D I S T R I C T 1 1 2017 CONSTRUCTION PROGRAM
JOHN R. KASICH, OHIO GOVERNOR | JERRY WRAY, ODOT DIRECTOR | LLOYD MACADAM, DISTRICT DEPUTY DIRECTOR
SERVING BELMONT, CARROLL, COLUMBIANA, HARRISON, HOLMES, JEFFERSON & TUSCARAWAS COUNTIES
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
CONSTRUCTION PROGRAM HIGHLIGHTS 1
BRIDGE
36 Projects
49 structures / $51M
MAJOR
Projects
$30M
141 Projects
PAVEMENT
22 Projects
175 miles / $41M
SAFETY
50 Projects
$74M
OTHER
31 Projects
$28M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
BELMONT COUNTY 2
Belmont County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
91866 IR70-5.92 Lady Bend Hill bridges near Exit 204 (US 40) between
Morristown and Barnesville Bridge Deck Replacement 6/4/15 8/10/15-6/30/17 $10,786,500
95600 IR70-19.17-23.69 Just west of Mall Rd. to east of Exit 220 Resurfacing, Four-Lane 2/11/16 5/1/16-10/15/17 $12,800,858.80
80599 IR70-14.24 US 40 and SR 331 Interchange Major Reconstruction 3/1/16 4/1/16-9/30/17 $19,520,051.33
97839 CR72-12.43 Mt. Hope Rd. over Wheeling Creek just west of Lafferty Bridge Replacement
(OBPP) 4/7/16 5/1/16-5/31/17 $754,400
97843 TR454-0.00 Maynard Hill Rd. over Sloans Run in Maynard Bridge Replacement
(OBPP) 5/5/16 5/1/17-6/30/17 $436,200
97842 CR4-23.52
TR291-0.01
Colerain-Martins Ferry Rd. over Glenns Run on the east side of Colerain
Crozier Ridge Rd. over Pipe Creek on the west side of Businessburg
Bridge Replacement
(OBPP) 4/21/16 5/15/17-7/31/17 $987,000
88922 SR148-10.70 About 1 mile west of SR 145 Bridge Replacement 4/21/16 5/31/16-5/31/17 $897,022
97423
US40-24.76
SR147-35.04
SR149-11.32
SR149-13.99
SR800-12.63
Between Blaine and Lansing
W. 23rd St. at Bellaire
Near Glencoe
Near SR 9 at Warnock
Between I-70 and Barnesville
Culvert Replacement 9/8/16 6/1/17-8/15/17 $1,110,048.66
88913 IR70-18.43 CR 4 over IR 70 just east of SR 9 (Exit 216) Bridge Replacement 11/17/16 3/1/17-10/31/17 $1,559,089.94
89314 CR29-Commons
Mall Crossing
1.66 mile connector from the intersection of Mall Rd and
Banfield Rd. and a new bridge over I-70 to connect to Phase I of
the Commons Mall Crossing
New Construction 12/1/16 3/1/17-10/31/18 $10,328,829.65
101533 SR7-9.14 North of Dilles Bottom, just south of TR 534 Slide Repair 3/1/17 4/1/17-6/30/17 $209,974
91550 IR70-12.23 CR 78 over IR 70 between Exits 208 and 213 Bridge Replacement 10/6/16 4/15/17-8/31/17 $1,519,515.31
91546 SR7-23.61 1.7 miles north of SR 647 at Martins Ferry Bridge Deck Replacement 1/19/17 4/15/17-9/30/17 $1,883,345
101412 IR70-23.69 East of Exit 220 and CR 214 Slide Repair 2/2/17 5/1/17-6/30/17 $239,348
97261 SR147-31.93 Just east of TR 302 Slide Repair 2/16/17 5/1/17-7/31/17 $683,000
101689 SR800-8.66 South of Barnesville Slide Repair 3/1/17 5/1/17-8/1/17 $277,150
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
BELMONT COUNTY 3
Belmont County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
101133 CR4-17.33 Just west of Loretta Rd. Slide Repair 3/1/17 5/1/17-7/31/17 $333,650
100971 SR800-8.28 South of Barnesville Slide Repair 3/1/17 5/1/17-8/1/17 $224,250
