Cross Project Dependencies 386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 1 Structured Solutions External Dependency Management Approach ........................................................................................... 2 Overview ................................................................................................................................................................................. 2 Manage External Dependencies ............................................................................................................................................... 3 Identify External Dependencies ............................................................................................................................................... 4 Definitions ........................................................................................................................................................................... 4 Enabling Microsoft Project Tools ........................................................................................................................................ 4 Tips & Tricks ....................................................................................................................................................................... 4 Code and Tag/Flag External Dependencies ............................................................................................................................. 4 Definitions ........................................................................................................................................................................... 4 Enabling Microsoft Project Tools ........................................................................................................................................ 6 Exercise Code and Flag External Dependencies ............................................................................................................... 7 Tips & Tricks ....................................................................................................................................................................... 8 Exercise Use SSI Tools to See External Dependency Codes and Flags ........................................................................... 8 Link External Dependencies from Predecessors in the Providing Project and to Successors in the Receiving Project ........... 9 Definitions ........................................................................................................................................................................... 9 Enabling Microsoft Project Tools ........................................................................................................................................ 9 Tips & Tricks ....................................................................................................................................................................... 9 Exercise Adding Predecessors to External Outputs and Successors to External Inputs ................................................. 10 Synchronize Dates in Providing and Receiving Project......................................................................................................... 11 Definitions ......................................................................................................................................................................... 11 Enabling Microsoft Project Tools ...................................................................................................................................... 11 Tips & Tricks ..................................................................................................................................................................... 11 Exercise Use Microsoft Project Tools to Combine Projects A & B ............................................................................... 13 Using SSI Link and Synchronize Tools ................................................................................................................................. 14 SSI Tools - Link Inputs/Outputs ........................................................................................................................................ 14 Exercise Use SSI Tools to Link and Synchronize Projects A & B ................................................................................. 15 SSI Tools - Sync Remote Projects ..................................................................................................................................... 17 Exercise Use SSI Tools Sync Remote Projects............................................................................................................... 19 SSI Tools - Synchronization Options ................................................................................................................................ 20 Schedule Roles Explained ......................................................................................................................................................... 21 Schedule Integrator ................................................................................................................................................................ 21 Schedule Contributor (Subproject owner) ............................................................................................................................. 22 Supported Environments............................................................................................................................................................ 23 Separate Subprojects are Always Controlled by Their Respective Subproject Owner .......................................................... 23 Summary Master Project with Milestones from Subprojects ................................................................................................. 25 Split one Project into Two or More Subprojects .................................................................................................................... 26
Transcript
  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 1

    Structured Solutions External Dependency Management Approach ........................................................................................... 2

    Overview ................................................................................................................................................................................. 2

    Manage External Dependencies ............................................................................................................................................... 3

    Identify External Dependencies ............................................................................................................................................... 4

    Definitions ........................................................................................................................................................................... 4

    Enabling Microsoft Project Tools ........................................................................................................................................ 4

    Tips & Tricks ....................................................................................................................................................................... 4

    Code and Tag/Flag External Dependencies ............................................................................................................................. 4

    Definitions ........................................................................................................................................................................... 4

    Enabling Microsoft Project Tools ........................................................................................................................................ 6

    Exercise – Code and Flag External Dependencies ............................................................................................................... 7

    Tips & Tricks ....................................................................................................................................................................... 8

    Exercise – Use SSI Tools to See External Dependency Codes and Flags ........................................................................... 8

    Link External Dependencies from Predecessors in the Providing Project and to Successors in the Receiving Project ........... 9

    Definitions ........................................................................................................................................................................... 9

    Enabling Microsoft Project Tools ........................................................................................................................................ 9

    Tips & Tricks ....................................................................................................................................................................... 9

    Exercise – Adding Predecessors to External Outputs and Successors to External Inputs ................................................. 10

    Synchronize Dates in Providing and Receiving Project......................................................................................................... 11

    Definitions ......................................................................................................................................................................... 11

    Enabling Microsoft Project Tools ...................................................................................................................................... 11

    Tips & Tricks ..................................................................................................................................................................... 11

    Exercise – Use Microsoft Project Tools to Combine Projects A & B ............................................................................... 13

    Using SSI Link and Synchronize Tools ................................................................................................................................. 14

    SSI Tools - Link Inputs/Outputs ........................................................................................................................................ 14

    Exercise – Use SSI Tools to Link and Synchronize Projects A & B ................................................................................. 15

