleterious Materials
7/29/2019 Construction and Environment Note Sode
39/96
By Prof SACHIN JAIN 39
Processed Concrete
Plasma Gasification Cupola for energy production from wastage
7/29/2019 Construction and Environment Note Sode
40/96
By Prof SACHIN JAIN 40
Plasma Gasification Cupola for energy production from wastage
7/29/2019 Construction and Environment Note Sode
41/96
By Prof SACHIN JAIN 41
This method is used in St Lucie Country which contains more than 4million tons of MSW.
The MSW will be conveyed to one of of six cupolas that will have aceramic interior and a steel exterior, the latter immersed in water
Six plasma torches will create arcs of artificial lightening in eachcopula that will heat the space to temperatures greater than thoseon the surface of sun, changing the municipal waste to a gaseous orliquid state.
The gas formed will exit the chamber at a temperature ofapproximately 2300oF (1260oC) and will be transported to a gascleaning facility, where wet scrubbers and a wet electrostaticprecipitator will extract sulfur, chlorines, dust and such volatilemetals as mercury and cadmium.
After the gashes been cleaned it will enter a gas turbine electricgenerator with a capacity of 160 MW per day.
7/29/2019 Construction and Environment Note Sode
42/96
By Prof SACHIN JAIN 42
40 MW of which will be used to power the gasification plant andremaining 120 MW is supplied to grid.
Supper heated liquid by product will be cooled to from a solidvitreous slag that will be broken to small granules.
These granules can be used as aggregate in asphalt or concrete.
The new plant will be capable of processing 3000 tones (2700metric tones)of MSW per day.
Some of 2000 tones of new MSW will be taken from existing
Landfills. Plant is capable of processing dewatered sludge and can take up to
15% of 3000 tones daily load as sludge.
7/29/2019 Construction and Environment Note Sode
43/96
By Prof SACHIN JAIN 43
Construction of Dry Tomb Land fill
7/29/2019 Construction and Environment Note Sode
44/96
By Prof SACHIN JAIN 44
Leave it Alone
7/29/2019 Construction and Environment Note Sode
45/96
By Prof SACHIN JAIN 45
Environment Impact Assessment
7/29/2019 Construction and Environment Note Sode
46/96
By Prof SACHIN JAIN 46
Environmental Impact Assessment (EIA) is an instrument ofreconciliation.
The Council on European Economic Committee, in their directive tothe member states, highlights the objectives of EIA.
The effects of a project on the environment must be assessed inorder to take account of
The concerns to protect human health,
To contribute by means of a better environment to the quality of life,
To ensure maintenance of the diversity of species and to maintainthe reproductive capacity of the ecosystem as a basic resource of
life.
7/29/2019 Construction and Environment Note Sode
47/96
By Prof SACHIN JAIN 47
Prevention Rather Than Cure
It is essential that consequences of projects, plans or policies
at different levels be assessed before they are executed.
EIA examines these consequences and predicts future
changes in the environment.
It guides administrative agencies in balancing conflicting social
values and environmental quality.
It helps them to make the best choice among various available
options.
EIA foresees and avoids potential dangers.
7/29/2019 Construction and Environment Note Sode
48/96
By Prof SACHIN JAIN 48
The Mandatory Model
Power coupled with duty is the most salient feature of the mandatorymodel of impact assessment.
The decision-making agency is obliged to study the impact of adevelopment proposal before it is approved.
The EIS serves as a guarantee of the right to information and abasis for proper impact assessment.
7/29/2019 Construction and Environment Note Sode
49/96
By Prof SACHIN JAIN 49
Pleas Against And In Favor
The EIS on which assessment is made is often too lengthy,
Environmentalists may try to delay development by raisingfalse pleas of defects in impact statements.
EIS may impose procedural burden rather than afford anopportunity to improve decision-making.
Public participation and judicial review play key roles asintegral parts of mandatory model.
