1 Corrib Onshore Pipeline and Status Update Project Completion Report
Transcript

1

Corrib Onshore Pipeline

and Status Update

Project Completion Report

Corrib Gas Onshore Pipeline Completion Report

Presentation Outline

Construction Timeline

Conclusions

Surface Water

Waste Management

Noise

Lighting and Visual

Archaeology

Ecology

03 December 2015 2

Corrib Onshore Pipeline Completion Report

January 2011 - An Board Pleanála Approval received

Precommencement conditions fulfilled

Environmental Management Plan

Manage and Control Environmental Aspects of Construction

Monitor the effectiveness of these controls

July 2011 commenced construction in Aughoose

03 December 2015 3

Corrib Gas Onshore Pipeline Completion Report

Construction Highlights

03 December 2015 4

2011 2012 2013 2014 2015

SC3 Tunnelling Compound

established and fully fenced.

Siltbuster

Surface Water Plant (SB3)

operational.

Offshore Pipeline precommissioned

Tunnelling

commenced

Commence stone road construction

Commence SC1

and SC2 in Glengad

Continue Tunnelling

Install reception

pit in SC2

Install pipeline in wayleave.

Install pipeline

between SC1 and SC2

Complete 190m and Leenamore

Crossing.

Pull-in of Offshore

Umbilical at SC1

Complete Tunnelling and remove TBM at

SC2

Reinstate Wayleave and

SC4

Install pipeline & services in Tunnelling

Test and

commission onshore

pipeline, LVI and umbilical

Complete tunnel grouting

Reinstate SC1 and SC2 & SC3

Corrib Gas Onshore Pipeline Completion Report

03 December 2015 5

February 2013 July 2013

Summer 2015

LVI

Corrib Gas Onshore Pipeline Completion Report

03 December 2015 6

February 2012 2013

Summer 2015

Aughoose Tunnelling Compound

Corrib Gas Onshore Pipeline Completion Report

03 December 2015 7

2009 July 2013

June 2014

Leenamore Crossing

03 December 2015 8

190m

2011 August 2013

September 2015

Corrib Gas Onshore Pipeline Completion Report

03 December 2015 9

Pipeline Wayleave

2013

September 2015

Corrib Gas Onshore Pipeline Completion Report

Corrib Gas Onshore Pipeline Completion Report

Surface Water Management

4 Surface Water Treatment Plants during construction at Glengad,

Aughoose, SC4 and Wayleave. (Lamella Plate Technology with

Chemical Flocculation)

Ongoing consultation with MCC regarding commissioning and

decommissioning plans for treatment units as works progressed

Post construction monitoring plans agreed and summary reports

containing results provided.

03 December 2015 10

03 December 2015 11

Post construction Monitoring Report DL6 Post construction January 2015

Corrib Gas Onshore Pipeline Completion Report

Surface Water Management

Corrib Gas Onshore Pipeline Completion Report

Waste Management

Waste Management Plan in Appendix B of the EMP.

Training and awareness programmes.

Colour coded waste segregration areas in all canteens.

Tunnel arisings and excavated materials from the LVI classified as by-products

under Article 27 of the European Communities (Waste Directive) Regulations, 2011

and reused at Coolturk Quarry and Kilcommon GAA pitch.

Wastewater generated during tunnelling works was transported via tanker to

licensed Wastewater Treatment facilities

03 December 2015 12

Corrib Gas Onshore Pipeline Completion Report

Noise

Noise Modelling carried out for potential noisy activities and all night time

construction (Tunnelling, Umbilical Pull-in and Commission )

Target level for design purposes was 35 dB(A) at Nearest Sensitive Receptor

Sentinel Noise Management System installed prior to tunnelling works

Real time information available to contractors .

Noise reports provided on a daily basis to monitor compliance

Play back of audio files to verify noise sources for elevated levels

03 December 2015 13

03 December 2015 14

Output for modelling exercise carried out for the construction of the tunnel reception pit and LVI in Glengad in 2013.

Corrib Gas Onshore Pipeline Completion Report

Corrib Gas Onshore Pipeline Completion Report

Lighting and Visual

Measures to minimise light pollution included downward facing lanterns and

non-transparent fencing panels

Lighting for Aughoose Tunnelling Compound designed in accordance with

EIS

Lighting assessment carried out prior to commencement of night time works

Other measures included ;

Painting fixed equipment Green

Tall structures painted gray (Gantry Crane and Crane Jibs)

03 December 2015 15

03 December 2015 16

Corrib Gas Onshore Pipeline Completion Report

Visual control measures at Aughoose Tunneling Compound.

Corrib Gas Onshore Pipeline Completion Report

Archaeology

Monitoring of all groundworks for pipeline and tunnelling arisings by licenced

archaeologists (11E0214 and 11R0090)

No features or artefacts of archaeological significance identified .