    SSI Tools - Sync Remote Projects ..................................................................................................................................... 17

    Exercise – Use SSI Tools Sync Remote Projects ............................................................................................................... 19

    SSI Tools - Synchronization Options ................................................................................................................................ 20

    Schedule Roles Explained ......................................................................................................................................................... 21

    Schedule Integrator ................................................................................................................................................................ 21

    Schedule Contributor (Subproject owner) ............................................................................................................................. 22

    Supported Environments............................................................................................................................................................ 23

    Separate Subprojects are Always Controlled by Their Respective Subproject Owner .......................................................... 23

    Summary Master Project with Milestones from Subprojects ................................................................................................. 25

    Split one Project into Two or More Subprojects .................................................................................................................... 26

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 2

    Structured Solutions External Dependency Management Approach

    Overview

    A “Program” is often a collection of Projects and Subprojects. Often, these projects and subprojects are

    owned and maintained by separate teams or organizations within a company or even by different

    companies.

    For the most part Projects and Subprojects have Internal Dependencies between their own tasks and

    milestones. In many cases, however, an External Dependency exists where the predecessor or

    successor is part of another project or subproject. Common names External Dependencies include

    “Givers” and “Receivers”, “Inputs” and “Outputs” or just “Cross Project Dependencies”

    Managing a Program having External Dependencies requires explicit identification of these

    dependencies which may include a Unique Identification Code or number and Tags to show which

    project Provides the external dependency (the “Giver” or “Provider”) and who Receives the external

    dependency (the “Receiver” or “User”).

    In the example below, Internal Dependencies are shown using Black arrows and External Dependencies

    are show using Red arrows.

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 3

    Manage External Dependencies

    The process steps for managing External Dependencies is shown graphically using a “process wheel”.

    A description of each step in the process, along with tips, tricks and tools used by the professional

    scheduler and schedule analyst are described in the following sections of this document.

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 4

    Identify External Dependencies

    Definitions

    External Dependencies exist in a Project or Subproject when the Predecessor or Successor of a

    scheduled item is found in another project or subproject.

    External Dependency Code is a Unique Code or number that is used by both the Provider and the

    Receiver of the item. The Unique Code is usually determined and assigned by the Provider.

    Enabling Microsoft Project Tools

    Simple tables in a spreadsheet can be used to log each instance of a Dependency that will be produced

    by one project (the “Giver” or “Provider”) and Received by another project (the “User” or “Receiver”)

    Tips & Tricks

    Have the Receiving Project or Subproject initiate the creation of External Dependencies. If done any

    other way you may end up with items being Provided that no other Project or Subproject needs.

    Code and Tag/Flag External Dependencies

    Definitions

    Giving a Unique Code to External Dependencies (#001 and #002 in the example below) is only a part of

    its identity. Knowing the direction of the dependency (i.e., which project provides and which project

    receives) is the other part. #001 is an Output from the perspective of Project A and it should be tagged

    (or flagged) as such in Project A. From the perspective of Project B, however, the same item is an

    Input.

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 5

    Example of External Dependency Codes & Tags/Flags are shown in the table below: External Dependency Tag or Flag is used to show

    the direction of the External Dependency. Since

    there are two ends of an External Dependency, the

    providing end will Tag or Flag the dependency as

    an “Output” and the receiving end of the

    dependency will Tag or Flag the dependency as an

    “Input”. The example below shows two

    Milestones that represent an External Dependency

    from Project A to Project B.

    External Dependency Relationship Types can be any of the following:

    One-to-One - the Output from one project is

    used by just one other project.

    One-to-Many – the Output from one project is

    used by more than one project.

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 6

    Enabling Microsoft Project Tools

    Microsoft Project has Text and Flag fields that are useful for Coding and Tagging/Flagging External

    Dependencies. Select One Text field and designate its use for External Dependency Codes. Pick one

    Flag field and designate its use to tag the Output side of the External Dependency. Pick another Flag

    field and designate its use to tag the Input side of the External Dependency. Figure 1 – Unsynchronized Example (not yet linked to source and target project) of Code and Tag/Flag used by a project Providing 2

    External Dependencies and Receiving 1 External Dependency using Microsoft Project Text and Flag fields

    Figure 2- Unsynchronized Example (not yet linked to source and target project) of Code and Tag/Flag used by a project Receiving 2

    External Dependencies and Providing 1 External Dependency using Microsoft Project Text and Flag fields

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 7

    Exercise – Code and Flag External Dependencies

    Practice – Session Exercise

    Start a new project in Microsoft Project with a Top level Summary in row 1 named “Project A

