Decision 2012-310
ATCO Gas and Pipelines Ltd.
Asset Swap Application November 22, 2012
The Alberta Utilities Commission
Decision 2012-310: ATCO Gas and Pipelines Ltd.
Asset Swap Application
Application No. 1608166
Proceeding ID No. 1723
November 22, 2012
Published by
The Alberta Utilities Commission
Fifth Avenue Place, Fourth Floor, 425 First Street S.W.
Calgary, Alberta
T2P 3L8
Telephone: 403-592-8845
Fax: 403-592-4406
Web site: www.auc.ab.ca
http://www.auc.ab.ca/
AUC Decision 2012-310 (November 22, 2012) • i
Contents
1 Introduction ........................................................................................................................... 1
2 Background ........................................................................................................................... 3
3 Issues ...................................................................................................................................... 5
4 Discussion of issues ............................................................................................................... 6 4.1 Depreciation ................................................................................................................... 7
4.1.1 Commission finding .......................................................................................... 7 4.2 Tranche timing and non-monetary adjustment .............................................................. 8
4.2.1 Commission finding .......................................................................................... 9
4.3 Income tax and other costs ........................................................................................... 10 4.3.1 Commission finding ........................................................................................ 11
4.4 Conclusion ................................................................................................................... 12
4.5 Other - board directions ............................................................................................... 14
5 Order .................................................................................................................................... 15
Appendix 1 – Proceeding participants ...................................................................................... 17
Appendix 2 – Summary of Commission directions .................................................................. 18
Appendix 3 – Tranche Timing and Asset Swap Map .............................................................. 19
List of tables
Table 1. Asset values to be swapped......................................................................................... 8
AUC Decision 2012-310 (November 22, 2012) • 1
The Alberta Utilities Commission
Calgary, Alberta
Decision 2012-310
ATCO Gas and Pipelines Ltd. Application No. 1608166
Asset Swap Application Proceeding ID No. 1723
1 Introduction
1. ATCO Gas and Pipelines Ltd. (AGPL), carrying on business under the trade name ATCO Pipelines (AP), filed an application with the Alberta Utilities Commission (AUC or
Commission) on February 15, 2012, requesting approval, pursuant to Section 26(2)(d) of the Gas
Utilities Act, RSA 2000, c. G-5 to transfer certain assets to NOVA Gas Transmission Ltd.
(NGTL) in exchange for assets of approximately equal net book value from NGTL consistent
with the terms of an integration agreement between AP and NGTL dated April 7, 2009.
Integration combines AP and NGTL’s physical assets in Alberta under a single rates and service
structure that operates assets under a single integrated system. The asset transfer exchanges and
realigns facilities between AP and NGTL to align asset ownership with their respective operating
areas.1
2. The legal requirement for AUC approval of the asset dispositions involved is found in Section 26(2)(d) of the Gas Utilities Act. Section 26(2)(d) of the Gas Utilities Act provides:
(2) No owner of a gas utility designated under subsection (1) shall
(d) without the approval of the Commission,
(i) sell, lease, mortgage or otherwise dispose of or encumber its
property, franchises, privileges or rights, or any part of it or them,
or
(ii) merge or consolidate its property, franchises, privileges or rights,
or any part of it or them,
and a sale, lease, mortgage, disposition, encumbrance, merger or
consolidation made in contravention of this clause is void, but nothing in this
clause shall be construed to prevent in any way the sale, lease, mortgage,
disposition, encumbrance, merger or consolidation of any of the property of
an owner of a gas utility designated under subsection (1) in the ordinary
course of the owner’s business.
3. The Commission and its predecessor, the Alberta Energy and Utilities Board (EUB), have traditionally applied a “no harm test” in assessing an application for the disposition of utility
property under Section 26(2)(d) of the Gas Utilities Act. In the present case, application of the no
harm test requires the Commission to consider whether any of service quality, service reliability
or customer rates are likely to be adversely affected by the transfer by AP of assets of
1 Once integration is completed, AP will own and operate assets located primarily around the Calgary –
Edmonton corridor (AP Footprint), while NGTL will own and operate assets located in the balance of Alberta
(NGTL Footprint).
Asset Swap Application ATCO Gas and Pipelines Ltd.
2 • AUC Decision 2012-310 (November 22, 2012)
approximately $114.6 million in net book value in exchange for NGTL assets of approximately
$115.6 million in net book value.
4. In this decision, the Commission considers this no harm test in deciding whether to approve this asset transfer; but the cost implications of the application on AP’s revenue
requirement associated with the exchange or transfer of assets between AP and NGTL is subject
to further scrutiny in AP’s next general rate application. AP’s rate base and the implications of
such for rate-making purposes is not determined in this decision but rather will be decided at the
time of AP’s next rate application.
5. On February 17, 2012, the Commission issued notice of this application. Any party who wished to intervene in this proceeding was required to file a statement of intent to participate
(SIP) with the AUC by March 2, 2012.
6. The Commission received an SIP from the following parties:
BP Canada Energy Company
NGTL
Encana Corporation
Canadian Association of Petroleum Producers (CAPP)
Office of the Utilities Consumer Advocate (UCA)
ATCO Gas, a division of ATCO Gas and Pipelines Ltd.
The City of Calgary
7. In their SIP, each of BP Canada Energy Company and Encana Corporation indicated that it had no issues with the application but reserved the right to participate. NGTL supported AP’s
application and reserved the right to participate. The UCA submitted that it neither opposed nor
supported the application and expected to file information requests and submit final argument.
As well, the UCA indicated that it was uncertain whether it would file evidence but reserved the
right to do so. CAPP, ATCO Gas and The City of Calgary did not object to the application.
8. Based on the submissions received from parties, the Commission determined that a written proceeding was suitable. Through a series of letters,2 the Commission established a
process schedule, with argument and reply argument due July 19, 2012 and August 2, 2012
respectively.
9. On July 4, 2012, the Commission received an email from Lacombe County that raised concerns regarding the novation of existing crossing agreements applicable to the pipeline assets
in Lacombe County being exchanged between AP and NGTL.
10. In a letter dated July 11, 2012, the Commission requested that Lacombe County file a statement of intent to participate if it wanted its July 4, 2012 email to be included and considered
on the public record of Proceeding ID No. 1723 (ATCO Pipelines Asset Swap application).
11. In an email dated July 11, 2012, Lacombe County filed its SIP with the AUC. Inadvertently, the SIP was not placed onto the public record of Proceeding ID No. 1723. As a
result, on October 25, 2012, the AUC requested that Lacombe County refile its SIP.
2 Exhibits 13.01, 18.01 and 24.01.
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 3
12. On October 26, 2012, Lacombe County refiled its SIP, along with documentation on crossing agreements.
13. On October 30, 2012, the Commission established a process schedule to address the concerns raised by Lacombe County’s October 26, 2012 SIP regarding the novation of existing
crossing agreements applicable to the pipeline assets in Lacombe County being exchanged
between AP and NGTL.
