+ All Categories
Home > Documents > D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and...

D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and...

Date post: 16-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
155
D4.3 Final results of the tests with lessons learnt, conclusions and recommendations Grant agreement no.: 325075 Pilot type A co-funded by the European Union under the Competitiveness and Innovation Programme ICT Policy Support Programme DG Communications Networks, Content and Technology Version number: 1.0 Main author: NavCert Dissemination level: PU Lead contractor: Due date: 31.12.2014 Delivery date: 17.12.2014 Delivery date updated document
Transcript
Page 1: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results of the tests with lessons learnt, conclusions and

recommendations

Grant agreement no.: 325075

Pilot type A co-funded by the European Union under the Competitiveness and Innovation Programme

ICT Policy Support Programme

DG Communications Networks, Content and Technology

Version number: 1.0

Main author: NavCert

Dissemination level: PU

Lead contractor:

Due date: 31.12.2014

Delivery date: 17.12.2014

Delivery date updated document

Page 2: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

Page left intentionally blank

Page 3: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

CONTROL SHEET

Version history

Version Date Main author Summary of changes

0.1 2014-02-18 Monika Hentschinski template

0.2 2014-09-08 to

2014-11-13 Monika Stapelfeld

including input pilot sites

0.3 2014-11-17 Martin Grzebellus internal review

0.4 2014-11-20 to

2014-11-25 Ana Paul peer review

0.5 2014-11-20 to

2014-11-25 Kate Yeadon language review

0.6 2014-11-25 to

2014-12-02 Martin Grzebellus, Monika

Stapelfeld integrating updates

0.7 2014-12-02 to

2014-12-05 pilot sites review, flavouring

1.0 21-12-2014 Andy Rooke Authorised

Name Date

Prepared Martin Grzebellus, Monika Stapelfeld 2014-11-17

Reviewed Ana Paul, Kate Yeadon 2014-11-25

Authorized Andy Rooke 21-12-2014

Circulation

Recipient Date of submission

Project partners 21-12-2014

European Commission 21-12-2014

Page 4: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 4 v 1.0

TABLE OF CONTENTS

Control sheet ......................................................................................... 3

Table of contents .................................................................................. 4

Figures ................................................................................................... 7

Tables .................................................................................................. 11

1 Management Summary ................................................................. 13

2 Terms and Abbreviations .............................................................. 16

3 Introduction ................................................................................... 18

3.1 Purpose of Document .................................................................................. 18

3.2 Intended audience of this document ............................................................ 18

3.3 HeERO 2 Contractual References ............................................................... 18

4 Overall Validation .......................................................................... 20

4.1 Validation Procedure ................................................................................... 21

4.2 Timings ........................................................................................................ 22

4.3 Results for KPIs ........................................................................................... 23

4.4 Results of Questionnaires ........................................................................... 26

4.4.1 Powered Two-Wheeled ...................................................................................26

4.4.2 Dangerous Goods Vehicles .............................................................................28

4.5 Recommendations on Performance Requirements ..................................... 31

4.6 General Recommendations ......................................................................... 33

4.7 Conclusions ................................................................................................. 33

5 Results of Pilot Sites ..................................................................... 35

5.1 Belgium ....................................................................................................... 35

5.1.1 General ...........................................................................................................35

5.1.2 Recommended KPIs .......................................................................................39

5.1.3 Evaluation results ............................................................................................40

5.1.4 Interoperability tests ........................................................................................42

5.1.5 Recommendations ..........................................................................................43

Page 5: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 5 v 1.0

5.1.6 Conclusions ....................................................................................................43

5.2 Bulgaria ....................................................................................................... 43

5.2.1 General ...........................................................................................................43

5.2.2 Recommended KPIs .......................................................................................44

5.2.3 Evaluation results ............................................................................................44

5.2.4 Interoperability tests ........................................................................................54

5.2.5 Recommendations ..........................................................................................54

5.2.6 Conclusion ......................................................................................................55

5.3 Denmark ...................................................................................................... 55

5.3.1 General ...........................................................................................................55

5.3.2 Recommended KPIs .......................................................................................56

5.3.3 Evaluation results ............................................................................................56

5.3.4 Recommendations ..........................................................................................70

5.3.5 Conclusions ....................................................................................................71

5.4 Luxembourg ................................................................................................ 71

5.4.1 General ...........................................................................................................71

5.4.2 Recommended KPIs .......................................................................................71

5.4.3 Evaluation results ............................................................................................71

5.4.4 Interoperability tests ........................................................................................78

5.4.5 Recommendations ..........................................................................................79

5.4.6 Conclusion ......................................................................................................80

5.5 Spain ........................................................................................................... 80

5.5.1 General ...........................................................................................................80

5.5.2 Recommended KPIs .......................................................................................85

5.5.3 Evaluation results ............................................................................................86

5.5.4 Interoperability tests ...................................................................................... 103

5.5.5 Recommendations ........................................................................................ 108

5.5.6 Conclusions .................................................................................................. 108

5.6 Turkey ....................................................................................................... 110

5.6.1 General ......................................................................................................... 110

5.6.2 Recommended KPIs ..................................................................................... 110

5.6.3 Evaluation results .......................................................................................... 111

Page 6: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 6 v 1.0

5.6.4 Interoperability tests ...................................................................................... 117

5.6.5 Recommendations ........................................................................................ 117

5.6.6 Conclusions .................................................................................................. 117

6 References ................................................................................... 118

ANNEX 1: eCall for P2W - User Acceptance Report ....................... 119

Abstract ............................................................................................................... 119

ANNEX 2: List of all evaluated KPIs................................................. 154

Page 7: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 7 v 1.0

FIGURES

FIGURE 1: MEASUREMENT OF PLANNED KPIS ............................................................... 21

FIGURE 2: TIME INTERVALS DURING ECALL .................................................................... 23

FIGURE 3: RESULTS FOR KPI5: MSD PRESENTATION TIME ............................................ 24

FIGURE 4: RESULTS FOR KPI7: VOICE CHANNEL BLOCKING TIME .................................... 24

FIGURE 5: SINGLE TEST CASES FOR KPI7: VOICE CHANNEL BLOCKING TIME .................... 25

FIGURE 6: RESULTS FOR KPI8: TIME FOR CALL ESTABLISHMENT .................................... 25

FIGURE 7: SERVER ARCHITECTURE (BE) ....................................................................... 35

FIGURE 8: GRAPHICAL USER INTERFACE OF ECALL SERVER (BE) ..................................... 36

FIGURE 9: SNAPSHOT OF THE GUI ON PSAP (BE) ......................................................... 37

FIGURE 10: IVS BY NXP/S1NN (BE) ........................................................................... 37

FIGURE 11: IVS BY GENEVA MICROSYSTEMS (BE) ........................................................ 38

FIGURE 12 : TIME SERIES KPI 7 AND 8 (BE) .................................................................. 40

FIGURE 13: DISTRIBUTION KPI 7A (BE) ........................................................................ 41

FIGURE 14: DISTRIBUTION KPI 8 (BE) .......................................................................... 42

FIGURE 15: TESTING PROCESS (BG) ............................................................................. 44

FIGURE 16: KPI_007 TIME SERIES TUS IVS (BG) ......................................................... 51

FIGURE 17: KPI_007 TIME SERIES ICOM IVS (BG) ...................................................... 51

FIGURE 18: KPI_008 TIME SERIES ICOM IVS (BG) ...................................................... 52

FIGURE 19: DISTRIBUTION OF KPI_007 FOR TUS (BG) .................................................. 53

FIGURE 20: DISTRIBUTION OF KPI_007 FOR ICOM (BG) ............................................... 53

FIGURE 21: DISTRIBUTION OF KPI_008 FOR ICOM (BG) ............................................... 54

FIGURE 22: LOCATION OF PILOT TEST CALLS, AS INDICATED IN THE IVS-UNIT (DK) ........... 56

FIGURE 23 – AN IVS-UNIT INSTALLED IN A TEST VEHICLE ................................................ 57

FIGURE 24: THE IVS-UNITS USED FOR TESTING (DK) ..................................................... 58

FIGURE 25 – GEOGRAPHICAL DISTRIBUTION OF SUCCESS RATE OF CALLS MADE DURING

PHASE ONE PILOT TEST, WITH THE SATELLITE POSITION REGISTERED IN THE IVS-UNITS (DK)

................................................................................................................................. 61

Page 8: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 8 v 1.0

FIGURE 26: TIME SERIES FOR SUCCESSFUL DURING FIRST PHASE. (DK) ........................... 63

FIGURE 27 – GEOGRAPHICAL DISTRIBUTION OF CALLS MADE DURING PHASE TWO, WITH THE

SATELLITE POSITION REGISTERED IN THE IVS-UNITS (DK) ............................................... 65

FIGURE 28: PHASE TWO CALLS (DK) ............................................................................ 67

FIGURE 29: PHASE TWO CALLS WITH FJT M2M SIM CARD (DK) ..................................... 67

FIGURE 30: PHASE TWO CALLS WITH FJT NORMAL SIM CARD (DK) ................................. 68

FIGURE 31: PHASE TWO CALLS WITH FJT NORMAL SIM CARD (DK) ................................. 68

FIGURE 32: PHASE TWO CALLS WITH GMV NORMAL SIM CARD (DK) ............................... 69

FIGURE 33: STATISTICAL DATA PHASE 2 (DK) ................................................................ 69

FIGURE 34: GEOGRAPHICAL DISTRIBUTION OF FAILED CALLS FOR PHASE 1 AND 2 (DK) ...... 70

FIGURE 35: KPI5 FUJITSU IVS (LU) .......................................................................... 75

FIGURE 36: KPI5 FUJITSU IVS (LU) .......................................................................... 75

FIGURE 37: KPI5 FICOSA 2 (LU) ............................................................................... 76

FIGURE 38: MSD PRESENTATION TIME (LU) .................................................................. 77

FIGURE 39: MSD PRESENTATION TIME (LU) .................................................................. 77

FIGURE 40: VOICE CHANNEL BLOCKING TIME (LU).......................................................... 78

FIGURE 41: CALL CHAIN FROM THE IVS TO FINAL PSAP ................................................. 80

FIGURE 42: GALICIAN SCENARIOS (ES) ......................................................................... 82

FIGURE 43: IVS CTAG IN THE REGIONAL CROSS BORDER .............................................. 83

FIGURE 44: P2W TEST ARCHITECTURE ......................................................................... 84

FIGURE 45: P2W WITH IVS INSTALLED ......................................................................... 84

FIGURE 46: TIME SERIES DIAGRAM OF IVS CTAG - KPI_05 (ES) ................................... 92

FIGURE 47: HISTOGRAM OF IVS CTAG - KPI_05 (ES) .................................................. 92

FIGURE 48: TIME SERIES DIAGRAM OF IVS CTAG - KPI_07A (ES) ................................. 93

FIGURE 49: HISTOGRAM OF IVS CTAG - KPI_07A (ES) ................................................ 93

FIGURE 50: TIME SERIES DIAGRAM OF IVS CTAG - KPI_07B (ES) ................................. 94

FIGURE 51: HISTOGRAM OF IVS CTAG - KPI_07B (ES) ................................................ 94

FIGURE 52: TIME SERIES DIAGRAM OF IVS CTAG - KPI_08 (ES) ................................... 95

FIGURE 53: HISTOGRAM OF IVS CTAG - KPI_08 (ES) .................................................. 95

Page 9: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 9 v 1.0

FIGURE 54: TIME SERIES DIAGRAM OF IVS CTAG - KPI_23 (ES) ................................... 96

FIGURE 55: HISTOGRAM OF IVS CTAG - KPI_23 (ES) .................................................. 96

FIGURE 56: TIMES SERIES DIAGRAM OF IVS CTAG - KPI_29 (ES) ................................. 97

FIGURE 57: HISTOGRAM OF IVS CTAG - KPI_29 (ES) .................................................. 97

FIGURE 58: KPI5 FOR GMV IVS (ES) .......................................................................... 98

FIGURE 59: KPI7A FOR GMV IVS (ES) ........................................................................ 98

FIGURE 60: KPI7B FOR GMV IVS (ES) ........................................................................ 99

FIGURE 61: KPI8 FOR GMV IVS (ES) .......................................................................... 99

FIGURE 62: MSD PRESENTATION TIME (ES) ................................................................ 100

FIGURE 63: VOICE CHANNEL BLOCKING TIME (ES) ....................................................... 100

FIGURE 64: VOICE CHANNEL BLOCKING TIME (ES) ....................................................... 101

FIGURE 65: MSD PRESENTATION TIME (ES) ................................................................ 101

FIGURE 66: TESTFEST#3 ........................................................................................ 104

FIGURE 67: SUMMARY OF CTAG RESULTS IN 2013 ..................................................... 105

FIGURE 68: SUMMARY OF ALL PARTICIPANTS’ RESULTS ................................................ 107

FIGURE 69: GMV’S IVS TEST RESULTS SUMMARY ....................................................... 107

FIGURE 70: TIME SERIES PLOT OF KPI_05 (TR) .......................................................... 114

FIGURE 71: TIME SERIES PLOT OF KPI_07A (TR) ........................................................ 115

FIGURE 72: THE FREQUENCY DISTRIBUTION PLOT OF KPI_05 (TR) ............................... 116

FIGURE 73: THE FREQUENCY DISTRIBUTION PLOT OF KPI_07A (TR) ............................. 116

FIGURE 74: GENDER OF THE RESPONDENTS ................................................................ 121

FIGURE 75: PYRAMID: AGES AND GENDER ................................................................... 121

FIGURE 76: YEARS OF EXPERIENCE DRIVING A MOTORCYCLE, BY GENDER ...................... 122

FIGURE 77: FREQUENCY OF USE ................................................................................ 123

FIGURE 78: FREQUENCY OF USE BY TYPE OF MOTORCYCLE .......................................... 123

FIGURE 79: AVERAGE NUMBER OF KM. DRIVEN PER YEAR ............................................. 124

FIGURE 80: ACCIDENT STATISTICS OF RESPONDENTS ................................................... 124

FIGURE 81: ACCIDENT STATISTICS OF RESPONDENTS BY AGE GROUP ............................ 125

Page 10: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 10 v 1.0

FIGURE 82: YEARS OF EXPERIENCE OF MOTORCYCLE DRIVERS THAT HAVE HAD AT LEAST ONE

ACCIDENT ................................................................................................................. 126

FIGURE 83: DID YOU CALL THE EMERGENCY SERVICES (YOURSELF)? ............................. 126

FIGURE 84: HOW MUCH TIME ELAPSED UNTIL THE EMERGENCY SERVICES ARRIVED? ...... 127

FIGURE 85: DISTRIBUTION OF ACCIDENTS BETWEEN URBAN AND INTERURBAN AREA ........ 127

FIGURE 86: AVERAGE TIME OF ARRIVAL OF THE EMERGENCY SERVICES TO THE ACCIDENT

SPOT DEPENDING ON THE TYPE OF AREA (URBAN / INTERURBAN) ................................... 128

FIGURE 87: ARCHITECTURE OF THE ECALL SERVICE FOR MOTORCYCLES ....................... 130

FIGURE 88: LEVEL OF ACCEPTANCE OF THE ECALL SERVICE FOR MOTORCYCLES ............ 131

FIGURE 89: RELEVANCE OF THE INFORMATION PROVIDED BY THE HELMET IN CASE OF

ACCIDENT ................................................................................................................. 132

FIGURE 90: WILLINGNESS TO PURCHASE A NEW HELMET COMPATIBLE WITH ECALL ........ 133

FIGURE 91: PRICE SENSITIVITY (FOR THE PRICE INCREASE OF AN ECALL COMPATIBLE

HELMET) ................................................................................................................... 133

FIGURE 92: IMPORTANCE RESPONDENTS GIVE TO DIFFERENT TYPES OF INFORMATION THAT

THE ECALL SERVICE FOR MOTORCYCLES COULD GENERATE .......................................... 135

FIGURE 93: SENSITIVITY TO DATA PRIVACY OF THE RESPONDENTS ................................ 141

FIGURE 94 : PRICE SENSITIVITY FOR AN AFTERMARKET ECALL SYSTEMECALL SERVICE ... 142

Page 11: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 11 v 1.0

TABLES

TABLE 1: STATISTICAL PARAMETERS DEFINITION ........................................................... 22

TABLE 2: RECOMMENDED VALUES FOR KPIS 05 TO 08 ................................................... 32

TABLE 3: MEASURED KPIS (BE) ................................................................................... 39

TABLE 4 : RESULTS KPIS (BE) ..................................................................................... 40

TABLE 5 : STATISTICS KPIS 7 AND 8 (BE) ...................................................................... 41

TABLE 6: EVENTS AND PARAMETERS RECORDED BY DIFFERENT IVS DEVICES (BG) .......... 46

TABLE 7: SUMMARY OF RESULTS (BG) .......................................................................... 49

TABLE 8: STATISTICAL PARAMETER (BG) ....................................................................... 52

TABLE 9: KPI 2B, 3, 4, 6 AND 7A WITH FOREIGN PSAPS (BG) ........................................ 54

TABLE 10 – RESULTS DERIVED FROM PHASE ONE PILOT TEST (DK) ................................. 61

TABLE 11: STATISTICS OF MANUAL INITIATED CALLS FOR SUCCESSFUL CALLS DURING FIRST

PHASE (DK) ................................................................................................................ 63

TABLE 12 – RESULTS DERIVED FROM PHASE TWO PILOT TEST (DK) ................................. 65

TABLE 13: SUMMARY OF RESULTS (LU) ........................................................................ 74

TABLE 14: STATISTICS OF MANUAL INITIATED CALLS (LU) ............................................... 76

TABLE 15: KPI 1B WITH OWN IVS AND FOREIGN PSAPS (LU) ........................................ 78

TABLE 16: KPI 2B, 3, 4 AND 6 WITH FOREIGN PSAPS (LU) ............................................ 79

TABLE 17: KPIS MEASURED DURING PHASE 1 (ES) ........................................................ 86

TABLE 18: SUMMARY OF CALCULATED KPIS DURING PHASE 1 (ES) ................................ 87

TABLE 19: SUMMARY OF CALCULATED KPIS DURING PHASE 2 (ES) ................................ 88

TABLE 20: SUMMARY OF GALICIAN TESTS ..................................................................... 89

TABLE 21: SUMMARY OF GALICIAN KPIS ....................................................................... 90

TABLE 22: STATICS OF INITIATED ECALLS (ES) ............................................................ 102

TABLE 23: STATISTICS OF INITIATED CALLS (ES) .......................................................... 103

TABLE 24: INTEROPERABILITY TESTS PERFORMED BETWEEN CTAG AND EUROPEAN PSAPS

IN 2014 .................................................................................................................... 106

TABLE 25 CTAG’S IVS MANDATORY TEST RESULTS IN 2014 ........................................ 106

Page 12: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 12 v 1.0

TABLE 26 : RECOMMENDED KPIS TESTED IN TURKEY ................................................... 111

TABLE 27: THE RESULTS OF OUR KPI EVALUATION (TR) ............................................... 112

TABLE 28: SUMMARY OF STATISTICAL EVALUATION RESULTS(TR) .................................. 115

Page 13: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 13 v 1.0

1 Management Summary

This document presents the test results for the HeERO 2 project from all pilot sites in a

consistent manner to allow comparison between the results of the pilot sites involved.

Results of HeERO have been documented in detail already and therefore here only results of

HeERO 2 are presented. As HeERO 2 incorporates recommendations of HeERO 1, the

overall evaluation of the HeERO projects can be deducted with the recommendations and

conclusions presented in this document. Details of the result for HeERO 1 are documented in

the already published document HeERO_WP4_DEL_D4 5_results_v1.0.pdf.

Well defined KPIs have been agreed to measure all aspects of the eCall communication. The

consolidated evaluation is based on results of the pilot sites (Belgium, Bulgaria, Denmark,

Luxemburg, Spain and Turkey). Each pilot site provided statistical evaluations of the

measured KPIs with derived recommendations and conclusions. The quantitative analysis

was complemented by a qualitative assessment of P2W and transport of dangerous goods.

This document is structured into three parts: First a summary is given of the achievements

for HeERO 1and HeERO 2. Then the consolidated results of all pilot sites are presented and

in the end the details of the results per pilot site are described. The qualitative analysis with

questionnaires for P2W is attached as annex.

All pilot sites proposed in the preparation phase individual KPIs, so that in total more than 30

KPIs have been defined. Out of this list, a subset of KPIs has been recommended which

should be tested by all pilot sites. The most important KPIs (KPI 1 to KPI 8) were tested from

almost all pilot sites. All recommended KPIs were tested by at least four pilot sites. From a

process point of view, the most important KPI is KPI 018 (time to activate rescue forces).

This KPI measures the overall objective for introduction of eCall, the reduction of time until

rescue forces arrive at incident location. However this KPI cannot be realistically tested in

test scenarios and compared to actual data. Thus this KPI was not measured at all.

The next important KPIs are KPI 005 (duration until MSD is presented in PSAP) and KPI

007a (voice channel blocking time). ECall provides additional information compared to 112

calls and this information is transmitted in the MSD. These KPIs are measurable and

comparable and in the scope of the project as well as the standards. During the transmission

time of the MSD the passenger in the vehicle cannot communicate with the call handler. As

the vehicle occupants do not know the technical aspects and reasons for the “dead line” of

the call, every second of silence is undesirable. Passengers need to leave the car quickly, so

voice contact has to be established as swiftly as possible. The KPIs 005 and 007a have been

measured and evaluated by nearly all pilot sites. The KPIs measured by the majority of pilot

sites are the various success rates KPI 002a (success rate of completed eCalls using 112),

Page 14: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 14 v 1.0

KPI 002b (success rate of completed eCalls using long number), KPI 003 (success rate of

received MSDs), KPI 004 (success rate of correct MSDs) and KPI 006 (success rate of

established voice transmissions). Unfortunately not all pilot sites were able to evaluate 112

call set up and initiated eCalls only via a long number. The importance for the 112 call set up

can be derived from KPI 02, as the highest success rate for call set up (KPI 02) is for 112 call

set up, as mobile networks are configured to give priority to 112 calls in case of network

congestion. The failure to test this KPI is solely due to mobile network operators in some pilot

sites still failing upgrading their network for the proper handling of the eCall flag.