103499 SR9-9.35 South of Warnock and Fador Rd. Slide Repair 4/1/17 5/1/17-9/30/17 $351,630
103510 US250-4.33 Just east of CR 14 between Colerain and Sunset Heights Slide Repair 4/1/17 5/1/17-7/31/17 $157,050
103643 SR647-
0.72/0.91/1.02 3 locations west of Darrah Rd. in Martins Ferry Slide Repair 4/1/17 5/1/17-8/31/17 $868,718
103404 US250-
8.10/8.14/8.15 3 locations west of Bridgeport near Beeson Ln. Slide Repair 4/1/17 6/1/17-8/1/17 $591,790
103630 US250-7.40 50 ft. south of CR 22 between Sunset Heights and Bridgeport Slide Repair 4/1/17 5/1/17-7/31/17 $340,080
103498 SR7-9.73 North of Dilles Bottom, 0.31 miles north of TR 534 Culvert Repair 4/1/17 5/1/17-6/1/17 $81,600
103641 SR9-7.00 Just north of SR 147 Slide Repair 4/1/17 5/1/17-7/31/17 $364,136
101980 CR30-5.65 In Bridgeport, Kirkwood Heights Rd. just west of Alexander Dr. Slide Repair 12/15/16 6/5/17-7/31/17 $151,999
100988 SR647-2.68 North of Martins Ferry and just west of CR 4 Slide Repair 4/1/17 6/1/17-10/1/17 $303,180
101508 SR331-2.22 Just east of Holloway corp. line Slide Repair 4/1/17 6/1/17-9/30/17 $425,000
101117 US40-20.80 Just east of Mall Rd. Slide Repair 3/2/17 5/1/17-8/31/17 $1,165,000
103395 SR647-6.63 0.37 miles north of Vickers Hill Rd. Slide Repair 4/1/17 6/1/17-8/1/17 $157,320
103393 SR647-3.97 1.3 miles north of CR 4 Slide Repair 4/1/17 6/1/17-9/1/17 $244,625
102372 SR7-16.68-17.86
SR7-20.06-26.44
From Bellaire to I-470
From Bridgeport to Yorkville Safety (Sign Upgrade) 5/25/17 7/1/17-11/30/17 $334,316
100987 US40-21.78 East of Banfield Rd. and across from TR 218 Slide Repair 5/1/17 8/1/17-10/31/17 $450,240
22778 IR470-6.54 Just west of SR 7 Bridge Repair 9/7/17 10/16/17-10/31/18 $3,169,638
101415 SR149-9.21 East of Glencoe and Regoli Rd. Slide Repair 7/2/17 9/1/17-11/30/17 $258,012
103513 SR7-18.50 Less than a ½ mile north of the I-470 intersection Culvert Repair 7/2/17 9/1/17-10/31/17 $266,800
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
BELMONT COUNTY 4
Belmont County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
99454 IR70-1.50 1.5 miles east of the Guernsey Co. line Slide Repair 7/13/17 9/1/17-10/31/17 $374,000
101501 SR148-17.91 East of Armstrongs Mills, 0.82 miles east of CR 5 Slide Repair 8/1/17 10/1/17-3/1/18 $520,180
101487 SR800-16.55 At Hendrysburg Slide Repair 8/1/17 10/1/17-11/30/17 $217,493
39 Total Projects worth more than $75M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
BELMONT COUNTY 5
BELMONT COUNTY
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
CARROLL COUNTY 6
Carroll County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
97185 SR43-22.00 Intersection of SR 183 in Brown Twp. Safety
(Intersection Improvement) 6/30/16 8/15/16-6/30/17 $605,019.47
95916 SR9-17.63 Intersection with SR 171 and CR 71 north of Carrollton Safety
(Intersection Improvement) 10/6/16 11/28/16-9/30/17 $1,126,422.78
95536
SR524-0.00-5.24
JEF-SR524-0.26-2.86
JEF-SR646-0.00-4.31
From the Jefferson Co. line to Mechanicstown
From the Carroll Co. line to Bergholz
From the Harrison Co. line at Annapolis to SR 152
Preventive Maintenance,