    Requirements”

    1. Add the following tasks: a. Write the Requirements Document (3 Day Duration) b. Requirements Document Published by Project A (Zero Day Milestone) c. Write the Requirements Verification Document (2 Day Duration) d. Requirements Verification Document Published by Project A (Zero Day Milestone) e. Receive Test Report From Project B (Zero Day Milestone) f. Review Test Report (2 Day Duration)

    2. Add the columns named Text9, Flag8, Flag9 3. Rename Text9 to “Ext Dep Code”, Flag8 to “Input” and Flag9 to “Output” 4. Enter “ProjA-001” in Text9 of item b. above (“Requirements Document Published by

    Project”) and mark it as an Output by setting Flag9 = Yes

    5. Enter “ProjA-002” in Text9 of item d. above (“Requirements Verification Document Published by Project A”) and mark it as an Output by setting Flag9 = Yes

    6. Enter “ProjB-001” in Text9 of item e. above (“Receive Test Report From Project B”) and mark it as an Input by setting Flag8 = Yes

    7. Save this project as ProjectA.mpp

    Start a new project in Microsoft Project with a Top level Summary in row 1 named “Project B

    (Product)”

    1. Add the following tasks: a. Requirements Document Published by Project A (Zero Day Milestone) b. Design Product Via Requirements (2 Day Duration) c. Requirements Verification Document Published by Project A (Zero Day Milestone) d. Test and Verify Product Performance (2 Day Duration) e. Deliver Test Report (Zero Day Milestone)

    2. Add the columns named Text9, Flag8, Flag9 3. Rename Text9 to “Ext Dep Code”, Flag8 to “Input” and Flag9 to “Output” 4. Enter “ProjA-001” in Text9 of item a. above (“Requirements Document Published by

    Project”) and mark it as an Input by setting Flag8 = Yes

    5. Enter “ProjA-002” in Text9 of item c. above (“Requirements Verification Document Published by Project A”) and mark it as an Input by setting Flag8 = Yes

    6. Enter “ProjB-001” in Text9 of item e. above (“Receive Test Report From Project B”) and mark it as an Output by setting Flag9 = Yes

    7. Save this project as ProjectB.mpp

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 8

    Tips & Tricks

    External Dependency Code Assignment - Have the Providing Project or Subproject assign the Code for

    External Dependencies. Using a convention that includes the provider’s project code can be helpful.

    “ProjA-001”, for example makes it clear that the item is provided by Project A. The Output codes

    shown in the example below will work well, but it’s hard to tell where the item is coming from.

    Use SSI Tools to code and Tag/Flag External Dependencies

    Use the tool named Identify

    Input/Output on the SSI

    Analysis Tools menu to enter

    Codes and Flags for External

    Dependencies

    1. Select a row in a project that represents an External

    Dependency

    2. Click Identify Input/Output on the SSI Analysis Tools

    menu

    3. Enter the I/O Code. If the active project is the Provider,

    make sure the code has not

    already been used by listing

    all existing Outputs by

    checking “Show Outputs”

    4. If the active project provides the item, Check Output. If

    the active project receives the

    item Check Input

    5. Click Apply to Selected Row 6. Use the Up/Down button to

    go to the next or previous

    item if needed

    Exercise – Use SSI Tools to See External Dependency Codes and Flags

    Practice – Session Exercise

    Open ProjectA from the previous exercise

    1. Click Identify Input/Output from the SSI Analysis Tools Multi Project menu 2. Use Go Next and Go Previous to see the External Dependency Codes and Flags used in the project 3. Click Show Outputs and Show Inputs to see all External Dependencies used in the project

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 9

    Link External Dependencies from Predecessors in the Providing Project and to Successors in the Receiving Project

    Definitions

    If an External Dependency is an Output of the active project, it should have one or more predecessors.

    Notice that “Requirements Document Published by Project A” is preceded by the task named “Write the

    Requirements Document”. In this example, “Write the Requirements Document” is a predecessor to

    “Requirements Document Published by Project A” using a Start to Start link with a 1 day lag.

    If an External Dependency is an Input to the active project, it should have one or more Successors.

    Notice that “Requirements Document Published by Project A” is succeeded by the task named “Design

    Product Via Requirements”. In this example, “Requirements Document Published by Project A” is a

    predecessor to “Design Product Via Requirements” using a Finish to Start link with 0 lag.