They make EIA into a reasoned and objective process andmake it an important tool in protecting and managing theenvironment.
7/29/2019 Construction and Environment Note Sode
50/96
50
The Discretionary Model
Merits
It depends on the discretionary powers of the administration.
This model exhibits flexibility and maintains a harmony betweendevelopmental needs and environmental values;
experts can make a choice from available alternatives.
Quick, expert and timely decision-making is the advantage of thismodel.
Public participation is not allowed as a matter of routine,
Demerits
Experts within the government may go wrong,
Reasons for decisions may not be disclosed;
Interests of weaker or vulnerable groups and regions could beneglected;
Alternative opinions, expressed outside the realms ofadministration, may be overlooked or disregarded;
7/29/2019 Construction and Environment Note Sode
51/96
By Prof SACHIN JAIN 51
METHODOLOGY OF EIA
7/29/2019 Construction and Environment Note Sode
52/96
By Prof SACHIN JAIN 52
The EIA can be broadly divided into the following steps,
basics,
environmental setting,
impact prediction and assessment.
7/29/2019 Construction and Environment Note Sode
53/96
By Prof SACHIN JAIN 53
Basics
One must have a fair understanding and knowledge of thestudy.
Starting with the need for the project one must identifyalternative solutions to meet this need.
Also with these solutions a no-project alternative should be
included.
Since impacts due to alternative solutions may widely differdepending upon the alternative itself it is necessary to broadlyexamine each alternative and the factors that are most
affected.
Environmental Setting
7/29/2019 Construction and Environment Note Sode
54/96
By Prof SACHIN JAIN 54
Environmental Setting
It provides baseline information against which predictions andassessments of the impacts for each alternative can be compared.
The factors can be classified under physical-chemical (e.g. air andwater quality, soil fertility, etc.) biological (flora and fauna), cultural(archaeological sites, recreation, etc.) and socio-economic (populationcharacteristics, economic state, etc.).
Impact Prediction and Assessment
This is a complex task involving widely different techniques in differing
disciplines.
As measurement techniques vary, interpretation varies, and therefore a
number of methodologies have been developed for presentation of theseimpacts to decision makers and the general public public.
7/29/2019 Construction and Environment Note Sode
55/96
By Prof SACHIN JAIN 55
Methodologies for Environmental Impact
Assessment
Adhoc
Checklists
Matrices
Networks
Overlay techniques
Adh
7/29/2019 Construction and Environment Note Sode
56/96
By Prof SACHIN JAIN 56
Adhoc
These were the first methods to be used in the preparation of EIA.
The procedure involves the bringing together of various experts in
particular fields to identify impacts in their area of expertise.
The environment is generally divided into broad categories, the
assessment of which could be intuitive or subjected to qualitativeinterpretation of quantitative results.
The adhoc approach has little or no formal analytical structure and
at most provides only a preliminary review.
Ch kli t
7/29/2019 Construction and Environment Note Sode
57/96
By Prof SACHIN JAIN 57
Checklists
Checklists can be of various types ranging from simple to fairlysophisticated.
Simple checklists have no guidelines on how to measure andinterpret environmental impacts.
Descriptive checklists are more structured with identification ofenvironmental parameter and guidelines on how parameterdata is to be measured.
Scaling checklists go a step further by providing information onhow the parameter values are scaled.
Lastly, there are scaling-weighting checklists that provideadditional information on relative weights of importance ofeach parameter.
7/29/2019 Construction and Environment Note Sode
58/96
By Prof SACHIN JAIN 58
Interaction Matrices
This method develops on the checklist method byincorporating a list of project activities to a checklist of potentialimpact environmental characteristics.
Developed by Leopold et al. (described in Canter, 1977) themethod involves the use of a matrix with 100 specified actionsand 88 environmental items.
Each cell represents an impact that is a result of interactionbetween an action and an environmental item.
As with the EES two aspects of each impact needs to bedetermined, namely, magnitude and importance.