Chip Seal 12/15/16 5/1/17-9/30/17 $560,000
100513
SR39-6.53-7.29
SR332-0.00-10.69
SR542-5.05-5.48
Through Dellroy
From Carrollton to the Harrison Co. line
Through Dellroy
Resurfacing, Two-Lane 1/19/17 5/1/17-10/31/17 $1,619,931
100509 SR9-0.00-13.76
SR43-0.00-7.31
From Carrollton to the Harrison Co. line
From SR 9 to the Jefferson Co. line at Amsterdam Resurfacing, Two-Lane 4/13/17 6/1/17-10/31/17 $2,859,291
88919 SR542-10.51 5.31 miles north of SR 39 at Dellroy and Atwood Lake Culvert Replacement 8/11/16 6/15/17-7/31/17 $250,263.17
92356 SR164-6.08 Just west of CR 61 near Perrysville and SR 332 Slide Repair 4/27/17 6/15/17-8/15/17 $415,650
7 Total Projects worth more than $7M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
CARROLL COUNTY 7
CARROLL COUNTY
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
COLUMBIANA COUNTY 8
Columbiana County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
103067
SR7-2.75
JEF-SR7-0.66
JEF-SR7-2.45/2.88
Near Wellsville
Near Tiltonsville
Near Rayland
Bridge Repair 7/14/16 10/3/16-6/30/17 $1,915,012.60
92354 SR39-0.93 Just west of State St. in Salineville Slide Repair 7/28/16 9/19/16-8/31/17 $590,723
98848 SR9-14.64 9 intersections in the city of Salem Safety (Signal Upgrade) 9/22/16 1/15/17-6/30/17 $329,950
97844 TR848-0.61 Hull Rd., over Nancy Run just west of Foundry Hill Rd. Bridge Replacement
(OBPP) 5/19/16 4/1/17-8/31/17 $426,845
100478 SR11-15.99-22.70 Between Lisbon/SR 154 Exit and Columbiana/Leetonia SR
558 Exit
Preventive Maintenance,
Microsurfacing 4/21/16 5/15/17-7/31/17 $667,662.58
22854 SR14-7.58 Over SR 11 between Columbiana and Washingtonville Bridge Replacement 3/16/17 4/15/17-11/15/17 $2,278,448
91841 SR165-3.37-6.36
SR170-17.38-20.27
Thru East Palestine, from SR 14/170 to the PA state line
From SR 14/SR 165 to the Mahoning Co. line Resurfacing, Two-Lane 8/25/16 5/1/17-10/31/17 $1,119,132.55
100539 SR164-18.00-22.23 From TR 859 to CR 440 (west of Columbiana corp. limit) Preventive Maintenance,
Chip Seal 2/2/17 5/1/17-10/15/17 $238,183
100534 SR154-2.27-9.85 From SR 11 to Rogers Resurfacing, Two-Lane 2/16/17 5/1/17-10/31/17 $1,098,205
100523 US62-0.00-4.86 From the Stark Co. line to CR 404 Preventive Maintenance,
Microsurfacing 2/16/17 5/1/17-10/31/17 $948,330
91840 SR164-22.23-24.31
SR344-2.79-8.35
From CR 440 to Union St. in Columbiana
Thru Leetonia, from just east of Perry TR 856 to SR 11 Resurfacing, Two-Lane 3/2/17 5/1/17-10/31/17 $1,355,196
97659 SR517-0.73-8.50 From Lisbon to SR 7 Resurfacing, Two-Lane 3/2/17 5/1/17-7/31/17 $1,304,426
98262 SR7-5.29-6.09 At East Liverpool, from south corp. limit to US 30 Resurfacing, Four-Lane 3/16/17 5/1/17-8/15/17 $723,789
100052 SR517-6.65 1.85 miles west of SR 7 and East Fairfield Bridge Replacement 3/30/17 5/1/17-8/31/17 $525,966
101452 SR164-7.10 Just north of TR 2501 and south of Gavers Slide Repair 12/15/16 3/6/17-6/15/17 $194,039.55
91562 SR39-0.15 Just east of the Carroll Co. line near Salineville Bridge Replacement 4/27/17 6/1/17-8/31/17 $331,530
88918 SR164-15.54 0.34 miles north of SR 45 at Lisbon Culvert Repair 4/27/17 6/7/17-7/31/17 $568,317