The KPIs didn’t improve from HeERO 1 to HeERO 2 as expected. The modifications in the

eCall standards based on recommendations were already available in HeERO 1 phase 2

leading to an improved performance. In HeERO 2 quite some suppliers started with their

development from scratch, so that the IVSs still being on a prototypical level. The success

rates for successful MSD transmission (KPI 03 and 04) are very good. The average for KPI

005 (time until the MSD is presented in PSAP) is now 12.9 seconds compared to HeERO 1

14.1 seconds. The average of the voice channel blocking time (KPI 07) is now 9.2 seconds

compared to HeERO 1 7.9 seconds, but with more variability. This indicates that the

manufacturers were struggling with overall functionality and still far away from a mass

production with successful performance optimisation.

By implementing best practise and optimization of all components values of 4s to 6s for KPI

05 and KPI 07 are achievable.

In that case, the additional delay caused by the transmission of the MSD is in the expected

range of about 4s.

Therefore following recommendations are given:

Vehicle manufacturers should implement best practise to minimize voice channel

blocking time

The heading information does still not provide in all implementations the direction of

travel but sometimes only the direction of the vehicle when the eCall was triggered.

This is not in conformance with the underlying standard CEN 17025.

When an IVS is triggered to retransmit the MSD, some implementations provide a

clone of the already transmitted MSD; others provide a new updated content of the

MSD at the moment of request for retransmission. As the MSD with an update of the

position provides valuable information to the PSAP especially to better identify false

alarms, in case of a retransmission of the MSD, the MSD content should always be

updated

Page 15: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 15 v 1.0

Due to limited GNSS coverage e. g. in tunnels, a GNSS position might not be

available in case of an eCall triggering. Therefore vehicle manufacturers should try to

use additional information from accelerometer, odometer, gyros etc. to determine the

position of the vehicle if feasible.

The intent of the HeERO pilot sites has been mainly to evaluate if the requested performance

of the eCall service can be met with a deployment of the approved European eCall standards

in the existing public mobile telecommunications networks and within the existing 112

system. This means that the testing has had a strong focus on the eCall standards and

capturing the key performance indicators, the KPIs. Other issues, such as the response time

of the rescue services and ambulances, use of EUCARIS and use of VIN in the operational

rescue chain, as well as non-operational issues, like legal liability, privacy issues, periodic

time inspections, change of a car ownership, etc. is not included in the work of the HeERO

pilot sites.

The outcome of the tests performed and reported in this document confirm that the pan-

European eCall is working according to expectations however there is still room for

improvement in the implementation by the suppliers.

Page 16: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 16 v 1.0

2 Terms and Abbreviations

Term Definition

3GPP Third Generation Partnership Project

AT Attention Command

CAN Controller Area Network

CEN Comité Européen de Normalisation

CIP Competitiveness and Innovation Programme

CRF Centro Ricerche Fiat

DoW Description of Work

EC European Commission

ECR Emergency Control Room

EGNOS European Geostationary Navigation Overlay System

ENT Ericsson Nikola Tesla

ETSI European Telecommunication Standards Institute

EUCARIS European Car and Driving License Information System

ESO European Standards Organization

GDOP Geometric dilution of precision

GIS Geographic Information System

GLONASS

Globalnaja Nawigazionnaja SputnikowajaNavigazionnaja Sputnikovaja

Sistema

GNSS Global Navigation Satellite System

GPS Global Positioning System

GPRS General Packet Radio System

GSM Global System of Mobile telecommunications

GSMA GSM Association

HDOP Horizontal Dilution Of Precision

Page 17: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 17 v 1.0

HTTP Hypertext Transfer Protocol

IMSI International Mobile Subscriber Identity

ISO International Standardization Organization

ITS Intelligent Transport Systems

IVS In-Vehicle System

KPI Key Performance Indicator

MNO Mobile Network Operator

MSC Mobile Switching Centre

MSD Minimum Set of Data

MSISDN Mobile Subscriber Integrated Services Digital Network Number

NIST National Institute of Standards and Technology

NMEA National Marine Electronics Association

PLMN

PND

Public Land Mobile Network

Personal Navigation Device

PSAP Public Safety Answering Point

RTTI Real-time traffic and travel information

SBAS Satellite Based Augmentation System

SDR Software Defined Radio

SIM Subscriber Identity Module

SOP Standard Operating Procedure

TIM Telecom Italia Mobile

TMC Traffic Management Centre

UMTS Universal Mobile Telecommunication System

USB Universal Serial Bus

UTC Universal Time Coordinated

VAS Value Added Services

VIN Vehicle Identification Number

Page 18: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 18 v 1.0

3 Introduction

3.1 Purpose of Document

The purpose of this document is to present the test results from all pilot sites in a

comprehensive and consistent manner that gives the provision of conclusions and

recommendations as a result of the HeERO projects. The overall evaluation is based on the

results from the pilot sites. Each pilot site was asked to provide statistical evaluations of the

measured KPIs, recommendations and conclusions.

3.2 Intended audience of this document

This document is aimed at the following audiences with their respective objectives:

European Commission: for information

Member states: for information

Stakeholders: for information

3.3 HeERO 2 Contractual References

HeERO 2 is a Pilot type A of the ICT Policy Support Programme (ICT PSP), Competitiveness

and Innovation Framework Programme (CIP). It stands for Harmonised eCall European Pilot.

The Grant Agreement number is 325075 and project duration is 24 months, effective from 01

January 2013 until 31 December 2014. It is a contract with the European Commission, DG

CONNECT.

The principal EC Project Officer is:

Aude Zimmermann

EUROPEAN COMMISSION

DG CONNECT

Office: BU 31 – 6/35

B - 1049 Brussels

Tel: +32 296 2188

E-mail: [email protected]

One other Project Officer will follow the HeERO project:

Dimitrios AXIOTIS

[email protected]

Page 19: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 19 v 1.0

Address to which all deliverables and reports have to be sent:

Aude Zimmermann

EUROPEAN COMMISSION

DG CONNECT

BU 31 – 6/35

B - 1049 Brussels

Tel: +32 296 2188

By mail: [email protected]

Any communication or request concerning the grant agreement shall identify the grant

agreement number, the nature and details of the request or communication and be submitted

to the following addresses:

European Commission

Communications Networks, Content and Technology

B-1049 Brussels

Belgium

By electronic mail: [email protected]

Page 20: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 20 v 1.0

4 Overall Validation

The evaluation was performed according to the agreed test specification and methodology

(Deliverable 4.1). The definition of all KPIs in detail is also documented in this deliverable.

The figure below shows the KPIs tested by the pilot sites. The major KPIs were measured by

almost all of the pilot sites. In the lower part of the graph some deviation between planning

and realisation can be seen. Compared to HeERO1 the test phases were shorter and there

was less time to re-plan or re-adjust between the two test phases.

Page 21: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 21 v 1.0

Figure 1: Measurement of Planned KPIs

Tested as planned

Planned, not tested

Not planned, not tested

Tested additionally

4.1 Validation Procedure

The validation considered the following criteria:

LU BE BG ES DK TR

KPI_001a planned but not evaluatedplanned but not evaluatedevaluated as plannedevaluated as plannednot plannedplanned but not evaluated

KPI_001b evaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_002a planned but not evaluatedevaluated as plannedevaluated as plannedplanned but not evaluatedplanned but not evaluatedevaluated as planned

KPI_002b evaluated as plannedevaluatedevaluated as plannedevaluated as plannedevaluatedplanned but not evaluated

KPI_003 evaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_004 evaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_005 evaluated as plannedplanned but not evaluatedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_006 evaluated as plannedplanned but not evaluatedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_007a evaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_007b not plannedplanned but not evaluatedevaluated as plannedevaluated as plannedevaluatednot planned

KPI_008 not plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluatednot planned

KPI_009 evaluatednot plannedevaluated as plannedevaluated as plannedevaluatednot planned

KPI_010 not plannednot plannedevaluated as plannedevaluated as plannednot plannednot planned

KPI_011 not plannednot plannedevaluated as plannedevaluated as plannednot plannednot planned

KPI_012 not plannednot plannedevaluated as plannedevaluated as plannednot plannednot planned

KPI_013 evaluated as plannednot plannedevaluated as plannedevaluated as plannedevaluated as plannedevaluated as planned

KPI_014 not plannednot plannedevaluated as plannedevaluated as plannednot plannednot planned

KPI_015 planned but not evaluatednot plannedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_016 planned but not evaluatednot plannedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_017 not plannedplanned but not evaluatedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_018 not plannednot plannedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_019 not plannednot plannedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_020 not plannednot plannedplanned but not evaluatedevaluated as plannednot plannednot planned

KPI_021 not plannedplanned but not evaluatedevaluated as plannedplanned but not evaluatedevaluatednot planned

KPI_022 not plannedplanned but not evaluatedevaluated as plannedplanned but not evaluatedevaluatednot planned

KPI_023 not plannednot plannedplanned but not evaluatedevaluated as plannednot plannednot planned

KPI_024 not plannedplanned but not evaluatedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_025 not plannedplanned but not evaluatedevaluated as plannedplanned but not evaluatednot plannednot planned

KPI_026 not plannednot plannedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_027 not plannednot plannedplanned but not evaluatedplanned but not evaluatednot plannednot planned

KPI_028 a planned but not evaluatedplanned but not evaluatedplanned but not evaluatedevaluated as plannedplanned but not evaluatednot planned

KPI_028 b planned but not evaluatednot plannedevaluated as plannedevaluated as plannedplanned but not evaluatednot planned

KPI_028 c not plannednot plannednot plannedevaluated as plannednot plannednot planned

KPI_29 not plannedplanned but not evaluatedplanned but not evaluatedevaluated as plannednot plannednot planned

KPI_30 planned but not evaluatednot plannednot plannednot plannednot plannednot planned

KPI_31 planned but not evaluatednot plannednot plannednot plannednot plannednot planned

Page 22: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 22 v 1.0

- Time series diagrams of the values of relevant KPIs

- Fundamental KPI statistical description for every time series (mean, median,

variance, standard deviation, skew, kurtosis and histogram with normal probability)

- Discussion

The procedures for the creation of the KPI time series diagrams, and the fundamental KPI

statistical description, are described in [2], and conducted in accordance to [1] and [3].

Statistical parameter Definition Comments

Time series diagram of KPI - Graphical representation of time series values v measurement time stamps

Mean x=

1

n∑i= 1

n

xi A numerical measure of the central location of the data values

Median The value at the middle when the data is sorted in ascending order

Variance s

2=

1

n− 1∑i= 1

n

( xi− x )2

A numerical measure of data values dispersion around the mean

Standard deviation σ=

s

√n

An observation variable proportional to the square root of its variance

Skewness γ1=μ3

μ2

3 /2 A measure of the symmetry of the data distribution

Kurtosis γ2=μ4

μ2

2− 3

A measure of the peakedness of the data distribution

Histogram with normal probability diagram

- A graphical representation of the frequency distribution of a KPI value

Table 1: Statistical Parameters Definition

4.2 Timings

Due to the fact that some of the defined KPIs are based on timing issues, timers were

defined already in HeERO 1 to allow a consistent measurement of KPIs in all pilot sites.

These are summarised in Figure 2 (provided by the Czech Pilot Site during HeERO 1)

overleaf.

Page 23: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 23 v 1.0

Figure 2: Time Intervals during eCall

4.3 Results for KPIs

In the following figures the values for the most important KPIs are shown as well as the test

cases from the HeERO1 pilot sites As the project time of HeERO1 was one year longer than

HeERO2, HeERO1 pilot sites had more time between the test phases and there was more

time to readjust the equipment.

As most of the pilot sites provided different test cases there are more columns than pilot sites

within the graphics. The test cases per pilot sites differ, either in time (phase 1 and phase 2

of testing),) or in the different PSAPs or IVSs used.

Page 24: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 24 v 1.0

Figure 3: Results for KPI5: MSD Presentation Time

The test cases from Romania, Greece (HeERO1) and from Turkey are notable in that they

are about 10 seconds longer than the results from the other pilot sites. If these three pilot

sites are excluded the mean value of the Duration until MSD is Presented in PSAP is 17.5

with a standard deviation of 7.9 seconds.

Figure 4: Results for KPI7: Voice Channel Blocking time

The voice channel blocking time does not differ as much as the MSD presentation time. The

minimal values are reached by the Bulgarian and Dutch test sites.

Page 25: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 25 v 1.0

Figure 5: single test cases for KPI7: Voice Channel Blocking time

Five seconds seems to be a plausible optimal minimum to be reached for a full scale

deployment across Europe.

At the moment a mean value of 9.2 seconds with a standard deviation of 2.8 seconds is

reached, giving much room for improvement.

Figure 6: Results for KPI8: time for Call Establishment

The time for call establishment differs greatly between the individual implementations. There

is unexpectedly no differentiation between eCalls with long numbers and with TS12 call set

up though in the dormant implementation the registration in the network takes place prior to

the call set up phase.

Page 26: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 26 v 1.0

4.4 Results of Questionnaires

Questionnaires were used to complement the quantitative analysis by a qualitative

assessment of special aspects. These questionnaires are designed to help to identify issues,

concerns and areas for improvement for stakeholders. These questionnaires have been

developed for two areas: Powered Two-Wheeled (P2W) and Dangerous Goods transport.

The evaluation of the questionnaires was done by the pilot site’s representative for the

specific scopes: Spain for P2W and Luxembourg for Dangerous Goods Vehicles.

It was planned to distribute the questionnaires in all pilot sites but this failed in most pilot

sites (except Bulgaria) because of the short time allowed and the fact that stakeholders were

missing who were willing to accept responsibility for this.

Spain received more than 600 answers to their questionnaire and created an excellent report

which is attached in the Annex of this document (eCall for P2W - User Acceptance Report).

The conclusions of this report are summarised in the following chapter.

The results of the Dangerous Goods questionnaire are summarised by the Luxembourg pilot

site in the subsequent chapter.

4.4.1 Powered Two-Wheeled

The user acceptance study conducted by RACC draws some interesting conclusions:

- On the sample of surveyed motorcycle drivers: one in three respondents has suffered an

accident that required the emergency services to intervene. The results don’t provide a

statistically relevant significance between the experience or age of the motorists and the

accidents. More than half of the respondents who has experienced an accident didn’t alert

the emergency services. Not surprisingly the average arrival time of the emergency services

at the accident site is significantly higher in inter-urban areas than urban areas. However, in

both cases it was clear that the arrival time at the accident site could be clearly improved, for

example with the help of an automatic alert to the closest PSAP.

- On the level of acceptance of the eCall service for motorcycles: a large majority of

respondents motorists would like to have eCall in their motorcycles, and in slightly smaller

proportions they would be willing to change their helmet to have the full functionality of the

system, although they consider that the estimated increase in price compared to the price of

Page 27: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 27 v 1.0

a conventional helmet is rather expensive. On the transition to a future eCall service for

motorcycles, users are receptive to paying for aftermarket devices to use eCall on their

motorcycles manufactured before the system becomes mandatory.

- On the expectations of users: surveyed motorists expect a high functionality from the eCall

service for motorcycles, and require some features that, conceptually, are outside the scope

of the eCall service. In this case, these features (sending of personal data and medical

history of the driver and passenger, etc.) might be implemented as value added services by

private service providers.

From the results of the first laboratory tests, as well as the expectations generated among

potential users, we can conclude that, although there are still many unresolved issues

(technical, standardisation, conceptual, privacy-related, ergonomics-related, costs, etc.), this

service will reduce fatalities, especially in interurban areas by providing a faster and more

efficient management of motorcycle accidents.

Page 28: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 28 v 1.0

4.4.2 Dangerous Goods Vehicles

The HeERO2 project has extended its evaluation of eCall support to dangerous goods

transports.

An important question is: How can the PSAPs get information about which dangerous goods

are loaded into a vehicle that has just reported an accident via the eCall service?

The standard eCall message transfers a Minimum Set of Data (MSD), containing

“emergency relevant” information. To embed information about the loads of commercial

vehicles, the data part of the Optional Additional Data can be used in two ways:

It could contain all the relevant data that needs to be transferred to the emergency

services

It could contain a reference to an external source with the relevant data e.g. a web

service providing detailed information about loaded dangerous goods or a link to a pdf

with the transport documentation.

To get a feeling how the users – in this case the logistic companies – think about the different

solutions for providing dangerous goods information with eCall we created a questionnaire

that asked the users for their opinion on which option is more relevant for them.

In addition to the general questions the questionnaire had three main sections:

1. Which information do you think it is important for the emergency services to know

when your truck is involved in an incident?

( 0 = ‘not important at all’ and 5 = ‘very important’)

0 1 2 3 4 5

What type of dangerous goods are loaded (UN-number)

The danger code of the goods

What quantity of dangerous goods are loaded

The current status of the dangerous good e.g. temperature

What damage has occurred to the containers

What damage has occurred to the truck

Who is the sender

Who is the receiver

What type of truck is involved

What speed was the truck going before the accident

How the DGs should be handled after the accident

2. Which information would you consider important to provide to the emergency services

in that your truck is involved in an incident:

( 0 = ‘not important at all’ and 5 = ‘very important’)

Page 29: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 29 v 1.0

0 1 2 3 4 5

What type of dangerous goods are loaded (UN-number)

The danger code of the goods

What quantity of dangerous goods are loaded

The current status of the dangerous good e.g. temperature

What damage has occurred to the containers

What damage has occurred to the truck

Who is the sender

Who is the receiver

What type of truck is involved

What speed was the truck going before the accident

3. In case that your truck is involved in an incident which way would you think is a

practical way to provide the information to the emergency services?:

( 0 = ‘not practical at all´ and 5 = ‘very practical’)

0 1 2 3 4 5

The information can be stored in a device in the truck and transferred to the emergency services in case of an accident

The information is stored in an electronic transport document e.g. a pdf file. In case of an accident, this document is provided to the emergency services.

The dangerous goods information is stored in your own database In case of an accident you would grant access to the needed information to the emergency service

The dangerous goods information is stored in the database of a centralised secured service. In case of an accident this service provides the needed information to the emergency service

The questionnaire was send to all HeERO2 partners for distribution to their logistic

companies and to 72 members of the Logistic Cluster Luxembourg. Unfortunately the

feedback was very low. We only received 3 answers from Luxembourg and 3 answers from

Bulgaria. However the results are still very interesting as they show a trend:

In order to maintain the anonymity of the persons who provided their feedback, we will

examine the average value of the answers. The responders were 3 large, 2 medium and 1

small logistic company from Bulgaria and from Luxembourg.

1. Which information do you think it is important for the emergency services to know

when your truck is involved in an incident?

( 0 = ‘not important at all’ and 5 = ‘very important’)

What type of dangerous goods are loaded (UN-number) 5.0

The danger code of the goods 4.2

What quantity of dangerous goods are loaded 4.0

The current status of the dangerous good e.g. temperature 3.3

Page 30: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 30 v 1.0

What damage has occurred to the containers 4.3

What damage has occurred to the truck 3.8

Who is the sender 3.0

Who is the receiver 2.3

What type of truck is involved 2.2

What speed was the truck going before the accident 1.5

How the DGs should be handled after the accident 4.8

2. Which information would you consider important to provide to the emergency services

in that your truck is involved in an incident:

( 0 = ‘not important at all’ and 5 = ‘very important’)

What type of dangerous goods are loaded (UN-number) 5.0

The danger code of the goods 4.2

What quantity of dangerous goods are loaded 4.0

The current status of the dangerous good e.g. temperature 3.5

What damage has occurred to the containers 4.3

What damage has occurred to the truck 3.8

Who is the sender 3.0

Who is the receiver 2.3

What type of truck is involved 2.3

What speed was the truck going before the accident 1.3

3. In case that your truck is involved in an incident which way would you think is a

practical way to provide the information to the emergency services?:

( 0 = ‘not practical at all´ and 5 = ‘very practical’)

The information can be stored in a device in the truck and transferred to the emergency services in case of an accident

2.3

The information is stored in an electronic transport document e.g. a pdf file. In case of an accident, this document is provided to the emergency services.

1.8

The dangerous goods information is stored in your own database In case of an accident you would grant access to the needed information to the emergency service

0.5

The dangerous goods information is stored in the database of a centralised secured service. In case of an accident this service provides the needed information to the emergency service

3.7

All responders agreed that it is very important that the emergency services know about and

receive information about the type of the dangerous goods (the UN-number) and the danger

code. Nearly all the responders think that the quantity of the dangerous goods loaded is

important or very important information to have and that it is important to know about the

damage of the container, while the damage to the truck does not seem to be important at all.

The responders also think that it is very important that the emergency services receive

information about the handling of the dangerous goods. The information about the sender

Page 31: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 31 v 1.0

and receiver of the dangerous goods seems to be less important. Not surprising nearly

nobody wants to see that the speed of the truck is provided to the emergency service.

The most interesting result concerned the question how the information about the dangerous

goods loaded should be provided:

Most of the responders see a central database as the best way for providing this information,

while responders from the large logistic companies say that a central database is not useful

for privacy reasons.

Nearly all responders agree that a link to an electronic transport document or access to a

database of the logistic company is not useful.

The storage of the dangerous goods in the on-board units is seen much differentiated:

3 responders coming from the bigger companies say it is very useful, the other 3 say it is

absolutely not useful.

Conclusion:

Even with the low number of responders the questionnaire shows some interesting results:

There is a common agreement about which information is needed by the emergency

services and should be provided to them: the type of the dangerous goods, the quantity and

if possible the damage of the container. The other information seems to be not as relevant.

Regarding the manner the information is provided to the emergency service, a central

database that secures full privacy of the data could be useful and could be recommended.

Storing the dangerous goods information in the IVS in the truck seems only is feasible for

large logistic companies that can afford the higher costs of the devices and the training of the

drivers.

4.5 Recommendations on Performance Requirements

The KPIs in WP4 were developed to measure the performance of the components and

processes. Within the HeERO projects the aim was to get values that measured “best

practise” and not to reach target values. Based on the results of the KPIs, in HeERO 1

recommendations for target values were developed and then updated. The KPIs were

defined only for those critical values which were measured during test drives on roads.

Many of these KPIs measure the critical spans of time, which are influenced by the

respective implementation of the IVS and/ or PSAP suppliers. Other KPIs measure the

Page 32: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 32 v 1.0

accuracy of the GNSS or the correctness of the heading information. This has to be

complemented by thresholds that are only measurable in a laboratory such as antenna gain,

acceleration or voice quality.

The following list provides a short definition of some of the KPIs together with the thresholds.

KPI05 describes the time duration from the initiation (automatically or manually) of an

eCall to the presentation of the MSD content in the PSAP.