Palaeo-environmental analysis of organic deposits found in tunnel arisings

No evidence of human activity

Vegetational history of Sruwaddacon Bay

Woodland landscape dominated by pine and hazel trees during the Early

Holocene/ Early Mesolithic period

03 December 2015 17

03 December 2015 18

Corrib Gas Onshore Pipeline Completion Report

Wood fragments

Hazelnuts

Inspection of tunnel arisings, Aughoose compound

Corrib Gas Onshore Pipeline Completion Report

Ecology

Residual Impact predicted in 2010 EIS remain valid after construction

Natural succession and re-establishment of vegetation cover at Glengad

is progressing as expected.

Deciduous woodland and wetlands created along the forested wayleave

Created wetland habitats in Aughoose

Overall net local slight to moderate positive impact in the long term

03 December 2015 19

03 December 2015 21

Corrib Gas Onshore Pipeline Completion Report

Created Wetlands on the Wayleave

22

Corrib Onshore Pipeline

and Status Update

Thank you.

CORRIB GAS PIPELINE

PMC Meeting 13th

April 2016

1

Construction Works Undertaken from

December

Outlook:

Aughoose

Pipeline

� No work undertaken on the pipeline

wayleave.

Glengad

� No work undertaken.

Aughoose

� Planting of plants and seeding.

Pipeline

� No planned works .

Glengad

� No planned works

Environmental Monitoring Jan-April 2016

Ecological Ongoing ecological monitoring being undertaken as outlined in EMP.

Geotechnical Geotechnical monitoring is ongoing as per geotechnical hazard risk

reporting. Reports submitted on a bi-monthly frequency, no unexpected

variations recorded during recent observations.

Complaints

There were no written complaints during the reporting period.

CORRIB GAS DEVELOPMENT Report for Onshore Pipeline Project Monitoring Committee Meeting on 13th April 2016. Prepared by Mr. Padraic Walsh, Senior Engineer, Project Manager for Mayo County Council.

• Environmental Monitoring Works at the Aughoose site are complete and the reinstatement of the site is now also complete with just some planting yet to be carried out. Works at Glengad on the LVI facility are complete and reinstatement works have also been completed. Reinstatement and landscaping works on the pipeline wayleave from Aughoose to the terminal site are complete. The works have been subject to ongoing monitoring by Mayo County Council staff and by the developer in accordance with the agreed EMP. As all construction works and reinstatement have now been completed and as surface water runoff has reverted to it’s normal state the monitoring of surface water has ceased. Vibration monitoring by the Developer has ceased. The remaining noise meters have been decommissioned and noise monitoring has ceased. Mayo County Council has not received any complaints regarding environmental issues during this reporting period. • Roads and Transportation Movement of plant, materials and equipment associated with the onshore pipeline phase of the project has now ceased. All traffic movements to date have been carried out in compliance with the Traffic Management Plan. The final post works haul road condition surveys have been completed and work is underway on the preparation of a final haul road reinstatement programme.

BORD NA MÓNA

BORD NA MÓNA ENERGY LIMITED

Srahmore Peat Repository WL 0199-02

Environmental Management System Up-Date No. 75 (13/ 04/16)

Environmental Monitoring:

• There were no non-compliances since the last meeting in November 2015 • There were no complaints since the last meeting in November 2015. • There were no incidents since the last meeting in November 2015.

Monitoring Results: Munhin 2016 (todate)

0

0.001

0.002

0.003

0.004

0.005

0.006

01234567

Am

mon

ia m

g/l

SS

mg/

l

Quarterly Suspended Solids and Ammonia

Up/Stream SS (mg/l)

D/Stream SS (mg/l)

Up/Stream Ammonia (mg/l)

D/Stream Ammonia (mg/l)

SW4/104/100&101 2016

0

5

10

15

20

25

30

35

40

45

3 7 11 15 19 23 27 31 4 8 12 16 20 24 28 3 7 11 15 19 23 27

mg/

l

Jan - Mar 2016

Suspended Solids (mg/l) 2016Location 7 (SW4)

SW104 ( toMunhin)

SW100

SW101

ELV 1 (8/10samples)

ELV 2 (2/10samples)

The average Suspended Solids to date for 2016 is 3mg/l at SW 4 and at the

discharge from the site to the Munhin at SW104, and 2mg/l at SW101.

SW100 has been removed from the monitoring system, as approved by the EPA as

it is not treating any process water from the site operations.

Srahmore Site Update:

Personnel: On Site

Tractor & General Oper. 0 Environmental 0

BnM (Engineering) 0 Fitters 0 Archaeological 0 Site Admin & Mgt. 1 Electricians 0 Site Supervisors 0 Excavator & Shovel 0

TOTAL EMPLOYED 1

Contractors Security 0 Catering 0

TOTAL EMPLOYED 0

Off Site Head Offices Staff 0 BnM (Support) 0 Environmental Officer 1

TOTAL EMPLOYED 1

OVERALL TOTAL EMPLOYED 2

Srahmore Site Operations: The site continuous to be stabilised and rehabilitated, with the site emissions well below the emission limit values to date in 2016. The water level in Bay 4 was raised to enable more stabilisation of the peat and to facilitate an increased retention time of surface water from the site. Upon verification of success following monitoring and assessment for stability and ecology, this will be extended to the remaining bays.

As of the 29th of March 2016 the Srahmore site is c ompliant with Waste

Licence W0199-02.