+ All Categories
Home > Documents > CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern...

CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern...

Date post: 23-Mar-2020
Category:
Upload: others
View: 2 times
Download: 1 times
Share this document with a friend
44
CONTRACT ADMINISTRATION AND DISPUTE. Ar Steven Thang
Transcript
Page 1: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

CONTRACT ADMINISTRATION AND DISPUTE.

Ar Steven Thang

Page 2: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

“No construction project is free of risk. Risk can be managed, minimised, shared, transferred or accepted. It cannot be ignored.”

Construction is a risky business!

Page 3: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

“Its difficult to be precise but something in the region of £150m has been wasted in the cost of prolongation flowing from design delays, over-optimistic scheduling and uncertain authority”

Lord Fraser of Carmyllie QC

Page 4: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Generally, for a building or construction project, there are three objectives

which the owner of the project is aiming.

money, quality and time

The question of time is an important one in construction contracts. There are

provisions in construction contracts, for example, that the Contractor must

complete the project, that the Engineer or the Architect or the S.O. must furnish

the necessary drawings and information to the Contractor, and that the Employer

must pay the Contractor, all before a certain date.

All these carry with them their respective legal implications and consequences. The

obligations of the Contractor to complete the project by a certain date and the

contractual consequences which may follow if he does not.

Page 5: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Time of the Essencesection 56 Contracts Act 1950. The material part of section 56Contracts Act 1950 is reproduced below:

“56(1) When a party to a contract promises to do a certain thing at or before a specified time, …, and fails to do any such thing at or before the specified time, the contract, or so much of it as has not been performed, becomes voidable at the option of the promisee, if the intention of the parties was that time should be of the essence of the contract.

56(2) If it was not the intention of the parties that time should be of the essence of the contract, the contract does not become voidable by the failure to do the thing at or before the specified time; but the promisee is entitled to compensation from the promisor for any loss occasioned to him by the failure.

56(3) If, in case of a contract voidable on account of the promisor’s failure to perform his promise at the time agreed, the promisee accepts performance of the promise at any time other than that agreed, the promiseecannot claim compensation for any loss occasioned by the non-performance of the promise at the timeagreed, unless, at the time of the acceptance, he gives notice to the promisor of his intention to do so.”

Page 6: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

In Tan Ah Kian v. Haji Hasnan*, Gill CJ identifies the following three situations

when time would be of the essence:

(a) the parties expressly state in the contract that it shall be so;

(b) where it was not originally stated to be of the essence but it wassubsequently made so by one party giving reasonable notice to the otherwho has failed to perform the contract with sufficient promptitude; or

(c) where from the nature of the contract or of its subject matter time must be taken to be of the essence.

* [1962] MLJ 400

Page 7: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

It can be said that in construction contracts, with the presence of extension of time and liquidated damages clauses, time is, more often than not, NOT of the essence with respect to completion date.

Page 8: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Time at Large

Time for completion of the Works is said to be “at large” when the Contractor’s obligation to complete the Works within the specified time or certified extended time is lost.

That is to say, the Contractor is no longer bound by the contractprovision that he has to complete the Works by a certain date or extended date.

The obligation of the Contractor is then to complete the Works within what is called “reasonable time”.

Page 9: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Time for completion of the Works can be said to be, or made, “at large” in thefollowing five situations:

(a) no time for completion is fixed in the contract;

(b) improper administration or misapplication of the extension of timeprovision in the contract;

(c) waiver of time requirements;

(d) the Employer’s interference in the certification process;

(e) when the extension of time provision does not confer power on theEngineer/Architect/S.O. to extend the time for completion of the Works onthe occurrence of event or events which fall(s) within the obligation of theEmployer.

Page 10: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

The significant consequence of time for completion being at large is that theliquidated damages clause in the contract becomes inoperative and the Employer cannot rely on this liquidated damages clause to impose liquidated damages onto the Contractor.

The Contractor’s remaining obligation is to complete the Works within what is called “reasonable time” the meaning of which we now turn.

Page 11: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Reasonable Time

The question of what duration of time is reasonable is one of fact, not law. It is a question of fact taking into consideration all relevant factors and circumstances, objectively assessed.