102809 US30-8.86 Intersection of SR 9 and CR 406 in Hanoverton Safety (Signal Upgrade) 5/25/17 7/5/17-12/31/17 $172,940
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
COLUMBIANA COUNTY 9
Columbiana County Projects Ref. PID Number
Route & Section Location Work Type Sale Date Estimated
Start & End Dates
Estimated Investment
102341 US62-4.86-10.83 From SR 165 to SR 45 Preventive Maintenance,
Microsurfacing 6/22/17 8/1/17-9/30/17 $690,331
21901 US30-28.07 CR 451 over US 30 just west of SR 267 Bridge Repair 8/24/17 9/25/17-11/30/18 $567,595
Local Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
89468 Bowstring Arch Bridge At county fairgrounds in Lisbon Enhancement
(Historic Bridge Renovation) 6/15/16 10/24/16-6/30/17 $1,127,898.15
97816 Leetonia Trail Head
Facility
New trail head facility near the existing High Street Trail
Connector and a bike/ped path from the trail head facility to
the Leetonia Cherry Valley Beehive Coke Ovens
Enhancement (Bikeways) 11/18/16 2/15/17-11/11/17 $210,843.02
96996 East 4th Street In East Liverpool Enhancement (Sidewalks) 12/8/16 3/15/17-8/15/17 $574,631.76
102125 CR422-0.00-2.02 From SR 7 to Duquesne St. Resurfacing 2/15/17 5/17/17-10/11/17 $327,175
101945 Multiple city streets in
East Liverpool
Jefferson (5th-Webber)
Webber Way (West of Jefferson-Dresden)
Jackson & Market (3rd-6th)
Broadway (2nd-St. Clair)
Resurfacing 3/8/17 5/17/17-10/18/17 $1,401,200
25 Total Projects worth more than $18.5M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
COLUMBIANA COUNTY 10
COLUMBIANA COUNTY
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
HARRISON COUNTY 11
Harrison County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
91603 SR799-3.90
SR799-4.52 North end of Clendening Lake, about 4 miles east of SR 800 Bridge Replacement 8/11/16 1/17/17-5/15/17 $2,478,646.90
100979 US22-23.82 Eastbound on-ramp to US 22 at Hopedale Slide Repair 10/6/16 11/21/16-8/15/17 $212,435.60
102285 Scio Outpost/Yard Along SR 151 in North Twp. just west of Scio (not mapped) Salt Storage Facility 2/16/17 4/1/17-8/31/17 $1,103,105
92357 SR151-19.67 Just east of TR 178 (Skit Rd.) between Jewett and Hopedale Slide Repair 12/1/16 5/1/17-8/31/17 $463,694.25
98108 US250-0.00-4.22
SR151-0.00-4.58
From the Tuscarawas Co. line to the Tappan Lake rest area
From US 250 to Bowerston Resurfacing, Two-Lane 2/2/17 5/1/17-10/31/17 $1,897,000
101534 SR799-4.15 At Clendening Lake, 0.65 miles south of TR 311 Slide Repair 3/1/17 5/1/17-6/30/17 $194,535
95538 SR9-13.24-18.58
SR151-17.42-22.61
Between CR 22 and CR 13 thru Jewett
From Jewett’s west corp. limit to US 22 Resurfacing, Two-Lane 3/30/17 5/1/17-10/31/17 $1,863,000
95541
SR342-0.00-4.87
SR800-0.51-3.25
TUS-SR342-0.00-0.40
From West Chester to SR 800 at Freeport
From Freeport to US 22 near Smyrna
From SR 258 to the Harrison Co. line
Resurfacing, Two-Lane 5/11/17 6/1/17-9/30/17 $2,076,306
99946 SR151-8.30/9.28 2 locations between Conotton and SR 332 Culvert Replacement 6/8/17 8/1/17-9/30/17 $145,032
Local Project
99559
CR2-0.00-18.25
(Moravian Trail Rd./
Deersville Ridge Rd.)