KPI07 represents the time the transmission of MSD blocks the voice channel. The

time the voice channel is blocked can be defined as a time between a successful call

setup (“connected” is reported by the network) and the opening of voice

communication in both directions after the MSD has been transmitted successfully or

the MSD transmission has been abandoned (after time out) and the voice

communication has been opened on both sides in both directions.

KPI07a evaluates the duration of the voice channel blocking if an automatic

retransmission of the MSD is initiated by the IVS on request by the PSAP.

KPI08 refers to the observed time difference between the time of the eCall initiation

(automatic and manual) and the time of the eCall reception at PSAP.

[seconds] mean median std. dev. minimum maximum

KPI05 12.9 13.0 3.3 8.6 21.0

KPI07 9.2 9.4 2.8 3.0 13.0

KPI07a 8.7 9.3 3.8 1.9 17.0

KPI08 7.2 6.8 4.0 2.4 17.0

Table 2: recommended values for KPIs 05 to 08

For the following KPIs the thresholds are specified directly.

KPI05, the time for MSD presentation shall be around 8 seconds based on

KPI07 plus average call establishment time of 3.5 to 4 seconds for a normal

call, as such about 3 seconds for emergency set up

KPI07, the voice blocking time should be as specified by the ETSI TS 126 269

around 4 seconds

KPI09, the accuracy of position shall reach the typical GNSS accuracy of 3 to

5m. In addition there shall be requirements for signal strength and how much

loss of signal is allowed.

For KPI13 the test criterion shall be to measure the travel direction not the

direction of the vehicle to be able to identify the right lane of the highway with

physical separation

Page 33: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 33 v 1.0

4.6 General Recommendations

The following recommendations are provided:

The heading information is given to the PSAP as required by EN 16072. The

manufacturers have to be made aware of these requirements.

When retransmitting the MSD the IVS should update the MSD content

according to EN16072.

For type approval a performance requirement for audio should be defined and

evaluated by the technical services.

Voice channel blocking time and MSD transmission times have to be as short

as possible and be in line with the defined thresholds for these KPIs. Vehicle

manufacturers shall implement best practise to minimize voice channel

blocking time.

In order to roll-out the use of filtering instances, procedures, guidelines,

criteria and rules are to be set up to provide the long numbers of PSAPs to

filtering instances. It is however recommended to do steps forward in setting

up this certification framework together with the definition of the conformity

assessment for PSAPs

Cross border communication between adjacent member states is an important

requirement for successful deployment of eCall. Today, emergency services

between different member states in Europe are not interconnected for data

exchange. A further study should evaluate data integration concepts in more

detail

Looking to the next generation of emergency calls, there the use of in-band

modem technology is to be replaced.

4.7 Conclusions

The intention of having HeERO pilot sites has been to evaluate if the requested performance

of the eCall service can lead to a deployment of the approved eCall standards in the existing

public mobile networks and within the existing 112 system. This means that the testing has

had a strong focus on the eCall standards and on capturing the key performance indicators,

the KPIs. Other issues, such as the response time of the rescue services and ambulances,

the use of EUCARIS and the use of the VIN in the operational rescue chain, as well as non-

operational issues, such as legal liability, privacy issues, periodic time inspections, change of

a car ownership, etc were not included in the work of the HeERO pilot sites.

The outcome of the tests performed tests reported in this document confirm that pan-

European eCall works according to expectations however there is still room for

improvement, both in European standards and in its implementation by the suppliers.

Page 34: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 34 v 1.0

One still open issue is the lack of commitment from some MNOPs to implement the

eCall flag.

Page 35: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 35 v 1.0

5 Results of Pilot Sites

5.1 Belgium

5.1.1 General

The Belgian pilot site planned to install a filtering instance at Touring, an eCall-PSAP service

centre at Astrid and to drive around with 6 IVS from NXP. Also the eCall-flag would be

deployed by Mobistar in part of the country.

The architectural discussion was held between Astrid and Touring for interconnection of the

2 servers. Following picture shows the way the different servers were interconnected and

where/how the data was stored.

Figure 7: server architecture (BE)

5.1.1.1 Filtering instance at Touring

The filtering instance was installed on a test server of Touring. The server SW was bought

from Oecon. Also an in-band modem was bought to receive the eCalls. The EN16102

interface was provided to Astrid. The necessary access through firewalls and other security

mechanisms was provided. The picture below shows a snapshot of the graphical user

interface of the Oecon server.

GSM/PSTN

PABXModem

PABX

PCbrowser

Filtercentrale

Push X

ML

Web of XML pull

CIC/PSAP DatacenterAstrid

Page 36: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 36 v 1.0

Figure 8: graphical user interface of eCall server (BE)

Although hardware was rather old (test-server) the server performed well and almost all

necessary tests could be executed. Only the re-transmit function was missing at the filtering-

instance side. This could be bought as an extension to the server-SW, but additional and

unplanned budget would be needed.

5.1.1.2 PSAP at Astrid

Astrid subcontracted the development of a test server to a small company. The SW was

installed on a test server of Astrid. It was properly receiving the MSDs. See below a snapshot

of the GUI.

The test-PSAP was setting up connection through the firewalls towards the test server at

Touring, using XML to extract all MSDs from the server and storing them in a local database

for access by the GUI. This concept functions quite well. It is however to be noted that, for a

real roll-out, an agreement should be made between PSAPs and filtering instance on filtered

transfers of the MSDs. As the implementation of these filtering rules is probably not really

difficult from technical point-of-view, this was not further worked out. Moreover, even if MSDs

would be sent unfiltered to the PSAP, this should not jeopardise the operation of the

services, nor impact on the operation of the operators at both the filtering instance and the

PSAP.

Page 37: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 37 v 1.0

Figure 9: snapshot of the GUI on PSAP (BE)

5.1.1.3 IVS

NXP, partner in the project, was to provide 6 IVS. For this they co-operated with S1NN. The

IVS were delivered (see picture right), but first tests revealed several technical issues. These

were solved throughout the first part of the project, besides of one important issue: the audio-

quality was so bad that the operator at the filtering instance could not understand the person

speaking in the IVS.

Figure 10: IVS by NXP/S1NN (BE)

Page 38: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 38 v 1.0

The cause of the technical issue was a configuration mismatch in the SW provided by NXP.

During the project, NXP transferred its activities related to HeERO2 to Telit. Although, S1NN

remained supporting the project, nor NXP, nor Telit solved the audio issues.

Figure 11: IVS by Geneva Microsystems (BE)

During the project, Geneva Microsystems was contacted to supply IVS with audio

functionality. Geneva Microsystems also provided 6 IVS. Tests with these IVS performed

well, but also here, a few technical issues needed to be resolved. Most of these issues were

solved, but unfortunately in the last SW-version, a new SW-bug slipped in which resulted in

non-functional GPS-reception. One of these technical issues was low reception and

performance in the 900 MHz band of the GSM network. To solve this, Geneva Microsystems

needed to execute a re-design. Geneva Microsystems started a new product design, but this

was unfortunately not available during the course of the project.

Summarized: when first tests were executed, none of both IVS performed good enough to be

distributed to the 6 assigned test drivers. This resulted in execution of only a limited number

of tests.

5.1.1.4 eCall flag by Mobistar

Mobistar rolled out the eCall flag in part of the Belgian country, the blue area on the picture

aside, covering about 7000 km². Mobistar also provided 12 SIM-cards for insertion in the IVS.

In the routing of the switching network, a special filter was installed for those 12 SIM-cards

that, when dialling 112 issuing an emergency call with eCall flag, the call was re-routed to the

Touring Filtering instance. The eCall-flag detection and handling functioned well. However,

some restrictions detected due to choices made:

The re-routing for these 12 SIMs was only available in the Mobistar network and not

on the 2 other networks (Belgacom and Base). At one occasion, it happened that the

IVS could not detect the Mobistar network (probably caused by a weak signal at a

Page 39: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 39 v 1.0

specific location), so the IVS registered in another network. When the emergency call

was signalled, the call was routed to a real PSAP. As this is the fall back later on, this

is not a problem for roll-out.

It was not possible to do cross border tests with 112 eCall flag, as the areas where

the eCall flag was rolled out in Belgium and neighbouring countries (Luxemburg)

were not next to each other.

5.1.1.5 Test coordination at Testronic labs

At Testronic labs, IVS were available to execute tests. Also access to the filtering service

was provided. Access to the test-PSAP was not provided, but this link showed to give the

least problems.

5.1.2 Recommended KPIs

In the beginning of the project, it was estimated that timestamps to measure KPÏs would be

available. Unfortunately, this was not the case.

The table hereunder shows the different KPI’s we have measured.

KPI Description KPI Description

01b Number of manually initiated eCalls 06 Success rate of established voice

transmissions

02a Success rate of completed eCalls

using 112

07a Duration of voice channel blocking

02b Success rate of completed eCalls

using long number

08 Time for call establishment

03 Success rate of received MSDs 28a Number of cross-border tests

04 Success rate of correct MSDs 28b Number of interoperability tests

Table 3: measured KPIs (BE)

The other KPI’s haven’t been measured because of lack of means or because it was not

possible (e.g. KPI_01a: number of automatically initiated eCalls).

The number of eCall tests was about 532 and for the two IVS 375. There were 443 without

eCall flag and 89 with eCall flag (respectively 286 and 89 with the two IVS). Despite this

large amount of data, it was not possible to evaluate statistically more than 10 tests.

Page 40: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 40 v 1.0

5.1.3 Evaluation results

5.1.3.1 Time series

For the time series, we have hereunder evaluated two KPI’s.: The duration of voice channel

blocking (KPI_007a) and the time for call establishment (KPI_008).

Figure 12 : time series KPI 7 and 8 (BE)

5.1.3.2 Statistical evaluation

For the KPI’s analysed we have the following results:

KPI NXP Geneva Microsystems

1b 323 52

2a 75% 79%

2b 75% 79%

3 73% 73%

4 73% 73%

7a 13 13

8 24 24

Table 4 : Results KPIs (BE)

The results for KPI’s nr 3, 4, 7a and 8 are the same for the two IVS because it was not

possible to distinguish them in our server. Furthermore, the results for KPI’s 3 and 4 are the

same because all the received MSDs were correct.

Page 41: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 41 v 1.0

We have seen that for KPI’s 7a and 8, we had time series.

Specifically, the time before we have the audio connection (KPI nr 8) is above 24 s. It is too

high and not acceptable for road safety.

KPI_007a KPI_008

Mean 13 s 24 s

Median 14 s 25 s

Minimum 6 s 19 s

Maximum 20 s 31 s

Range 14 s 12 s

Standard deviation 5 s 4 s

Skewness -0.1464 0.02912

Kurtosis -1.4111 -1.5810

Table 5 : statistics KPIs 7 and 8 (BE)

Figure 13: Distribution KPI 7a (BE)

Page 42: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 42 v 1.0

Figure 14: Distribution KPI 8 (BE)

For these two distributions, they aren’t similar to Gauss curves. The standard deviation is of

course high.

5.1.3.3 Discussion of results

In general, besides the technical open issues, which have not been solved due to resourcing

and priorities at the providers for the IVS and the system, the results of the tests are quite

good. However, still a few items to be noted:

The use of In-band modem technology is not state-of-the-art. Between pushbutton

and audio connection, timings of 20 seconds were often measured, mostly consumed

to transfer the MSD in the audio band. A silence of 20 seconds in case of

emergencies is not acceptable.

During the tests, retransmits could not be tested. As the combination of filtering

instances and PSAPs with retransmits poses several questions, it is a pity that this

could not be further worked out. However, all considerations have been captured in a

document and have been sent to the WP6-leader for further integration into

recommendations.

5.1.4 Interoperability tests

Cross border testing with eCall flag is not straight forward. For this, it is advised to set up a

consortium of different countries with MNOs who are capable and willing to roll out the eCall

Page 43: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 43 v 1.0

flag in the different countries with adjacent geographical areas. Instead of Cross border

testing interoperability tests were executed in following tests:

Members of the LUX pilot site visited Belgium and executed tests of their IVS using the long

number of the filtering instance. These tests gave similar results as former tests, of course

noting the shortcomings which were known.

5.1.5 Recommendations

The use of in-band modem technology is to be replaced by out-of-band technologies

or other performant architectures. By enabling filtering instances to connect to

PSAPs, the market for private eCall will become attractive, thus replacing the public

eCall and related in-band technologies. DEL 6.7 will elaborate in more detailed on the

strategy behind filtering instances.

In order to roll-out the use of filtering instances, procedures, guidelines, criteria and

rules are to be set up to provide the long numbers of PSAPs to filtering instances. It

was expected to make steps forward and create (draft) certification guidelines for

certifying filtering instances to connect to PSAPs in Belgium. Due to the complex

situation of both the Belgian political playfield as well as the uncertain and shifting

approach for introducing eCall in the European commission, the certification

guidelines have not been drafted, yet. It is however recommended to do steps

forward in setting up this certification framework.

Per today, cross border testing across different countries was not feasible.

Emergency services between different countries in Europe are not interconnected in

a uniform way, even outside the scope of eCall. Also MNOs between different

countries are often in competing positions, making cross border tests not a

straightforward test case. To do steps forward, in cross border and cross country

eCall, an integrated project should be set up on European level.

5.1.6 Conclusions

Although there are technical issues and many of the tests could not be executed as planned,

it is not to be expected that technical issues will be the roadblock for rolling out eCall in

Belgium.

5.2 Bulgaria

5.2.1 General

The information within this chapter is based on the test results including the second

realization stage of the Bulgarian pilot - after eCall Flag implementation, Sofia’ PSAP SW

application upgrade for integration with eCall test environment, connection to national VIN

database or EUCARIS. During the test phase the incoming calls were treated as test calls

with further processing only in the test environment, incl. simulation of emergency call centre,

Page 44: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 44 v 1.0

or were answered automatically without intervention. The test client was used to display

MSD data on its screen (incl. GIS location) and the voice channel was activated.

This chapter outlines the Bulgarian results including results of the second evaluation phase

of HeERO2.

5.2.2 Recommended KPIs

The recommended KPIs were successfully evaluated during the testing periods in both

phases of the Bulgarian pilot.

5.2.3 Evaluation results

5.2.3.1 Evaluation process

In order for all possible KPIs to be evaluated IVS and PSAP logs were made. Some KPI

parameters are based mainly on IVS logs (assuming that the IVS events are synchronized

with PSAP events with time difference <0.5 seconds) and only checked for compliance with

the PSAP logs afterwards. This is done for double check of the test results.

In order to evaluate KPIs IVS devices from two manufacturers were used – TUS’ IVS and

ICOM’s IVS.

For the KPI logging and evaluation some IVS devices were configured in special testing

mode making automatic eCalls in predefined periods of time making more tests while driving.

These tests produced logs used to measure most of the KPIs that don’t require operator to

be logged on from PSAP side. Some of the automatically performed eCall tests were made

from stationary devices (no heading information available), but most were conducted from

inside moving vehicles travelling across the country. These tests were performed in a test

scenario where the car was equipped with a device operating in automatic mode and an

interactive voice response system answering from PSAP side. A pre-recorded message was

played to the driver after MSD was sent in order to confirm the established voice connection.

These tests were performed in the manner showed in Figure 15.

IVS power ONIVS initialization

procedureUpdate the MSD &

Call 112

Send MSDDriver hears

automatic IVR response

IVS write log file Wait for timeout

Figure 15: testing process (BG)

Page 45: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 45 v 1.0

For the KPIs involving actual voice connection to 112 operators the eCalls were made

manually including initialisation, MSD transfer, talking to test operator, confirming voice

connection and integrity of received data.

In order to be able to evaluate as many KPIs as possible the IVS devices record different

events and parameters. The following table shows different types of IVS events and

parameters and the logging capabilities of the manufacturers:

Event Short Description

IVS

Manufacturer

TUS ICOM

Dial Start IVS starts dialling the PSAP. X X

Ring Start Call has reached PSAP. X X

Call Established

Connection is established. Due to the PUSH mode

voice connection is open, but is used by the In-

Band modem.

X X

IVS sends ‘START’

signal

IVS attempts to sync with PSAP and asks for MSD

transfer. X X

IVS starts sending

MSD MSD transfer has started X X

IVS stops sending

MSD

MSD transfer has ended. At this point voice

communication is available between operator and

occupant in the car.

X X

Call end Operator or occupant hangs up. X X

Parameter

MSD successfully

sent

‘Yes’ or ‘No’ based on PSAP feedback to IVS.

PSAP feedback includes info about MSD’s

successful transfer and decoding.

X X

eCall flag Shows whether None /Auto/Manual flag is used. X X

GSM level Signal strength of GSM network. X X

Satellites in view Number of usable satellites. X X

Heading Heading in degrees according to North. X X

Page 46: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 46 v 1.0

GDOP Shows the geometric dilution of precision. X X

GPS coordinates Accident GPS coordinates. X X

Speed Speed over ground. X X

Time between

successful positioning

fixes

Measures the time between two GPS position

fixes with accuracy of 1 second. X X

Number of

passengers

Implemented in a later version as a device

configuration parameter. X X

* True GPS coordinates used for Recent Vehicle

Location n-1 and n-2. X X

Table 6: Events and parameters recorded by different IVS devices (BG)

The PSAP is capable of logging all internal events during an eCall. The events are separated

in two categories – ‘info’ and ‘debug’. It also logs and archives all information regarding the

MSD message: its binary representation and its decoded content.

The following KPIs were measured mainly with IVS logs and then only checked for

compliance with the PSAP log: KPI_001a, KPI_001b, KPI_002a, KPI_002b, KPI_003,

KPI_006, KPI_007a, KPI_009, KPI_010, KPI_011, KPI_012 and KPI_013.

The following KPIs were measured by cross examining IVS and PSAP logs: KPI_004,

KPI_005, KPI_006, KPI_008, KPI_021, KPI_022, KPI_023, KPI_024, KPI_025 and KPI_028b

(using logs from foreign PSAPs).

5.2.3.2 Evaluation results

KPI TUS IVS/

Test PSAP Sofia

ICOM IVS/

Test PSAP Sofia

Unit Remarks and notes about

method of testing

KPI_001a 1 609 45 - Logging in IVS

KPI_001b 1 074 147 - Logging in IVS

KPI_002a 93 98 % Logging in IVS and PSAP (if

eCall flag is available)

Note: eCall flag is available in

Mtel network

KPI_002b 85 96 % Logging in PSAP (short

Page 47: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 47 v 1.0

number is used during the

initial tests)

KPI_003 93 85 % Logging in IVS and PSAP

KPI_004 100 100 % Logging in IVS and PSAP

KPI_005 11 11 s Logging in IVS and PSAP

KPI_006 98 100 % Logging in IVS and PSAP

KPI_007a 5 3 s Logging in IVS

KPI_007b 5 3 s Logging in IVS

KPI_008 4 5 s Logging in IVS and PSAP

MNO measures once - 2.5

sec + 112 to PSAP time

KPI_009 acceptable 1.5 m Logging in IVS

KPI_010 10 >12 - Logging in IVS

KPI_011 1.37 <1.5 - Logging in IVS

KPI_012 1 1 s Logging in IVS

KPI_013 100 100 % Logging in IVS

KPI_014 100 100 % Logging in IVS and PSAP

Note: Test VIN data base is

used.

KPI_015 N/A N/A % Logging in PSAP

(if Bulgaria becomes a

member of eCall EUCARIS

agreement or after connection

with Traffic Police vehicle

registers DB)

Note: The connection to

EUCARIS is not available.

KPI_016 N/A N/A s Logging in PSAP

(if Bulgaria becomes a

member of eCall EUCARIS

agreement or after connection

Page 48: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 48 v 1.0

with Traffic Police vehicle

registers DB)

Note: The connection to

EUCARIS is not available.

KPI_017 N/A N/A % Logging in PSAP

Note: The value is not

available as no real PSAP is

used but only "test PSAP".

KPI_018 N/A N/A s Logging in PSAP

Note: The value is not

available as no real PSAP is

used but only "test PSAP".

KPI_019 N/A N/A s No

KPI_020 N/A N/A % No

KPI_021 92 10 - Logging in PSAP

Note: Measure the cases

when an operator accepts the

eCall in test environment in

PSAP Sofia

KPI_022 100 100 % Logging in PSAP

KPI_023 <3 <3 s Logging in IVS

MNO measures once - 2,5

sec.

KPI_024 <1 s Logging in IVS

KPI_025 2.5 2.5 s Logging in PSAP

Note: The source of

information is COCON report.

KPI_026 N/A N/A s Logging in PSAP

Note: The value is not

available as no real PSAP is

used but only "test PSAP".

KPI_027 N/A N/A s No

Page 49: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 49 v 1.0

KPI_028 a N/A N/A - Logging in PSAP

KPI_028 b 104 8 - Logging in IVS and PSAP

KPI_028 c N/A N/A - No

KPI_29 N/A N/A s Logging in PSAP

Note: The value is not

available as no real PSAP is

used but only "test PSAP".

Table 7: summary of results (BG)

5.2.3.3 Comments

KPI_001a, KPI_002a

The first phase of the Bulgarian pilot included testing before the implementation of the eCall

flag. Instead the short number 107 was used as a substitute to the eCall flag. This is why

tests performed with 107 are actually referenced and measured for both KPI_001a

(automatically initiated eCalls) and KPI_002a (Success rate of completed eCalls using long

number).

KPI_003

A link-layer ACK received by the IVS is counted as a successful delivery of the MSD to the

PSAP. The low value comes only from the automatic tests using ‘long’ number (107). The

success rate with the later manual tests using eCall flag is 100%.

KPI_007a, KPI_007b

This time is measured as the time elapsed between two events: IVS sends ‘START’ signal

and IVS stops sending MSD.

KPI_008

This time is measured as the time elapsed between an eCall is initiated (the GSM modem

starts dialling) until the PSAP picks up the call.

KPI_009

The number of available satellites is available and measured in all test sessions. However

this does not give the accuracy in meters, rather than a reference for the accuracy of the

Page 50: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 50 v 1.0

positioning. Having in mind that the average number of usable satellites is 10, which gives

accuracy well below 100m, KPI_009 is marked as ‘acceptable’.

KPI_012

The IVS uses fixed positioning rate of 1 s.

KPI_013

Heading information uses the true direction of travel as delivered by the GPS module.

Contrary to the standard, heading is delivered using true geographical north instead of

magnetic north.

KPI_014

The decoding of the VIN number was done with a local VIN database configured for testing

purposes, but architecturally the same as a real-life solution.

KPI_021, KPI_022

The IVS logs voice calls, including call-backs. The value in KPI_022 is based on a verbal

connection between operator and driver.

