+ All Categories
Home > Documents > Daily Progress Report

Daily Progress Report

Date post: 23-Oct-2014
Category:
Upload: krishna-prasad
View: 152 times
Download: 5 times
Share this document with a friend
1
LARSEN & TOUBRO LTD. ,ECCD DAILY PROGRESS REPORT PROJECT QUALITY PLAN QUALITY MANAGEMENT RMZ CENTENNIAL DATE:- FORMAT NO. QAF/DPR/20 REV NO.00 PROJECT Name of Work : Employer : Contractor : Dur. in Days: Total Elapsed Balance SITE Normal Day Rainy From : To : Site Conditions: Slushy Dry WORK PROGRESS LOCATION UNIT TOTAL QTY. FOR THE DAY PL. NEXT DAY % COMP PLANNED ACHIEVED EXCAVATION BACKFILLING FORMWORK PCC REINFORCEMENT RCC BLOCKWORK BRICKWORK SSM PLASTER WATER PROOFING LABOUR & MATERIAL MAN POWER M A T E R I A L DESCRIPTION PLANNED ACTUAL DESCRIPTION UNIT RECEIPTS CONSUMPTION FOR DAY TILL DATE FOR DAY TILL DATE TOTAL CONSTRAINTS Distribution Prepared by: Construction manager Contract Start Date Contract Completion ACTIVITY DESCRIPTION Cum Achieved
Transcript
Page 1: Daily Progress Report

LARSEN & TOUBRO LTD. ,ECCDDAILY PROGRESS REPORT

PROJECT QUALITY PLAN

QUALITY MANAGEMENT RMZ CENTENNIAL DATE:-

FORMAT NO. QAF/DPR/20 REV NO.00

PRO

JEC

T

Name of Work :

Employer :

Contract CompletionContractor :

Dur. in Days: Total Elapsed Balance

SITE Normal Day Rainy

From : To : Site Conditions: Slushy Dry

WO

RK

PR

OG

RES

S

LOCATION UNIT TOTAL QTY.FOR THE DAY

PL. NEXT DAY % COMPPLANNED ACHIEVED

EXCAVATION

BACKFILLING

FORMWORK

PCC

REINFORCEMENT

RCC

BLOCKWORK

BRICKWORK

SSM

PLASTER

WATER PROOFING

LAB

OU

R &

MA

TER

IAL

MAN POWER M A T E R I A L

DESCRIPTION PLANNED ACTUAL DESCRIPTION UNITRECEIPTS CONSUMPTION

FOR DAY TILL DATE FOR DAY TILL DATE

TOTAL

CO

NST

RA

INTS

Distribution Prepared by: Construction manager

Contract Start Date

ACTIVITY DESCRIPTION

Cum Achieved

Recommended