+ All Categories
Home > Documents > CXC Manager’s Status Report For the period Oct 05 – Mar 06 Chandra Users’ Committee Meeting...

CXC Manager’s Status Report For the period Oct 05 – Mar 06 Chandra Users’ Committee Meeting...

Date post: 18-Dec-2015
Category:
View: 214 times
Download: 0 times
Share this document with a friend
Popular Tags:
18
CXC Manager’s Status Report For the period Oct 05 – Mar 06 Chandra Users’ Committee Meeting Roger Brissenden 5 April 2006
Transcript

CXC Manager’s Status ReportFor the period Oct 05 – Mar 06

Chandra Users’ Committee Meeting

Roger Brissenden

5 April 2006

5 April 2006 CXC Status Report/CUC Page 2

Topics

• Program Level Status– Program Management

– Spacecraft

– Mission Planning

– Science Instruments and Calibration

– OCC

– Data Processing

– CXCDS

– CDO

– Education and Outreach

• Mission Metrics

• Chandra Grant Awards

5 April 2006 CXC Status Report/CUC Page 3

Program Level Status

• Program Management– Budget: NASA required a 5% reduction to the FY06 CXC

budget in February and steps are being taken to accommodate this mid-year. Plans are not final, but steps will include some reduction to GO funds (aim is to minimize this), freezing open/future-attrition positions and moving staff as needed to fill required functions, and modifying phasing of funds to subcontractors. Further reductions in FY07 would impact CXC functions.

– Staffing: The Flight team has undergone a series of staff changes beginning with the retirement of the FOT manager, Leon McKendrick and the promotion of Dan Shropshire to the position. New Ground Team and Facilities Team leads are also being appointed through internal hiring. We are confident in the new FOT and OCC team organization and staffing.

– Facilities: The CXC Data System group moved (Dec 05) from offices in Harvard Square to new leased space at Cambridge Discovery Park, about 1.5 miles northwest of 60 Garden Street, that also houses other SAO units. The move was accomplished smoothly, with no disruption to operations.

5 April 2006 CXC Status Report/CUC Page 4

CXC Organization

Education & OutreachLestition

Director's OfficeWilkes

Grants Award SectionSozanski

Online OperationsMission Planning & TestingSpacecraft EngineeringFlight SoftwareFactory Support Team

Flight Operations TeamShropshire

Facility Systems TeamIntegration & Ground

S/W MaintenanceGround Ops Team

OCC OperationsEagan

Ops. Science SupportCalibrationMission PlanningSci. Data Sys. PlanningIPI Teams

ScienceTananbaum

Hardware & SystemsSoftware DevelopmentTestArchive OperationsData Processing Operations

Science Data SystemFabbiano

Systems EngineeringHolmes

Chandra X-ray Center Program OfficeTananbaum

Canizares (MIT)Brissenden

MSFC Space Systems Programs & Projects OfficeHefner

5 April 2006 CXC Status Report/CUC Page 5

Flight Operations Team Staff ChangesChristine Harbison (Operations Manager, Flight Software) left the program

Craig Mahon assumed Acting Operations Manager duties in January 2006

Eric Page assumed Flight Software responsibilities in January 2006

Rich Myers assumed SMF management duties in January 2006

Brad Bissell completed transition from MP to Eng

Sabina Bucher transitioning to become MP Manager

Ken Gage transitioning to become Propulsion / PCAD engineer

DelMar

NGST Program Manger

D. Shropshire

Mission Planning Manager

S . Bucher

Operations Manager (Acting )

C. Mahon

Administrative Assistant

J. Park

Contracts : M .

LeonardBusiness : G.

Smith -Lee

NGST Factory POC

P. Pohlen

EPS / Thermal

R. Giordano

Ground Software

TBD

Senior Engineer PCAD / Prop

E . Martin

CCDM / Mech / SMF

R. Myers

Flight Software

E . Page

Senior Mission Planner

K . Marsh

Mission Planner / Ops Controller

B. Williams

Senior Ops Controller

D. Wicker

Ops Controller

D. Balke

Cmd ControllerJ. Wellington

Cmd ControllerS . Stewart

J. WiderK . Patrick

Etc .