14. Both NGTL and AP were afforded an opportunity to file a reply submission to address Lacombe County’s SIP and standing in the current proceeding, and provide submissions on
further process by November 1, 2012. Lacombe County was also given an opportunity to reply to
any submissions from NGTL and AP by November 5, 2012.
15. The Commission received a submission from AP on October 31, 2012, followed by a reply from Lacombe County dated November 6, 2012.
16. Based on the review of submissions from Lacombe County and AP, the Commission ruled on Lacombe County’s submission. In its November 9, 2012 ruling, the Commission found
that AP’s October 31, 2012 response provided Lacombe County with the assurance sought in its
SIP, in addition to that already extended in AP’s Landowner Package,3 that novations or
assignments of such agreements needed for the ongoing operation of the pipeline assets being
transferred to AP will be properly affected in the ordinary course of conveyancing.
17. The Commission considers that the record for this proceeding closed on November 9, 2012.
18. In reaching the determinations contained within this decision, the Commission has considered all relevant materials comprising the record of this proceeding, including the
evidence and argument provided by each party. Accordingly, references in this decision to
specific parts of the record are intended to assist the reader in understanding the Commission’s
reasoning relating to a particular matter and should not be taken as an indication that the
Commission did not consider all relevant portions of the record with respect to that matter.
2 Background
19. In order to streamline the provision of natural gas transmission services and address competitive pipeline issues in Alberta, AP and NGTL entered into the Alberta System
Integration Agreement dated April 7, 2009 (Integration Agreement).4 The Integration Agreement
requires AP and NGTL, subject to necessary regulatory approvals, to exchange ownership of
certain physical assets within distinct operating territories or “footprints” in Alberta (Asset
Swap), and to work together in Alberta under a single rates and services structure, while
maintaining separate ownership, management and operation of their own assets (Integration).
NGTL would be the party that interfaces contractually with customers for regulated gas
transmission services using the combined regulated AP and NGTL gas transmission systems
within Alberta (collectively, the Alberta System). AP’s approved revenue requirement would be
3 Exhibit 20.01, AUC-AP-9(a) attachment.
4 On September 8, 2008, ATCO Ltd. issued a news release indicating that AP and NGTL had reached a proposed
agreement to provide seamless natural gas transmission service to customers.
Asset Swap Application ATCO Gas and Pipelines Ltd.
4 • AUC Decision 2012-310 (November 22, 2012)
included in NGTL’s revenue requirement through a monthly charge from AP to NGTL. The total
Alberta System revenue requirement would therefore be composed of the AP revenue
requirement approved by the Commission and charged to NGTL plus the NGTL revenue
requirement approved by the National Energy Board (NEB).5 This would form the basis for the
determination of Alberta System rates and tariffs for all customers. As part of the
implementation of the Integration, all AP contracts would be transitioned to Alberta System
contracts with NGTL.
20. On June 26, 2009, AP filed an application (Integration Application) with the AUC that sought a number of approvals from the Commission with respect to Integration and a request to
approve AP’s revenue requirement for each of 2010, 2011 and 2012. On April 29, 2009, the
Commission approved AP’s request to negotiate the revenue requirements for 2010, 2011 and
2012 and the parties reached a negotiated settlement on the requirements.
21. In its Integration Application, AP requested that the Commission:
(i) issue an Order, pursuant to section 22 of the Gas Utilities Act, declaring that Integration is in the public interest and furthers the convenience of the public and to
provide approval for AP to proceed with implementing Integration
(ii) approve, pursuant to section 36 of the Gas Utilities Act:
(a) the AP revenue requirements for 2010, 2011 and 2012, as set out in the
Negotiated Settlement
(b) the AP charge payable by NGTL to AP as of the Integration implementation date
and equal to the AP revenue requirement as approved under (a)
(iii) approve the transitioning of AP contracts to NGTL Alberta System contracts,
effective on the Integration implementation date, in accordance with the Integration
Application, pursuant to sections 22 and 36 of the Gas Utilities Act
(iv) approve, the sale of AP assets to NGTL to effect a swap of assets between AP and
NGTL, as reflected in the Integration Agreement; and provide such further and other
relief as AP may request or the Commission may deem appropriate, pursuant to
section 26 of the Gas Utilities Act6
22. In Decision 2010-228,7 the Commission approved AP’s 2010-2012 Negotiated Settlement (Settlement) with regard to its 2010-2012 General Rate Application (GRA) Phase I and
concluded that the proposal to integrate regulated gas transmission services in Alberta involving
the AP and NGTL systems was in the public interest and furthered the convenience of the public.
23. Decision 2010-228 also approved the proposed AP-NGTL asset swap in principle.8 The transitioning of AP contracts to NGTL Alberta System contracts effective on the implementation
of integration, and a swap of certain assets between AP and NGTL were to be determined in a
separate proceeding. Contract transitioning was approved in Decision 2011-1609 and the transfer
5 NGTL is regulated by the NEB.
6 Proceeding ID No. 223, ATCO Pipelines Alberta, System Integration Application, page 19. 7 Decision 2010-228: ATCO Pipelines 2010-2012 Revenue Requirement Settlement and Alberta System
Integration, Application No. 1605226, Proceeding ID. 223, May 27, 2010. 8 Decision 2010-228, page 46, paragraph 167.
9 Decision 2011-160: ATCO Pipelines Contract Transition, Application No. 1606374, Proceeding ID No. 732,
April 20, 2011. In paragraph 151 Decision 2011-260, AP was directed to notify the Commission of the date that
AP contracts cease to exist and customer contracts are transitioned to NGTL. In a letter dated August 23, 2011,
AP advised the Commission that the Integration Implementation date was October 1, 2011.
http://www.auc.ab.ca/applications/decisions/Decisions/2010/2010-228.pdfhttp://www.auc.ab.ca/applications/decisions/Decisions/2011/2011-160.pdf
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 5
of certain assets to implement a portion of the asset swap is the subject of the current
proceeding10 before the Commission.
24. On August 12, 2010, the NEB also approved Integration in Decision RHW-1-2010. In May 2011, AP and NGTL applied to the Federal Competition Bureau for an advisory opinion
(and Advance Ruling Certificate) under the Competition Act. On July 8, 2011, the Federal
Competition Bureau issued a standard “No Action” letter, with no conditions regarding
Integration and the Asset Swap and requesting notification of the closing date.