Both of these are assigned a numerical scale from one to ten.
7/29/2019 Construction and Environment Note Sode
59/96
By Prof SACHIN JAIN 59
It is possible to expand or contact the matrix, i.e. action or
environmental items not included can always be added and vice-
versa i.e. items or action having no relevance he project underquestion can be deleted.
It is also possible to represent cell entries as qualities estimates of
the cause effect relationships.
Networks
7/29/2019 Construction and Environment Note Sode
60/96
By Prof SACHIN JAIN 60
Networks
Network approaches can expand on the matrix theme byintroducing a cause condition effect network, which allowsidentification of cumulative or indirect effects.
The network is depicted in the form of a tree, called arelevance or impact tree, and is used to relate and recordsecondary, tertiary and higher order effects.
To understand this technique considers the impact tree.
Activity A has two primary impacts, three secondary impactsand four tertiary impacts.
There are ten branches of the tree.
O l T h i
7/29/2019 Construction and Environment Note Sode
61/96
By Prof SACHIN JAIN 61
Overlay Techniques
This methodology essentially consists of developing a set of
maps of environmental characteristics such as physical, social,etc. for a project area and overlaying these maps
(transparencies) to create a composite map, which shows the
spatial distribution of the selected impacts.
The overlay approach is generally effective in its ability to set aproposed project within a geographical context and to indicate
spatial relationships between the environmental factors that
are regarded as relevant to the assessment of the project.
However it cannot be used to identify impacts or identifysecondary and tertiary relationships.
7/29/2019 Construction and Environment Note Sode
62/96
By Prof SACHIN JAIN 62
The method has been used to identify the optimal routing fortransmission lines and site selection processes for coal and oilrelated developments (Codoni et al., 1985).
The method was also applied on the Huasai- Thale- Noi RoadProject in Thailand where the project was halted due toenvironmental concern.
An alternative route was determined by using rough overlays of theenvironmental site selection parameters (lohani and Halim, 1986).
7/29/2019 Construction and Environment Note Sode
63/96
By Prof SACHIN JAIN 63
Conceptual EIA of large
scale electric power plants
India produces electricity mainly from coal hydro and from nuclear
7/29/2019 Construction and Environment Note Sode
64/96
By Prof SACHIN JAIN 64
India produces electricity mainly from coal, hydro, and from nuclearalbeit in a limited way.
The environmental impacts from each of these modes are widely
different. Also within each type, differences in magnitude arise due to location
features, type of inputs, equipments, etc.
The setting up of a power plant leads to growth and development inthat area.
These benefits would arise irrespective of the type of power plant.
The negative impacts occur through the air water and land mediaand are type and location-specific.
The issues/methodology for quantification of the impacts and theirrelative weighting for different type of power plants are brieflydiscussed below.
7/29/2019 Construction and Environment Note Sode
65/96
By Prof SACHIN JAIN 65
Coal based thermal power
generation
7/29/2019 Construction and Environment Note Sode
66/96
By Prof SACHIN JAIN 66
Air Pollution
Air pollution occurs as a result of the emission of
Particulates (SPM),
Oxides of Sulphur (SOx),
Oxides of Nitrogen (NOx),
Fly ash
7/29/2019 Construction and Environment Note Sode
67/96
By Prof SACHIN JAIN 67
Air pollution control
SPM Control
SOx Control
NOx Control
SPM C t l
7/29/2019 Construction and Environment Note Sode
68/96
By Prof SACHIN JAIN 68
SPM Control
Pre and post combustion control measures exist for all the majorpollutants.
At present, the installation of electrostatic precipitators (ESP) for thecontrol of SPM emissions are mandatory in India
The average cost of SPM control by ESPs is approximately 1 % of thecost of generation.
ESP usually operate at efficiencies of 99 percent and above, theefficiencies generally being relatively insensitive to particle size butgrade efficiency curves indicate a minimum in the 0.2-2 micrometerrange (Wall 1986).