    Enabling Microsoft Project Tools

    Display the Microsoft field named Predecessors and Successors or display the Predecessor/Successor

    form. Add Predecessors to Outputs and Successors to Inputs.

    Tips & Tricks

    Use zero duration milestones for External Dependencies in Microsoft Project. Though this is not a

    requirement, it makes for easy identification of External items in a project. Notice in the example below

    that External Dependencies (shown in yellow) are Milestones.

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 10

    Exercise – Adding Predecessors to External Outputs and Successors to External Inputs

    Practice – Session Exercise

    Open ProjectA from the previous exercise

    Add Predecessors to External Outputs

    1. Link the Task named “Write the Requirements Document” to the Milestones named “Requirements Document Published by Project A” using a Start to Start dependency with 1 day of lag

    2. Link the Task named “Write the Requirements Verification Document” to the Milestones named “Requirements Verification Document Published by Project A” using a Finish to Start dependency

    with 0 lag

    Add Successors to External Inputs

    3. Link the Milestone named “Receive Test Report From Project B” to the task named “Review Test Report” using a Finish to Start dependency with 0 lag

    Add Remaining Dependencies in ProjectA

    4. Link the Task named “Write the Requirements Document” to the Task named “Write the Requirements Verification Document” using a Finish to Start dependency with 0 lag

    5. Link the Task named “Write the Requirements Verification Document” to the Task named “Review Test Report” using a Finish to Start dependency with 0 lag

    Open ProjectB from the previous exercise

    Add Successors to External Inputs

    1. Link the Milestone named “Requirements Document Published by Project A” to the task named “Design Product Via Requirements” using a Finish to Start dependency with 0 lag

    2. Link the Milestone named “Requirements Verification Document Published by Project A” to the task named “Test and Verify Product Performance” using a Finish to Start dependency with 0 lag

    Add Predecessors to External Outputs

    1. Link the Task named “Test and Verify Product Performance” to the Milestones named “Deliver Test Report” using a Finish to Start dependency with 0 lag

    Add Remaining Dependencies in ProjectB

    2. Link the Task named “Design Product Via Requirements” to the Task named “Test and Verify Product Performance” using a Finish to Start dependency with 0 lag

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 11

    Synchronize Dates in Providing and Receiving Project

    Definitions

    Synchronized External Dependencies have the same date and completion status in the providing and

    receiving project. Both the date and the completion status is usually determined by the provider.

    Enabling Microsoft Project Tools

    Post status in Microsoft Project to tasks that precede External Dependencies that are Output. Inform

    stakeholders in receiving or using project of the Date and Completion status of External Dependencies

    so they can apply the same date and status to External Dependencies that are Inputs.

    Tips & Tricks

    After Identifying, Coding, Tagging/Flagging and Linking External Dependencies you can make a

    consolidated project, sometimes called an Integrated Master Schedule (IMS) and synchronize External

    Dependences as follows:

    Combine Projects/Subprojects into a Consolidated IMS

    Record an Interim Plan before Synchronizing External Dependencies to enable Change Tracking in the Consolidated IMS

    Link and Synchronize External Dependencies in the Consolidated IMS

    Perform Analysis of Schedule Variances caused by Synchronized External Dependencies

    Distribute the Synchronized dates of External Dependencies to the projects Receiving/Using External Dependency items

    Combine Projects/Subprojects into a Consolidated IMS

    Consolidated IMS Preparation:

    Calendars

    Resource Tables

    Fields

    Project Status date

    A consolidated project (or IMS) and all its subprojects should be

    using a common set of Calendars, Resource Tables and Fields.

    The IMS and each subproject should have the same Project Status

    date with all tasks updated through the Project Status date.

    Insert Subprojects into the

    Consolidated IMS using

    Microsoft Project tools.

    1. Select Subproject from the Insert group on Microsoft

    Project’s Project menu

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 12

    2. Browse to the location of each project/subproject to

    insert into the Consolidated

    IMS

    3. Remove the option to Link to Project

    4. Press the Insert button

    Inserted Projects in a Consolidated IMS

    Consolidated Project with Project A and Project B Combined

    Projects have not been Synchronized yet

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 13

    Exercise – Use Microsoft Project Tools to Combine Projects A & B

    Practice – Session Exercise

    Open a new Project in Microsoft Project and set its Project Start date to 2/23/2017 (Use Project

    Information from the Project menu in Microsoft Project)