What constitute reasonable time has to be considered in relation to circumstances which existed at the time the contract obligations are performed but excluding circumstances which are under the control of the party performing those obligations, normally the Contractor in our case.*

* British Steel Corporation v. Cleveland Bridge & Engineering Co (1981) 24 BLR 94 per Robert Goff J

Page 12: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

The Meaning of Completion

There have been many opinion as to what constitute “completion” andthe use of some phrases in certain standard forms of building and constructioncontracts such as “practical completion”, “substantial completion” and otherscertain do not help

The completion of the Works comprised within a contract is important as not only it has a direct bearing on the question of whether the Employer can levy liquidated damages on the Contractor, but it also usually marks the transfer of certain risks of certain rights between the Contractor and the Employer inter-se

Page 13: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

it may also be used to determine the extent of the right to payment in those contracts which provide for stage payments and in most standard contract forms, “completion” also marks the commencement of defects liability period and also the release of half of the retention monies

In the decision of HHJ John Newey QC in Emson Eastern Ltd v. E.M.E. Development Ltd*. Judge Newey confessed in Emson that he took the position somewhere between Salmon LJ and Viscount Dilhorne in Jarvis (in the Court of Appeal and in the House of Lords respectively) and concluded that there was no difference in meaning between completion and practical completion. Completion could take place before defects and otherdefaults had to be remedied. In arriving at this conclusion, Judge Newey tookaccounts of the realities of building sites and that a building could seldom be builtprecisely as required by drawings and specifications as could a manufacturer withevery screw and every brush of paint correct.

* (1991) 55 BLR 114

Page 14: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

EXTENSION OF TIME CLAUSES IN CONSTRUCTION CONTRACTS

In the absence of such a provision, the Contractor would not be able to claim for extension of time and hence, on that pretext, no claim for “loss and expense” can be entertained.

Those contracts also contain a provision for the imposition of liquidated damages (hereinafter referred to as “LD”) for delay to completion.

Page 15: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

There are attempts to limit as much as possible the grounds on which the Engineer/Architect/S.O. can grant EoT. With respect, such over-zealousness in protecting one party may be counter-productive and glaringly displays an ignorance of the purpose, and legal implications, of EoT clause in construction contracts. To properly understand this, an understanding of the concept of what is called the “prevention principle” is necessary.

It is now settled law that if the Employer is wholly or partly responsible for the failure of the Contractor to complete on time, he cannot recover LD; the LD clause can be said to have been invalidated. This prevention principle as it has come to be called, was explained andenunciated in the English Court of Appeal decision of Peak Construction (Liverpool) Pty Ltd v. McKinney Foundation Ltd, arguably the leading case on this subject.

Page 16: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

The law can thus be simply put. If the reason for the Contractor’s failure tocomplete on time is wholly or partly the fault of the Employer, time may become“at large” and the Contractor’s obligation is then to complete within “reasonabletime”. Similarly, the LD clause is inoperative as there is no date from which LDcould run. However, if there is EoT clause which extends the time forcompletion due to delay occasioned by the Employer, and such delay is amongthe grounds on which the Engineer/Architect/S.O. can exercise his power to grantEoT, and the Engineer/Architect/S.O. validly exercises that power, then the LDclause survives.

Page 17: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

THE CERTIFIER

Since the celebrated case of Hedley Byrne and Co Ltd v. Heller and PartnersLtd, professionals (for which an engineer or an architect is certainly one) arepotentially liable in tort for negligent misstatements. This principle is extended toan architect’s duty of care to contractors when issuing certificates. In MichaelSalliss and Co Ltd v. Calil, the Architect was held to have been negligent infailing to properly extend the completion date and failure to certify the loss andexpense.

Page 18: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

NOTICE REQUIREMENTS

A reading of almost all EoT clauses will reveal that before theEngineer/Architect/S.O. can grant EoT, the Contractor will have to serve a noticeto that effect. This will lead to the following questions:

(a) What if the Contractor has not served a notice?

(b) If so, when should the notice be served?

(c) In what form should the notice be?

(d) Must full information be given to the Engineer/Architect/S.O. at the timeof the service of the notice?

Page 19: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

most EoT clauses provide for the requirement of a notice to be served, a failure to serve notice would not be fatal to the Contractor’s claim. Minutes of the meetings that record the delay to the Works do not per se constitute notice: a notice has to be “served”. There is stilldebate as to whether there is such a thing as “constructive notice” in constructioncontracts. For the notice requirement to be mandatory, the EoT clause must stateprecisely the time within which notice ought to be served. It should also be thatthere should not be a mandatory requirement to serve notice if the delay is causedby the Employer.

Page 20: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

QUANTUM OF TIME EXTENSION

The determination of the quantum of EoT becomes even more complex whenthere are several causes of delay some of which give the Contractor entitlement toEoT and some do not; these are sometimes called “concurrent delays”. For each and every of this delay event on which the Contractor is entitled to EoT, a causal link must also be established. There are several ways of dealing with thissituation when a determination of the entitlement and quantum of EoT is calledfor.