25. AP’s integration with NGTL was effective on October 1, 2011. As of this date, AP no longer invoices customers directly, but instead invoices NGTL monthly, based on AP’s approved
revenue requirement.11
26. AP and NGTL entered into an Asset Swap Agreement dated June 15, 2011 (Asset Swap Agreement).12 The key components of the Asset Swap Agreement are as follows:
it provides for the overall asset transfer to be conducted in one or more tranches (closings)
it provides for a due diligence process on behalf of the transferee
it provides for non-monetary adjustments for closings prior to the final closing to ensure no harm to the rate base of either party as a result of the timing and selection of assets for
each closing
it provides for monetary adjustments at the final closing for: (i) any difference in aggregate net book value of the assets received by a party; (ii) any expenditures in respect
of the assets not already included in the value of the assets; and (iii) any abandonment
costs relating to the assets already collected by the transferee13
Upon completion of the operational review of all assets within each tranche applications to
approve transfer of pipeline and facility licenses will be made to the AUC and the NEB
respectively. The close of each tranche will occur upon the completion of the license transfer of
each respective tranche.
3 Issues
27. Before reaching a determination with respect to approval of AP’s asset transfer and related dispositions, the Commission must address “the no harm test” and the specific concerns
raised by the UCA:
1. the treatment of information that will allow accurate depreciation costs to be calculated in the future
10
Application No. 1608166, Proceeding ID No. 1723. 11
Decision 2011-494: ATCO Pipelines 2011 Final Revenue Requirements, Final Rates Filing and Deferral
Account, Application No. 1607451, Proceeding ID No. 1314, December 20, 2011, page 2. 12
A copy of the executed Asset Swap Agreement is provided as Attachment 2 to the application. 13
Exhibit 1, application, page 5, paragraph 15.
Asset Swap Application ATCO Gas and Pipelines Ltd.
6 • AUC Decision 2012-310 (November 22, 2012)
2. the potential that AP will earn an additional return on mid-year rate base as a result of the timing of asset tranche transfers
3. AP income tax treatment under the Asset Swap Agreement
4 Discussion of issues
28. The no harm test considers the proposed transaction in the context of both potential financial impacts and service level impacts to customers and has been reviewed in several EUB
and Commission decisions. The test was summarized in Decision 2000-4114 when the EUB
stated:
The Supreme Court of Canada has stated that the Board’s jurisdiction to “safeguard the
public interest in the nature and quality of the service provided to the community by
public utilities” is “of the widest proportions.”15
The Board has also noted that its
governing legislation provides no explicit guidance for the exercise of the Board’s
discretion in approving an asset disposition by a designated owner of a public utility.16
The Board has held that its discretion under essentially similar provisions of the GU Act
must be exercised according to a “no harm” standard. More specifically, the Board has
held that it must be satisfied that customers of the utility will experience no adverse
impact as a result of the reviewable transaction.17
…
The Board believes that its duty to ensure the provision of safe and reliable service at just
and reasonable rates informs its authority to approve an asset disposition by a public
utility pursuant to Section 91.1(2) of the PUB Act. Therefore, the Board is of the view
that, subject to those issues which can be dealt with in future regulatory proceedings …,
it must consider whether the disposition will adversely impact the rates customers would
otherwise pay and whether it will disrupt safe and reliable service to customers. As
already noted, the Board also accepts that it must assess potential impacts on customers
in light of the policy reflected in the EU Act, namely the unbundling of the generation,
transmission and distribution components of electric utility service and the development
of competitive markets and customer choice. As a result, rather than simply asking
whether customers will be adversely impacted by some aspect of the transactions, the
Board concludes that it should weigh the potential positive and negative impacts of the
transactions to determine whether the balance favours customers or at least leaves them
no worse off, having regard to all of the circumstances of the case. If so, then the Board
considers that the transactions should be approved.
________________
15 ATCO Ltd. v. Calgary Power Ltd. [1982] 2 S.C.R. 557, at 576 (per Estey J.)
16 Decision U99102, p.7
17 See Decision U98084, NOVA Corporation, et al., Application for Regulatory Approvals in
Connection with a Proposed Merger of NOVA Corporation and TransCanada Pipelines
Limited (May 19,1998), p. 6; Decision U98097, Westcoast Energy Inc. et al., Sale of Shares
in Centra Gas Alberta Inc. from Westcoast Energy Inc. to AltaGas Services Inc. (June 29,
1998), p.3; Decision U99102, supra, p.8
14
Decision 2000-41: TransAlta Utilities Corporation, Sale of Distribution Business, Application No. 2000051,
File No. 6404-3, July 5, 2000, pages 7 and 8.
http://www.auc.ab.ca/applications/decisions/Decisions/2000/2000-41.pdf
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 7
4.1 Depreciation
29. In its information request UCA-AP-3(b), the UCA questioned whether AP was aware of the depreciation procedures used by NGTL with respect to the assets being transferred from
NGTL to AP.15 AP’s response was that AP is generally aware of the depreciation procedures
NGTL uses to depreciate its assets but has not done an analysis of the specific procedure used in
relation to the assets to be transferred. AP added that it will be engaging a depreciation expert to
perform a depreciation study to incorporate the NGTL assets into AP’s asset base.16
30. The UCA submitted that there is a clear risk that when AP and its depreciation expert(s) conduct future depreciation studies, they will discover the information required for estimating
the historical and forecast life and net salvage is deficient, incomplete, or otherwise needs to be
supplemented by information currently held by NGTL.17
31. The UCA noted that following a similar failure to scrutinize asset data after the transfer of assets from TransAlta to Aquila Networks Canada (Alberta) Ltd. (ANCA), the Commission’s
predecessor stated in EUB Decision 2003-019:18
The Board notes ANCA’s comments that it was unaware of the deficiencies in the
required data for a depreciation study. The Board considers that it was the responsibility
of ANCA to take all reasonable steps available to it, to ensure that it was able to provide
a depreciation study when it made the commitment to its customers and stakeholders that
it would do so.
32. The UCA argued that AP should at least be requesting NGTL to provide all available information needed to ensure the data being incorporated into AP’s depreciation data matches
and has integrity. The UCA requested that the Commission make clear in any decision approving
this application that any associated future harm to customers, such as delayed or expensive
depreciation studies, incomplete or imprecise estimations of life and net salvage, or ad hoc
depreciation methods for the transferred assets, will be at the expense of AP and not its
customers.19
33. In reply argument, AP submitted that it is taking all prudent steps to acquire and ensure the accuracy of the information and data required to perform a depreciation study and discounted
the UCA’s concern that NGTL would not cooperate with AP on an ongoing basis with respect to
matters affecting the Alberta System. AP argued that the Integration Agreement specifically
contains a “Further Assurances” clause committing the parties to continue working together once
Integration is implemented.20
4.1.1 Commission finding
34. The Commission recognizes that the Asset Swap and its depreciation implications for AP have not been subject to an extensive review by a depreciation expert. Consistent with Decision
2003-019, the Commission considers that any deficiencies in the data required to conduct a
15
Exhibit 16.02, page 4. 16
Exhibit 21.01. 17
Exhibit 31.01 UCA argument, paragraph 13. 18
Decision 2003-019: Aquila Networks Canada (Alberta) Ltd., 2002/2003 Distribution Tariff, Application No.