KPI_024

The routing in the national 112 network is done entirely inside a software environment which

leads to very low latency times. The exact time cannot be measured, but with tests it was

confirmed that it is well below 1 second.

5.2.3.4 Time series

5.2.3.4.1 TUS IVS/ Test PSAP Sofia

Page 51: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 51 v 1.0

Figure 16: KPI_007 time series TUS IVS (BG)

As it can be seen in Figure 16 the values for duration of voice block are very similar. In rare

cases there are extreme values, but analysis of the logs showed that these are cases where

caused by poor GSM signal strength forcing several retransmissions of the MSD.

5.2.3.4.2 ICOM IVS/ Test PSAP Sofia

Figure 17: KPI_007 time series ICOM IVS (BG)

Page 52: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 52 v 1.0

Figure 18: KPI_008 time series ICOM IVS (BG)

5.2.3.5 Statistical evaluation

Table 8 shows different statistical parameters of KPI_007 and KPI_008.

KPI_007 KPI_008

TUS IVS ICOM IVS ICOM IVS

Minimum 4.4 2.0 1.0

Maximum 9.6 13.0 18.0

Mean 4.7 3.2 5.6

Median 4.4 3.0 5.0

Variance 2.3 2.5

Standard deviation 0.56 1.5 1.6

Skewness 3.351 5.1 4.05

Kurtosis 29.88 31.49

Table 8: statistical parameter (BG)

Page 53: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 53 v 1.0

5.2.3.5.1 TUS/ Test PSAP Sofia

Figure 19: distribution of KPI_007 for TUS (BG)

In Figure 19 the distribution of KPI 7 shows, that the most data are between 4 and 6

seconds. Less but notable amount is between 6 and 8 seconds, which are still very

acceptable values.

5.2.3.5.2 ICOM/ Test PSAP Sofia

Figure 20: distribution of KPI_007 for ICOM (BG)

Page 54: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 54 v 1.0

Figure 21: distribution of KPI_008 for ICOM (BG)

5.2.4 Interoperability tests

This chapter documents the results of the interoperability tests between TUS IVS, ICOM IVS

and PSAPs in Greece, Croatia and Romania.

PSAP KPI 2b KPI 3 KPI 4 KPI 6 KPI 7a

IVS

TUS

IVS

ICOM

IVS

TUS

IVS

ICOM

IVS

TUS

IVS

ICOM

IVS

TUS

IVS

ICOM

IVS

TUS

IVS

ICOM

GR 100 - 100 - 100 - 100 - 11 -

HR 100 100 100 100 100 100 100 50 7 4

RO 100 100 100 100 100 100 100 100 N/A N/A

Table 9: KPI 2b, 3, 4, 6 and 7a with foreign PSAPs (BG)

KPI_007a is not available due to lack of IVS log data and unavailability of the Romanian

PSAP for further testing after IVS logging upgrade.

5.2.5 Recommendations

The following recommendations are given:

The heading information is given to the PSAP as provided by the GPS receiver in the

IVS. This creates inaccuracies when the vehicle is not moving during eCall initiation.

Page 55: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 55 v 1.0

Thus the IVS manufacturers should provide a better direction information by

implementing their own calculation algorithms, e.g. based on previous GPS positions.

When retransmitting the MSD not all IVS devices update the MSD content. As

updating the fields gives new information to the PSAP operator thus leading to better

judgement of the incident environment it is recommended that all IVS devices update

the content of the re-sent MSDs with the latest GPS and other available information.

5.2.6 Conclusion

The IVS devices used in all test sessions are designed and developed by two independent

manufacturers (TUS and ICOM), but perform in a very similar way and the KPIs measured

with them differ only in acceptable ranges. This means that in addition to the successful

interoperability tests during the project, PSAP implementation should not have problem

communicating with different brands of IVS equipment though both the IVS devices and the

PSAP are still in a pilot implementation stage.

The eCall flag is already implemented by one Bulgarian MNO – Mobiltel. The other two

national MNOs are already conducting tests in test environments.

5.3 Denmark

5.3.1 General

This chapter outlines the Danish results of the first and second phases of testing within

HeERO2.

The results reflected here, are solely derived from vehicles equipped with IVS driving

throughout Denmark and calling the Danish HeERO2 PSAP Test Environment. The figure

below shows the locations in Denmark where the calls have been made from.

Page 56: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 56 v 1.0

Figure 22: Location of pilot test calls, as indicated in the IVS-unit (DK)

It shows all attempted call, where a satellite position within the frame of the map was

registered by the IVS-units. Please not, that the land mass between Zealand and Bornholm

belongs to Sweden. Please also note the four dots in the Baltic Sea, which are errors.

5.3.2 Recommended KPIs

The recommended KPI’s 1a and 2a couldn’t be tested during the project. The test-design did

not allow for testing automatically initiated calls, and none of the Danish Mobile Network

Operators supports the eCall flag yet.

5.3.3 Evaluation results

5.3.3.1 Evaluation process

Basis of the evaluation are the datasets derived in field testing with a number of eCall-

equipped vehicles driving around Denmark on other business.

Page 57: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 57 v 1.0

Figure 23 – An IVS-unit installed in a test vehicle

5.3.3.1.1 Phase one testing

Phase one testing was conducted in June and July 2014 with drivers calling to a setup with

an Intelligent Voice Response (answering machine).

Phase one evaluation is based on: Log from IVS, Log from PSAP (eCall-router), and log from

drivers (manually entered information in a log book).

5.3.3.1.2 Phase two testing

Phase two testing was conducted Monday 22 September 2014 from 9 am to 3 pm, and

Tuesday 23 September 2014 from 9 am to 3 pm with a dedicated PSAP operator standing by

at the HeERO2 eCall test equipment.

Phase two evaluation is based on: Log from IVS, Log from PSAP (eCall-router), log from

drivers (manually entered information in a log book), log from PSAP operator (manually

entered information in a log book).

5.3.3.1.3 Time deltas

It was not possible to calibrate the timestamps in the IVS-logs with the timestamps in the

PSAP-log. In some of the IVS-logs time and date was not always set correct (showing time

since boot, instead of actual time).

At the PSAP, the clock loses seconds every day.

Therefore, some of the time deltas in this report differ from the definitions. Please note, that

the resulting time deltas have been validated in lab-testing with external clocks (stop

watches).

Please see below for calculation of KPI5, KPI 7 and KPI 8

Page 58: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 58 v 1.0

5.3.3.1.4 IVS-units tested

Nine IVS-units participated in the test. All units were retrofit devices. For the purpose of ease

of use for the test drivers, the units were put in small cases and all the test driver had to do,

was add power from the vehicle.

Five units from Fujitsu-TEN with special profile SIM cards installed (could only call

to/be called from a limited set of telephone numbers: 112 and the long-number used

for testing). These units were part of both phase one and phase two

Two units from Fujitsu-TEN with normal Danish SIM-cards installed. These units were

part of both phase one and phase two

Two units from GMV with Spanish SIM-cards installed. These units were only part of

phase two

Figure 24: The IVS-units used for testing (DK)

5.3.3.1.5 KPI 5

Instead of calculating T2-PSAP – T0-IVS, we simply add up the results from finding KPI 7

and KPI 8.

5.3.3.1.6 KPI 7a

Fujitsu-TEN

Instead of calculating T2-PSAP – T1-IVS, we calculate T2-PSAP – T1-PSAP and add the

time indicated in the IVS-logs for the establishment of a communication channel

(EVT0_IND_VOICE_CALL_START), until the modem synchronization commences (first

“EVT0_IND_ECALL_SYNC_DETECTED” after “EVT0_IND_VOICE_CALL_START”).

GMV

Page 59: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 59 v 1.0

Instead of calculating T2-PSAP – T1-IVS, we calculate T2-PSAP – T1-PSAP.

Please note further

T2-PSAP is the timestamp for when the MSD can be presented at the PSAP. In the test-

setup, and in the live environments, where will be an additional delay due to an obligatory

voice response telling callers in the test setup, that they have “reached the eCall test

environment, please hold.”.

5.3.3.1.7 KPI 7b

KPI7b are calculated from the eCall routers data as the difference in time between the two

following events:

event:dtmf_detected signal=5 call-ref=INTERNAL

event:call_voice_connection_established

5.3.3.1.8 KPI 8

Fujitsu-TEN

Instead of calculating T0-PSAP – T0-IVS, this KPI have been derived directly from

timestamps in the Fujitsu-TEN IVS log, as the time from initiating (T0-IVS) to the IVS has

established communication channel (EVT0_IND_VOICE_CALL_START).

GMV

Instead of calculating T0-PSAP – T0-IVS, this KPI have been derived directly from

timestamps in the GMV IVS log, as the time from initiating (T0-IVS) to the IVS has

established communication channel (MSD_Start).

5.3.3.1.9 KPI 9 and KPI 13

The evaluation of „Accuracy of position“ and „Success rate of heading information“ are based

on the opinion of trained PSAP-operators only as „Acceptable“ or „not acceptable“.

To calculate the KPI 9, the formula given in D4.1 has been used (even though the Danish

Pilot site, do find the formula misleading): “Accuracy of position”=”Acceptable accuracy”/”not-

acceptable accuracy”

5.3.3.1.10 KPI 15 and 16

As Denmark is not part of EUCARIS, these two KPI’s cannot be tested.

5.3.3.1.11 KPI 17, 18 19, 20, 26 and 27.

As the Danish eCall implementation is based on a principle of „minimum work routine

changes“, there are no changes in the communication protocols between PSAP and TMC

and Rescue forces. Therefore, these KPI’s have not been evaluated.

Page 60: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 60 v 1.0

5.3.3.1.12 KPI 10

Only the GMV-logs had information about number of satellites.

5.3.3.1.13 Dormant testing (KPI 32)

All IVS-units had the capability of letting the GSM-radio is dormant (not registering on the

network, until a call is made). All tests were performed with this setting.

5.3.3.2 Evaluation results for phase one

KPI Name of KPI Fujitsu-TEN

7 units Unit

KPI_001a Number of automatically initiated eCalls N/A -

KPI_001b Number of manually initiated eCalls 185 -

KPI_002a Success rate of completed eCalls using 112 N/A %

KPI_002b Success rate of completed eCalls using long number 94% %

KPI_003 Success rate of received MSDs 99% %

KPI_004 Success rate of correct MSDs 100% %

KPI_005 Duration until MSD is presented in PSAP 13.6 s

KPI_006 Success rate of established voice transmissions 95% %

KPI_007a Duration of voice channel blocking 9.9 s

KPI_007b Duration of voice channel blocking: automatic retransmission of MSD Phase 2 s

KPI_008 Time for call establishment 3.7 s

KPI_009 Accuracy of position Phase 2 %

KPI_010 Number of usable satellites N/A -

KPI_011 Geometric dilution of precision N/A -

KPI_012 Time between successful positioning fixes N/A s

KPI_013 Success rate of heading information Phase 2 %

KPI_014 Success rate of VIN decoding without EUCARIS N/A %

KPI_015 Success rate of VIN decoding with EUCARIS N/A %

KPI_016 Time for VIN decoding with EUCARIS N/A s

KPI_017 Dispatch time of incident data to rescue forces N/A %

KPI_018 Mean time to activate rescue forces N/A s

KPI_019 Dispatch time of incident data to TMC N/A s

KPI_020 Success rate of presented incident data in TMC N/A %

KPI_021 Number of successful call-backs Phase 2 -

KPI_022 Success rate of call-backs Phase 2 %

Page 61: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 61 v 1.0

KPI_023 GSM network latency N/A s

KPI_024 112 national network latency N/A s

KPI_025 112 operator reaction time N/A s

KPI_026 Time for acknowledgement of emergency services N/A s

KPI_027 Total response time N/A s

KPI_028 a Number of cross-border tests N/A -

KPI_028 b Number of interoperability tests TBD -

KPI_028 c Number of cross regional tests N/A -

KPI_29 Dispatch time of Intermediate PSAP N/A s

KPI_30 Number of calls flagged as dangerous good N/A -

KPI_31 Number of successful access of dangerous goods information N/A -

KPI_32 Number of Dormant SIM card tests 185

Table 10 – Results derived from phase one pilot test (DK)

Please note, that KPI’s noted N/A are not measured (see above). KPI’s noted Phase 2 was

derived from phase two.

Figure 25 – geographical distribution of success rate of Calls made during phase one pilot test, with the satellite position registered in the IVS-units (DK)

Page 62: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 62 v 1.0

The few red dots in Figure 28 indicate that either the call was not successful, or that the MSD

was not received at the PSAP.

5.3.3.3 Comments on results from phase one

The majority of failed calls occurred at the beginning of the test-period. There is

therefore a risk that these calls may have failed due to the drivers handling of the

equipment.

Some timestamps in both IVS-units and at eCall-router have been reconstructed. We

believe these reconstructions have been conducted so that they represent correct

timing. The cause for the need for reconstructions are:

o If an IVS-unit calls shortly after it has been booted, it has not yet received

timing information from the GSM-network.

o The clock in the eCall-router is missing approximately a minute a day.

Some of the logs in the IVS-units were not readable. For these calls, data have been

reconstructed by extrapolating data from eCall-router-logs with the drivers manually

entered log-info. Missing data have been omitted from the statistical calculations.

For the majority of the MSDs received at the PSAP, the flag “Position cannot be

trusted” was set, even though the position given, was pretty accurate.

5.3.3.4 Time series from phase one

The figure to the right shows the time series of the KPIs 5 and 7. Note that we do not have

data for KPI 7, for the event causing the maximum for KPI 5. Gaps in the curve indicates a

successful event, with lack of data in the IVS-log

Page 63: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 63 v 1.0

5.3.3.5 Statistical evaluation from phase one

Table 11: Statistics of manual initiated calls for successful calls during first

phase (DK)

The statistics (Table 11) and the time series

(Figure 26), shows, that KPI 5 and KPI 7

normally are pretty close to a mean time of

13,5 and 10.0 seconds, with only a few calls

(approximately 10) causing relatively long

waiting time for the driver.

KPI5 KPI7

Minimum 10.1 7.1

Maximum 27.9 24.9

Mean 13.5 9.9

Median 13.5 10.0

Std dev 2.4 2.2

Skewness 2.1 2.5

Figure 26: time series for successful during first phase. (DK)

Page 64: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 64 v 1.0

5.3.3.6 Evaluation results phase two

KPI Name of KPI

Fujitsu-TEN DORMANT SIM-CARD

5 units

Fujitsu-TEN Normal

SIM-CARD 1 unit

GMV Roaming

SIM-CARD

2 units Unit

KPI_001a Number of automatically initiated eCalls N/A N/A N/A -

KPI_001b Number of manually initiated eCalls 43 9 21 -

KPI_002a Success rate of completed eCalls using 112 N/A N/A N/A %

KPI_002b Success rate of completed eCalls using long number

93% 67%1 95%

%

KPI_003 Success rate of received MSDs 100% 100% 95%

%

KPI_004 Success rate of correct MSDs 100% 100% 100%

%

KPI_005 Duration until MSD is presented in PSAP 13.1 11.8 18.7

s

KPI_006 Success rate of established voice transmissions 93% 67% 100%

%

KPI_007a Duration of voice channel blocking 9.6 8.5 11.6

s

KPI_007b Duration of voice channel blocking: automatic retransmission of MSD

9.1 8.9 8.8 s

KPI_008 Time for call establishment 3.6 5.2 7.1

s

KPI_009 Accuracy of position 77% 20% 13%

%

KPI_010 Number of usable satellites N/A N/A 9.1 -

KPI_011 Geometric dilution of precision N/A N/A N/A -

KPI_012 Time between successful positioning fixes N/A N/A N/A s

KPI_013 Success rate of heading information 69% 0%2 6%

3 %

KPI_014 Success rate of VIN decoding without EUCARIS N/A N/A N/A %

KPI_015 Success rate of VIN decoding with EUCARIS N/A N/A N/A %

KPI_016 Time for VIN decoding with EUCARIS N/A N/A N/A s

KPI_017 Dispatch time of incident data to rescue forces N/A N/A N/A %

KPI_018 Mean time to activate rescue forces N/A N/A N/A s

KPI_019 Dispatch time of incident data to TMC N/A N/A N/A s

KPI_020 Success rate of presented incident data in TMC N/A N/A N/A %

KPI_021 Number of successful call-backs 0 5 14 -

KPI_022 Success rate of call-backs 0%4 100% 87% %

KPI_023 GSM network latency N/A N/A N/A s

1 This poor result may be caused by one faulty IVS or that the vehicle was driving in areas with risk of

poor network-coverage (or a combination of the two). 2 This KPI is based on one single IVS. There could be a problem with this single device, and not to the

fact, that it was equipped with a normal SIM card. 3 The GMV-devices are prototypes (as are the Fujitsu devices). The poor result is based on the fact

that the GMV-device sends data on the cars current heading, and not the heading the car was driving, prior to the call (accident). 4 Call back was tried 35 times. Please see comments below for explanation for this poor result.

Page 65: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 65 v 1.0

KPI_024 112 national network latency N/A N/A N/A s

KPI_025 112 operator reaction time N/A N/A N/A s

KPI_026 Time for acknowledgement of emergency services N/A N/A N/A s

KPI_027 Total response time N/A N/A N/A s

KPI_028 a Number of cross-border tests N/A N/A N/A -

KPI_028 b Number of interoperability tests TBD TBD TBD -

KPI_028 c Number of cross regional tests N/A N/A N/A -

KPI_29 Dispatch time of Intermediate PSAP N/A N/A N/A s

KPI_30 Number of calls flagged as dangerous good N/A N/A N/A -

KPI_31 Number of successful access of dangerous goods information N/A N/A N/A -

KPI_32 Number of Dormant SIM card tests 43 9 21 -

Table 12 – Results derived from phase two pilot test (DK)

Figure 27 – geographical distribution of calls made during phase two, with the satellite position registered in the IVS-units (DK)

In Figure 27 the red dots that indicate that either the call was not successful, or that the MSD

was not received at the PSAP. Please also note the green dot in the Baltic Sea (and the

three red dots), where no vehicle was during testing.

5.3.3.6.1 Comments on results from phase two

In lab-testing 14 May 2014, all Fujitsu-TEN equipment was tested for call-back, and it

worked. BUT, when conducting the phase two „call back did NOT work for Fujitsu-

Page 66: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 66 v 1.0

TEN equipment with profiled SIM-card (to simulate the Dormant SIM-card

requirements). So even though call back for Fujitsu-TEN with the special profiled SIM-

cards was tried 35 times, there was no success.

One of the Fujitsu-TEN units started phase 2 with calling 112, instead of the long

number as it was configured to call with. This gave some additional information from a

real life operator, who had difficulties hearing what the driver was saying.

It took at least one reboot of the IVS for it to get back to its proper configuration, and

we no longer harassed real PSAP-operation.

GMV-units were equipped with Spanish SIM-cards. As we only tested with long-

number, the roaming may have caused problems, which would not happen, if the

roaming call could have used 112 instead. With long-number there will be some data

traffic from the Danish MNO to the Spanish MNO. With 112 (or TS12 call) the call will

be handled exclusively and prioritized within Denmark. This may have inflicted

negatively on the values for KPI_002b, KPI_003, KPI_005, KPI_007a and KPI_008.

It happened at least one time with Fujitsu-TEN equipment that the Satellite position in

the MSD was from the last call (made 15-20 minutes earlier). This was only detected

due to the manual communications between test-operator and test-driver.

Some of the test-drivers put equipment on the back-seat of the car, and they had to

turn around when talking, for the operator to properly hear them.

Some calls did not have data package with the call, but it was retrieved when a

resend of MSD was requested

Notes from interview with test-operator:

Audio quality is a real issue. Static occurs for all equipment, making it difficult for the

operator to communicate with driver.

The visual implementation on screen is perfect.

I’m pretty impressed with the accuracy of the system, this will make a difference.

Resend of MSD only takes five seconds, this is really nice, as it increases my trust in

the position

I’m a little nervous with the call-button. It would be nice, if you had a plastic guard

over the button that drivers have to switch open, before pushing for manual 112-call.

5.3.3.7 Time series from phase two

The four figures below show the time series of the KPIs 5 and 7. Gaps in the curve indicate a

successful event, with lack of data in the IVS-log.

Page 67: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 67 v 1.0

Figure 28: Phase two calls (DK)

Figure 29: Phase two calls with FJT M2M SIM card (DK)

Page 68: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 68 v 1.0

Figure 30: Phase two calls with FJT normal SIM card (DK)

Figure 31: Phase two calls with FJT normal SIM card (DK)

Page 69: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 69 v 1.0

Figure 32: Phase two calls with GMV normal SIM card (DK)

5.3.3.8 Statistical evaluation from phase two

KPI5

(all calls)

KPI7

(all calls)

KPI5

(FJT

M2M)

KPI7

(FJT

M2M)

KPI5

(FJT

normal)

KPI7

(FJT

normal)

KPI5

(GMV)

KPI7

(GMV)

Minimum 9.9 6.9 9.9 6.9 13.3 7.0 15.9 9.9

Maximum 31.3 24.3 19.0 14.1 20.8 11.8 31.3 24.3

Mean 15.2 10.1 13.1 9.6 16.6 8.5 18.7 11.6

Median 14.4 10.0 13.4 10.0 15.8 8.0 18.0 10.0

Std dev 3.8 2.5 2.2 1.6 3.8 1.9 3.4 3.2

Skewness 1.4 3.0 0.7 0.1 1.0 1.1 2.9 3.3

Figure 33: statistical data phase 2 (DK)

The GMV shows poorer results than FJT. This may be due to the fact, that the GMV-units

were equipped with Roaming SIM-Cards and that they had to use a long-number for calling

instead of 112.

Page 70: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 70 v 1.0

5.3.3.9 Discussion of results

Figure 34: geographical distribution of failed calls for phase 1 and 2 (DK)

Figure 34 shows where the IVS-units had registered to be, while attempting a call that either

failed, or where the MSD was not received at the PSAP.

The data presented above are based on non-complete datasets, as not all log-files from IVS

units were readable or accessible. This gives raise to interesting results (see footnote 2,

page 64).

The equipment used for the pilot-test were prototypes (among the first), and some of them,

arrived very late to the pilot site, because the vendor had to give the IVS-unit the capability of

letting the GSM-radio be dormant (not registering on the network, until a call is made).

The problems with obtaining, configuring and using special profiled SIM-Cards , underlines a

recommendation to put all “Dormant”-functionality on the IVS, and not in the SIM-card profile.