Fabric filters are preferred for their high overall collection efficiency,which is maintained over a wide range of particle sizes.
For submicron particles, bag filter systems in terms of collectionefficiencies are superior to all other control technologies.
SO C l
7/29/2019 Construction and Environment Note Sode
69/96
By Prof SACHIN JAIN 69
SOx Control
Given the low levels of sulphur in most Indian coals, the emissionsof SOx in most cases are likely to fall within ambient standards
Only those areas that are already having high sulphur emissionssuch as the Singrauli area or in certain metropolitan cities wouldrequire Flue Gas Desulphurisation (FGD) equipment.
Damage from SOx emissions are maximum in areas which alreadyhave heavy particulate loading.
FGDs typically operate at efficiencies around 90 percent andcontribute to a 25-30 percent increase in the cost of generation.
NOx Control
7/29/2019 Construction and Environment Note Sode
70/96
By Prof SACHIN JAIN 70
NOx Control
NOx emissions were never considered significant contributorsto environmental degradation.
However, in recent years increasing attention is being paid tothe environmental damage from NOx emissions and methodsto reduce it.
Low NOx burners provides an inexpensive way with operatingefficiencies below fifty percent.
Selective Catalytic Reduction (SCR) equipment operate atefficiencies of approximately 85 percent but increase the costsof generation by approximately 7- 10 percent
Quantification of environmental damage
7/29/2019 Construction and Environment Note Sode
71/96
By Prof SACHIN JAIN 71
Quantification of environmental damage
The damage caused due to air pollution from a power plantwould depend upon the dosage received by the surroundingpopulation, as well as their physiological, socio- economic andhealth characteristics.
The dosage received by the population is a function of both theground level concentrations as well as the period over whichthe population is exposed.
Concentrations are generally computed on a short term (lessthan 24 hours), seasonal and on an annual basis.
Their levels depend upon both the technical features of theplant (quantity and characteristics of the fuel used, type ofplant and state of operation, height of stacks, etc. andatmospheric conditions (wind directions, atmospheric stability,etc.).
These can be computed using several approaches, the mostcommonly used one being the Gaussian Dispersion Model.
7/29/2019 Construction and Environment Note Sode
72/96
By Prof SACHIN JAIN 72
In order to determine the exposure, the seasonal/annual concentrationsfrom the plant will need to be determined added to the backgroundconcentrations, the sum of which when mapped the surrounding populationwould give the total exposure.
The mapping of pollutants onto the recipient population, requires dose-response curves of the population
Therefore the estimate of damage is based on air quality standards.
A value function curve for air would be used to ascertain the deterioration inair quality.
Figure below shows the short term and long term concentration for differentwind speeds.
7/29/2019 Construction and Environment Note Sode
73/96
By Prof SACHIN JAIN 73
No Typical emissions from a power plant : Scenario 1 (down wind ad unstable
conditions).
Ash Disposal
7/29/2019 Construction and Environment Note Sode
74/96
By Prof SACHIN JAIN 74
Ash Disposal
Given the high percentage of ash in Indian coals (averaging 40
percent), significant quantities of both fly and bottom ash aregenerated (80:20 respectively).
The ash can be disposed or utilized in a number of ways
Disposal
Ash Utilization
Disposal
7/29/2019 Construction and Environment Note Sode
75/96
By Prof SACHIN JAIN 75
Disposal
There are two types of disposal
Wet disposal system
Dry disposal system
7/29/2019 Construction and Environment Note Sode
76/96
By Prof SACHIN JAIN 76
Wet disposal system
The most common disposal method is the wet disposal system.
In this System, the ash is transported by slurry pipelines and
deposited at the disposal site in a fluid state.
Every tone of fly ash requires approximately 8-10 liters of water to
convert it to slurry System differences arise in terms of how the
transport water and supematent are handled in terms of treatment
and discharge, recycle, evaporation or impoundment.