1250392, February 28, 2003, page 62. 19
Exhibit 31.01, UCA argument, paragraph 17. 20
Exhibit 33, AP reply argument, pages 1-2.
http://www.auc.ab.ca/applications/decisions/Decisions/2003/2003-019.pdf
Asset Swap Application ATCO Gas and Pipelines Ltd.
8 • AUC Decision 2012-310 (November 22, 2012)
depreciation study, the depreciation method previously employed by NGTL, and the impact of
any required future adjustments to depreciation costs, estimations of life, or net salvage are to be
borne by AP’s shareholders, unless AP is able to justify why customers should bear any
subsequent adjustments. The Commission directs AP to advise the Commission of any material
adjustments to depreciation under consideration or being made (including changes to
environmental liabilities and abandonments) in its next general rate application.
35. The Commission considers that any adverse future consequences resulting from this concern raised by the UCA may be dealt with more effectively in AP’s next general rate
application. Accordingly the Commission is not persuaded that depreciation matters raised by the
UCA are likely to result in harm to AP customers.
4.2 Tranche timing and non-monetary adjustment
36. The Asset Swap transfers assets of approximately equal net book value between AP and NGTL in four tranches (see Appendix 3) over an 18-month period to align asset ownership with
the respective operating areas.21 The value of each of these tranches as at December 31, 2010, is
provided below (these are preliminary values which will be updated at the time of each closing).
Table 1. Asset values to be swapped
NGTL Assets transferring to AP ($millions) AP Assets transferring to NGTL ($millions)
Tranche Historic
cost Accumulated depreciation
Net book value
Tranche Historic
cost Accumulated depreciation
Net book value
1 12.9 -6.1 6.8
1 28.4 -10.8 17.6
2a 96.5 -52.6 43.9
2 32.5 -13.4 19.1
3 19.9 -9.5 10.4
3 6.3 -2.2 4.1
4a 100.3 -45.8 54.5
4 96.3 -22.5 73.8
Total 229.6 -114 115.6
163.5 -48.9 114.6
37. The Asset Swap Agreement also provides for adjustments for tranche closings prior to the final closing to prevent harm to the rate base of either party as a result of the timing and
selection of assets for each tranche closing. These consist of monetary adjustments for
differences in aggregate net book value and also abandonment costs related to the assets already
collected by the transferee. Further, any adjustments required for differences in line pack with
respect to transferred assets will be made pursuant to Article 7.2(b) of the Asset Swap
Agreement.
38. The UCA argued that AP’s proposed asset swap in four tranches could result in rate base additions for AP greater than its retirements during the calendar year. As such, the annual return
could be over and above the amount that would be earned absent the asset swap.22
39. The UCA submitted that it remained unclear how the mechanics of the bilateral agreement between AP and NGTL would affect AP’s filings before the Commission. As shown
in Ms. Radway’s evidence and information request responses on behalf of the UCA, depending
on how the regulatory information is filed, and notwithstanding the presence of the Non-
Monetary Adjustment in the Asset Swap Agreement, the UCA stated that it is possible for AP to
21
Exhibit 1, Application, Attachment 4 Schedule A & Schedule B, pages 19-21. 22
Exhibit 31.01, UCA argument, paragraph 18.
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 9
earn an increased return based on the actual mid-year rate base additions, amounting to between
$1 million and $1.5 million.23 The UCA submitted that to avoid any extra return, inadvertently or
otherwise, and to ensure transparency in the years where the assets are transferred, the AUC
should include a condition preventing AP from earning an increased return as a result of transfer
timing. The UCA added that AP should also be directed to include the reconciliation of the
tranche transfers in subsequent annual regulatory filings. The UCA further submitted that to
ensure transparency, such a reconciliation table should include the capital additions and
retirements on an actual basis as separate line items.24
40. AP submitted that the Non-Monetary Adjustment mechanism would eliminate any differences in the net book value of the rate base additions and retirements as part of the Asset
Swap Agreement. AP stated that the only time when rate base would be impacted by a difference
in the tranche values is at the time of the final asset swap tranche.
41. AP noted that Section 3.3(b) of the Asset Swap Agreement states:
The Non-Monetary Adjustments are intended to ensure no harm to the rate base of either
Party as a result of the timing and selection of Transferred Assets at each Closing.
(emphasis added by AP).
42. AP argued that the Non-Monetary Adjustment mechanism allows the value of the tranches being swapped to be equalized prior to the completion of the Asset Swap and ensures
that the rate bases of AP and NGTL remain unchanged. The UCA’s evidence should therefore be
rejected.25
4.2.1 Commission finding
43. The Commission is satisfied that the Non-Monetary Adjustment mechanism will negate any increased return that might result from the timing of asset tranche transfers with varying net
book values prior to completion of the Asset Swap. The Commission finds that the rebuttal
evidence submitted by AP26 satisfactorily demonstrates that the Non-Monetary Adjustment
mechanism will operate to offset the cumulative difference in the tranche values so that rate base
remains unchanged after the first three tranches. Any difference in rate base will only occur after
the final tranche is completed as a result of the difference between the $115.6 million transferred
from NGTL to AP and the $114.6 million being transferred from AP to NGTL. This will result
in a net $1 million increase in rate base for AP. Even if the Commission were to accept the
UCA’s evidence, any increased return that might occur should be weighed against the forecast
benefit or savings27 associated with Integration. Given the expected monetary benefit of
Integration, the Commission expects any resulting marginal increase in return will be immaterial.
The UCA’s recommendation regarding the inclusion of a condition preventing AP from earning
an increased return as a result of transfer timing is therefore unnecessary and is rejected.
44. The Commission concurs with the UCA’s submission that AP should file a reconciliation of each of the tranche transfers, similar in format to that shown in the tables included in AP’s
23
Exhibit 23.03, paragraph A10 and Exhibits 29.01 and 29.03 re: AUC-UCA-1(a) and (b). 24
Exhibit 31.01, UCA argument, paragraphs 22-24. 25
Exhibit 32.01, AP argument, paragraph 14. 26
Exhibits 30.01 and 30.02. 27
Exhibit 1, application, paragraph 11, net cumulative savings for the period from 2010 through 2017 to
customers are $41.3 million.
Asset Swap Application ATCO Gas and Pipelines Ltd.
10 • AUC Decision 2012-310 (November 22, 2012)
rebuttal evidence. This will help to monitor the progress of the asset swap and serve as a check
that the Non-Monetary Adjustment mechanism is functioning as represented by AP. The
Commission directs AP to submit the reconciliation of the tranche transfers upon the closing of
each tranche and also as part of the subsequent general rate application(s) and the subsequent
Rule 005: Annual Reporting Requirements of Financial and Operational Results (Rule 005)
annual regulatory filings. To ensure transparency, the reconciliation tables should include the
capital additions and retirements on an actual basis as separate line items.28
4.3 Income tax and other costs
45. The UCA expressed concerns that AP identified increased income tax as a consequence of the Asset Swap, due to different capital cost allowances between the incoming and exiting
assets, and that AP proposed to capture these extra expenditures in the “Integration deferral
account”.29 As part of its evidence30 the UCA submitted the following concerns with this
proposal:
It is not clear that the “Integration deferral account” currently exists.