Page 21: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

American construction jurisprudence recognizes three distinct types of delay:

(a) excusable delay – this delay will ordinarily entitle the Contractor to an EoT;(b) compensable delay – this comprises delay for which the Employer is at fault;(c) inexcusable delay – this comprises delay which is the fault of the Contractoror for which he assumes the risks.

For excusable delay, the Contractor is entitled to an EoT but there will be no financial compensation. For compensable delay, the Contractor is entitled not only to an EoT but also to financial compensation. For inexcusable delay, the Contractor is entitled to neither an EoT nor financial compensation. Examples of excusable delay would be exceptionally inclement weather, act of God etc. The issuance of a variation order or the discovery of a design errors would be examples of compensable delay whereas inexcusable delay would be delay due to time spent in rectifying defects.

Two common approaches as example:(i) When an excusable delay occurs concurrently with inexcusable delay, neither the Contractor and the Employer can recover financial compensation: the Contractor would be given an EoT but not “loss andexpense”, by granting EoT to the Contractor it also denies the Employer of any financial compensation in the form of LD. (ii) When compensable delay occurs concurrently with non-compensabledelay, the Contractor is allowed Eot but denied financial compensation.

Page 22: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

The Dominant Cause Approach

This approach is the approach favoured and supported in Keating on Building Contracts:

“If there are two causes, one the contractual responsibility of the Defendant and the other the contractual responsiblity of the Plaintiff, the Plaintiff succeeds if he establishes that the cause for which the Defendant is responsible is the effective, dominant cause. Which cause is dominant is a question of fact, which is notsolved by mere point of order in time, but is to be decided by applying common sense standards.”

Page 23: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

The Malmaison Approach

This approach takes its name from a decision of HHJ Dyson (as His Lordship then was) in Henry Boot Construction (UK) Ltd v. Malmaison Hotel (Manchester) Ltd:

“… if there are two concurrent causes f delay, one of which is a relevant event , and the other is not, then the contractor is entitled to an extension of time for the period of delay caused by the relevant event notwithstanding the concurrent effect of the other event.”

Not all EoT’s will carry with them financial compensation. Generally, delays due to neutral events which occasion EoT will not carry with them financial entitlement whereas those due to the Employer’s defaults will. It is therefore important for the Engineer/Architect/S.O. to certify EoT and specifying the grounds provided for in the EoT clause that allows him to so certify.

Page 24: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

LIQUIDATED DAMAGES

Almost all construction contracts will have as their provisions deduction for LD by the Employer when the Contractor fails to complete by the contractual or extended completion date.

There are some confusions if “liquidated damages” means the same and carry the same legal meaning and legal effects as “liquidated and ascertained damages”

The word “liquidated” already suggests a fixed and specified sum, the use of the word “ascertained” is strictly superfluous.

Page 25: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

In Selvakumar a/l Murugiah v. Thiagarajah a/l Retnasamy* the Federal Court held that theEmployer would still have to prove loss; by having this requirement to prove loss, it is suggested that there is in Malaysia no liquidated damages as it is popularly understood to be. Selvakumar has been followed by the Malaysian Court of Appeal in Reliance Shipping & Travel Agencies v. Low Ban Siong.** It may be undesirable from certain viewpoint, but it is submitted that this is now settled law.

* [1995] 2 MLJ 817** [1996] 2 MLJ 543

© Oon Chee Kheng15.10.2003 @ 2.13 p.m.

Page 26: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Design professionals

The responsibility for design, and any disputes that subsequently arose, was that of either the architect or the engineer. Today, design liability can attach to an architect, an engineer, builders and their sub-contractors, and can revert to the employer where it makes a choice during design.

The design professional: architect/interior designer/engineer’s duty – tort vs contract

Design professionals may be liable to their clients and third parties for damage and loss caused by breach of contract and/or negligence. A design professional, like any other professional, owes a duty to exercise reasonable care and skill in the performance of its work.

Page 27: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Torts and crimes

A Crime is a wrong which is punished by the state

Tort is action between the wrong doer and the victim, and the aim is to compensate the victim for the harm done.

Torts and breaches of contract

A tort involves breach of duty which is fixed by law, while breach of contract is a breach of a duty which the party has voluntarily agreed to assume.