5.3.4 Recommendations

IVS must be in compliance with the eCall standards regarding interpretation and

understanding of what are in the MSD. We noticed, that the GMV-units sends the

Page 71: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 71 v 1.0

“Heading”-direction the vehicle has post-crash, instead of sending the heading the

vehicle was driving pre-crash.

Focus on audio quality when installing a retrofitted IVS in vehicles. Maybe this must

be further standardised.

5.3.5 Conclusions

The system works. Even with prototypes (and all the problems that follow) our operators in

the pilot-test could recognize the value of eCall.

But we need to have better retrofit able IVS-units in the market.

5.4 Luxembourg

5.4.1 General

This chapter outlines the Luxembourg results of the evaluation phase of HeERO 2. In

addition to phase 1, KPIs 9 and 13 were evaluated.

5.4.2 Recommended KPIs

The recommended KPI 2a couldn’t be tested during the project as the eCall Flag was not

updated into POST Luxembourg’s MSCs until the end of August. Unfortunately the first tests

after that showed that the Bit setting (6 and 7) for the routing was not added in the current

SW version. A SW version implementing a workaround could only be used in a closed test

environment beginning of October. This test environment is in fact a shielded metal box, with

a size of 80cm x 80cm x 30cm that contains the antenna of a base station. This box is

needed to avoid any interference of new feature or functionalities with the commercial

network. Therefore only a couple of tests were possible and putting an IVS into this box and

pressing the eCall button. The tests showed that the updated version works well. The final

SW version including the complete eCall routing support is planned for implementation into

POST Luxembourg’s networks in Q2 2015.

5.4.3 Evaluation results

5.4.3.1 Evaluation process

The basis of the evaluation was made using the datasets that were derived from the field

tests that were carried out between March 2014 and October 2014.

Unfortunately the KPIs regarding the eCall flag could not be tested. Although the eCall Flag

has been updated in POST Luxembourg’s switches the bits setting for the routing was not

Page 72: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 72 v 1.0

defined and this means that 112 eCalls cannot be routed as required. (An update that will

resolve this this will be available to POST in Q2 2015.)

In the following section, special cases in the evaluation are described.

5.4.3.1.1 KPI5

To compute the time until the MSD is presented in the PSAP (KPI_5) two calculation

methods were used:

1. IVS protocol available? The time from when the activation of the eCall was initiated in

the IVS (button pressed) until the ACK-MSD was received by the IVS was used.

2. The typical time for call setup of 3 seconds was added to the time when the call

reached the PSAP and the time when the MSD is presented to the operator. This

typical value was derived from the median of the delay measured by the IVS.

5.4.3.1.2 Manual and automatic tests

Only manual tests have been executed. For the manual tests all planned KPIs are evaluated.

5.4.3.1.3 KPI 13

The evaluation of the heading was made, in the manual tests, by comparing the board

instrument of the car and the heading presented to the operator when the car was stationary.

The aim of the evaluation of this KPI was to determine if it makes sense to transmit the

heading as a separate value besides the last three positions.

5.4.3.1.4 KPI 9

In the definition of KPIs there are two possibilities for specifying the result of this KPI (value

of the accuracy in meters or the success rate of the accuracy; success is defined as the

accuracy is within 100m). Here the success rate of the accuracy was measured by a

comparison of the real location and the presented location. The real position was reported to

the operator by the driver during the voice communication. The operator compared the

shown location with the real position and entered the result into the report.

The Fujitsu IVS showed a systematic error in the location. In the first eCall after powering up

the location was correct. For the second eCall the location of the first eCall was transmitted

and only when requesting a retransmission of the MSD the correct location was transmitted.

The manufacturer is working on this topic. As it is unrealistic that two eCall are issued directly

after each other as it is executed in the tests, we assumed the location as correct, when the

location was correct after the retransmission of the MSD.

Page 73: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 73 v 1.0

5.4.3.1.5 KPI_15 Success rate of VIN decoding with EUCARIS

KPI 15 could not be tested as EUCARIS access was not available in Luxembourg as of

August 2014.

5.4.3.1.6 KPI_16 Time for VIN decoding with EUCARIS

KPI 16 could not be tested as EUCARIS access was not available in Luxembourg as of

August 2014.

5.4.3.1.7 KPI_28a Number of cross border tests

As the 112 eCall flag was not available at the border of Luxembourg to Belgium and

Germany cross border tests could not be executed.

5.4.3.1.8 KPI_28b Number of interoperability tests

Some interoperability tests have been executed. The results are shown in chapter 5.4.4.

5.4.3.1.9 KPI_30 Number of calls flagged as dangerous good

The handling of dangerous goods transports in European eCall has been defined in this

project. It was decided that instead of a flag only additional information should be provided in

the additional information field of the MSD. This standardisation was more complex than

expected and needed more time. The ESA project that should provide the implementation of

the dangerous goods tracking service was delayed until end of 2014Therefore test

implementations of IVS were not available during the project.

5.4.3.1.10 KPI_31 Number of successful access of dangerous goods information

See above

5.4.3.1.11 KPI_32 Number of Dormant IVS tests

No tests with dormant SIM cards have been executed.

Page 74: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 74 v 1.0

5.4.3.2 Evaluation results

FUJITSU man FICOSA 1 man FICOSA 2 man Unit

KPI_001a - - -

KPI_001b 317 263 98 -

KPI_002b 62% 67% 79% %

KPI_003 62% 67% 79% %

KPI_004 100% 100% 100% %

KPI_005 11.6 s 14.4 s

KPI_006 98% % 97% %

KPI_007 8.9 s 12.1 s

KPI_009 97% 94% 100% %

KPI_013 97% 94% 100% %

Table 13: Summary of Results (LU)

5.4.3.2.1 Comments

In July FICOSA provided updated Firmware for the IVS. The new IVS (FICOSA) shows some

improvements in MSD transmission, especially in difficult environments. (Not visible in the

KPIs)

KPI 5 (MSD presentation time) is longer than KPI 7 (voice channel blocking time). This is as

expected. The FICOSA IVS has a significant higher MSD presentation time and Voice

Channel Blocking than Fujitsu. This is caused by the long synchronisation and codecs

selection time before transmitting the MSD

The accuracy of the GPS positioning is as good as expected and is beside of few outliers

between 3 and 5 meters.

The information of the heading shows the actual direction of the stationary vehicle and not

the recent direction of travel, when the vehicle was driving. So the implementation of the

heading information is not in conformance to the requirements of the standard. It does not

provide the expected additional benefit for the rescue team to know on which side of the

highway the incident happened.

Page 75: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 75 v 1.0

5.4.3.3 Time series

Figure 35: KPI5 FUJITSU IVS (LU)

Figure 36: KPI5 FUJITSU IVS (LU)

Page 76: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 76 v 1.0

Figure 37: KPI5 FICOSA 2 (LU)

Due to a problem with the eCall router logging only a few values could be calculated.

In Figure 36 the chronological sequence of KPI 5 during the manual test is drawn.

5.4.3.4 Statistical evaluation

The statistical evaluation was made according to the agreed procedures in Chapter 4.1.

KPI 5 KPI7

FUJITSU FICOSA1 FICOSA2 FUJITSU FICOSA1 FICOSA2

Minimum 5.0 12.0 12.0 3.0 10.0 10.0

Maximum 25.0 20.0 16.0 24.0 19.0 14.0

Mean 11.6 14.4 14.2 8.9 12.2 11.6

Median 9.0 14.0 14.0 6.0 12.0 12.0

Std dev 5.9 1.8 1.1 6.0 2.0 1.1

Skewness 1.4 1.7 -0.4 1.8 2.4 0.5

Table 14: Statistics of manual initiated calls (LU)

Page 77: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 77 v 1.0

Figure 38: MSD presentation time (LU)

Figure 39: MSD presentation time (LU)

Page 78: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 78 v 1.0

Figure 40: Voice channel blocking time (LU)

In Figure 39 the distribution of KPI 7 shows that most data is between 4 and 8 seconds. The

values of the FICOSA IVS are little smaller after the software update but there is a wider

scattering. In principle both IVS show a similar distribution.

5.4.4 Interoperability tests

In this chapter the results of the interoperability tests of the Luxembourg IVS are

documented. The tests done with the Luxembourg PSAP are documented in the chapters of

the home country of the testing IVS.

PSAP IVS 1 IVS2

BG 5 0

DE 10 10

BE 10 7

RO 5 0

Table 15: KPI 1b with own IVS and foreign PSAPs (LU)

PSAP KPI 2b KPI 3 KPI4 KPI6

IVS 1 IVS2 IVS1 IVS2 IVS1 IVS2 IVS1 IVS2

Page 79: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 79 v 1.0

BG 100 0 80 0 80 0 80 0

DE 100 100 80 70 80 70 80 70

BE 100 100 80 100 80 100 80 100

RO 100 0 60 0 60 0 60 0

Table 16: KPI 2b, 3, 4 and 6 with foreign PSAPs (LU)

5.4.5 Recommendations

The following recommendations are given:

Voice channel blocking time and MSD transmission times are too high for both IVS.

The new version of the FICOSA SW reduces the time, but it is still too long. The

problem seems to be in the synchronisation of the IVS and the PSAP modem. We

recommend reviewing the synchronisation process to reduce this time.

The heading information does not provide the direction of travel as intended in all

implementations. The FUJITSU and the FICOSA units provided the heading

information from the current location of the car when the eCall was triggered. If the

car had turned around during the accident this is no longer the direction of travel. The

last three positions in the MSD should be used to determine the direction of travel

only. The PSAP SW needs to show the last three positions on the map in addition to

the last location

When an IVS is triggered to retransmit the MSD, the IVS provides updated content of

the MSD at the moment of request for retransmission. As the MSD containing the

updated position provides valuable information to PSAPs in case of a retransmission

of the MSD (especially for identifying false alarms), the content should always be

updated.

Luxembourg project partner POST Luxembourg particularly recommends that MNOs

planning on testing the eCall switch firstly check that the correct software is installed

that will allow the subsequent routing of the calls through Bits 6 and 7. After

“swapping stories” with several of the other MNO partners in theHeERO2 project this

has been shown to be a relatively common problem and the responses of the MSC

software suppliers can vary greatly as to availability and pricing.

Page 80: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 80 v 1.0

5.4.6 Conclusion

The success rates of completed calls and received MSD could be improved in comparison

with the results of Phase 1. As such the correctness of the modifications in the standard has

been validated.

The IVS are still prototypes and so there are minor problems with stability etc. which should

be solved when the final overall introduction of eCall gets closer. The biggest problem is the

success rate of the MSD transmission and the long voice channel blocking time that needs to

be improved.

The testing proved valuable where it revealed problems that were not necessarily anticipated

to be problems; specifically the Bit routing software’s importance to the success of the call

transmission for many partners.

5.5 Spain

This chapter outlines the Spanish results of the eCalls performed in Phase 1 and Phase 2.

Sub-phase A in Phase 1 was executed in October 2013 and Sub-phase B in Phase 1

between January and March 2014. This phase was used to properly configure all the system

in order to assure the correct data logging at each stage of the e-Call chain. Phase 2 was

undertaken in October 2014 with all the logging issues solved as well as some operational

improvements learned from Phase 1,

5.5.1 General

Unlike other test sites, Spanish test site has an intermediate PSAP belonging to the Spanish

National Traffic Authority (DGT) and located in Madrid capital, in charge of managing all the

eCalls coming from Spanish territory. Once the data from the IVS gets this PSAP at DGT and

the voice channel is established, it decides what regional 112 can support the vehicle

according to its position. At that same time, the PSAP is able to communicate directly with

the IVS and retrieve the significant data of the IVS (the decoded MSD) in its PCs. Tests in

Madrid were done with Madrid and Castilla y León PSAPs and tests in Galicia with Galicia

and Castilla y León PSAPs, which allowed testing cross-regional aspects too.

Figure 41: Call chain from the IVS to final PSAP

Page 81: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 81 v 1.0

Madrid

All KPIs have been calculated according to the information and data registered at the IVS

and intermediate PSAP at DGT. Unfortunately, some KPIs related to communication

between intermediate PSAP at DGT and regional 112 PSAPs have not been calculated due

to the absence of the necessary timestamps at the regional 112 PSAPs.

In addition, in any the tests done, the 112 number has not been used. Always a long number

was configured at the intermediate PSAP at DGT. For this reason, KPI_002a could not be

calculated.

Another KPI that could not be resolved is KPI_011. In this case, due to absence of

information from the device, this KPI is not possible to be determined.

A remark related to KPI_013 follows: No information related with the accuracy of the heading

has been recovered. Heading information provided by the IVS is considered not significant,

as no reference system is used on-board to conclude on a % of success.

In case of Call-back-related KPIs (KPI_021, KPI_022), the call-backs are considered from

intermediate PSAP at DGT to the IVS.

The protocol followed by the intermediate PSAP at DGT and by the regional 112 PSAPs was

agreed between the different participant PSAPs in the Spanish HeERO2 pilot and is

comparable to the protocol presented for the Galician Test Site.

The scenarios where the tests were conducted were similar to the ones used in the Galician

Test Site, including:

Standard Environmental Conditions (STD) with normal cellular network coverage and good

GNSS signal conditions

Weak GSM signal scenario (WEAK) where the environments chosen had low GSM coverage

High traffic load of GSM data scenario (HTRA): this environment was reproduced in areas with

high traffic load of GSM data, in urban areas.

Driving in regional cross border (REGC): it was tested with neighbouring region of Castilla y

León

High and low speed of vehicle (HIGH, LOW): the car was driving at high speed and at low

speed or stopped

Galicia

In order to get comparable results, the intermediate PSAP uses an answering protocol to set

up the basics of the communication among IVS, intermediate PSAP and final PSAP. The

Galician IVS can initiate the eCall in two modes: manual and automatic:

There is a button to push in case of manual eCall and other button to push in automatic mode

that simulates the airbag activation.

Once the eCall is initiated, the intermediate PSAP receives the data, creates the log entry and

answers the incoming call to establish voice communication with the passenger.

Page 82: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 82 v 1.0

At this moment, the intermediate PSAP confirms some data with the IVS, such as VIN

decoding, type of call or position in GIS.

The intermediate PSAP can request a MSD retransmission if there are discrepancies between

IVS and PSAP information.

If there is a break in the eCall the intermediate PSAP can restore the contact with a call-back.

Based on the location of the IVS, the intermediate PSAP decides what PSAP is going to

attend the eCall (Galicia or Castilla y León) and creates the data for transmission

The intermediate PSAP contacts with the final PSAP and forwards the call from IVS

Final PSAP and IVS establish voice transmission

Figure 42: Galician scenarios (ES)

Five different scenarios were employed to conduct the tests, taking into account the climate

conditions of Galicia, which included rainy and cloudy days when the tests were carried out:

- Standard environmental conditions (STD): IVS drove around Porriño town, N550 road and A55 motorway. These are busy areas in south western Galicia with normal network coverage and GPS signal conditions.

- Weak GSM signal scenario (Weak): these tests were performed in environments far for population nucleus in south western Galicia

- High traffic load of GSM data scenario (HTRA): to test this scenario IVS went to Vigo city. It is a great urban area, with more than 300.000 inhabitants, where there is a high traffic load of GSM data.

- Driving in international cross border (INTC): because of the situation of the Galician region, it was possible to test the GSM coverage with the neighbouring country of Portugal.

- Driving in regional cross border (REGC): it was tested with the neighbouring region of Castilla y León.

Page 83: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 83 v 1.0

Figure 43: IVS CTAG in the regional cross border

P2W

Also, Powered 2-wheelers (P2W) have been tested. The P2W test has been completed in 2

phases. First an emulator of PSAP has been used for validation test, and in the second

round of tests the IVS communicated with the real intermediate PSAP in DGT.

Test architecture

The test setup for the IVS of the P2W is described below:

The IVS has 3 main parts, the helmet itself, the accident detection unit and the call

unit.

o The intelligent helmet measures the impacts in the head and provides an

accident severity index, which may be useful for PSAP operators.

o The on-board accident detection unit sends the order for making a call to the

call unit. For the detection it uses several inertial sensors and an algorithm for

processing the information given by them. A manual activation button is

included in this module for a manual emergency call. It receives the severity

index from the helmet by Bluetooth.

o The call unit is the responsible for making the call and sending the MSD to the

PSAP. An audio channel is established with the helmet via Bluetooth.

Page 84: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 84 v 1.0

The PSAP emulator is composed by an electronic board and a PC with a PSAP

software. The Software provides the main functionality for a PSAP operator: MSD

decoding, call tracking, etc.

The call between IVS and the PSAP emulator is a real call under a real Network, which

increases the cost of each test, but results more realistic and closer to the final behaviour.

The schema of the test architecture is shown in the next figure.

Figure 44: P2W Test architecture

Figure 45: P2W with IVS installed

The test results can be shown in the next table, where calls has been divided in successful

calls (OK), Failed Calls and other where the voice connection has been established, but with

some errors in the MSD, usually related to positioning.

Type of call Total Calls OK Failed Calls Connected with MSD error

Accident Detection Unit

call +MSD GPS

PSAP emulator

Accident Severity

Index

Voice

Page 85: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 85 v 1.0

Manual 40 39 (98%) 0 (0%) 1 (3%)

Automatic 40 38 (95%) 0 (0%) 2 (5%)

Total 80 77 (96%) 0 (0%) 3 (4%)

5.5.2 Recommended KPIs

Phase 1

Data obtained may not be representative enough to be taken into account for a complete

evaluation. Table 17 includes the KPIs that could be measured during Phase 1

KPI Description

1a Number of manually initiated eCalls

1b Number of manually initiated eCalls

2b Success rate of completed eCalls using long number

3 Success rate of received MSDs

4 Success rate of correct MSDs

5 Duration until MSD is presented in PSAP

6 Success rate of established voice transmissions

8 Time for call establishment

9 Accuracy of position

10 Number of usable satellites

11 Geometric Dilution of Precision (GDOP)

12 Time between successful positioning fixes

14 Success rate of VIN decoding without EUCARIS

20 Success rate of presented incident data in TMC

21 Number of successful call-backs

22 Success rate of call-backs

28c Number of cross regional tests

Page 86: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 86 v 1.0

Table 17: KPIs measured during Phase 1 (ES)

Phase 2

Galicia and Madrid, as Spanish test sites, planned to calculate the KPIs included in ‘D4.1

Final agreed KPIs, test specification and methodology’. The great number of eCalls

performed allowed obtaining all the committed KPIs and managing them in a proper

statistical way. KPI_19 (Dispatch time of incident data to TMC) and KPI_20 (Success rate of

presented incident data in TMC) were not obtained because of the particularities of Spanish

eCalls where TMC is actually the intermediate PSAP. In this sense, for the Spanish Test

Site, KPI_19 would be the same as KPI_07a, and KPI_20 would be the same as KPI_02a.

In the case of the Spanish pilot, KPI 2a has not been tested due to the fact that the eCall

Flag has not been deployed yet in Spain. Our device is able to do this type of eCall but only

in case of a short number configured as PSAP (for example number 112).

5.5.3 Evaluation results

Phase 1

Table 18 summarizes the KPIs calculated in Spain during Phase 1.

Galicia Madrid Unit

KPI_001a 37 115 -

KPI_001b 137 117 -

KPI_002b 72.41 62.5 %

KPI_003 83.70 64.34 %

KPI_004 83.70 62.5 %

KPI_005 -- 15 s

KPI_006 82.09 62.5 %

KPI_008 -- 17 s

KPI_009 -- 100 %

KPI_010 8.74 9 Satellites

KPI_011 1.44 -- DOP

KPI_012 1 0.1 s

KPI_014 96.77 -- %

Page 87: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 87 v 1.0

KPI_020 83.70 62.5 %

KPI_021 93 32 -

KPI_022 98.94 84 %

KPI_028c 38 45 -

Table 18: Summary of calculated KPIs during Phase 1 (ES)

Phase 2

Table shows the KPIS calculated in Phase 2.

Galicia Madrid P2W Unit

KPI_001a 163 258 81 -

KPI_001b 194 216 79 -

KPI_002b 88 75.3 100 %

KPI_003 89 76.8 96.2 %

KPI_004 90 100 100 %

KPI_005 20.9 18.2 11.7 s

KPI_006 99 75.3 -- %

KPI_007a 10.7 10.6 -- S

KPI_007b 1.9 9.7 -- s

KPI_008 15.9 12.8 3,6 s

KPI_009 11.9 100 -- %

KPI_010 7.8 9 -- Satellites

KPI_011 1.4 -- -- DOP

KPI_012 165.,3 1 -- s

KPI_013 39 -- -- %

KPI_014 88 100 100 %

KPI_020 -- -- -- %

KPI_021 -- 54 0 -

KPI_022 -- 72 0 %

Page 88: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 88 v 1.0

KPI_023 60 -- -- s

KPI_028a 42 -- -- -

KPI_028b 42 69 -- -

KPI_028c 68 45 -- -

KPI_029 44.7 -- -- s

Table 19: Summary of calculated KPIs during Phase 2 (ES)

5.5.3.1 Evaluation process

The evaluation process is based on the data collected during tests performed during the two

phases in which Spanish Pilot Site was divided.

In Galicia and Madrid, due to some problems with PSAP in Phase 1, the first part of the tests

done (Sub-phase A) shows a bad behaviour of the duration to connect with the PSAP or the

TMC. But in the second round of tests (Sub-phase B), the tests were OK as most of

problems were solved. All info collected takes into account both situations and the data must

be understood with this observation.

Galicia

Table 20 summarizes the tests performed in Phase 2 in October 2014. A total of 357 eCalls

and 68 call-backs were carried out from Galician IVS. Separating the tests by scenarios 123

were performed in STD scenario, 62 with weak GSM signal, 86 with a high load of GSM

network, 88 in the regional cross-border and 64 in the international cross-border. 81% of the

MSD sent by IVS were successfully received by the intermediate PSAP and 84% of the data

sent by this PSAP reached the final PSAP. The success in the voice communication is

almost 100%.

Da

te

Sc

en

ari

o

IVS PSAP INT 112

eC

all

sen

t

Ma

n.

Au

to

Ca

ll-b

ack s

en

t

Su

cc

es

s c

all-b

ack

MS

D s

en

t

MS

D s

uc

ce

ss

tra

ns.