Decision 2010-228 notes that AP stated in an Information Request response that it “may” have an “Integration deferral account” in 2010 resulting from AP’s Negotiated
Settlement with regard to its 2010-2012 General Rate Application (GRA) Phase I –
but that is not the approval of an actual deferral account.
The Settlement’s treatment of income taxes does not consider a deferral account.
Using a deferral account to broadly capture income tax (or other material costs) without any sense of their magnitude does not allow the Commission to apply the “no
harm test” to the transfer of a regulatory asset, required under s. 26(2)(d)(i) of the
Gas Utilities Act .
Upon disposition, a deferral account would represent an increased cost to AP ratepayers that will have to be paid at some point, contrary to the Alberta System
Integration Agreement.
46. In order to assess harm, the UCA submitted that there must be full disclosure and transparency in the sale of any regulated asset. The UCA argued that there must be full
disclosure of costs included in AP’s Integration deferral account, and absent that transparency,
costs such as income tax should not be approved for inclusion in AP’s Integration deferral
account.
47. To ensure that the Asset Swap’s benefits to customers are not significantly eroded, the UCA submitted that the Commission should condition any approval of the present application on
the basis that increased AP customer costs, which are neither included in the application’s net
present value calculation nor offset by a matching benefit from the NGTL system, should be
borne by AP’s shareholders and not its customers.
48. AP indicated that its proposed treatment of the increase in income taxes due to lower capital cost allowance deduction claims resulting from the Asset Swap is consistent with the
spirit and intent of the Integration Agreement. Section 5.1(a) of the Integration Agreement states:
The swap of assets will not affect the revenue requirement of either Party.
28
Exhibit 31.01, UCA argument, paragraphs 22-24. 29
Exhibit 20.01, AUC-AP-7(f). 30
Exhibit 25.03, UCA evidence A16 and A17.
http://www.auc.ab.ca/acts-regulations-and-auc-rules/rules/Pages/Rule005.aspx
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 11
AP added that Section 5.1(b) (ii) of the Integration Agreement further states:
… the intent that neither Party is to be negatively impacted by such swap …
49. AP argued that the charges in the deferral account will be completely offset by tax deductions for NGTL.31
50. AP argued that the UCA’s submission was entirely inappropriate for a number of reasons. First, it amounted to requiring AP to “guarantee” the savings that will result from integration.
That had never been part of the Integration equation, nor had AP’s return been premised on any
such risk. Imposing such a risk would certainly have return implications. Further, the condition
requested by the UCA places non-symmetrical risk on AP. AP submitted that the UCA was
seeking to have the Commission make rate determinations that may affect a number of
stakeholders. AP did not consider the current process was the proper forum to make such a
determination and potentially affected parties had not had notice that such issues may be raised.
The proper forum for determining AP's revenue requirement is a rate proceeding where all
relevant facts are before the Commission and all interested parties have an opportunity to
participate.32
4.3.1 Commission finding
51. Section 5.1(a) and Section 5.1(b) (ii) of the Integration Agreement indicates that neither party is intended to be impacted by the swap of assets between parties. The Commission is
mindful of the submission of the UCA that “[u]sing a deferral account to broadly capture income
tax costs (or other material costs) without any sense of their magnitude does not allow the
Commission to apply the “no harm test” to the transfer of a regulatory asset,33 required under s.
26(2)(d)(i) of the Gas Utilities Act (GUA)”. The Commission accepts AP’s contention that any
increase in income taxes for AP as a result of reduced capital cost allowance deductions will be
offset by a corresponding decrease for NGTL, all other things being equal. Even though this
means that the revenue requirements for each of AP and NGTL may be affected by the Asset
Swap, the overall combined revenue requirements are not likely to be materially impacted and it
is this combined revenue requirement which is used in determining customers’ rates. As such,
customers are not likely to be harmed by a potential increase in AP’s income taxes associated
with the Asset Swap as the combined revenue requirement and rates are essentially unchanged.
52. With respect to the UCA’s submission that it is not clear that an Integration deferral account was approved by the Commission, Decision 2010-228 states:
“Flow through” items are items that either: (i) have offsetting revenues and expenses (e.g.
franchise fees); or (ii) have the difference between the actual amount and forecast amount
placed in a deferral account for collection from or refund to customers at a later time (e.g.
hearing costs, Integration costs/savings).34
53. Although Decision 2010-228 may not have explicitly approved an Integration deferral account, the Commission approved the Settlement as filed which contained the above section. As
31
Exhibit 32.01, AP argument, paragraph 20. 32
Exhibit 33.01, AP reply argument, paragraph 21. 33
Decision 2000-41, as cited in Exhibit 1, application, paragraph 52. 34
Decision 2010-228, paragraph 37.
Asset Swap Application ATCO Gas and Pipelines Ltd.
12 • AUC Decision 2012-310 (November 22, 2012)
a result, the Commission considers that creation of an Integration deferral account was therefore
implicitly approved. The Commission is satisfied that AP’s proposal to capture the extra cost in
the “Integration deferral account” is reasonable. The Commission and interested parties will be
given the opportunity to examine and challenge any extra income tax expenditures when AP files
application to settle the balance in the Integration deferral account. The Commission directs AP
to clearly identify any increased income tax amounts resulting as a consequence of the Asset
Swap in AP’s Integration deferral account approval application.
4.4 Conclusion
54. The Asset Swap Agreement provides for adjustments for tranche closings prior to the final closing to prevent harm to the rate base of either party as a result of the timing and selection
of assets for each closing. These consist of monetary adjustments for differences in aggregate net
book value and also abandonment costs related to the assets already collected by the transferee.
Section 3.3(b) of the Asset Swap Agreement also includes Non-Monetary Adjustments intended
to ensure no harm to the rate base of either party as a result of the timing and selection of
transferred assets at each tranche closing. AP and NGTL also conducted province-wide
landowner and stakeholder information publication and consultation efforts and no formal
objections to the Asset Swap were recorded throughout the process.