Page 28: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Areas of disputes

Page 29: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

• Site conditions• Construction drawings• The contract document• Material performances• Defect issues• Sub-contractors/suppliers• Certification• Variation Order• EOT/ CNC• LD

• Architects Instruction• CCC• Completion• Programme

Page 30: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

PAM 2006 Form has been more emphasizing on procedures requiring the Contractor, Employer and consultants to ensure all the parties strictly adhere to time provisions with the inherent loss of rights or incurring of liabilities.

Compare to PAM 1998 Form, the PAM 2006 Form limit the rights of Employers while reducing the risks borne by Contractors. This reallocation of risks proportionately increases the Employer’s exposure and burden in terms of claims and payments while providing more possible grounds for disputes between the Contractor and Employer.

Further, the PAM 2006 imposes definite time periods on the Architect and the consultant team to carry out certain duties, for example, certification and approvals within a specified time. The failure to do so may open the consultant team to professional negligence claims.

Page 31: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Pre Tender

• Adequacy of drawings• Are all the necessary details included?• Are all authorities requirement obtained?• Type and form of Tender• Are all specifications complete?

• Duration of Tender• Tender report/ errors in calculation• Tender deposit• Tenderers and nos.• Closing of tender

Page 32: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Letters of intent

Starting work without a formal contract but merely a letter of intent is an invitation for disputes. The absence of an agreement of all major terms and conditions which will apply can create serious problems for the parties.

Letter of intent should be avoided, if at all possible. Always make provision in the letter of intent as to what will happen if no contract comes to being. Most important is the provision for a basis of payment for work undertaken.

Page 33: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Site condition

• ‘Tenderer is deemed to have visited the site and accepted as found’• Access to site• Responsible of site during construction• Working hours• Surrounding owners• Local council requirements• Complicating matters is the fact that many construction contracts exclude liability

for information given by employer about the site, while generally held that to be reasonable, many problems ensue. Was site fit for its purpose for construction.

Delay in handling over the site to the contractor may cause Time at large.

The discussion of what exactly is “possession” in a construction contract continues into the realm of licenses.

Page 34: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Possession is not necessarily exclusive but rather dependant upon other provisions and conditions.

Employers frequently retain the right to bring other contractors on site to carry out specific works.

Claim for “unforeseen ground conditions”, the issue being what was “unforeseen” as against “unforseenable”

Page 35: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Construction drawings

• Completeness, all drawings coordinated between Architects and Engineers• “ Contractor deem to have check for any discrepancies and report……”• Drawing numbers and drawing references• Details• Revisions after contract was awarded.• Contractor claims of late issuance of drawings.

Page 36: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

The contract drawings

Discrepancies between contract and tender drawings, not updated.

Additional drawings, usually details, included but was absent in tender.

Page 37: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Material (performances)

Choice of materials and their performance

Availability

Controlled?

Compliance?

Fit for its purpose

Durability

Page 38: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Defects

Patent against Latent

De minimis

What Hudson said to this is:

“on grounds of both principle and practicality, a contractor will be in immediate breach of contract whenever his work fails to comply with the contract descriptions or requirements, although no doubt, as envisaged by Lord Diplock, the damages will be at best nominal in a case where he can show that he intends to rectify it at some more convenient time before completion without affecting the quality of the remaining work. Subject to this, it is submitted that there is effectively an implied entitlement of the owner to call for prompt and timeous contract compliance, and that refusal to comply would be a repudiation by the contractor entitling the owner to rescind”.

Page 39: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Sub-contractors/suppliers

Set Off by employer- If disagreement, may refer to adjudication.

Executed under PC or Provisional sum,

Liabilities on Main Contrator.

Page 40: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Variation OrderThe contractor is not obliged to carry out variations where the instruction is issued after CPC unless there is a clause in the contract which gives the architect/engineer power to issue an instruction.

Omitting and given to another contractor.

Due to a VO, an order for supply of material was cancelled by the contractor. Can contractor claim?

Page 41: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Architects Instruction

A verbal agreement is not worth the paper it is written on!

Written, reference to appropriate clause, may have implication.

Page 42: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Programme

• Contractual acceptance• Bar chart/Gnatt charts• CPM• ‘S’ curve• Progress report• Milestone chart• Crash

Page 43: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

A party to a dispute, particularly if there is an arbitration or litigation will learn three lessons (often too late): the importance of records, the importance of records and the importance of records!

Page 44: CONTRACT ADMINISTRATION AND DISPUTE - PAM Northern …architecturemalaysia.com/Files/Pool/97...pamnc... · Similarly, the LD clause is inoperative as there is no date from which LD

Thank You


Recommended