    1. Select Subproject from the Insert group on Microsoft Project’s Project menu

    2. Browse to the location of ProjectA and ProjectB

    3. Remove the option to Link to Project 4. Press the Insert button

    5. Save this combined project as “IntegratedProject-A-Plus-B.mpp”

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 14

    Using SSI Link and Synchronize Tools

    SSI Tools - Link Inputs/Outputs

    Link and Synchronize External Dependencies in the Consolidated IMS

    Use the SSI Tool named Link

    Inputs/Outputs on the Multi

    Project group of the SSI

    Analysis Tools menu to find,

    link and synchronize External

    Dependencies

    1. Press the button named Code & Flag Field Setup and

    select the Microsoft Project

    fields used for the External

    Dependency Code and Flags

    Note - The setup page

    includes a user defined

    project field that is used to

    Log each link or link error.

    2. Press the button named Link to find, link and synchronize

    External Dependencies

    3. Check the Log field for the following

    a. Linked @ Date & Time b. Link Error No Successor c. Link Error No

    Predecessor

    Note the Option Named Copy Current Input/Output Dates to

    When using this option, the current Dates for Inputs and Outputs are recorded in a date field before

    the synchronizaton is performed. This enables change tracking of the schedule impact caused by

    linking Outputs to their respective Inputs

    Note the Option Named If Output is 100% Complete then

    Use this option to pass actual comletion status from Outputs to their respective Input.

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 15

    After Linking, Input/Output dates are Synchronized in each Project

    Exercise – Use SSI Tools to Link and Synchronize Projects A & B

    Practice – Session Exercise

    Open the combined project named “IntegratedProject-A-Plus-B.mpp” from the previous Exercise

    1. Click Link Inputs/Outputs from the Multi Project group on the SSI Analysis Tools menu and select the options shown below

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 16

    2. Select Code & Flag Field Setup and Apply the Setup shown below

    3. Click Link on the form named Link Inputs/Outputs

    4. Save the Project as “IntegratedProject-A-Plus-B.mpp”

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 17

    SSI Tools - Sync Remote Projects

    Importing or Exporting Synchronized Dates Between a Local Project and Remote Projects

    Now that Input/Output dates have been synchronized in a combined project, you can export (or

    “Post”) those dates to each respective individual project or import (“Get”) those dates from the

    Integrated Project using Sync Remote Projects

    1. Select Sync Remote Projects from the Multi Project group of the SSI Analysis Tools menu 1. Browse and select Remote Projects 2. Post Dates to Remote Subprojects uses Output dates in the current project to synchronize

    Input dates in remote projects

    3. Get Dates from Remote Subprojects does just the opposite. It uses the Output dates in Remote subprojects to update matching Input dates in the current project

    Export (“Post”) Output dates from the Integrated Project to corresponding Inputs in Remote Projects

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 18

    Import (“Get”) Output dates from the Integrated Project to corresponding Inputs in Remote Projects

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 19

    Inputs and Output dates are Synchronized after using Post (to Export dates to Individual Projects) or

    Get (to import dates from Consolidated Project)

    Exercise – Use SSI Tools Sync Remote Projects

    Practice – On your own

    Open the combined project named “IntegratedProject-A-Plus-B.mpp” from the previous Exercise

    or open ProjectA.mpp or ProjectB.mpp

    1. Use Sync Remote Projects to Get or Post External Dependency dates using the instructions shown in the previous section.

    2. Try the same using Options on the page named Synchronization Options (See the instructions below)

    3. Try generating Synchronization Reports

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 20

    SSI Tools - Synchronization Options

    Select the tab named Synchronization Options to make changes to the Text and Flag fields used to

    Code and Tag/Flag Inputs and Outputs. This page also shows options for Synchronization of Inputs

    and Outputs in remote Subprojects.

    Select the option named “If Output is 100% Complete Make Input 100%

    Complete if Input is a Milestone” to

    automatically post status to zero

    duration Inputs in the remote

    subproject if the corresponding

    Output is complete

    Select the option named “Log Synchronization Transaction

    Notes… to record each Post or Get

    transaction in the active project

    Options when Posting dates from the

    active project to remote projects:*

    Select the option named “Post Output Dates in this Project…” to

    record Output dates from the active

    project to matching Outputs in

    remote projects

    Select the option named “Post Input Dates in this Project…” to record

    Input dates from the active project to

    matching Inputs in remote projects

    Options when Getting dates from

    remote projects:*

    Select the option named “Get Outputs in Remote Projects…” to

    record Output dates found in Remote

    Projects to the corresponding Inputs

    in the active project

    Input/Output Identification Settings:

    Select the button named “Change Settings” to change the fields used to

    Code and Tag/Flag Inputs and

    Outputs

    Different treatment of Input/Output matching when using

    Get vs. Post actions:

    *When Getting dates from remote projects, SSI tools looks

    for Outputs in remote projects having codes that match

    Inputs in the active project. (Matching via. Output-to-

    Input).