55. When evaluating AP’s asset transfer and considering whether the” no harm test” is satisfied, the Commission is mindful of the overall benefits of Integration when weighed against
specific costs identified in the asset transfer approval application. In Decision 2010-228, the
Commission concluded the following with respect to Integration:
Integration eliminates stacked tolls for customers who transport gas in Alberta on both the AP and NGTL pipeline systems, eliminates the need for duplicative terms of service,
and reduces the regulatory burden and costs which result when NGTL and AP compete
for customers in Alberta, often leading to protracted and contentious regulatory
proceedings.35
Integration should enhance the orderly, efficient, and cost effective expansion of the Alberta System in that system planning for an expansion is anticipated to be performed
on a coordinated basis.36
The exclusive footprint areas should lead to efficiencies for facility applications.37
The 2010-2012 GRA Phase I Settlement forecasted cost savings to AP’s customers due to Integration, and reduced business risk for AP.38
Most customers requiring the use of both the AP and NGTL pipeline systems should benefit by the removal of dual or stacked tolls that inhibited cost effective transportation
of gas in the province. However, the rate impact to individual customers will be explored
in NGTL’s rate application to the NEB.39
35
Decision 2010-228, paragraph 131. 36
Decision 2010-228, paragraph 131. 37
Decision 2010-228, paragraph 131. 38
Decision 2010-228, paragraph 131. 39
Decision 2010-228, paragraph 132.
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 13
56. Based on its review of the evidence in this proceeding, the Commission is satisfied that AP has met the requirement of the no harm test, specifically as it relates to concerns regarding
service quality, reliability, and increased costs to customers, which has been applied by the
Commission in determining whether to approve a disposition under Section 26(2)(d) of the Gas
Utilities Act. In reaching its finding on the “no harm test,” the Commission relied significantly
on the assertions in AP’s application:
In applying the no harm test, the Commission first considers if the disposition would
disrupt safe and reliable service to customers or otherwise affect the quality and/or
quantity of services being provided to ratepayers. It is respectfully submitted that the
proposed disposition of the AP Swap Assets in conjunction with Integration will not
disrupt safe and reliable service, nor will it adversely affect the quality and/or quantity of
services being provided to ratepayers. On the contrary, the proposed swap will allow for
the efficiencies and streamlining of service contemplated by Integration to be fully
realized.
........ With respect to the potential for the proposed disposition to adversely impact the
rates customers would otherwise pay, it is respectfully submitted that the proposed
disposition will have no such adverse impact. The proposed disposition involves a swap
of AP assets for NGTL assets of approximately equal value. As such, the respective rate
bases of AP and NGTL remain unchanged as a result of the swap.40
57. The Commission finds that the UCA’s concerns with respect to income tax, increased return due to tranche timing and differences in the net book value of assets transferred between
NGTL and AP, and depreciation, have been adequately addressed by AP. Further the
Commission is satisfied that AP’s landowner and stakeholder engagement adequately informed
affected parties of the intended asset transfer by AP. Nevertheless, the implications of the Asset
Swap for rate-making purposes should not be construed as approved by this decision and remain
subject to further scrutiny and determination in AP’s next general rate application(s).
58. The Commission is also satisfied that AP and NGTL have entered into four operating agreements “to ensure the safe and reliable operation of the pipeline system during the Asset
Swap and on an ongoing basis once the Asset Swap is completed.” The agreements consist of the
following:
i. The Transitional Operating Agreement41
ii. The Long-Term Operating Agreement
iii. The Odourization Agreement
iv. The Cathodic Protection Services Agreement42
59. In response to CAPP-AP-5(i),43 AP explained that it will not be requesting further approvals for the Asset Swap, but will be applying for the required pipeline and facility license
transfers 30 days in advance of the closing of each tranche. The Commission considers that AP’s
40
Exhibit1, application, paragraphs 53 -54. 41
Once all assets are transferred, this agreement will no longer be in effect. 42
Exhibit 1, application, page 14, paragraph 44. 43
Exhibit 19.01.
Asset Swap Application ATCO Gas and Pipelines Ltd.
14 • AUC Decision 2012-310 (November 22, 2012)
proposed timeline to address pipeline and facility license transfers is reasonable. The
Commission directs AP to provide written notice to the AUC that the tranche is ready to close 30
days prior to each tranche closing date in accordance with Section 6(f) of the Transitional
Operating Agreement.
60. AP’s asset transfer to NGTL and related dispositions are approved as filed pursuant to Section 26(2)(d) of the Gas Utilities Act.
4.5 Other - board directions
61. In Decision 2010-228, the Commission directed AP clarify the matter of outstanding directions in its future detailed application for the Asset Swap:
The Commission has compiled a summary of outstanding directions from 2003 to the end
of 2009 (refer to Appendix 5), many of which are ongoing and some applicable to a GRA
Phase II. AP should review and identify those that will be become redundant in the event
Integration receives universal approval and a GRA Phase II or other routine filings
become unnecessary. AP is directed to clarify the matter of outstanding directions in its
future detailed application for the Asset Swap.44
62. The Commission is satisfied that AP’s application complies with the above direction from Decision 2010-228 because it clearly identified the proceedings wherein AP has complied
with outstanding directions, where a direction continues to be an ongoing matter to be addressed
in a future application, and the specific cases where Integration has made the direction moot.
44
Decision 2010-228, page 48, paragraph 179.
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 15
5 Order
63. It is hereby ordered that:
(1) ATCO Gas and Pipelines Ltd.’s asset transfer to Nova Gas Transmission Ltd. and
related disposition is approved as filed pursuant to Section 26(2)(d) of the Gas Utilities
Act and subject to the Commission’s directions in this decision.
Dated on November 22, 2012.
The Alberta Utilities Commission
(original signed by)
Mark Kolesar
Vice-Chair
(original signed by)
Anne Michaud
Commission Member
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 17
Appendix 1 – Proceeding participants
Name of organization (abbreviation) counsel or representative
ATCO Pipelines (AP)
N. Gretener B. Jones S. J. Mah
ATCO Gas (AG)
A. Green M. Bayley
BP Canada Energy Company
C. G. Worthy The City of Calgary
D. Evanchuk M. Rowe H. Johnson
Canadian Association of Petroleum Producers (CAPP)
R. Fairbairn K. Folkins
Encana Corporation
R. Powell D. Dunlop
Lacombe County
T. Hager
NOVA Gas Transmission Ltd. (NGTL)
L. Angus
Office of the Utilities Consumer Advocate (UCA)
R. B. Wallace M. Keen B. Shymanski
The Alberta Utilities Commission Commission Panel
M. Kolesar, Vice-Chair A. Michaud, Commission Member
Commission Staff
J. Petch (Commission counsel) M. McJannet R. Armstrong, P.Eng. N. Mahbub D. Mitchell L. Ou
Asset Swap Application ATCO Gas and Pipelines Ltd.
18 • AUC Decision 2012-310 (November 22, 2012)
Appendix 2 – Summary of Commission directions
This section is provided for the convenience of readers. In the event of any difference between
the directions in this section and those in the main body of the decision, the wording in the main
body of the decision shall prevail.