Land requirements are roughly 0.4 ha per MW installed capacity.
7/29/2019 Construction and Environment Note Sode
77/96
By Prof SACHIN JAIN 77
Control of leachates (discussed below) and prevention of groundwater contamination IS more The primary advantage of wet systemsare that they are simple, relatively inexpensive to operate andnormally unobtrusive (quiet, no fugitive dust, no transport traffic).
They are also flexible with respect to short-term variability
The main disadvantages are associated with the disposal site.
A large disposal area is required due to the large volume of effluents.
Preparation of the disposal site requires dams and dykes whichincrease the cost.
difficult to ensure, and liners are required. Flexibility to long termchanges are less.
D di l t
7/29/2019 Construction and Environment Note Sode
78/96
By Prof SACHIN JAIN 78
Dry disposal system
The dry disposal system transports and deposits the waste in the
landfill as a solid.
Bottom ash is transported hydraulically to a dewatering bin or pond;
Fly ash is collected in silos for transport to the disposal site.
They are generally transported and disposed separately.
Ash is typically trucked to the landfill, dumped, spread and
compacted with the use of water.
7/29/2019 Construction and Environment Note Sode
79/96
By Prof SACHIN JAIN 79
Advantages of dry disposal techniques lie in a lower requirement forland and water and often lower capital costs.
Control of leachates and ground water protection is easier. Site closure and revegetation is simpler and cheaper.
The most important positive aspect is the ease of reclamation infuture use of ash
The primary disadvantages centre on greater quantities of dust,noise and traffic, and higher operating costs.
Water Pollution due to thermal plant
7/29/2019 Construction and Environment Note Sode
80/96
By Prof SACHIN JAIN 80
Water Pollution due to thermal plant
Both thermal and chemical discharges are responsible for waterpollution.
Thermal pollution of the water bodies occur with boiler blowdownand/or when condenser cooling occurs.
This could affect the aquatic system in a number of lays.
For some fish species, warmer water spells disaster in the form ofincreased mortality rates and increased susceptibility to disease.
For some other species, warmer water could imply a higher metabolicrate, which leads to shorter maturing periods and shorter reproductioncycles.
7/29/2019 Construction and Environment Note Sode
81/96
By Prof SACHIN JAIN 81
The cooling systems fall mainly into two categories,
Once through systems: These systems circulate water through
the plant condensers and return it to the environment
Closed cycle systems: These systems circulate water from the
condenser to another device in which the flow is cooled,generally by evaporation to he atmosphere.
Common used cooling devices are cooling towers, cooling
ponds and spray systems.
7/29/2019 Construction and Environment Note Sode
82/96
By Prof SACHIN JAIN 82
For regulatory purposes, the discharge streams from power plants aredivided into several point source categories of
Cooling water, i.e. once through and cooling tower blowdown,
Ash transport water, i.e. fly ash and bottom ash transport water,
Metal cleaning wastes,
Low volume wastes,
Material storage run off i.e. coal pile and ash pile run off
7/29/2019 Construction and Environment Note Sode
83/96
By Prof SACHIN JAIN 83
Hydro
7/29/2019 Construction and Environment Note Sode
84/96
By Prof SACHIN JAIN 84
Building of a dam or formation of a reservoir leads to the
submergence of large areas If land.
The two major issues therefore are
large-scale displacement and rehabilitation of the people and
loss of large areas of land under forest cover.
Large Scale Displacement
7/29/2019 Construction and Environment Note Sode
85/96
By Prof SACHIN JAIN 85
Large Scale Displacement
Displacement and consequently the rehabilitation of people from the landthey have occupied for centuries is a tough task.
People are emotionally attached not only to the land but also to theirlifestyles.
Although in recent years rehabilitation packages offered have been veryliberal but their implementation is not perfect.
This leads to a large degree of discontent amongst the oustees.
Often tribal who are displaced from their forest homeland and have tochange their way of life.
