    Sr. ASMAWAN BIN MOHD SARMANSemester: January 2015

    CVE 3204 ESTIMATING & CONTRACT

    TOPIC 1: INTRODUCTION TOCOST ESTIMATING

    1

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    2/27

    Learning Objectives:

    The student will able to;Define the terminologyIdentify the purpose/ importance of cost estimating

    Understand the different methods of cost estimating processand techniques to different stages of project development.Identify different methods of construction estimateRecognize cost data for estimating purposesIdentify the purpose/ importance of cost estimating forparties in construction project.Recognize the estimate methods and selection of methods.

    2

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    3/27

    Regardless of size, shape or function of any

    proposed work, a method of producing aaccurate estimate of the project is essential. A

    contractor cannot afford to make an unrealisticoffer to a client who is instructing the work being

    undertaken.

    3

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    4/27

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    5/27

    Definition: Cost Estimate

    Technique to forecast the possible costs incurred fora certain building or construction project viasystematic calculation employing certain

    techniques.

    It is part of cost planning process in controlling

    the project cost at the design stage before anydrawings are embarked upon.

    5

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    6/27

    Main Importance of Cost Estimate @Design Stage

    According to Seeley (1996, p.154),the primary function of approximate or preliminary

    estimating is to produce a forecast of probable cost offuture project, before the building has been designed indetail and contract particulars prepared. In this way the

    building client is made aware of the likely financial

    commitments before existence design work undertaken. Estimating process:

    Initial stage design stage tender stage co nf i rm / p rec isecon t rac tua l su m (co nt rac t s tage)

    6

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    7/27

    - Design estimate- Bid estimate- Control estimate

    Types of Construction Estimate7

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    8/27

    Types of construction estimate

    Design Estimates ( consultants / client's estimate ) during design stage

    Screening estimates (or order of magnitude estimates)Preliminary estimates (or conceptual estimates)Detailed estimates (or definitive estimates)Engineer's estimates based on plans and specifications

    Bid Estimates ( contractor estimate ) Tender stage / bidding stage

    As a contractor, a bid estimate is submitted to the owner either forcompetitive bidding or negotiation.

    Control Estimates post construction stageBudget estimate for financingBudgeted cost after contracting but prior to constructionEstimated cost to completion during the progress of construction.

    8

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    9/27

    The relationship of estimating process inproject development stages

    Table 1 shows the chronological development of the project, and the way inwhich the cost estimating relate to the plan of work and cost planningprocess.

    9

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    10/27

    Cost Procedure & Techniques(RIBA stages)

    RIBAStages

    Inception Feasibility Outlineproposal

    Schemedesign

    Detail design

    CostProcedure

    Cost study ,establish cost

    limit

    Feasibilitystudies

    Outline costplan

    Preparedetail cost

    plan

    Prepare costcheck

    Costingtechniques

    Cost study ofsamples ofsimilarbuilding

    Preliminaryestimates:either fromdeveloper /consultant(usingfinancialmethod /interpolationmethod)

    Estimatesbased ongroupelements

    Estimatebased onindividualelements

    Approximatequantitiesmethod

    Continued (next page)

    10

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    11/27

    Cost Procedure & Techniques

    Productinformation

    Bills ofquantities

    Tenderaction

    Projectplanning

    On-siteoperation

    Completion feedback

    PrepareBQ

    Costanalysis ,tenderevaluation

    Costreport

    Preparefinalaccount

    Updaterecord

    Elementalcostanalysis of

    tender

    Monthlychecking ofvariations

    andinstructions

    11

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    12/27

    TOTAL COST TARGET = COST TARGET = COST LIMIT(individual elements) (group elements)

    Cost Estimate as Design GuideCost limit

    lump sum estimate of $2,000,000

    Cost Target

    $600,000

    Cost Target

    $750,000

    Cost Target

    $650,000

    Elements

    Groupelements

    Individualelements

    12

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    13/27

    Cost Estimate as Design Guide

    Cost estimate functions as design guide whether the project isappropriate to the cost limit / target allocation made earlier.

    What if cost estimate > cost limit / target ???What if cost estimate < cost limit / target ??What if cost estimate = cost limit / target ??

    Remedial action taken / adjustment ???

    13

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    14/27

    Remedial action taken / adjustment ???

    If the estimate is > the allocated sum for the particularproject, the following could be carried out:

    The design could be altered to reduce costExtra provisions are sought after or requested from the clientThe project is postponed is cancelled.

    If the estimate is < the allocated sum, the following couldbe done;

    To accept the estimateTo modify the design and/or the specifications to increase the estimateappropriate to the provisions set aside.

    14

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    15/27

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    16/27

    COST DATA in estimating16

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    17/27

    Cost data

    COSTDATA

    Technical data

    Priced books

    Informationservices / cost

    information

    Tender /contract

    document / BQ

    Govtpublications:

    PWD- unitpembangunan dan

    khidmat kos,Contract & QS

    dept

    Dept. of

    Statistics,Malaysia

    Journals, magazines, etc.E.g.the Malaysian Surveyormagazineby ISM Spons Architects

    & Builders pricedbook

    SponsInternationalConstruction CostHandbooks

    Spons Asia PacificConstruction CostHandbooks

    Elemental CostAnalysis inthe

    MalaysianSurveyormagazineby ISM

    Previous project tender BQ/Contract document(cost

    analysis / ECA)

    Available books of costdata:- Average cost/ m2 for

    (building work)- Schedule of rates;

    - For minor & repair

    works- For tender basedon drawings andspecs

    - Construction Cost Guide(for the preparation ofpreliminary estimate)

    - Building Material CostIndex

    - Annual Survey ofConstruction Industries

    17

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    18/27

    Cost Data (others)

    Other Government publications ; publish policies cost,interest rates, labour etc. ( Ministry of Housing And Local Government,Bank Negara Malaysia).

    Media

    comments on economy, announcementi.e. changes

    to government policies, changes to the control cost of building materials or currentrate of inflation.

    Other sources:research conducted by Universities or other relevant bodies

    Suppliers quotations or materials cataloguesContractor , subcontractor quotations

    Cost information obtained from Client and consultant

    18

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    19/27

    Cost Estimate Parties Design Stage19

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    20/27

    CLIENT / EMPLOYER

    A cost estimate,assist in ALLOCATING THE BUDGETrequiredto execute a planned project.

    20

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    21/27

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    22/27

    CONTRACTOR / BUILDERS

    Cost estimate will,assists in the preparation of OFFER PRICEtoensure the offer price forwarded is reasonablefor bidding / tendering process.

    22

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    23/27

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    24/27

    BUILDING MANAGER

    Cost estimate;

    assists in establishing information on theprobable total cost of repairs andmaintenance of the building when the buildingis completed.

    24

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    25/27

    - Preliminary estimate- Approximate quantity- Elemental estimate

    Methods of Estimate25

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    26/27

    Methods of Estimate

    Preliminary Estimate

    Used to establish theprobable initial allocation orthe approximate estimateof a project. Methodsemployed:

    Unit Cubic Floor area Storey-enclosure

    Later stage estimate

    It used to produce value,which is comparable to thelowest tender sum. Methodsemployed:

    Approximate quantity Elemental estimate

    Options appraisal schematic design Detailed design tendering

    26

  • 8/9/2019 CVE4215. Topic 1-Introduction to Estimating

    27/27

    The selection of method

    Depends on:The information and time to prepare the estimate

    Time is short simple / easy method used

    More info thorough method may be utilized.

    The experience of the QS.

    The total and type of cost data available:Relevant / updated cost data/ analysis, drawings, projectspecifications.