1. The Commission recognizes that the Asset Swap and its depreciation implications for AP have not been subject to an extensive review by a depreciation expert. Consistent with
Decision 2003-019, the Commission considers that any deficiencies in the data required
to conduct a depreciation study, the depreciation method previously employed by NGTL,
and the impact of any required future adjustments to depreciation costs, estimations of
life, or net salvage are to be borne by AP’s shareholders, unless AP is able to justify why
customers should bear any subsequent adjustments. The Commission directs AP to advise
the Commission of any material adjustments to depreciation under consideration or being
made (including changes to environmental liabilities and abandonments) in its next
general rate application. ................................................................................... Paragraph 34
2. The Commission concurs with the UCA’s submission that AP should file a reconciliation of each of the tranche transfers, similar in format to that shown in the tables included in
AP’s rebuttal evidence. This will help to monitor the progress of the asset swap and serve
as a check that the Non-Monetary Adjustment mechanism is functioning as represented
by AP. The Commission directs AP to submit the reconciliation of the tranche transfers
upon the closing of each tranche and also as part of the subsequent general rate
application(s) and the subsequent Rule 005: Annual Reporting Requirements of Financial
and Operational Results (Rule 005) annual regulatory filings. To ensure transparency, the
reconciliation tables should include the capital additions and retirements on an actual
basis as separate line items. ............................................................................. Paragraph 44
3. Although Decision 2010-228 may not have explicitly approved an Integration deferral account, the Commission approved the Settlement as filed which contained the above
section. As a result, the Commission considers that creation of an Integration deferral
account was therefore implicitly approved. The Commission is satisfied that AP’s
proposal to capture the extra cost in the “Integration deferral account” is reasonable. The
Commission and interested parties will be given the opportunity to examine and
challenge any extra income tax expenditures when AP files application to settle the
balance in the Integration deferral account. The Commission directs AP to clearly
identify any increased income tax amounts resulting as a consequence of the Asset Swap
in AP’s Integration deferral account approval application. ............................. Paragraph 53
4. In response to CAPP-AP-5(i), AP explained that it will not be requesting further approvals for the Asset Swap, but will be applying for the required pipeline and facility
license transfers 30 days in advance of the closing of each tranche. The Commission
considers that AP’s proposed timeline to address pipeline and facility license transfers is
reasonable. The Commission directs AP to provide written notice to the AUC that the
tranche is ready to close 30 days prior to each tranche closing date in accordance with
Section 6(f) of the Transitional Operating Agreement. ................................... Paragraph 59
http://www.auc.ab.ca/acts-regulations-and-auc-rules/rules/Pages/Rule005.aspx
Asset Swap Application ATCO Gas and Pipelines Ltd.
AUC Decision 2012-310 (November 22, 2012) • 19
Appendix 3 – Tranche Timing and Asset Swap Map
(return to text)
Appendix 3 - Tranche Timing
(consists of 3 pages)
Appendix 3 - Asset Swap Map
(consists of 1 pages)
- 4 -
Phases Site Pre-Closing Activities Responsibilities Phase V-VII None anticipated Not applicable 9. Diagram of Pre-Closing Activities
The following diagram illustrates the Pre-Closing Activities:
Transferring Party is Owner
Receiving Party is Owner
Time
Month 0
Month 6
Month 8
Month 9
AUC / NEBApproval
PreliminaryEng. Design
ATCO – TCPL Project Launch, Site
discovery and Project Execution Plan
Tranche 1
Phase I -Tranche planning
and detailed site Design
Procurementbegins Phase II -
ConfigurationFAT
(Testing) Phase VI -AUC / NEB
30 daynotification
Phase III -Initial Acceptance
Checklist-processed for
each site
Site FacilityOwnership
Site FacilityOperator
Phase VII -Tranche Closes
Transferring Party is Operator Receiving Party is Operator
Receiving Party is Operator
Receiving Party is Operator
Phase IV -Site
Commissioning
Phase V -Acceptance
Checklist Processed
Pre-Closing Activities
Future Tranches 2-4...
Diagram of Pre-Closing Activities
Both Parties*Receiving Party is Operator
Both Parties*
Transferring Party is OperatorBoth Parties*
Both Parties*
Transferring Party is OperatorBoth Parties*
Both Parties*Both Parties*
Transferring Party is OperatorBoth Parties*
Project KickoffProject Execution
Plan start
*Both Parties- During this time, Transferring Party operates equipment it owns; Receiving Party operates gas control and equipment installed during
Pre-Closing Activities
Project Close out
Legend
Transferring Party
Receiving Party
60-90 days per Tranche
ATCO PipelinesAsset Swap Application - Attachment 4
February 15, 2012
Page 19 of 21
Asset Swap Application
ATCO Gas and Pipelines Ltd. Appendix 3 - Tranche Timing Page 1 of 3
AUC Decision 2012-310 (November 22, 2012)
SCHEDULE “B”
Tranche Map
See attached page.
ATCO PipelinesAsset Swap Application - Attachment 4
February 15, 2012
Page 20 of 21
Asset Swap Application
ATCO Gas and Pipelines Ltd. Appendix 3 - Tranche Timing Page 2 of 3
AUC Decision 2012-310 (November 22, 2012)
- 2 -
ATCO PipelinesAsset Swap Application - Attachment 4
February 15, 2012
Page 21 of 21
Asset Swap Application
ATCO Gas and Pipelines Ltd. Appendix 3 - Tranche Timing Page 3 of 3
AUC Decision 2012-310 (November 22, 2012)
NATIONAL PARK
GLACIER
PROV. PARK
MACKLIN
SPARW OOD
KOOTENAY
NATIONAL
YOHO
PARK
NATIONAL
PARK
GLACIER
PARK
NATIONAL
ELK LAKES
THE W ORLD
TOP OF
PROV. PARK
MARY’S
PROV. PARK
MT. ASSINIBOINE
ST.
PARK
ALPINE
PROV. PARK
PROV. PARK
GLACIER
HAMBER
PROV. PARK
KOKANEE
PROVINCIAL
PARK
PROVINCIAL
MT. ROBSON
PARK
W ELLS GRAY
CRANBROOKFERNIE
CASTLEGAR
KIMBERLEY
ROSSLAND
NELSON
TRAIL
CRESTON
GOLDEN
ST.JOHN
DAW SON
FORT
CREEK
RIVER
CLEARW ATER
PROVINCIAL PARK
LAKEMEADOW
PARKPROVINCIAL
URANIUM
FORT SMITH
CITY
River
Saskatchewan
River
Lake
Ministikwan
Lake
Bronson
Reflex
Lakes
Bitter
Lake
Cabri Lake
Manito
L.
Riv
er
Tho
mpson
River
Colu
mbia
North
River
Fraser
River
River
Kootenay
River
River
Pend
River
Kootenay
d’Oreille
Kootenay
Th
om
pso
n
Kootenay
R.