Therefore there are two features that need to be looked at in the designstage.
the rehabilitation package
the scale of displacement
Quantification of displacement
7/29/2019 Construction and Environment Note Sode
86/96
By Prof SACHIN JAIN 86
Quantification of displacement
Value function graphs would need to be drawn.
Rehabilitation packages would range from 0 to 10 starting from the
worst to the best.
The scale of displacement would range from 0 (for large number of
people displaced, say > 100,000) to 10 (none, or a very small
number of people displaced).
Forest Loss
7/29/2019 Construction and Environment Note Sode
87/96
By Prof SACHIN JAIN 87
Forest Loss
Often, with the construction of a darn, large areas of forest are lost.
Here timber and other minor forest products lost also environmentalservices like prevention of soil erosion, climate regulation,production of oxygen, absorption of carbon-dioxide and mostimportantly a provision of a habitat for birds and animals is
damaged.
In addition, tribal and other communities have their lives deeplywoven around forests.
Therefore this is a major issue and should be included in theevaluation
Q tifi ti f F t l
7/29/2019 Construction and Environment Note Sode
88/96
By Prof SACHIN JAIN 88
Quantification of Forest loss
This is difficult to quantify.
The scale would be similar to the scale of displacement
graph, i. e. 0 for large forest loss and 10 for no forest
loss.
Others
7/29/2019 Construction and Environment Note Sode
89/96
By Prof SACHIN JAIN 89
Others
These losses are
Siltation,
Diseases (malaria, encephalitis, schistosomiasis, Fluorosis, etc.)
Risk of enhanced earthquakes in the area.
Although these are of relatively less importance than the two majorissues, value function graphs can be made for each impact.
7/29/2019 Construction and Environment Note Sode
90/96
By Prof SACHIN JAIN 90
Nuclear
The setting up of a nuclear plant may pose radiological dangers toth l l l ti i th f f l l l di ti f d
7/29/2019 Construction and Environment Note Sode
91/96
By Prof SACHIN JAIN 91
the local population in the form of low-level radiation, surface andground water radio-active contamination, and from waste disposal atplant site.
As part of the plant design radioactive discharges are kept muchbelow threshold (safe) levels, and therefore based on designoperating features, the normal operation of a nuclear plant will causeno radiological threat to the neighboring population and countryside.
In the event of an accident (due to internal or external causes) alarge release of radioactivity may result in catastrophicconsequences.
Non radiological threat includes 'thermal cooling' of the typedescribed in the case of coal plants but with a higher degree of
magnitude.
7/29/2019 Construction and Environment Note Sode
92/96
By Prof SACHIN JAIN 92
Finalizing the EIA
7/29/2019 Construction and Environment Note Sode
93/96
By Prof SACHIN JAIN 93
Value function graphs provide a way of quantifying the majorimpacts.
These impacts need to be weighted in terms of their relativeimportance.
Since this is a value judgment, the value assigned is arrived at byconducting a survey.
The sample group needs to be carefully chosen over the cross-section of society.
It is important that the representative sample be truly representativeof the population, and not just the policy makers.
7/29/2019 Construction and Environment Note Sode
94/96
By Prof SACHIN JAIN 94
This will ensure the value of the weights are unbiased towards anygroup and therefore would reflect an objective result.
Issues such as displacement would probably attract a wide range ofvalues which is major cause for protest in Hydro projects.
Once the weight and scores are all' obtained, the EIU with andwithout the power plant can be calculated.
If the result is positive then the setting up of the power plant isenvironmentally acceptable
Reference
7/29/2019 Construction and Environment Note Sode
95/96
By Prof SACHIN JAIN 95
Reference
Construction and Environment by NICMAR
Developing a strategic approach to construction waste
by Gilli Hobbs
Construction and demolition waste management A hand
book for contractors and site managers by A FAS &
construction industry federation initiative
7/29/2019 Construction and Environment Note Sode
96/96
THANKYOU