112

ca

ll s

en

t fr

om

PS

AP

112

ca

ll s

uc

ce

ss f

rom

PS

AP

MS

D i

nfo

rma

tio

n s

en

t

fro

m P

SA

P t

o 1

12

su

ccess r

eceiv

ed

info

rma

tio

n a

t P

SA

P

07-oct STD 40 22 18 10 1 40 31 31 29 31 29

Page 89: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 89 v 1.0

INTC 24 15 9 5 1 24 22 16 13 16 13

08-oct

STD 27 15 12 13 4 26 23 11 14 12 14

Weak 28 28 0 0 0 28 24 21 19 21 19

INTC 25 14 11 10 4 25 21 14 11 15 11

09-oct Weak 29 14 15 5 6 29 17 16 10 16 10

HTRA 50 25 25 1 0 50 50 40 40 40 40

16-oct STD 29 12 17 4 3 27 23 17 17 17 17

HTRA 35 20 15 0 0 35 35 35 35 35 35

17-oct REGC 68 28 40 20 12 59 43 61 34 60 34

Total 355 193 162 68 31 343 289 262 222 264 222

Table 20: Summary of Galician tests

Table 21 shows the Galician KPIs in the format required by ‘D4.1 Final agreed KPIs, test

specification and methodology’. It gives a general overview of the development of the

Galician tests. These KPIs were calculated for each scenario and also taking into account

the overall eCalls.

KPI_01a and KPI_01b show that was intended to conduct a comparable number of tests in

all the scenarios. KPI_02b, KPI_03, KPI_04, KPI_06, KPI_13 and KPI_14 were calculated in

the piece of chain from IVS to PSAP as it is here where the MSD transmission is produced.

KPI Name of KPI

Galician scenarios

Total Unit

STD Weak HTRA INTC REGC

01a Number of automatically initiated eCalls

46 15 40 22 40 163 -

01b Number of manually initiated eCalls

49 42 45 30 28 194 -

02b Success rate of completed eCalls using long number

94 63 100 87 85 88 %

03 Success rate of received MSDs 94 86 100 88 88 89 %

04 Success rate of correct MSDs 87 97 100 93 74 90 %

05 Duration until MSD is presented in PSAP

20.1 24.2 18.6 19.8 22.7 20.9 s

06 Success rate of established voice transmissions

99 100 99 100 97 99 %

07a Duration of voice channel blocking

10.1 13.7 8.8 10.1 12.0 10.7 s

07b Duration of voice channel 1.2 4.0 2.8 1.0 1.2 1.9 s

Page 90: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 90 v 1.0

blocking: automatic retransmission of MSD

08 Time for call establishment 15.1 18.2 14.0 15.5 17.4 15.9 s

09 Accuracy of position 12.7 11.2 38.5 7.2 6.5 11.9 m

10 Number of usable satellites 7.8 6.4 8.6 8.4 7.7 7.8 -

11 Geometric dilution of precision 1.3 1.8 1.6 1.4 1.3 1.4 -

12 Time between successful positioning fixes

168.6 174.9 125.6 143.3 176.3 165.3 s

13 Success rate of heading information

32 57 62 35 39 39 %

14 Success rate of VIN decoding without EUCARIS

94 62 100 88 89 88 %

23 GSM network latency 61.9 67.8 49.1 71.5 50.9 60 s

28 a Number of cross-border tests 42 -

28 b Number of interoperability tests

42 -

28c Number of cross regional tests 68 -

29 Dispatch time of Intermediate PSAP

46.6 49.5 35.0 56.7 36.6 44.7 s

Table 21: Summary of Galician KPIs

Madrid

Basis of the evaluation were the datasets derived in the field tests from February to October

2014. In the following paragraphs, special cases in the evaluation are described.

All the information shown in this chapter has been calculated based on manual and

automatic eCalls.

5.5.3.1.1 Information collected

Due to some problems in PSAP, the first part of the tests done (phase 1) showed a bad

behaviour at the time to connect with the regional 112 PSAP or the TMC. However, problems

were fine-tuned and in phase 2 these problems had already been fixed and the tests were

successful most of the time. All the information collected takes in account both situations and

the data must be understood with this observation.

5.5.3.1.2 KPI5

The calculation of this KPI (Duration until MSD is presented in PSAP)) has been carried out

considering the time between the activation of the eCall in the IVS (Button pressed or

automatic eCall execution) until the MSD is presented at the intermediate PSAP at DGT.

Page 91: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 91 v 1.0

5.5.3.1.3 KPI 9

In the definition of KPIs there are two possibilities to specify the result of this KPI (value of

the accuracy in meters or the success rate of the accuracy; success is defined as the

accuracy is within 100m). Here, the success rate of the accuracy was measured by

comparison of the real location and the presented location. The operator compared the

shown location with the real position and entered the result into the report.

Although, the position obtained in the intermediate PSAP at DGT from MSDs was

commented between the driver and the person on PSAP, and in all cases location was

completely OK.

5.5.3.1.4 Comments

All KPIs have been calculated according to information registered in IVS and data registered

at the intermediate PSAP at DGT. For some KPIs, information related to communication

between DGT PSAP and regional 112 PSAP is needed. Unfortunately, this information was

not available.

Due to this, some of the KPIs proposed have not been calculated. In any case, they are not

within the group of recommended KPIs. These KPIs are:

KPI 019, KPI 020 and KPI 023: Information from regional 112 PSAP is needed to

make these calculations, however, it is not available

KPI 011.

KPI 013

P2W

In this phase the emulated PSAP was substituted by the real intermediate PSAP in DGT. 81

automatic calls were initiated and 79 manual calls. The operator in the PSAP accessed via

VPN, so voice associated KPIs couldn’t be measured. This functionality was already tested

in the tests of the Phase 2.1.

5.5.3.2 Time series

Galicia

A time series analysis is carried out to better understand KPI_05, KPI_07a, KPI_07b,

KPI_08, KPI_23 and KPI_29. In this framework, it shows the evolution of the studied KPIs

with the temporal passing of eCalls. Figure 57 shows the plot series and histograms for these

KPIs.

Page 92: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 92 v 1.0

Figure 46: Time series diagram of IVS CTAG - KPI_05 (ES)

Figure 47: Histogram of IVS CTAG - KPI_05 (ES)

0

5

10

15

20

25

30

35

40

1 41 81 121 161 201 241 281 321

eCalls

Dura

tion u

ntil M

SD

is p

resente

d in

iPS

AP

(s)

0

10

20

30

40

50

60

70

80

90

<10 10-12 12-14 14-16 16-18 18-20 20-22 22-24 24-26 26-28 28-30 30-32 32-34

Duration until MSD is presented in iPSAP (s)

frequency

Page 93: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 93 v 1.0

Figure 48: Time series diagram of IVS CTAG - KPI_07a (ES)

Figure 49: Histogram of IVS CTAG - KPI_07a (ES)

0

5

10

15

20

25

30

1 41 81 121 161 201 241 281

eCalls

Dura

tion o

f voic

e c

hannel blo

ckin

g (

s)

0

20

40

60

80

100

120

140

160

180

0-2 2-4 4-6 6-8 8-10 10-12 12-14 14-16 16-18 18-20 20-22 22-24 24-26

Duration of voice channel blocking (s)

frequency

Page 94: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 94 v 1.0

Figure 50: Time series diagram of IVS CTAG - KPI_07b (ES)

Figure 51: Histogram of IVS CTAG - KPI_07b (ES)

0

1

2

3

4

5

6

7

1 5 9 13 17 21 25 29 33 37 41

eCalls

Dura

tion o

f voic

e c

hannel blo

ckin

g:

auto

matic r

etr

ansm

issio

n o

f M

SD

(s)

0

5

10

15

20

25

30

35

0-2 2-4 4-6

Duration of voice channel blocking: automatic retransmission of MSD (s)

frequency

Page 95: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 95 v 1.0

Figure 52: Time series diagram of IVS CTAG - KPI_08 (ES)

Figure 53: Histogram of IVS CTAG - KPI_08 (ES)

0

5

10

15

20

25

30

35

1 41 81 121 161 201 241 281 321

eCalls

Tim

e f

or

call

esta

blis

hm

ent

(s)

0

20

40

60

80

100

120

0-2 2-4 4-6 6-8 8-10 10-12 12-14 14-16 16-18 18-20 20-22 22-24 24-26 26-28 28-30

Time for call establishment (s)

frequency

Page 96: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 96 v 1.0

Figure 54: Time series diagram of IVS CTAG - KPI_23 (ES)

Figure 55: Histogram of IVS CTAG - KPI_23 (ES)

0

50

100

150

200

250

1 41 81 121 161 201

eCalls

GS

M n

etw

ork

late

ncy (

s)

0

20

40

60

80

100

120

0-20 20-40 40-60 60-80 80-100 100-120 120-140 140-160 160-180 180-200

GSM network latency (s)

frequency

Page 97: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 97 v 1.0

Figure 56: Times series diagram of IVS CTAG - KPI_29 (ES)

Figure 57: Histogram of IVS CTAG - KPI_29 (ES)

Madrid

0

20

40

60

80

100

120

140

160

180

200

1 41 81 121 161 201

eCalls

Dis

patc

h t

ime o

f iP

SA

P (

s)

0

10

20

30

40

50

60

70

0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180

Dispatch time of iPSAP (s)

frequency

Page 98: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 98 v 1.0

Figure 58: KPI5 for GMV IVS (ES)

In the previous figure, the MSD presentation in time calculated as KPI_005 with all the data

obtained along all the test process.

Figure 59: KPI7a for GMV IVS (ES)

Page 99: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 99 v 1.0

Figure 60: KPI7b for GMV IVS (ES)

Figure 61: KPI8 for GMV IVS (ES)

Page 100: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 100 v 1.0

Figure 62: MSD presentation time (ES)

In KPI_005 distribution figure, most data are between 18 – 20 seconds. Less but notable

amount is between 16 and 18 seconds.

Figure 63: Voice channel blocking time (ES)

Page 101: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 101 v 1.0

Figure 64: Voice channel blocking time (ES)

In the two previous figures about the KPI_007 distribution, it is possible to see that most data

are between 8 – 12 seconds (if we take in account the values obtained for KPI_007a and

KPI_007b).

Figure 65: MSD presentation time (ES)

Page 102: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 102 v 1.0

5.5.3.3 Statistical evaluation

The results of statistical analyses by KPIs are systematically presented in this chapter. It

was done according to the agreed procedures in chapter ‘5.2 Validation Procedure’.

Galicia

Minimum Maximum Mean Median Std dev Skewness

KPI_05 10 34 20.9 21.0 4.4 -0.54

KPI_07a 3 24 10.7 10.0 3.1 1.56

KPI_07b 1 6 1.9 1.0 1.5 1.51

KPI_08 5 29 15.9 16.0 3.2 0.82

KPI_09 0.3 68.7 11.9 5.5 24.0 4.76

KPI_10 3 12 7.82 8.0 1.6 -0.02

KPI_11 0.9 4.6 1.4 1.3 0.50 2.66

KPI_12 49.0 592.0 165.3 122.0 121.3 1.95

KPI_23 26 196 60.0 52.0 28.3 1.91

KPI_29 12 178 44.7 36.0 29.6 2.08

Table 22: Statics of initiated eCalls (ES)

The low values of standard deviation and Skewness in KPI_05 indicate that there is no

dispersion around mean value (20.89s) and talk about the good precision of the measure.

KPI_09 is a measure of the accuracy of position. It was calculated with the known Haversine

formula, being one of the points the position sent by IVS to PSAP and the other one the

actual position of the vehicle. The mean value is 11.91m. (less than 100m between these two

points is considered as ‘acceptable’) but it can be seen that the standard deviation is high, as

the Skewness value.

KPI_10 shows that 7.82 satellites were used on average to estimate the position. As this

number of available satellites is high enough, the GDOP (KPI_11) ranges between 1 and 2

that denotes an excellent rating

KPI_12 is strongly affected by the duration of voice time in each eCall. The time between

eCalls is not uniform so, this KPI does not provide a reliable result. In fact, value for standard

deviation is very similar to mean or median values. Skewness value is also far from 0.

Page 103: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 103 v 1.0

KPI_23 is also affected by the variable duration of voice phase.

Madrid

KPI_005 KPI_007a KPI7_007b

GMV GMV GMV

Minimum 7 2 4

Maximum 49 54 16

Mean 18.2 10.6 9.7

Median 23.5 15.5 9

Std dev 4.6 4.7 2.9

Skewness 2.5 4.4 0.6

Table 23: Statistics of initiated calls (ES)

5.5.3.4 Discussion of results

KPIs denote a satisfactory success of the tests carried out in Galicia and Madrid Pilot Sites.

All the proposed scenarios passed the evaluation process and there are no great differences

among KPIs calculated in different scenarios.

5.5.4 Interoperability tests

Galicia

Interoperability tests were performed in the framework of the second and third TESTFEST

events organized by ERTICO and ETSI. Those events were hosted in CETECOM in

September 2013 and CTAG test lab from 27th to 31th October 2014. TESTFESTs were

focused on checking eCall implementations confidently against other devices and eCall

standards requirements. This eCall TESTFEST event enables IVS vendors and PSAP

vendors to run interoperability test sessions using test descriptions provided in approved

guidelines

Page 104: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 104 v 1.0

Figure 66: TESTFEST#3

So, among other tests, it was performed by CTAG IVS a set of eCalls with other European

PSAPs such as: AREU (Italy), HiTec (Luxembourg), OECON (Germany), VTT (Finland),

Belgium or Bulgaria. All of them carried out the following mandatory tests:

TD_MAN_01: Using the pull mode

TD_MAN_02: Voice communication after receipt of AL-ACK

TD_MAN_03: Retransmission of MSD on request from PSAP

TD_MAN_04: Voice communication after retransmission of MSD

TD_MAN_05: Clear down / PSAP initiated network clear down

TD_MAN_06: Clear down / PSAP initiated application layer AL-ACK

TD_MAN_07: Call Back / PSAP initiated call back to IVS

Page 105: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 105 v 1.0

Figure 67: Summary of CTAG results in 2013

Page 106: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 106 v 1.0

Table 24 and Table 25 summarize the satisfactory results of these tests since 74% of them

show the excellent compliance in terms of interoperability requirements.

PSAP TD_MAN

_01

TD_MAN

_02

TD_MAN

_03

TD_MAN

_04

TD_MAN

_05

TD_MAN

_06

TD_MAN

_07

Italy OK OK OK OK OK OK OK

Luxembourg OK OK OK OK OK NA OK

Germany OK OK OK OK OK OK OK

Finland OK OK OK OK OK NA OK

Belgium OK OK NA NA OK OK OK

Bulgaria NA NA NA NA NA NA NA

Table 24: Interoperability tests performed between CTAG and European PSAPs in 2014

Interoperability Not Executed Totals

OK NO NA OT Run Results

43 (97, 7%) 1 (2, 3%) 4 (8, 2%) 0 (0.0%)

44 (89,

8%) 49

Table 25 CTAG’s IVS Mandatory test results in 2014

Madrid

All the interoperability tests were done during the eCall Test Fest#2 in Essen in September

2013 and the eCall TestFest #3 in Vigo in October 2014.

The KPI only reflects the number of tests carried out with the PSAPs (either local or remote)

in 2014 and does not compute the many other tests which were carried out against

simulators and test systems.

Mandatory tests were able to be done with several PSAPs from other countries like: Bulgaria,

Italy, Luxembourg, Belgium, Finland and Germany.

GMV’s IVS interoperability results in 2013 are presented respectively in the following tables.

Page 107: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 107 v 1.0

Figure 68: Summary of all participants’ results

Figure 69: GMV’s IVS test results summary

The comparison of GMV’s IVS results with the results of all of the participants at the eCall

Testfest shows the good interoperability and, also, good performance of GMV’s IVS.

In the eCall Testfest #3, in Vigo, October 2014, interoperability was tested between the IVS

and local and remote PSAPs from different countries and providers; concretely,

interoperability was tested with the following PSAPs: HiTec (Luxembourg), OECON

(Germany), Cestel (Spain), Telefónica (Spain), AREU (Italy), PicoSoft (Italy), VTT (Finland),

Belgium and Bulgaria. The tests used long numbers to call the PSAP. Manual and automatic

eCall tests were performed.

Page 108: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 108 v 1.0

Tests were also carried out between IVS and test systems, including IVS testers (IOP) such

as ANRITSU, Picosoft and Rohde&Schwarz, Speech Testers (Head Acoustics) and IOP

PSAP simulators (NavCert). The tests were carried out using emergency numbers (112) in

some cases.

An improvement in the number of successful tests was observed from eCall Testfest 2013 to

eCall Testfest 2014 for GMV’s IVS.

5.5.5 Recommendations

The following recommendations are given:

GPS positioning is not accurate enough as it can be observed in values provided by

KPI_09 and KPI_13. This should be improved.

The answering protocol should establish a fixed period for the voice communication to

better assess KPI_12 and KPI_23

Voice channel blocking times should be minimized and also a sound could be

reproduced while the channel is blocked to avoid transmission noise.

In many situations the vehicle heading information does not show correctly the

direction of travel and in some cases only the direction of the vehicle when the eCall

was triggered is not enough. MSD could provide previous information about the two

or three last positions to determine the travel direction perfectly.

In case of an MSD request (once the voice channel is open and a previous MSD has

been received at the PSAP) instead of sending the same MSD Data, the best option

in this case would be updating all the MSD information with location, heading, etc.

This could be useful in case the vehicle has moved due to the impact and this is also

a way to identify false alarms.

5.5.6 Conclusions

Galicia

The number of eCalls performed in Phase 1 had not been enough to calculate some KPIs or

undertake time series or statistical analysis. Phase 1 was focused on solving various issues

and technical problems with the intermediate PSAP and final PSAPs. In Phase 2, serious

efforts have been carried out by the three actors in the eCall chain (IVS CTAG, PSAP and

Group OK NO OK NO

Mandatory 67 (98,5%) 1 (1,5%) 1232 (93,9 %) 80 (6,1%)

Optional_CFG_01 44 (100%) 0 (0,0%) 830 (93,5%) 58 (6,5%)

Optional_CFG_02 2 (100%) 0 (0,0%) 33 (89,2%) 4 (10,8%)

Total results of eCall eventCTAG IVS

Page 109: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 109 v 1.0

PSAP) to fulfil the requirements by ‘D4.1 Final agreed KPIs, test specification and

methodology’. These efforts include:

- Improvements in the logging system

- An increased number of operators and day tests to perform a larger number of eCalls

- Development of tools to perform the statistical analysis

Special mention should be made to cross regional tests performed in Castilla y Leon. PSAP

was able to redirect properly the eCall from IVS to Galicia PSAP or Castilla y León PSAP

taking into account the GPS position of the IVS. The performance of the system in this

scenario was similar to other scenarios (Table 21).

All eCall tests in Galicia were carried out dialling to a long number (without eCall Flag) given

that the MNO has not implemented the changes necessary in the network to support it.

Nevertheless CTAG has tested in laboratory the compatibility of its IVS with eCall flag.

Additionally, it was planned to do some tests in December 2015 with Vodafone Spain to test

eCall flag implementation in a development network environment.

Madrid

The success rates of completed calls and received MSD in PSAP show an improvement with

respect to the results in the fine-tuning phase (phase 1). In phase 2 different modifications

were incorporated in order to adapt to the upgrading of standards.

The IVSs are still prototypes and for this reason, minor problems with stability, sound, etc.

have been observed. These will be solved when going to a commercial phase.

A great number of cross-regional tests were carried out between Madrid and Castilla y León

and in all the tests the intermediate PSAP at DGT was able to redirect eCalls to the correct

regional 112 PSAP based on the IVS’s reported position. The performance of the system in

this scenario was similar to other scenarios.

The eCall flag has not been implemented by the MNO; therefore, no calls to the emergency

number 112 have been tested. Laboratory tests have been performed with a test version of

the network implementing the eCall with Vodafone and results are satisfactory.

Page 110: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 110 v 1.0

5.6 Turkey

5.6.1 General

The goal of testing and validation of eCall service in Turkey is to validate technological and

functional properties of the system. The testing environment covers the whole service chain

from the IVS unit to eCall PSAP.

The field tests are carried out with two different IVS devices. Civitronics IVS units are used

for system verification. Magneti Marelli IVS units are used for both system verification and

data collection. Civitronics IVS units are supplied by Renault and Magneti Marelli IVS units

are supplied by Tofaş. The IVS units used Turkcell’s 3G network for establishing eCall.

The tests involve only manually initiated eCalls which were activated by pressing a button on

the IVS equipment.

5.6.2 Recommended KPIs

The recommended KPIs are listed in Table 26. All the recommended KPI’s except KPI_28a

and KPI_28b are tested in the scope of our field tests. We are currently working on

interoperability tests. We will add the results of the interoperability tests under KPI_28b once

they are available. KPI_028a which defines the cross border tests is out of the scope of our

tests.

ID of KPI Name of KPI rec. Remark

KPI_01b

Number of manually

initiated eCalls

Y Describes number of “real” eCall

scenarios with vehicle not moving and

voice communication

KPI_02a

Success rate of

completed eCalls using

112

Y It is recommended to use eCall flag for call

establishment with 112

KPI_03

Success rate of received

MSDs

Y Measures exactly what differs eCall from

112 call

Page 111: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 111 v 1.0

KPI_04

Success rate of correct

MSDs

Y Measures proper en-/de-coding of MSD

KPI_05

Duration until MSD is

presented in PSAP

Y Measures time until information is

available to operator

KPI_06

Success rate of

established voice

transmissions

Y Measures basics of eCall, MSD and voice

transmission

KPI_07a

Duration of voice channel

blocking

Y Most important to minimize, as during this

time passengers in the vehicle do not

know if eCall does work or not

KPI_13

Success rate of heading

information

Y This value is calculated by IVS and is

critical to identify right side on highways

KPI_28a

Number of cross border

tests

Y Required tests and should be specified

per member site with which cross border

was performed

KPI_28b

Number of interoperability

tests

Y Required tests and should be specified

per member site with which interoperability

was performed

Table 26 : Recommended KPIs tested in Turkey

5.6.3 Evaluation results

The field tests provide quantitative metrics about system quality and performance. The

results of our KPI evaluation are given in Table 27.

Antalya Unit

KPI_01b 969 -

KPI_02a 98 %

KPI_03 98 %

KPI_04 99 %

Page 112: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 112 v 1.0

KPI_05 35 seconds

KPI_06 98 %

KPI_07a 7 seconds

KPI_13 97 %

Table 27: The results of our KPI evaluation (TR)

KPI_001b: Number of manually initiated eCalls: 969

KPI_002a: Success rate of completed eCalls using 112: 98 %

Number of initiated eCalls: 969

Number of failed eCalls: 16

Number of successful eCalls: Number of initiated eCalls – Number of failed eCalls = 953

eCall success rate: Number of successful eCalls / Number of initiated eCalls = 98 %

KPI_003: Success rate of received MSDs: 98 %

In all the successful test calls, MSD was presented on the operator PC. KPI_002a tells that

98 % of the calls were successful.