From Tuscarawas Co. line to US 250 at Cadiz Safety (Pavement Marking) 5/10/17 7/19/17-10/4/17 $95,000
10 Total Projects worth more than $10.5M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
HARRISON COUNTY 12
HARRISON COUNTY
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
HOLMES COUNTY 13
Holmes County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
91845 SR241-0.00-7.75 From SR 39 in Millersburg to CR 235 near Mount Hope Resurfacing, Two-Lane 6/2/16 7/11/16-6/30/17 $1,214,435.70
95539 US62-0.00-5.66
SR60-4.22-10.33
From Knox Co. line to Stillwell
From Killbuck’s north corp. limit to SR 39 Resurfacing, Two-Lane 2/16/17 5/1/17-10/31/17 $2,073,030
100980 SR557-6.24 Just north of Charm Slide Repair 3/1/17 5/1/17-7/31/17 $308,504
98304 US62-18.64 Intersection of Washington St. and Glen Dr. in Millersburg Safety (Signal Upgrade) 9/8/16 3/9/17-7/31/17 $225,912.38
101528 SR60-2.56 South of Killbuck and 0.39 mile south of US 62 Slide Repair 4/1/17 6/1/17-8/15/17 $311,645
91561 US62-8.29 4.45 miles west of SR 520 Bridge Replacement 4/13/17 6/1/17-8/15/17 $268,645
91559 US62-18.10 1.53 miles west of SR 39 Bridge Replacement 2/16/17 6/15/17-9/30/17 $670,000
Local Project
85365 Trail, Phase 5B US 62 near Brinkhaven to CR 25 at Glenmont (7.47 miles) Enhancement (Bikeways) 11/17/16 2/15/17-10/15/17 $2,079,885.49
8 Total Projects worth more than $7M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
HOLMES COUNTY 14
HOLMES COUNTY
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
JEFFERSON COUNTY 15
Jefferson County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
94058 SR7-4.80 At Rush Run, south of Brilliant Slide Repair 7/10/14 4/1/15-6/30/17 $15,974,744.65
93192 SR7-10.0 Just north of Brilliant Slide Repair 2/5/15 4/20/15-6/30/18 $29,978,283.40
81314 SR7-17.29 In Steubenville at the intersection of US 22, SR 7 and
University Blvd.
Safety
(Intersection Improvement) 10/22/15 1/15/16-11/30/17 $9,931,409.14
88920 SR213-4.67 At CR 56 intersection between Taylortown and Pekin Bridge Replacement 2/11/16 5/27/16-5/31/17 $3,994,196.65
101597 CR46-1.75/1.91 About a ½ mile east of TR 376 near Wallace Heights at Toronto Slide Repair 8/25/16 10/24/16-6/30/17 $319,913
97846 CR7-1.10
CR7-2.45
Dillonvale-Longrun Rd. bridge over Short Creek just west of Newtown
Dillonvale-Longrun Rd. bridge over Short Creek just west of Olszeski Town
Bridge Replacement
(OBPP) 4/21/16 4/1/17-8/31/17 $1,435,850
97847 CR10-2.62 North Mill St. bridge over Short Creek in Adena Bridge Replacement
(OBPP) 4/21/16 6/2/17-10/15/17 $995,600
97848 CR50-1.24 East Ave. bridge over the North Fork of Yellow Creek in Irondale Bridge Replacement
(OBPP) 5/5/16 5/1/17-11/30/17 $635,600
94161 SR43-0.90 Lawson Ave. over SR 43 in Steubenville Bridge Deck Replacement 9/22/16 3/1/17-7/31/17 $1,174,000
101455 SR43-12.30 About ½ mile west of SR 152 at Richmond Slide Repair 10/20/16 3/1/17-5/31/17 $149,149
100982 SR7-32.60 About 1 mile south of SR 213 near Yellow Creek Slide Repair 2/16/17 3/27/17-7/31/17 $535,542
91564 SR7-1.31 At Tiltonsville, 1.07 miles south of SR 150 Bridge Repair 11/17/16 4/1/17-8/31/17 $1,642,000
91566 SR7-7.71 TR 163 over SR 7 at Salt Run Bridge Repair 2/2/17 4/1/17-9/30/17 $1,771,061
91569 SR150-12.54 0.33 miles west of SR 7 at Rayland Bridge Replacement 9/22/16 4/15/17-9/30/17 $1,261,890.55
94207 SR150-5.10 Just north of CR 7 near Dillonvale Bridge Deck Replacement 3/2/17 4/15/17-9/30/17 $985,338
91846 SR151-12.02-16.16 From New Alexandria to SR 7 at Georges Run Resurfacing, Two-Lane 2/16/17 5/1/17-10/31/17 $1,108,396
101596 CR53-3.65 Nearly 4 miles east of SR 164 at Bergholz Slide Repair 2/16/17 5/1/17-7/31/17 $300,000