    When Posting to remote projects Outputs are matched to

    Outputs and Inputs are matched to Inputs (Matching via.

    Output-to-Output and Input-to-Input)

    Why the difference?

    The reason for different treatment of Input/Output

    matching when using Get vs. Post is based on the different

    role of a Schedule Integrator (who uses Post from an IMS)

    vs. that of a Schedule Contributor (who may use Get while

    working in a subproject)

    See the illustration of “Scheduler Roles” on the next page

    for a pictorial explanation of the

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 21

    Schedule Roles Explained

    Schedule Integrator

    The role of a Schedule Integrator is to combine two or more subprojects and link them through their

    Inputs and Outputs as an Integrated Master Schedule or IMS. Once linked, the IMS has calculated the

    cumulative effect of Outputs that drive Inputs. The Schedule Integrator may be responsible for Posting

    synchronized dates to subprojects.

    In an IMS, there is often a “daisy chain” effect where an output in one subproject is being driven by

    external dependencies from another subproject. The IMS calculates more accurate dates for Inputs and

    Outputs because it takes “daisy chaining” into account.

    Once the IMS is integrated, synchronized Inputs in the IMS should be posted to corresponding Inputs in

    subprojects (Input in IMS to Input in subproject). The process of posting Input dates this way

    automatically synchronizes Outputs in subprojects as well. But… just to be sure, SSI Tools includes an

    option to post IMS Output dates to corresponding Outputs in subprojects (Output in IMS to Output in

    subproject)

    Figure 3 - Integrated Master Schedule (IMS) is a schedule that combines two or more subprojects

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 22

    Schedule Contributor (Subproject owner)

    The role of a Schedule Contributor is to develop a credible schedule that yields accurate dates -

    including the dates for their own Outputs. From time to time, a Schedule Contributor may need to Get

    dates from the IMS. When doing this action, the subproject needs to receive Output dates from the IMS

    and use those dates to synchronize Inputs dates in their own project. (IMS Output to Input in the

    subproject)

    Figure 4 - Subproject Gets its Input dates from outputs in the IMS or another Subproject

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 23

    Supported Environments

    Separate Subprojects are Always Controlled by Their Respective Subproject Owner

    In this environment, Subprojects (Microsoft project files) are owned and maintained by more than one

    project team. Though they may be combined from time to time (as an IMS) to synchronize External

    Inputs/Outputs between teams, they are never “locked” or “checked out” to the IMS “integrator” and are

    always available for use by their individual owner.

    1. Two or more Subprojects are developed and maintained by separate “owning” teams 2. Teams collaborate via a “dependency workshop” to identify External Inputs & Outputs and

    agree on their scope/content and deadline dates

    3. From time to time, Subprojects are integrated into an IMS and External Inputs & Outputs are validated and synchronized

    o Using Microsoft Project - Insert Subproject tools (with or without “Link to Project” option)

    o Using SSI Tools – Link Inputs/Outputs

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 24

    4. Synchronized Dates for Inputs are given to Subproject owners for implementation in each subproject

    o Using SSI Tools – Synchronize External Dependencies

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 25

    Summary Master Project with Milestones from Subprojects

    In this environment, Subprojects (Microsoft project files) are owned and maintained by more than one

    project team. Subprojects are never combined but a “Summary Master Project” containing Key

    Milestones only is maintained at the “Program” level

    1. A collection of projects or subprojects (Project portfolio) is developed by separate “owning” teams

    2. From time to time, information from the Project portfolio is queried for use in a Summary Master Project

    o Using SSI Tools – Synchronize External Dependencies

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 26

    Split one Project into Two or More Subprojects

    In this environment, the team has developed an Integrated Master Schedule (IMS) and wants to split it

    into Subprojects (Microsoft project files) that can be owned and maintained by more than one project

    team.

    1. Identify “split” points of the IMS’s Work Breakdown Structure 2. Log the dependencies that are external to each split

    o Using SSI Tools – Automatic Identification of External Dependencies

    http://www.ssitools.com/

  • Cross Project Dependencies

    386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: [email protected] Page 27

    3. Separate the Subprojects o Using SSI Tools - Distribute