KPI_004: Success rate of correct MSDs: 99 %

Number of received MSDs: 953

Number of incorrect MSDs: 4

Number of correct MSDs: Number of received MSDs - Number of incorrect MSDs = 949

MSD success rate: Number of correct MSDs / Number of received MSDs = 99 %

KPI_005: Duration until MSD is presented in PSAP: 35 seconds

MSD presentation time: Point of time of presentation of MSD at operator’s desk in PSAP –

point of time for IVS initiated the eCall

KPI_006: Success rate of established voice transmissions: 98 %

Number of successful voice transmissions: 953

Number of all initiated voice transmissions: 969

Voice transmission success rate: Number of successful voice transmissions / Number of all

initiated voice transmissions = 98 %

KPI_007a: Duration of voice channel blocking: 7 seconds

Duration of voice channel blocking = Start of phase “voice transmission” – IVS starts MSD

transmission

Page 113: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 113 v 1.0

KPI_013: Success rate of heading information: 97 %

All reported heading information: 353 (Heading information was tested in only a subset of the

total test calls)

Correct heading information: 341

Heading information success rate: correct heading information / all reported heading

information = 97 %

5.6.3.1 Evaluation process

The KPIs are evaluated according to the data collected in field tests which were performed in

September- October 2014. All the field tests took place in the province Antalya. 112 PSAP in

Antalya was used as the PSAP for handling eCalls. Manually triggered eCalls were used for

collecting test data. The location of the vehicle was available from two sources. One of them

was the GPS receiver of the IVS unit and the other is the Mobile Network Operator’s position

information. The test statistics were collected both from the logs on the IVS units and the

records in the PSAP centre.

The field tests were performed with a test vehicle exploring different locations in Antalya.

Two test operators were used to gather the call information from the IVS unit in the vehicle

and operator PC in PSAP simultaneously.

Vehicle site:

The test vehicle was equipped with an IVS unit to trigger the manual eCalls and a test PC to

read the IVS log data through serial port. During each call, the test operator in the vehicle

executed the following tasks:

Initiates the manual eCall by pressing a button on the IVS unit and records the start

time of the call.

Checks the availability of voice communication with the other test operator in PSAP

through IVS unit.

Reads the IVS log data from the serial port of the test PC and records the log for

future processing

Records the reference GPS location from a handheld GPS unit.

PSAP side:

Page 114: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 114 v 1.0

A dedicated operator PC was used to perform the field test. This operator PC runs the eCall

operator application. This application had a statistics interface which can be accessed by

authorized personnel only. Figure 2 shows the statistics interface. This interface included the

time duration statistics related with each Call. These statistics were used in the calculation of

the KPIs. During each call, the test operator in the PSAP executed the following tasks:

Receives the eCall and records the time of reception of the call.

Checks the availability of the MSD information, records the MSD content and the time

of reception of the MSD information.

Checks the availability of voice communication with the other test operator in the test

vehicle through the operator application.

Records the timing statistics.

Compares the location information gathered from the MNO database with the one

obtained from the IVS unit and documents the integrity of the two data sources.

5.6.3.2 Time Series

The time series plots of KPI_05 and KPI_07a are given in Figures 7.6.1 and 7.6.2

respectively.

Figure 70: Time series plot of KPI_05 (TR)

Page 115: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 115 v 1.0

Figure 71: Time series plot of KPI_07a (TR)

5.6.3.3 Statistical evaluation

The statistical evaluation is carried according to the procedure given in Section 4.2. Table 28

summarizes the statistical evaluation results.

KPI_05 KPI_07a

min 20 2

max 74 19

mean 35 7

median 35 6

std dev 4 2

skewness 3.95 4.90

Table 28: summary of statistical evaluation results(TR)

The frequency distribution plot of KPI_05 is given in Figure 72.

Page 116: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 116 v 1.0

Figure 72: The frequency distribution plot of KPI_05 (TR)

The frequency distribution plot of KPI_07a is given in Figure 73.

Figure 73: The frequency distribution plot of KPI_07a (TR)

Page 117: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 117 v 1.0

5.6.3.4 Discussion of results

The test results obtained in field tests in Antalya show that the eCall implementation is quite

successful. Operation tests were done in two phases. In the first phase, results were quite

satisfactory. In order to cover whole Antalya region, as a second phase, more tests were

performed than that was planned before. One another fact we discovered during the tests is

that MNO GSM coverage rate of Antalya is quite high. We noted that even in the rural areas,

most of the time the GSM signal was available. This is due to the fact that all Antalya regions

are a very popular tourism destination and the MNOs have implemented enough GSM

stations so that the GSM system is able to give service even in the rural areas.

5.6.4 Interoperability tests

Interoperability tests are planned to be executed in November with Civitronics IVS units.

Calls will be initiated from Romania and Calls will be routed to Ankara Test Bed system.

Therefore the results of these tests are not included in this document.

5.6.5 Recommendations

Vehicle manufacturers shall implement best practise to minimize voice channel blocking

time.

5.6.6 Conclusions

The field tests gave us the opportunity to test our eCall service solution in real life conditions.

The KPIs show that the implementation is quite successful. In our system solution, the eCall

PSAP and 112 PSAP was operating under the same roof and some system components

were used in common. The field tests showed that the two PSAPs can operate together

without degrading the other’s performance.

Page 118: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 118 v 1.0

6 References

[1] Hughes, I G and T P A Hase, Measurements and their Uncertainties: A Practical

Guide to Modern Error Analysis, Oxford University Press, Inc., New York, NY, 2010,

ISBN 978-0199566334

[2] Maindonald, J and W J Brown, Data Analysis and Graphics Using R - an Example-

Based Approach (3rd edition), Cambridge University Press, Cambridge, UK, 2010,

ISBN 978-0521762939.

[3] Ott, R L and M Longnecker, An Introduction to Statistical Methods and Data Analysis

(5th ed), Duxbury, Thomson Learning, Inc., Pacific Grove, CA, 2000, ISBN 978-

0534251222.

Page 119: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 119 v 1.0

ANNEX 1: eCall for P2W - User Acceptance Report

Abstract

The RACC has conducted a study aimed at analysing the acceptance, level of expectations

and possible deployment barriers that an eCall service for motorcycles might have among its

potential future users.

The public pan-European eCall service will only be available for cars, initially. The eCall

service for motorcycles that has been designed and tested in the Spanish pilot in HeERO2 is

partly based on the technical standards that support the eCall service for cars (encoding

information in the MSD, protocol for communication with the PSAP, etc.). However, there are

certain aspects of this system that pose technical and ergonomic/user acceptance

challenges (expectations, perceived usefulness, willingness to pay for the service, privacy).

These latter aspects justify the present study, which has been articulated through an online

survey for motorcycle drivers.

The survey was set up with the "Evalandgo" tool (http://www.evalandgo.com); it was

launched on the 3rd of February and has remained online until 7th of April 2014. The survey

has been structured into five distinct parts, which serve to establish the blocks in which the

study is structured:

1 - Characterization of motorists: age, gender, motorcycle driving experience, type of

(frequent) motorcycle and mobility habits. These data serve to further disaggregate data by

driver profile.

2 - Accident statistic: the respondents have been asked to make a very brief account of their

life as motorcycle drivers, whether they have had any accident, if so, in which environment

and how the actions of the emergency services developed. The objective is to estimate the

utility, mainly in saved time, the eCall service for motorcycles might have to improve (time of)

assistance in case of accident.

3 - Acceptance of the eCall service for motorcycles: the main features of the system have

been introduced to the user (i.e. automatic data acquisition and sending to PSAP in case of

accident; option of using a helmet connected to the system and capable of acquiring

additional data, send to the PSAP together with data from the motorcycle and establishing a

Page 120: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 120 v 1.0

voice call hands-free) and we have asked about the usefulness and acceptability of this

solution as well as the willingness to pay for a helmet compatible with eCall and an

aftermarket device.

4 - User Expectations: we have asked what data / information is considered useful or

desirable that the system would be able to acquire and send to the PSAP, and the relative

importance of these for the emergency management. The objective is to identify what

characteristics or requirements, in terms of information, might be interesting that an eCall

service for motorcycles would consider, and that would differentiate from the standard set of

data that is sent for cars (MSD).

5 - Other issues: privacy of the data has been assessed, especially if the user would

voluntarily opt to use a helmet with sensors capable of acquiring much more data than the

standardised set of data in the MSD; finally, we have asked about the introduction of the

eCall service for motorcycles, and how you could have access to it through aftermarket

devices for those motorcycles that would not have the built-in system because were

produced before mandatory implantation.

From the analysis and further processing of the received responses, we have derived the

following statistics and conclusions.

A 1 Characterization of motorists

A 1.1 Profile of respondents

636 people have responded to the survey. The majority (83.96%) of respondents is males

and only 16.04% are female.

Page 121: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 121 v 1.0

Figure 74: Gender of the respondents

Most respondents are concentrated in the adult age groups (27-30, 31-34, 35-38 and 39-42)

and there are few young motorcycle drivers or older than 50. However, we emphasize that

the women driving motorcycles seem to tend to be younger than men (we have not picked

any response from a woman motorist in the age range from 55 years old), a fact possibly due

to later incorporation of women to driving motorcycles.

Figure 75: Pyramid: ages and gender

This hypothesis seems to be confirmed if we look at the data referring to the years of

experience of drivers, since women report fewer years of experience than men driving

motorcycles:

83,96%

16,04%

Male

Female

14% 12% 10% 8% 6% 4% 2% 0% 2% 4%

15-18

19-22

23-26

27-30

31-34

35-38

39-42

43-46

47-50

51-54

55-58

59-62

63+

Men % Women %

Page 122: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 122 v 1.0

Figure 76: Years of experience driving a motorcycle, by gender

A.1.1.1 Mobility patterns of the respondents

The type of motorcycle more respondents report they use is the "scooter", followed by the

model "naked". Two thirds of motorists surveyed (nearly 67%) responded that they drive a

motorcycle daily. Among these, the scooter type model is the most used (34.51% of users

driving a motorcycle on a daily basis, take a scooter).

Men

25,71%

23,44%23,25%

15,12%

12,48%

0-5

6-10

11-20

21-30

More than 30

Women

32,00%

28,00%

20,00%

18,00%

2,00%

0-5

6-10

11-20

21-30

More than 30

Page 123: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 123 v 1.0

Figure 77: Frequency of use

Figure 78: Frequency of use by type of motorcycle

The average number of driven kilometres per year is according to the following statistic:

66,98%

33,02%

On a daily basis

Only weekends, bank

holidays or sporadically

3,76%

0,70%

23,71%

34,51%

9,39%

12,21%

2,58%

10,56%

0,23%

0,47%

1,88%

-6,67%

-3,81%

-26,19%

-13,81%

-18,10%

-11,90%

-4,76%

-12,86%

-0,48%

-1,43%

40% 30% 20% 10% 0% 10% 20% 30% 40%

Custom

Enduro

Naked

Scooter

Sport

Sport touring

Touring

Trail

Trial

Electric

Other

Daily Only weekends, bank holidays or sporadically

Page 124: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 124 v 1.0

Figure 79: Average number of Km. driven per year

A 1.2 Accident statistics

Nearly a third of respondents have suffered an accident in which medical assistance was

needed and / or traffic police had to intervene.

“Have you suffered any accident that involved the emergency services and/or the

traffic police?”

Figure 80: Accident statistics of respondents

41,20%

32,39%

17,45%

8,96%

< 5.000 Km

5.001 - 10.000 Km

10.001 - 15.000 Km

> 15.000 Km

29,40%

70,60%

Yes

No

Page 125: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 125 v 1.0

Figure 81: Accident statistics of respondents by age group

We have not found a clear relationship between years of experience driving a motorcycle

and the accidents statistics. Among respondents motorists that have had an accident,

statistics on years of experience is very distributed:

Page 126: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 126 v 1.0

Figure 82: Years of experience of motorcycle drivers that have had at least one accident

More than half (55.32%) of motorists who have ever had an accident did not personally call

the emergency services, and 14.36% did not in most cases. In these cases, an automatic

warning when the accident occurs could be particularly useful.

Figure 83: Did you call the emergency services (yourself)?

Negatively surprising are the statistics on the average time of arrival of the emergency

services to the accident spot, with 16.49% of motorists who answer that it took between 30

and 50 minutes, while 4.79% said it took more 50 minutes, which can clearly be improved

(for example, with the help of the eCall service). Only 17.02% said that emergency services

arrived within 10 minutes or less.

12,97%

24,32%

28,65%

18,92%

15,14%

0-5

6-10

11-20

21-30

More than 30

10,64%

19,68%

14,36%

55,32%

Yes, in most cases

Yes, in all cases

No in most cases

No, never

Page 127: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 127 v 1.0

Figure 84: How much time elapsed until the emergency services arrived?

Among respondents who have ever suffered a motorcycle accident, the distribution of these

between urban / interurban area (road) is the following:

Figure 85: Distribution of accidents between urban and interurban area

The average time of arrival of the emergency services depending on the accident location

(urban, city / intercity area, road) is the following:

Urban (City)

17,02%

48,40%

16,49%

4,79%

13,30%

< 10 minutes

10 - 30 minutes

30 - 50 minutes

> 50 minutes

I don't remember

61,70%

38,30%

Urban (City)

Interurban (Road)

Page 128: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 128 v 1.0

Interurban (Road)

Figure 86: Average time of arrival of the emergency services to the accident spot depending on the type of area (urban / interurban)

Statistics shows that in urban areas the time of arrival of the emergency services to the spot

of a motorcycle accident is lower, on average, than on the road. So while in town in about 2

out of every 3 accidents (59%) the time of arrival of the emergency services is between 10

and 30 minutes, in road environment statistics is almost 1 in 3 (32 %) while statistics is the

opposite as to accidents assisted between 30 and 50 minutes after the accident, with only

20,87%

58,26%

6,96%

3,48%

10,43%

< 10 minutes

10 - 30 minutes

30 - 50 minutes

> 50 minutes

I don't remember

11,11%

31,94%

31,94%

6,94%

18,06%

< 10 minutes

10 - 30 minutes

30 - 50 minutes

> 50 minutes

I don't remember

Page 129: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 129 v 1.0

7% in the city and 32% in road environment. Twice as many accidents are attended within 10

minutes compared with inter urban area (21 % vs. 11%).

Overall, it seems clear that the eCall service for motorcycles will be particularly useful to help

shorten assistance to a motorcycle accident especially interurban area, where time of arrival

of emergency services at an accident spot usually takes longer than in urban areas, in part

because there are greater distances to travel between accident locations and emergency

centres.

A 1.3 Acceptance of the eCall service for motorcycles

In this part of the survey was briefly introduced the characteristics of the eCall service by the

following explanation:

"In the future eCall service for motorcycles, the motorcycle will have a built-in device able to

acquire data from the accident and send it to the 112 emergency services (just like the eCall

for cars). Besides, and optionally, if you have an eCall compatible helmet it will be capable of

acquiring additional data and send it, together with the rest of data, to the 112. Moreover, the

helmet will also allow to automatically establishing a hands-free voice call with the PSAP."

Page 130: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 130 v 1.0

Figure 87: Architecture of the eCall service for motorcycles

The following question was asked about the degree of acceptance that such a system would

have among its potential users, and the results were clearly positive, with the vast majority of

motorists who would strongly agree (60.53%) or agree (29.25%) in that the eCall service for

motorcycles would be very useful to reduce mortality caused by motorcycle accidents, and

therefore would like to have this system available on their motorcycle.

"Do you think the eCall for motorcycles would help reduce fatalities and/or injuries

caused by motorcycle accidents and, consequently, would you like that your

motorcycle or scooter would have this system?"

Page 131: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 131 v 1.0

Figure 88: Level of acceptance of the eCall service for motorcycles

Extra details about the feature, optional, which would provide a helmet compatible with the

eCall service, were provided:

"In the prototype system we are proposing, the helmet would have sensors capable of estimating the injure caused on the driver or passenger (severity of the impact on the head). Besides, the helmet will also help know whether there was an additional passenger in the motorcycle (apart from the driver), determine the final position after the accident, etc.

All this information would also be sent to the emergency services, automatically, in case of

accident. "

We asked motorists about the relevance, in its discretion, of this type of information. Again, a

large majority considers this information as relevant (30, 03%) or very relevant (64, 31%):

60,53%

29,25%

7,08%3,14%

Strongly agree

Agree

I little agree

Disagree

Page 132: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 132 v 1.0

Figure 89: Relevance of the information provided by the helmet in case of accident

Unlike the eCall service for cars (which will come fitted as standard equipment in all new cars

from the mandatory implementation of this system at European level) motorcycle drivers will

have to make an additional investment in order to have all the features a compatible helmet

will be able to provide.

While it is not mandatory to replace the helmet, since the built-in eCall service will be able to

send a minimum set of information about the accident (timestamp, location, direction, etc.),

as previously noted, users believe that the additional information that the helmet can send is

not only complementary, but relevant or very relevant for the emergency management, so

the willingness of respondents to buy a new helmet is very big. This is the question we

formulated:

"It is estimated that a helmet compliant with eCall will have an extra cost of around 150€

compared with a “conventional” helmet…

Would you change your helmet in order to be able to send additional information (about the

impact on the head, etc.) and to speak with the 112 after an accident?”

64,31%

30,03%

4,09%

1,57%

Very relevant

Relevant

A bit relevant

No relevant at all

Page 133: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 133 v 1.0

Figure 90: Willingness to purchase a new helmet compatible with eCall

However, we observe that the proportion of respondents who considered the information that

the helmet can send as relevant or very relevant (94.33%) does not match the proportion of

users who would be willing, therefore, to buy a new compatible helmet (77,83%). It is quite

evident that there is a clear relationship between this result and the observed price sensitivity

(of the helmet) that some of the respondents have shown. This is the question we have

made in this regard:

"You think that the approximate extra cost of 150€ is"

And this is the result we have obtained:

Figure 91: Price sensitivity (for the price increase of an eCall compatible helmet)

77,83%

22,17%

Yes

No

14,62%

51,26%

26,42%

7,70%

Unreasonably expensive

Expensive

A fair price

Cheap, considering the

features of the system

Page 134: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 134 v 1.0

2 out of 3 respondents (65.88 %) consider the price increase of a helmet compatible with

eCall as expensive or unacceptably expensive (however, a significant proportion of these

would change their helmet anyway).

We have not observed any noteworthy tendency in the statistics of the willingness to change

the helmet in relation with the type of motorcycle driven by the respondent, having in all

cases a very similar proportion to that in Figure 90: Willingness to purchase a new helmet

compatible with eCall We have not detected a greater willingness to purchase a new helmet

eCall support among those motorists who have had an accident, or less willingness among

those who have never had an accident. In both cases, the proportion is very similar to that of

Figure 90: Willingness to purchase a new helmet compatible with eCall. All this seems to

indicate a very homogeneous and transverse interest for the eCall service for motorcycles,

as users understand its potential to be useful in case of accident.

It is interesting how using data from figures 1-16, 1-17 and 1-18 we come to the following

conclusions:

- Among those who consider that the information that the helmet can send in case of

accident is very relevant but still would not change their helmet, 3 out of 4

respondents consider this price increase as expensive (51.06%) or unacceptably

expensive (25.53%).

- Among those who consider that the information that the helmet can send in case of

accident is relevant but still would not change their helmet, 41.27% of respondents

consider this price increase as expensive while 44.44% consider it unacceptably

expensive.

A 1.4 User Expectations

The eCall service for cars is fully standardized, that is not the case with the eCall for

motorcycles. The development of this system poses challenges at a technical level and at

user level. It is important to have a vision of what the expectations are, in terms of

requirements, manifested by the future users of the system, because this way we can design

a system that is suited to their needs.

Page 135: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 135 v 1.0

We have tackled this topic in the following way:

"In case of accident, the eCall service will automatically send information about it to the

emergency rescue service (112). Among other data, it will send the timestamp and exact

location where the accident has occurred.

A motorcycle accident is usually different to an accident involving a car, for this reason it

might be interesting to send additional data that are currently not part of the eCall service for

cars."

The following types of information could be generated from data collected by the telematics

system embedded on the motorcycle and / or the helmet. We evaluated the importance

motorists give to these types of information on a scale of 0-5.

These are the results we obtained:

Figure 92: Importance respondents give to different types of information that the eCall service for motorcycles could generate

Overall, respondents expressed a considerable interest in the types of information suggested

by CEIT and NZI. If we arrange and analyse in further detail the assessments of the

respondents, we can draw some interesting conclusions:

Page 136: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 136 v 1.0

Type of information Score Comments

Final location of the driver 4,67 Motorists give more importance to be able to

send the final location of the driver (4.67 rating

points, on average, over 5) or of the other

passenger (4.64 rating points, on average, over

5) versus final location of the motorcycle (3.03

rating points, on average, over 5). In fact, this

information is the most valued by respondents.

Final location of the other

passenger (if there was any) 4,64

Number of impacts (against the

ground, obstacles, etc.) suffered

by the driver

4,53

Motorists are clearly more concerned about

information relating to the severity of the impacts

on the driver (number of impacts, deceleration)

as a result of the accident that the same

information on the motorcycle, giving these types

of information a very high score, close to the

maximum of 5 points.

Deceleration caused due to the

impacts on the driver 4,45

Speed of the motorcycle when the

accident happened 3,69

The speed at which the accident occurred

together with the final location of the motorcycle

and the severity of the impacts are important

types of information, because they provide an

estimation of the severity the accident might

have, but get a lower valuation compared with

the information directly related to the severity of

the accident on the driver.

Distance between the motorcycle

and the driver 3,18

Final location of the motorcycle 3,03

Deceleration caused due to the

impacts on the motorcycle 3

Number of impacts (against the

ground, obstacles, etc.) suffered

by the motorcycle

2,92

The main conclusion we draw is the importance motorists confer to the information that a

helmet compatible with eCall can send about the location of the driver (and passenger if any)

and the severity of the impacts suffered by them in the accident, besides information directly

related to the motorcycle.

Additionally, we asked respondents to indicate, on a free text field, what other types of

information they would consider useful to automatically send in case of accident and the

Page 137: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 137 v 1.0

features they would like the system could offer. We have grouped the responses into

thematic blocks. Following is a summary of these:

Proposals from the

respondents Comments

Personal data of the driver

and passenger (if any)

A large number of respondents have stated that it would be interesting

to send the PSAP the following personal information about the

occupants of the motorcycle:

- Name, Date of birth, Weight, Height, etc.