101601 CR56-10.58 1.11 miles east of SR 213 Slide Repair 3/1/17 5/1/17-6/30/17 $131,520
101457 SR151-12.10 Between TR 162 and TR 163 at New Alexandria Slide Repair 4/1/17 6/1/17-9/30/17 $561,988
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
JEFFERSON COUNTY 16
Jefferson County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
101458 SR151-12.43 ¼ of a mile west of CR 19 at New Alexandria Slide Repair 4/1/17 6/1/17-9/30/17 $248,941
101459 SR152-8.20 Just east of CR 22A near Broadacre Slide Repair 4/1/17 6/1/17-10/31/17 $680,350
99960 SR213-0.00 Southern intersection with SR 7 at Alikanna
Safety
(Intersection Improvement
& Signal Upgrade)
10/19/17 11/19/17-10/31/18 $343,393
95536
SR524-0.26-2.86
SR646-0.00-4.31
CAR-SR524-0.00-5.24
From the Carroll Co. line to Bergholz
From the Harrison Co. line at Annapolis to SR 152
From the Jefferson Co. line to Mechanicstown
Preventive Maintenance,
Chip Seal 12/15/16 5/1/17-9/30/17 $560,000
103067
SR7-0.66
SR7-2.45/2.88
COL-SR7-2.75
Near Tiltonsville
Near Rayland
Near Wellsville
Bridge Repair 7/14/16 10/3/16-6/30/17 $1,915,012.60
Local Projects
90234 Lovers Lane/Fort
Steuben Drive
At the intersection of Lovers Lane and Fort Steuben Drive
in Steubenville
Safety
(Intersection Improvement) 7/13/16 3/6/17-7/31/17 $1,389,945.40
89450 CR74-1.36 Over Cross Creek, 0.70 miles south of CR 28 Bridge Replacement 7/21/16 11/1/16-5/1/17 $1,530,193.50
86475 CR75A-0.15 Over Yellow Creek Bridge Replacement 5/15/17 7/15/17-5/15/18 $830,000
89323 CR74-1.91 Over Cross Creek and Dry Fork, 0.15 miles south of CR 28 Bridge Replacement 5/15/17 7/15/17-4/15/18 $2,127,229
28 Total Projects worth more than $82.5M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
JEFFERSON COUNTY 17
JE
FF
ER
SO
N C
OU
NT
Y
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
TUSCARAWAS COUNTY 18
Tuscarawas County Projects
Ref. PID Number
Route & Section Location Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
99411 SR800-28.47
Construct bike lanes on bridge over the Tuscarawas River
for the Ohio Erie Canal Towpath Trail between CR 81
(Canal Rd.) and SR 212, also includes intersection lighting
Enhancement (Bikeways) 7/14/16 10/17/16-6/30/17 $365,778.20
24975 US250-22.51 Between US 36/Water St. Exit and 2nd St. Exit at Dennison Bridge Deck Replacement 9/22/16 4/1/17-10/31/17 $2,836,805.42
101683 Sherman Street In Dennison, from N. Third St. to N. Fifth St. Enhancements (Sidewalks) 3/2/17 4/30/17-7/31/17 $670,117
95558 IR77-7.56-12.39 Between Stone Creek and Newcomerstown Resurfacing, Four-Lane 1/19/17 5/1/17-10/31/17 $1,890,317
96790 SR416-4.61-9.85 From Tuscarawas ’ north corp. limit to New Philadelphia’s
south corp. limit
Preventive Maintenance,
Microsurfacing 3/2/17 5/1/17-9/30/17 $677,865
91567 SR93-3.33 0.87 miles north of SR 39 at Sugarcreek Bridge Replacement 5/11/17 6/15/17-8/31/17 $381,878
97262 SR800-8.57 In Dennison, just north of Center St. Slide Repair 4/27/17 7/1/17-9/30/17 $353,097
103650 SR416-9.01 1.8 miles south of US 250 and just south of 416 Sand & Gravel Bridge Repair 5/25/17 7/1/17-10/31/17 $200,937
87320 SR212-1.07-5.11
SR212-9.49-18.23
From the Stark Co. line to Hess Mill Rd. north of Zoar
From SR 800 to the Carroll Co. line Resurfacing, Two-Lane 6/8/17 7/1/17-10/31/17 $2,644,777
95541
SR342-0.00-0.40
HAS-SR342-0.00-4.87
HAS-SR800-0.51-3.25
From SR 258 to the Harrison Co. line From
West Chester to SR 800 at Freeport
From Freeport to US 22 near Smyrna
Resurfacing, Two-Lane 5/11/17 6/1/17-9/30/17 $2,076,306
Local Projects
96501 Dover Signals, Phase 1 Wooster Ave. from Ohio Ave. to Iron Ave.; Iron Ave. from
Wooster Ave. to Boat St. Safety (Signals) 2/9/16 5/2/16-4/14/17 $1,793,016
97063 Dennison Depot,
Phase 8 Dennison Depot Museum, 400 Center St.