Configuration Manager / QA

J. Rose

Mission Planner

M. Pendexter

Cmd Controller

F. Schackart

PCAD / Prop

K . Gage

Engineering Manager

P. Viens

EPS / Thermal

T. Trinh

CCDM / Mech / Ops Controller

B. Bissell

Cmd Controller

J. Price

Ops Controller

TBD

FOT Software Manager

TBD

Changes since last Quarterly in Blue

5 April 2006 CXC Status Report/CUC Page 6

Program Level Status

• Spacecraft– Continues to operate extremely well overall

– Nominal passage through winter 2006 eclipses and lunar eclipse on 11/1/05

– Patched Flight Software to raise EPHIN E1300 channel high-radiation threshold

– Patched On-Board Computer to eliminate SIM move to mid-point during SCS107, to reduce temperature spikes on translation motor

– Completed final build and reviews of recompiled Flight Software; preparing to enter test phase

– ACA dark current calibrations 11/12/05, 3/5/06

5 April 2006 CXC Status Report/CUC Page 7

• Spacecraft (con’t): Anomalies– On 1/12/06, a command overlap condition was identified between

the JAN1106A mission loads and the autonomous eclipse exit commanding (SCS 33) that resulted in the Sun Position Monitor being enabled outside the Fine Sun Sensor’s field of view (unexpected state). We disabled the monitor via the appropriate ground commands. Additional Mission Planning Guidelines and load review tool updates are in work to prevent future occurrences.

– A brief amount of anomalous telemetry was seen (15 Dec) in the secondary engineering portion of the HRC telemetry stream. The anomalous data had no operational impact, and no corruption of the x-ray event data was observed. The event is under investigation.

• Mission Planning– SCS107 ran once (21 Mar) due to high radiation event,

requiring replan– 5 load interrupt TOOs:

Date Target Days10/25/05 GRB051022 112/22/05 GRB051221 101/04/06 GRB051221 (followup) 801/11/06 GRB060108 303/29/06 SGR 1900+14 3

Program Level Status

5 April 2006 CXC Status Report/CUC Page 8

Program Level Status

• EPHIN– Spacecraft temperatures have increased due to

degradation of the metalized Mylar insulation– Keeping the EPHIN (Electron Proton Helium Instrument)

particle detector cool caused substantial constraints on spacecraft attitudes, restricted observation durations and made mission planning very difficult.

– Investigation showed that EPHIN can operate at up to 120F without damage. The Flight Director Board authorized increasing the allowed EPHIN temperature from 96F to 110F, and the trigger threshold of one of the electron detection channels (E1300) by a factor of two.

– E1300 threshold increase will decrease false SCS107 triggers due to puffed-up radiation belts

– Temperature increase will increase number of 27-volt power supply dropouts, but this is considered not harmful, and is acceptable to the engineering team and the EPHIN principal investigator

– These changes have resulted in more flexible mission planning

5 April 2006 CXC Status Report/CUC Page 9

Program Level Status

• Science Instruments– Instruments are operating extremely well

– The HRC Engineering (‘proof of concept’) unit will be integrated with the spacecraft simulator (the Avionics and Software Validation Test set) to allow testing new or modified HRC on-orbit procedures directly with the simulator.

• OCC– The OCC ground system was successfully migrated

from Silicon Graphics to Linux-based computers 29 Nov. Operations continued seamlessly, with no disruption.

– Telex/RTS was selected to replace the voice communications system; delivery expected May 06.

5 April 2006 CXC Status Report/CUC Page 10

• Data Processing– Automatic processing is current; median data

delivery time 31.1 hours from end of observation to delivery to user

– Complete data reprocessing (Repro 3) began 15 Feb; incorporates most recent algorithms and calibrations; 8 months of data (starting Jan 05) reprocessed to date

• CXC Data System Major ReleasesVersion Date Main contentsDS 7.6.4 Nov05 Multi-obi V&V fix; obs completion policyCIAO 3.3 Nov05 Science tools & library upgrades; new

tools; cycle 8 proposal toolsDS 7.6.5 Dec05 Cycle 8 proposal s/w; charge time updateDS 7.6.6 Jan06 Implement new observ policy in archiveDS 7.6.7 Feb06 Repro 3 s/w; telem & aspect enhancementsAlso: 6 data system patches (Nov, Dec [2], Jan, Feb, Mar)

– s/w fixes & updates

Program Level Status

5 April 2006 CXC Status Report/CUC Page 11

• Calibration Database (CalDB) Releases2 releases: v. 3.2.0 (21 Nov), v. 3.2.1 (15 Dec) incorporate

updates in 10 calibration product areas

• GO and Fellows Programs– Cycle 8 Call for Proposals was issued 16 Dec;

proposal deadline was 15 March– 726 proposals were received; process went smoothly – 9th Chandra Fellows cycle: Record 88 applications

received (accepted electronically, by 9 Nov); peer review 18 Jan, 5 Fellows selected (from Spain, U.S., Italy, Japan; to Rutgers, Inst. Adv. Study, CfA, Michigan, Penn State)

