Sr. ASMAWAN BIN MOHD SARMANSemester: January 2015
CVE 3204 ESTIMATING & CONTRACT
TOPIC 1: INTRODUCTION TOCOST ESTIMATING
1
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
2/27
Learning Objectives:
The student will able to;Define the terminologyIdentify the purpose/ importance of cost estimating
Understand the different methods of cost estimating processand techniques to different stages of project development.Identify different methods of construction estimateRecognize cost data for estimating purposesIdentify the purpose/ importance of cost estimating forparties in construction project.Recognize the estimate methods and selection of methods.
2
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
3/27
Regardless of size, shape or function of any
proposed work, a method of producing aaccurate estimate of the project is essential. A
contractor cannot afford to make an unrealisticoffer to a client who is instructing the work being
undertaken.
3
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
4/27
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
5/27
Definition: Cost Estimate
Technique to forecast the possible costs incurred fora certain building or construction project viasystematic calculation employing certain
techniques.
It is part of cost planning process in controlling
the project cost at the design stage before anydrawings are embarked upon.
5
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
6/27
Main Importance of Cost Estimate @Design Stage
According to Seeley (1996, p.154),the primary function of approximate or preliminary
estimating is to produce a forecast of probable cost offuture project, before the building has been designed indetail and contract particulars prepared. In this way the
building client is made aware of the likely financial
commitments before existence design work undertaken. Estimating process:
Initial stage design stage tender stage co nf i rm / p rec isecon t rac tua l su m (co nt rac t s tage)
6
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
7/27
- Design estimate- Bid estimate- Control estimate
Types of Construction Estimate7
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
8/27
Types of construction estimate
Design Estimates ( consultants / client's estimate ) during design stage
Screening estimates (or order of magnitude estimates)Preliminary estimates (or conceptual estimates)Detailed estimates (or definitive estimates)Engineer's estimates based on plans and specifications
Bid Estimates ( contractor estimate ) Tender stage / bidding stage
As a contractor, a bid estimate is submitted to the owner either forcompetitive bidding or negotiation.
Control Estimates post construction stageBudget estimate for financingBudgeted cost after contracting but prior to constructionEstimated cost to completion during the progress of construction.
8
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
9/27
The relationship of estimating process inproject development stages
Table 1 shows the chronological development of the project, and the way inwhich the cost estimating relate to the plan of work and cost planningprocess.
9
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
10/27
Cost Procedure & Techniques(RIBA stages)
RIBAStages
Inception Feasibility Outlineproposal
Schemedesign
Detail design
CostProcedure
Cost study ,establish cost
limit
Feasibilitystudies
Outline costplan
Preparedetail cost
plan
Prepare costcheck
Costingtechniques
Cost study ofsamples ofsimilarbuilding
Preliminaryestimates:either fromdeveloper /consultant(usingfinancialmethod /interpolationmethod)
Estimatesbased ongroupelements
Estimatebased onindividualelements
Approximatequantitiesmethod
Continued (next page)
10
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
11/27
Cost Procedure & Techniques
Productinformation
Bills ofquantities
Tenderaction
Projectplanning
On-siteoperation
Completion feedback
PrepareBQ
Costanalysis ,tenderevaluation
Costreport
Preparefinalaccount
Updaterecord
Elementalcostanalysis of
tender
Monthlychecking ofvariations
andinstructions
11
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
12/27
TOTAL COST TARGET = COST TARGET = COST LIMIT(individual elements) (group elements)
Cost Estimate as Design GuideCost limit
lump sum estimate of $2,000,000
Cost Target
$600,000
Cost Target
$750,000
Cost Target
$650,000
Elements
Groupelements
Individualelements
12
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
13/27
Cost Estimate as Design Guide
Cost estimate functions as design guide whether the project isappropriate to the cost limit / target allocation made earlier.
What if cost estimate > cost limit / target ???What if cost estimate < cost limit / target ??What if cost estimate = cost limit / target ??
Remedial action taken / adjustment ???
13
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
14/27
Remedial action taken / adjustment ???
If the estimate is > the allocated sum for the particularproject, the following could be carried out:
The design could be altered to reduce costExtra provisions are sought after or requested from the clientThe project is postponed is cancelled.
If the estimate is < the allocated sum, the following couldbe done;
To accept the estimateTo modify the design and/or the specifications to increase the estimateappropriate to the provisions set aside.
14
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
15/27
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
16/27
COST DATA in estimating16
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
17/27
Cost data
COSTDATA
Technical data
Priced books
Informationservices / cost
information
Tender /contract
document / BQ
Govtpublications:
PWD- unitpembangunan dan
khidmat kos,Contract & QS
dept
Dept. of
Statistics,Malaysia
Journals, magazines, etc.E.g.the Malaysian Surveyormagazineby ISM Spons Architects
& Builders pricedbook
SponsInternationalConstruction CostHandbooks
Spons Asia PacificConstruction CostHandbooks
Elemental CostAnalysis inthe
MalaysianSurveyormagazineby ISM
Previous project tender BQ/Contract document(cost
analysis / ECA)
Available books of costdata:- Average cost/ m2 for
(building work)- Schedule of rates;
- For minor & repair
works- For tender basedon drawings andspecs
- Construction Cost Guide(for the preparation ofpreliminary estimate)
- Building Material CostIndex
- Annual Survey ofConstruction Industries
17
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
18/27
Cost Data (others)
Other Government publications ; publish policies cost,interest rates, labour etc. ( Ministry of Housing And Local Government,Bank Negara Malaysia).
Media
comments on economy, announcementi.e. changes
to government policies, changes to the control cost of building materials or currentrate of inflation.
Other sources:research conducted by Universities or other relevant bodies
Suppliers quotations or materials cataloguesContractor , subcontractor quotations
Cost information obtained from Client and consultant
18
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
19/27
Cost Estimate Parties Design Stage19
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
20/27
CLIENT / EMPLOYER
A cost estimate,assist in ALLOCATING THE BUDGETrequiredto execute a planned project.
20
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
21/27
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
22/27
CONTRACTOR / BUILDERS
Cost estimate will,assists in the preparation of OFFER PRICEtoensure the offer price forwarded is reasonablefor bidding / tendering process.
22
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
23/27
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
24/27
BUILDING MANAGER
Cost estimate;
assists in establishing information on theprobable total cost of repairs andmaintenance of the building when the buildingis completed.
24
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
25/27
- Preliminary estimate- Approximate quantity- Elemental estimate
Methods of Estimate25
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
26/27
Methods of Estimate
Preliminary Estimate
Used to establish theprobable initial allocation orthe approximate estimateof a project. Methodsemployed:
Unit Cubic Floor area Storey-enclosure
Later stage estimate
It used to produce value,which is comparable to thelowest tender sum. Methodsemployed:
Approximate quantity Elemental estimate
Options appraisal schematic design Detailed design tendering
26
8/9/2019 CVE4215. Topic 1-Introduction to Estimating
27/27
The selection of method
Depends on:The information and time to prepare the estimate
Time is short simple / easy method used
More info thorough method may be utilized.
The experience of the QS.
The total and type of cost data available:Relevant / updated cost data/ analysis, drawings, projectspecifications.
27