Enhancement
(Historic Preservation) TBD TBD $150,000
101982 CR21-8.75-16.01 From Stone Creek to New Philadelphia Resurfacing, Two Lane 6/22/17 8/17/17-11/1/17 $2,656,100
13 Total Projects worth nearly $17M
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
TUSCARAWAS COUNTY 19
Resurfacing
Reactive/Preventive Maintenance
Bridge/Culvert
Continued Construction from 2013
New Construction in 2014
Sale in 2014; Construction in 2015
TU
SC
AR
AW
AS
CO
UN
TY
D IS T R IC T 11 2017 CONS T R U C T ION PR O GR AM
DISTRICT MAINTENANCE PROJECTS 20
District Maintenance Projects (Not Mapped)
Ref. PID Number Project Name Work Type
Sale Date
Estimated Start & End Dates
Estimated Investment
102277 D11 SP FY 2017(B) Spot Paving
(Various locations to be determined) 6/16/16 8/15/16-6/30/17 $940,925
94502 D11 PM FY 2017B Pavement Markings 6/16/16 8/15/16-6/30/18 $1,543,210
94504 D11 LG FY 2017 Lighting 6/16/16 8/1/16-7/31/17 $365,150
100611 D11 DS FY 2016 Deck Sealing/Bridge Maintenance 6/16/16 4/15/17-7/31/17 $433,620.18
94500 D11 PM FY 2017A Pavement Markings 9/22/16 4/1/17-11/15/17 $294,654.05
99547 D11 HS FY 2017B Herbicidal Spraying
(Carroll, Columbiana, Holmes & Tuscarawas) 1/19/17 4/1/17-9/30/17 $88,343
94503 D11 RPM FY 2017 Raised Pavement Markers 1/19/17 4/1/17-5/15/18 $145,737
99545 D11 HS FY 2017A Herbicidal Spraying
(Belmont, Harrison & Jefferson) 3/2/17 5/1/17-9/30/17 $130,000
100495 D11 CS FY 2017 Crack Sealing 3/30/17 5/1/17-10/31/17 $304,950
100616 D11 Various Deck Sealing/Bridge Maintenance 3/30/17 5/1/17-9/30/17 $500,000
104171 D11 SP FY 2017(C) Spot Paving
(Various locations to be determined) 4/13/17 5/1/17-9/30/17 $2,199,757
98464 D11 GR FY 2017 Guardrail Repair/Reconstruction 4/13/17 6/5/17-4/1/18 $1,524,368
98107 D11 SP FY 2018 Spot Paving
(Various locations to be determined) 6/8/17 8/1/17-10/31/17 $1,000,000
96877 D11 LG FY 2018 Lighting 6/8/17 8/1/17-7/31/18 $350,000
14 Total Projects worth nearly $10M
To provide easy conveyance of people
and goods from place to place, we will:
Take care of what we have;
Make our system work better;
Improve safety;
Enhance capacity
A long-term, reliable, professional and
highly productive organization
O U R M I S S I O N
O U R V I S I O N
For more information, contact:
District 11 Deputy Director Lloyd MacAdam, P.E., P.S., CPM at (330) 308-3950,
District 11 Construction Administrator Nick Susich, P.E. at (330) 308-6931, or
District 11 Public Information Officer Becky Giauque at (330) 308-3949.
Like us on Facebook: facebook.com/ODOTEasternOhio
Follow us on Twitter: twitter.com/ODOT_EasternOH
Statewide Traffic Information: www.Ohgo.com
For general information, call (330) 339-6633 or visit District 11’s Web site at: www.Transportation.Ohio.Gov/Dist11