• Education and Public Outreach– 13 press activities– 1 press conference & release at January AAS, with 6

images– 8 press releases, 5 image releases– 32 major print articles, incl. 2 in USA Today; 269

major web articles; 2 items on broadcast news (NRP, Voice of America)

Program Level Status

5 April 2006 CXC Status Report/CUC Page 12

Mission MetricsMUPS Fuel Usage

5 April 2006 CXC Status Report/CUC Page 13

Mission MetricsThruster Warm Starts

5 April 2006 CXC Status Report/CUC Page 14

Mission Metrics Scheduled Observing Efficiency

Scheduled Observations

Month Seconds in month (ks) Scheduled Observing Time (ks) Scheduled Observing Efficiency

Mar-05 2678.4 1723.6 0.64

Apr-05 2592.0 1638.3 0.63

May-05 2678.4 1772.2 0.66

Jun-05 2592.0 1709.0 0.66

Jul-05 2678.4 1781.3 0.67

Aug-05 2678.4 1498.2 0.56

Sep-05 2592.0 1305.1 0.50

Oct-05 2678.4 1744.2 0.65

Nov-05 2592.0 1560.9 0.60

Dec-05 2678.4 1717.9 0.64

Jan-06 2678.4 1739.8 0.65

Feb-06 2505.6 1512.8 0.60

5 April 2006 CXC Status Report/CUC Page 15

Mission MetricsObserving Efficiency

0.40

0.45

0.50

0.55

0.60

0.65

0.70

0.75

0.80

Mar-05 Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06

Scheduled Efficiency

5 April 2006 CXC Status Report/CUC Page 16

Data Delivery EffectivenessAs of middle of following month As of 3/14/06

Month Number of Obs

Days to Data Delivery Number Deliv

Number Outstanding

Number Deliv

Number Outstanding

Obsids Outstanding(see below for details)

Min Avg Max

Mar-05 71 0 1 8 71 0 71 0

Apr-05 56 0 1 11 56 0 56 0

May-05 55 0 2 13 54 1 55 0

Jun-05 67 0 1 20 67 0 67 0

Jul-05 83 0 1 4 83 0 83 0

Aug-05 43 0 1 9 43 0 43 0

Sep-05 35 0 1 6 35 0 35 0

Oct-05 67 0 1 12 67 0 67 0

Nov-05 76 0 1 5 76 0 76 0

Dec-05 76 0 2 14 76 0 76 0

Jan-06 67 0 1 3 63 4 67 0

Feb-06 91 0 1 4 91 0 91 0

5 April 2006 CXC Status Report/CUC Page 17

Grant Award EffectivenessNon-Federal (SAO-Issued) Awards (2)

As of middle of following month As of 3/17/06

Month of Data

Delivery

Federal Awards

(1)

Non-Federal

Awards (3)

No. Grants Awarded

No. Outstanding

Avg days to award

(4)

No. Grants Awarded

No. Outstanding

Outstanding AwardsProposal no, Comments

Mar-05 1 9 6 3 20 9 0

Apr-05 0 13 7 6 16 13 0

May-05 0 26 26 0 15 26 0

Jun-05 2 10 7 3 11 10 0

Jul-05 3 10 9 1 16 10 0

Aug-05 2 4 4 0 9 4 0

Sep-05 4 6 2 4 6 6 0

Oct-05 2 3 1 2 10 3 0

Nov-05 0 5 2 3 9 5 0

Dec-05 1 7 7 0 13 7 0

Jan-06 6 61 56 5 12 61 0

Feb-06 0 16 11 5 8 11 5 7400430, 7501083 A&B, 7701063, 7700998

(1) Grants awarded to scientists at Federal institutions as interagency transfers through MSFC. (2) Grants awarded to scientists at non-Federal institutions through SAO Contracts and Grants Department.(3) Number of grants eligible for award, for which data were delivered to the observer in the month(4) Average days from data delivery to grant award to observer.

5 April 2006 CXC Status Report/CUC Page 18

Grant Award Efficiency

CXC GO Award Distribution (# Of Days from Data Distribution to Award )October 15, 2005 through February 28, 2006

0

25

50

75

100

125

10/1 11/1 12/2 1/2 2/2

Data Dis tribution Date

# of Days

S AO Da ys to Awa rd S AO O uts ta nding Awa rds


Recommended