+ All Categories
Home > Documents > D-handout

D-handout

Date post: 14-Apr-2018
Category:
Upload: lo-shun-fat
View: 218 times
Download: 0 times
Share this document with a friend

of 21

Transcript
  • 7/27/2019 D-handout

    1/21

    1

    TSP: 052-12C30-D

    DATE: 001023

    Training Support Package

    PREPARED BY

    MANEUVER SUPPORT

    CENTER

    Float Bridge

    Student Handout

    SFC Timothy Girard__________ 001023 ___________

    12C30 COURSE MANAGER Date

    _Mr. Harold Drossel ___________ 001023___________

    Chief, CMF 12 DOTD Date

    _Mr. Ollie Jackson_____________ 001023___________

    Chief, Warrior Engineer Division Date

  • 7/27/2019 D-handout

    2/21

    2

    RIBBON BRIDGERIBBON BRIDGE

    OVERHEAD CABLE SYSTEMOVERHEAD CABLE SYSTEM

    SUPERVISE INSTALLATION OF AN OVERHEAD

    ANCHORAGE SYSTEM Pages 3 - 7

    DIRECT ASSEMBLY OF A RIBBON BRIDGE Pages 8 - 17

    DIRECT RAFTING OPERATIONS AS RAFTCOMMANDER Pages 18 - 21

  • 7/27/2019 D-handout

    3/21

    3

    SUPERVISE INSTALLATION

    OF AN OVERHEADANCHORAGE SYSTEM

  • 7/27/2019 D-handout

    4/21

    4

    Overhead Anchorage Components

    Guy lines

    Anchorage Cable

  • 7/27/2019 D-handout

    5/21

    5

    DEADMAN DESIGN

  • 7/27/2019 D-handout

    6/21

    6

    Cable Clamp Setup

    Attach Bridle Lines

  • 7/27/2019 D-handout

    7/21

    7

    NOTES

  • 7/27/2019 D-handout

    8/21

    8

    DIRECT ASSEMBLY OF A

    RIBBON BRIDGE

  • 7/27/2019 D-handout

    9/21

    9

    Launch Site Crew

    Check to ensure that the bridge bay

    latches are thrown and the cable is out

    of the cable guide

    Lock down the driver side aft tie-down

    Ground guide the transporter into the

    water and release the bay when directed

  • 7/27/2019 D-handout

    10/21

    10

    Boat Operators

    Boat operators are normally a crew of

    two licensed soldiers

    Safety boats also have two operators, both

    trained on the correct method of

    recovering soldiers from the water, basic

    first aid, artificial respiration and correct

    radio procedures

    The safety boats should be equipped, as a

    minimum with the standard equipment

  • 7/27/2019 D-handout

    11/21

    11

    Bridge Centerline Crew

    This crew assembles on the hold boat with

    the necessary equipment. ie:

    * Wrench bay drive pin / T-bar

    * Crow bar / 60 bar

    * Tie-off rope / Throw rope

    * Roadway tool / J-hook

    * Ramp connecting hook / C-clamp

    * Portable hoist / Ramp to bay connector

    The bridge centerline crew connects bay to

    bay until the bridge is built across the gap

  • 7/27/2019 D-handout

    12/21

    12

    Transporter Shuttle Crew

    The shuttle crew are drivers that shuttles the

    prepared bays from the engineer equipment

    park to the launch site. The NCOIC of theengineer equipment park has control over

    these soldiers

    License drivers that understands hand

    signals for ribbon bridge

    The transporter shuttle crew prepares the

    bays for launch while the vehicles are staged

    in the engineer equipment park

  • 7/27/2019 D-handout

    13/21

    13

    Anchorage Crew

    Depending on what type of anchorage is

    being constructed, you will then assign

    soldiers for constructing either short termanchorage or long term anchorage.

    Soldiers assigned this duty will use either

    bridge erection boats with approach guys,

    shore guys, kedge anchors with anchor lines,or the overhead cable system used with bridle

    lines.

  • 7/27/2019 D-handout

    14/21

    14

    Assembly Time for

    Ribbon Bridges

    Example 1

    How much time is required to construct a 500ft

    ribbon bridge during daylight operations?

    500ft divided by 600ft per hour =.833 hours(day)

    Convert .833 to actual time.833hrs x 60min =49.98 round up 50 minutes

    Example 2

    How much time is required to construct a 500ft

    ribbon bridge during night operations?

    500ft divided by 600ft per hour =.833 hours(day)

    Convert .833 to actual time

    .833hrs x 60min =49.98 round up 50 minutes

    (Construction by night add 50 percent).833hrs x 30min =24.99 round up 25 minutes

    50min + 25min = 1 hour 15 minutes (night build)

  • 7/27/2019 D-handout

    15/21

    15

    Supervise Float Bridge

    Maintenance

    PMCS TRANSPORTERS

    PMCS RIBBON BRIDGE BAYS

    PMCS ERECTION BOATS

    PMCS CRADLES

  • 7/27/2019 D-handout

    16/21

    16

    Long Term Standing

    Float Equipment

    Make sure all bilge plugs are in place

    Make sure roadway latches are in the

    proper position

    Make sure lower lock drives are completely

    engaged

    Periodic checks on roadway surface forpunctures

    Inspect previously mentioned items

    periodically

  • 7/27/2019 D-handout

    17/21

    17

    NOTES

  • 7/27/2019 D-handout

    18/21

    18

    DIRECT RAFTING

    OPERATIONS ASRAFT COMMANDER

  • 7/27/2019 D-handout

    19/21

    19

    Directs the Centerline Crew

    Assist in connecting the boats to the raft and

    issues life jackets to soldiers on the raft

    Throw ramps for loading & unloading

    equipment from the raft. helps as lookout for

    the raft commander

    Secures the raft to the shore with tag lines or

    approach guys to prevent the raft from

    moving away from the shore when loading

    equipment

    Places the vehicles chock blocks to stabilize

    before departing from the shoreline and

    removes the chock blocks upon arrival to the

    far shore

    The centerline crew push or cut away debrisfrom the raft

    Operates the hydraulic pumps on the ramps

  • 7/27/2019 D-handout

    20/21

    20

    Periodic Operational Checks

    While Rafting

    Check ponton latches and lower lock

    drive pins.

    Pontons will be inspected for leakage at

    least once every 3 hours during heavy

    traffic.

    Debris will be cut from or removed from

    the water to ensure safe travel.

    Roadway pontons will be washed downperiodically of mud, dirt, rocks and

    checked for cracks or holes.

    Ramp cylinder valves will constantly be

    checked for leakage and for properoperation.

    Shore erosion will be monitored and back

    filled when necessary.

  • 7/27/2019 D-handout

    21/21

    21

    NOTES


Recommended