- Medical data: allergies, blood type, medical history, etc.

- Contact numbers of family or friends to notify in case of accident.

- Other data: if the user is a donor (in case of death in the accident).

The data would be linked to the helmet, so that a helmet would be

uniquely associated with a user. For obvious reasons, this is

information that would be sent optionally, provided the user gives

consent.

For the owner of the helmet to update these data, the helmet could

have an associated unique identifier. The user would sign in the

helmet manufacturer's website, enter this unique identifier and fill in a

form with all the data referenced above. These data would be stored in

a database. The website of the manufacturer of the helmet should fulfil

and require acceptance by the user of a privacy and data protection

policy.

In the event of an accident, the helmet could send its unique identifier

encoded in one of the optional fields of the MSD, and emergency

services could access a pan-European database where, entering this

identifier they could retrieve all relevant data of the user for a better

management of the emergency. The access protocol and design of

this database should be standardized at European level.

The user would be responsible to update the data, for example, in

case of change of ownership of the helmet.

Page 138: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 138 v 1.0

Vital signs of the injured

users

A number of respondents indicated that they would like the helmet was

able to collect data about the user state after the accident:

- Level of consciousness

- Heartbeat

- Temperature

- Etc.

The helmet designed by NZI is unable, for the moment, to acquire this

type of data. Feasibility (at technical level) of taking vital data about

the user should be researched, and data should be standardized in the

optional data fields of the MSD. Again, the challenge of data privacy

(and probably more expensive helmet for additional instrumentation to

acquire such data) arises.

Characterization / accident

reconstruction

Some users found it interesting that the eCall service would be able to

function as a black box capable of collecting data to help latter

reconstruction of the accident. For example:

- The possibility to determine the location of the impact/s on

motorcycle (if the accident was due to a frontal impact, side impact,

rear impact ...).

- If it is an accidental fall or accident is mainly due to the impact

against an obstacle or another vehicle.

- The tilt angle of the motorcycle at the time of the accident.

- Operated controls on the motorcycle before the impact (for example,

if the motorcycle broke, which would indicate a previous reaction to the

accident).

- Video Recording / Photos: ability to store photos / video seconds

before and after an accident.

- Trace prior to the accident: store and send several lat-long

coordinates before the accident.

- Involvement of other vehicles in the accident (through correlation with

eCall sent by other vehicles in the same place and time)

Regardless of the feasibility, at technical level, to get this type of data

(and subsequent algorithms needed to process and draw conclusions

from them), the question arises whether the eCall service should, from

Page 139: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 139 v 1.0

a conceptual point of view, serve for this purpose, as the automatic

emergency call has one goal which is to shorten the time for

assistance in case of accident and provide useful information to the

emergency services (fire brigade, ambulance, ...) for a better

emergency management.

It seems clear that this type of information would be useful not so

much for the emergency management but for subsequent claims (for

example, for the insurance company, or if any of those involved in an

accident were to give evidence in a possible lawsuit).

Again, the acquisition data other than the MSD standard poses a

challenge in terms of privacy (the user should be free to allow - or not -

that these data would be sent in case of accident, and to decide which

to which service provider these would be sent).

Finally, it is clear that the installation of a telematics device on the

motorcycle (and helmet, optionally) can serve as a basis for the

development of many applications / additional services to eCall, and

this poses a new challenge to enable service providers (such as auto

clubs, insurance companies, etc.) to develop and offer value-added

services based on the eCall service.

Environmental conditions

at the accident site

Some users have suggested that it might be interesting to transmit

data on the environmental conditions at the accident site.

- Temperature

- Humidity (if it is raining)

- etc.

The system designed by CEIT is unable, for the moment, to get this

type of data. Feasibility (at technical level) of introducing temperature

sensors, humidity, etc. should be researched, and data should be

standardized in the optional data fields of the MSD. Again, this could

increase the cost for the additional system instrumentation to acquire

such data.

Data after the accident Some users have contributed with ideas on data that could be sent

once the accident has occurred, such as:

Page 140: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 140 v 1.0

- Position the driver / passenger after the event.

- Position of the motorcycle after the accident, if it varies, it

could mean that the driver is not unconscious or there is

someone who can provide help.

- Ability to detect if the helmet is in the head of the occupants

after the accident.

As with the cases before, it is very questionable the usefulness of this

type of information for the emergency management, as this must be as

fast as possible and there (in principle) should not exist any other

information that might distract that is not strictly necessary for prompt

assistance. However, for different applications, such as reconstruction

of an accident, these might be useful, and in this case the technical

and privacy challenges noted above would need to be considered.

Other features

- Option that the driver can manually activate or cancel the

eCall (already implemented in the system designed by CEIT).

- Enable light signal (LED or similar) in the helmet if the

accident occurs at night on unlit roads.

- The device should be easily disabled, if the user wishes so

(for example, in order to run in circuits without the eCall

activated).

A 1.5 Other issues

We have evaluated the aspect of data privacy. More than two thirds of respondents do not

care (46.38%) or care little (25.79%) that data is transmitted from the eCall service. This is

the statistic:

Page 141: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 141 v 1.0

Figure 93: Sensitivity to data privacy of the respondents

Finally, in a scenario like that which will occur in the case of cars, where motorcycles without

the eCall service coexist with new motorcycles with the built-in eCall service, we asked about

the willingness to pay for an aftermarket eCall service, obtaining the following results.

"If your motorcycle does not have the built-in eCall service… Would you buy and install in

your motorcycle an aftermarket device that would be compliant with eCall?"

46,38%

25,79%

7,08%

14,78%

5,97%

I am not concerned

I am a bit concerned

I do not know

I am concerned

I am very concerned

Page 142: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 142 v 1.0

Figure 94 : Price sensitivity for an aftermarket eCall systemeCall service

28,46%

47,64%

16,04%

7,86%

Yes, but only if the total cost of the device (including cost of the installation in my

motorcycle) would not exceed 50€

Yes, but only if the total cost of the device (including cost of the installation in my

motorcycle) would not exceed 100€

Yes, but only if the total cost of the device (including cost of the installation in my

motorcycle) would not exceed 200€

No

Page 143: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 143 v 1.0

A 2 Conclusions

The Spanish pilot in HeERO2 is one of the first experiences at European level to develop,

implement and test an automatic eCall emergency call designed for two-wheeled vehicles.

The user acceptance study conducted by the RACC allows us to draw some interesting

conclusions about this system:

- On the sample of surveyed motorcycle drivers: one in three respondents has suffered an

accident that required the emergency services to participate. We have not identified a clear

link between the experience of motorists and accidents, not by age either. More than half of

respondents who have ever had an accident not personally alerted the emergency services,

while the average time of their arrival at the accident spot is significantly higher in interurban

area compared with urban. However, in both cases the time of arrival at the accident spot

could be clearly improved, for example with the help of an automatic warning to the closest

PSAP.

- On the level of acceptance of the eCall service for motorcycles: a large majority of

respondents motorists would like to have eCall in their motorcycles, and in slightly smaller

proportion they would be willing to change their helmet to have the full functionality of the

system, although they consider that the estimated increase in price compared to the price of

a conventional helmet is rather expensive. On the transition to a future eCall service for

motorcycles, users are receptive to pay for aftermarket devices to be able to have eCall on

their motorcycles manufactured before the system is implemented at European level in all

new motorcycles.

- On the expectations of users: surveyed motorists place a high potential to the eCall service

for motorcycles, and require some features that, conceptually, are outside the scope of the

eCall service. In any case, these features (sending of personal data and medical history of

the driver and passenger, etc.) will most likely be implemented as value added services by

private service providers.

From the results of the first laboratory tests, as well as the expectations generated among

future potential users, we can conclude that, although there are still many unresolved issues

(technical, standardization, conceptual, privacy-related, ergonomics-related, of costs, etc.),

Page 144: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 144 v 1.0

this system could be useful for a faster and more efficient management of motorcycle

accidents, helping to reduce fatalities in these vehicles, especially in interurban area.

Page 145: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 145 v 1.0

A 3 Questionnaire used

Survey eCall for motorcycles

eCall for motorcycles: the user point of view

From October 2015 all passenger cars in the EU will come with an electronic safety

system that, in case of a severe accident, will automatically call the emergency

services (112). This system will inform the 112 about the exact location of the accident

and will send additional data, such as the number of passengers in the car, the vehicle

identification number, etc. shortening the overall rescue time and contributing to save

up to 2500 lives a year in Europe.

However, this system won’t be initially available for motorcycles!

Within the HeERO2 European project a pilot system for eCall for motorcycles is being

developed, and RACC Automobile Club is coordinating a study to investigate the

requirements needed to extend the eCall to this kind of vehicles. This study is made in

cooperation with the Directorate-General of Traffic in Spain together with other

partners of the project.

In order to better understand which specific needs the eCall service for motorcycles

should take into account, we would like to ask you, only if you are a motorcycle driver,

that you answer the following questions. It will not take you more than 5 minutes and

it will be a great source of information for us.

Page 146: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 146 v 1.0

Thank you very much for your cooperation.

[All questions are to be defined as mandatory in the Evalandgo tool]

1. Your gender

a) Male b) Female

2. Year of birth

(1900/1901/…/up to 1999)

3. Years of driving experience (motorcycle or scooter)

Page 147: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 147 v 1.0

a) 0-5 b) 6-10 c) 10-20 d) 20-30 e) More than 30

4. How often do you drive a motorcycle or scooter?

a) Daily b) Only weekends, bank holidays or sporadically

5. What kind of motorcycle do you drive most frequently?

a) Custom

b) Enduro / MotoCross

c) Naked

d) Scooter

Page 148: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 148 v 1.0

e) Sport

f) Sport Touring

g) Touring

h) Trail

Page 149: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 149 v 1.0

i) Trial

j) Electric

k) Other: please specify

6. How many km do you usually drive per year by motorcycle or scooter?

a) Less than 1500 b) Between 1500 and 3000 c) Between 3001 and 5000 d) Between 5001 and 10000 e) Between 10001 and 15000 f) Between 15001 and 20000 g) More than 20000

7. Have you suffered any accident that involved the emergency services and/or the traffic police?

a) Yes b) No

[CONDITIONAL, if answer to question 7. is ‘Yes’ continue to question 8. if answer

in ‘No’ skip to question 11: be careful to configure this properly in the “Evalandgo”

tool]

Page 150: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 150 v 1.0

8. Did you call the emergency services (yourself)?

a) Yes, always b) Yes, in the majority of cases c) In the majority of cases, No d) No, never

9. How much time elapsed until the emergency services arrived?

a) Less than 10 minutes b) Between 10 and 30 minutes c) Between 30 and 50 minutes d) More than 50 minutes e) I don’t remember

10. The accident was in…

a) Urban zone b) Interurban zone

In the future eCall service for motorcycles, the motorcycle will have a built-in device

able to acquire data from the accident and send it to the 112 emergency services (just

like the eCall for cars). Besides, and optionally, if you have an eCall compatible helmet

it will be capable of acquiring additional data and send it, together with the rest of

data, to the 112. Moreover, the helmet will also allow to automatically establishing a

hands-free voice call with the 112.

Page 151: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 151 v 1.0

Now we will ask you some more specific questions about this system…

11. Do you think the eCall for motorcycles would help reduce fatalities and/or injuries caused by motorcycle accidents and, consequently, would you like that your motorcycle or scooter would have this system?

a) I do not agree b) I partially agree c) I agree d) I strongly agree

12. In the prototype system we are proposing, the helmet would have sensors capable of estimating the injure caused on the driver or passenger (severity of the impact on the head). Besides, the helmet will also help know whether there was an additional passenger in the motorcycle (apart from the driver), determine the final position after the accident, etc.

All this information would also be sent to the emergency services,

automatically, in case of accident. For the emergency management, you

consider this information as:

Page 152: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 152 v 1.0

a) Not relevant at all b) A bit relevant c) Relevant d) Very relevant

It is estimated that a helmet compliant with eCall will have an extra cost of around

150€ compared with a “conventional” helmet…

13. Would you change your helmet in order to be able to send additional information (about the impact on the head, etc.) and to speak with the 112 after an accident?

a) Yes b) No

14. You think that the approximate extra cost of 150€ is:

a) Too expensive b) Expensive c) A fair price d) Cheap, considering what the system does

In case of accident, the eCall service will automatically send information about it to the

emergency rescue service (112). Among other data, it will send the timestamp and

exact location where the accident has occurred.

A motorcycle accident is usually different to an accident involving a car, for this

reason it might be interesting to send additional data that are currently not part of the

eCall service for cars.

15. Please, rate in a scale from 0 to 5 how important are, in your opinion, the following types of information, where 0 = ‘not important at all’ and 5 = ‘very important’

a) Speed of the motorcycle when the accident occurred b) Number of impacts (ground, obstacles) suffered by the motorcycle c) Number of impacts (ground, obstacles) suffered by the driver d) Deceleration suffered due to the impacts on the motorcycle e) Deceleration suffered due to the impacts on the driver f) Final location of the motorcycle

Page 153: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 153 v 1.0

g) Final location of the driver h) Final location of the passenger (if there is one, and wears a compliant

helmet) i) Distance between the motorcycle and the driver

Please, tell us what other kind of information you would consider useful to be

sent (automatically): [free text field] [NOT mandatory]

16. Are you concerned that such a system would have access to your personal data (for example, your location, in case of accident), even if it is a public service?

a) I am not concerned b) I am a bit concerned c) I do not know d) I am concerned e) I am very concerned

17. If your motorcycle does not have the built-in eCall service… Would you buy and install in your motorcycle an aftermarket device that would be compliant with eCall?

a) No b) Yes, but only if the total cost of the device (including cost of the

installation in my motorcycle) would not exceed 50€ c) Yes, but only if the total cost of the device (including cost of the

installation in my motorcycle) would not exceed 100€ d) Yes, but only if the total cost of the device (including cost of the

installation in my motorcycle) would not exceed 200€

Page 154: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 154 v 1.0

ANNEX 2: LIST OF ALL EVALUATED KPIS

FT-

LUX

1

FIC

-

LUX

2

FIC

-

LUX

3B

E 1

BE2

BG

1B

G2

Gal

icia

ph

1 -

ES1M

adri

d

ph

1-

Mad

rid

ph

2 -

ES

Gal

icia

ph

2 -

ES Fu

j-D

K 1Fu

j-d

orm

-D

K 2Fu

j-D

K3

GM

V

DK

4TK

IVS

1/P

SAP

1IV

S 2

/PSA

P 1IV

S 1

/PSA

P 1

IVS

2/P

SAP

17

un

its

DO

RM

AN

TN

orm

al

Ro

amin

Res

ult

Res

ult

Res

ult

Res

ult

Res

ult

Res

ult

Res

ult

5 u

nit

s1

un

its

5 u

nit

s

KP

I_0

01

aN

um

ber

of

auto

mat

ical

ly in

itia

ted

eC

alls

--

-1

60

94

53

71

15

25

81

63

N/A

KP

I_0

01

bN

um

ber

of

man

ual

ly in

itia

ted

eC

alls

31

72

63

16

35

32

10

74

14

71

37

11

72

16

19

41

85

43

92

19

69

KP

I_0

02

aSu

cces

s ra

te o

f co

mp

lete

d e

Cal

ls u

sin

g 1

12

--

-7

5.2

78

.99

2.7

79

7.7

7N

/AN

/AN

/AN

/A9

8

KP

I_0

02

bSu

cces

s ra

te o

f co

mp

lete

d e

Cal

ls u

sin

g lo

ng

nu

mb

er6

2.4

69

6.9

69

6.9

47

5.2

07

8.9

08

4.9

29

5.9

27

2.4

16

2.5

75

.38

89

4.0

59

3.0

26

6.6

79

5.2

4

KP

I_0

03

Succ

ess

rate

of

rece

ived

MSD

s6

2.4

66

7.3

07

8.5

77

3.3

07

3.3

09

2.7

78

5.4

28

3.7

64

.34

76

.88

99

9.4

31

00

10

09

5.2

49

8

KP

I_0

04

Succ

ess

rate

of

corr

ect

MSD

s1

00

10

01

00

73

.37

3.3

10

0.0

01

00

83

.76

2.5

10

09

01

00

10

01

00

10

09

9

KP

I_0

05

Du

rati

on

un

til M

SD is

pre

sen

ted

in P

SAP

9.8

81

4.1

51

4.0

01

1.0

01

1--

15

18

.22

0.8

91

3.5

51

3.0

71

1.8

31

8.7

23

5

KP

I_0

06

Succ

ess

rate

of

esta

blis

hed

vo

ice

tran

smis

sio

ns

98

.42

96

.96

96

.94

98

.06

10

08

2.0

96

2.5

75

.39

99

4.5

99

3.0

26

6.6

71

00

98

KP

I_0

07

aD

ura

tio

n o

f vo

ice

chan

nel

blo

ckin

g7

.54

11

.90

11

.29

13

13

5.0

03

10

.61

0.7

29

.88

9.5

98

.49

11

.56

7

KP

I_0

07

bD

ura

tio

n o

f vo

ice

chan

nel

blo

ckin

g: a

uto

mat

ic

--

-5

39

.71

.88

-9

.06

8.8

88

.75

KP

I_0

08

Tim

e fo

r ca

ll es

tab

lish

men

t-

--

24

45

--1

71

2.8

15

.93

3.7

3.6

5.2

-

KP

I_0

09

Acc

ura

cy o

f p

osi

tio

n9

7.1

61

93

.91

00

acce

pta

ble

1.5

--1

00

10

01

1.9

1-

3.3

80

.25

0.1

4

KP

I_0

10

Nu

mb

er o

f u

sab

le s

atel

lites

--

-1

0.5

0>1

28

.74

99

7.8

2 N

/A N

/A N

/A N

/A

KP

I_0

11

Geo

met

ric

dilu

tio

n o

f p

reci

sio

n-

--

1.3

7<1

,51

.44

--1

.41

N/A

N/A

N/A

N/A

KP

I_0

12

Tim

e b

etw

een

su

cces

sfu

l po

siti

on

ing

fixe

s-

--

11

10

.11

16

5.3

2 N

/A N

/A N

/A N

/A

KP

I_0

13

Succ

ess

rate

of

hea

din

g in

form

atio

n9

7.1

61

93

.91

00

10

01

00

39

Ph

ase

26

8.5

70

6.2

59

7

KP

I_0

14

Succ

ess

rate

of

VIN

dec

od

ing

wit

ho

ut

EUC

AR

IS-

--

10

01

00

96

.77

--1

00

88

 N/A

 N/A

 N/A

 N/A

KP

I_0

15

Succ

ess

rate

of

VIN

dec

od

ing

wit

h E

UC

AR

IS-

--

n/a

n/a

 N/A

 N/A

 N/A

 N/A

KP

I_0

16

Tim

e fo

r V

IN d

eco

din

g w

ith

EU

CA

RIS

--

-n

/an

/a N

/A N

/A N

/A N

/A

KP

I_0

17

Dis

pat

ch t

ime

of

inci

den

t d

ata

to r

escu

e fo

rces

--

-n

/an

/a N

/A N

/A N

/A N

/A

KP

I_0

18

Mea

n t

ime

to a

ctiv

ate

resc

ue

forc

es-

--

n/a

n/a

 N/A

 N/A

 N/A

 N/A

KP

I_0

19

Dis

pat

ch t

ime

of

inci

den

t d

ata

to T

MC

--

-n

/an

/a N

/A N

/A N

/A N

/A

KP

I_0

20

Succ

ess

rate

of

pre

sen

ted

inci

den

t d

ata

in T

MC

--

-n

/an

/a8

3.7

62

.5 N

/A N

/A N

/A N

/A

KP

I_0

21

Nu

mb

er o

f su

cces

sfu

l cal

l-b

acks

--

-9

21

09

33

25

4 P

has

e 2

05

14

KP

I_0

22

Succ

ess

rate

of

call-

bac

ks-

--

10

01

00

98

.94

84

72

 Ph

ase

21

00

87

.5

KP

I_0

23

GSM

net

wo

rk la

ten

cy-

--

<3<3

59

.96

 N/A

 N/A

 N/A

 N/A

KP

I_0

24

11

2 n

atio

nal

net

wo

rk la

ten

cy-

--

<1 N

/A N

/A N

/A N

/A

KP

I_0

25

11

2 o

per

ato

r re

acti

on

tim

e-

--

2.5

35

2.5

35

 N/A

 N/A

 N/A

 N/A

KP

I_0

26

Tim

e fo

r ac

kno

wle

dge

men

t o

f em

erge

ncy

ser

vice

s-

--

n/a

n/a

 N/A

 N/A

 N/A

 N/A

KP

I_0

27

Tota

l res

po

nse

tim

e-

--

n/a

n/a

 N/A

 N/A

 N/A

 N/A

KP

I_0

28

aN

um

ber

of

cro

ss-b

ord

er t

ests

--

-n

/an

/a4

2 N

/A N

/A N

/A N

/A

KP

I_0

28

bN

um

ber

of

inte

rop

erab

ility

tes

ts-

--

10

48

69

42

 TB

D T

BD

 TB

D T

BD

KP

I_0

28

cN

um

ber

of

cro

ss r

egio

nal

tes

ts0

00

n/a

n/a

38

45

83

68

 N/A

 N/A

 N/A

 N/A

KP

I_2

9D

isp

atch

tim

e o

f In

term

edia

te P

SAP

n/a

n/a

44

.71

 N/A

 N/A

 N/A

 N/A

KP

I_3

0N

um

ber

of

calls

fla

gged

as

dan

gero

us

goo

d0

00

n/a

n/a

 N/A

 N/A

 N/A

 N/A

KP

I_3

1N

um

ber

of

succ

essf

ul a

cces

s o

f d

ange

rou

s go

od

s in

form

atio

n0

00

n/a

n/a

 N/A

 N/A

 N/A

 N/A

KP

I_3

2N

um

ber

of

Do

rman

t SI

M c

ard

tes

ts1

85

43

92

1

Nam

e o

f K

PI

FT/m

an/P

SAP

1FI

C I/

man

/PSA

P 1

FIC

II/m

an/P

SAP

1

Page 155: D4.3 Final results · D4.3 Final results of the tests with lessons learnt, conclusions and recommendations DG Communications Networks, Grant agreement no.: 325075 Pilot type A co-funded

D4.3 Final results

17/12/2014 155 v 1.0


Recommended