Reach
ArmSullivan
Bush
Arm
Arm
Wood
Columbia
Adams
Lake
Duncan
Upper
Lake
Lake
Lake
Slocan
Arrow
Koocanusa
Lake
Kootenay
Lake
Revelstoke
Lake
Kinbasket
Kinbasket
Lake
Lake
LakeRevelstoke
Pine
R.
cP
e
ee
Rvi
a
r
Lake
Kwokwullie
Lake
Buffalo
Kotcho
Lake
Tazin
R.
R.
Tazin
Lake
Preston
Bartlett
LakeArchibald
L.
Tsalwor Lake
Vermette
Carswell
Lake
L.
Lloyd L.
Forrest L.
Patterson
Dillon
Lake
Lake
Tazin
Lake
Peter
Pond
Lake
Primrose
Lake
La
Loche
Lac
5
5
16
16
1
1
1
54°
53°
52°
51°
50°
49°
110°111°112°113°114°115°
53°
52°
51°
50°
49°
120° 119° 118° 117° 116°
55°
60°
59°
58°
57°
56°
121° 120° 119° 118° 117° 116° 115° 114° 113° 112° 111° 110° 109°
60°
59°
58°
57°
56°
55°
54°
W
O
S
AC
N A
E
K
AH
ST
M
N
T N
A
AH OIW ASHINGTON D A
AM
R
B
I H
I
TS
UC
B
O
I
L
I
T E
L
A
S
B
I
U
WO
I
R
R
C
M
HT
H
B
T
S
N
O
E
A
R
W
AS
K
R
C
N
SETR
H
A
T E IO
S
T
I
89
26
55
14
7
3
17 15
13
31
40
43
17
17
51
44
21
26
321
371
232
93
23
6
95
31
95
23
93
31
23
6
31
3A
21
3B
23
6
3
93
9593
1
95
3
95
3A
93
6
93
25
3A
95A
31A
29
97
1
2
97
5
5
955
955
1
1
AT
HA
BA
S C
A
16
I.R. 123
Louis Bull
Lake
128
Valley
I.R. 137
I.R. 133A
Wabamun
Samson
Ermineskin
White
Alexander
Stoney
139
I.R. 147B
Makaoo
Cold
Kehewin
Wabamun I.R. 133B
I.R. 138A
I.R. 121
Eden
I.R. 148A
Fish
I.R. 216
I.R. 138B
I.R. 149
I.R.
Blood
I.R.
142 143 144
Valley
I.R. 216
I.R. 137 Samson
Alexis
Eden
Unipouheous
I.R. 142B
I.R. 120
I.R.
I.R. 133
Stoney
Puskiakiwenin
Lake
Montana
Samson
I.R. 134
I.R. 138Buck Lake
I.R. 137A
I.R. 133C
Pigeon Lake
I.R. 122
I.R. 125
Saddle Lake
I.R. 145
Blood
I.R. 147
I.R. 146
Siksika
I.R. 148
C.F.B.
W AINW RIGHT
SUFFIELD
C.F.B.
LAKES
PARK
ELK ISLAND
NAT.
PARK
W ATERTON
NATIONAL
CYPRESS HILLS
LLOYDMINSTER
CAMROSE
W ETASKIW IN
RED DEER
MEDICINE HAT
ST. ALBERT
LETHBRIDGE
SASKATCHEW AN
LEDUC
GROV E
AIRDRIE
FORT
SPRUCE
CALGARY
EDMONTON
R
I
D
M
IA
II
IA
TH
DE
N
N
F O U R T H
FF
R
EM
LAMONT
OKOTOKS
PICTURE
PLAIN
PASS
ROCKY
CASTOR
MUNDARE
GRANUM
MAGRATH
CREEK
SEDGEW ICK
CALMAR
HIGH RIV ER
REDCLIFF
SMOKY
HANNA
BOW ISLAND
DIDSBURY
LAKE
DEV ON
NANTON
CARSTAIRS
V ERMILION
COCHRANE
STONY
TOFIELD
ELK POINT
CLARESHOLM
BUTTE
RIMBEY
BEAUMONT
V ULCAN
ST. PAUL
MORINV ILLE
REDW ATER
CORONATION
LAKE
BLACK DIAMOND
V EGREV ILLE
SYLV AN
THREE
KILLAM
HOUSE
BRUDERHEIM
PENHOLD
COALDALE
BLACKFALDS
DAYSLAND
ECKV ILLE
BASSANO
FORT
HILLS
PROV OST
PINCHER
V AUXHALL
OLDS
CROW SNEST
BROOKS
BARRHEAD
COALHURST
TW O HILLS
LACOMBE
TROCHU
MILLET
TURNER V ALLEY
OYEN
CHESTER
MERE
BASHAW
STRATHMORE
GIBBONS
BO
NN
YVIL
LE
V IKING
CROSSFIELD
BON
BOW DEN
W AINW RIGHT
SUNDRE
HARDISTY
CARDSTON MILK RIV ER
MACLEOD
ACCORD
TABER
RAYMOND
STETTLER
STAV ELY
INNISFAIL
MOUNTAIN
W ESTLOCK
PONOKA
217
24
28
20
9
44
6
31
10
2
50
18
15
56
45
35
3
11
47
47
43
5
6
33
14
18
1
41
8
26
52
49
55
60
3
56
19 16
46
11
19
1
25
9
6
27
62
2
17
8
14
5
3
18
38
23 41
37
39
20
5
2
34
46
20
19
4
4
59
11
8
16
36
22 21
13
53
10
62
6
15
6
12
27
29
26
42
59
61
54
11
4
58
3
37
1
28
21
7
24
48
36
115
35
45
17
32
57
29
31
24
49
27
40
14
20
30
28
53
22
26
7
50
28
4
39
7
51
48
51
93
3
15
5
43
44
34
4
7
33
29
25
10
58
25
60
27
8
61
18
13
12
30
7
55
2312
57
21
22
13
12
5
136
19
1416
10
54
32
21
17
26
40
2 1
23
4
k
h
River
c
a
Deer
h
Bow
a
h
River
n
S
h
River
Riv
er
w
Deer
c
S
Old
man
t
a
e
River
Bow
North
South
t
O
w
c
s
Deer
d
a
n
River
t
River
River
River
Red
River
k
wa
n
s
R.
n
s
Red
River
Deer
ka
t
l
Red
Red
m
a
n
e
a
Sout
h
River
a
S
e
River
a
a
ka
w
S
s
a
Bow
ec
Nort
h
RiverOldman
n
GarnerL.
L
Elkwater L.
gikoC
Keho Lake
Reservoir
St. Mary
L.
Gleniffer
.o
L.Stobart
L.
L.Kehiwin
Marion
LakeMoose
Lake
Gough
Lake Res.
LakeGoodfish
LakeWhitefish
LakeDowling
Travers Reservoir
Little Bow
Tide Lake
Res.
Sylvan Lake
WabamunLake
Lake
Ne
well
Sounding
Lake
Frog
McGregor
Pakowki
Lake
Muriel
Lake
Lake
Lake
Pigeon
Lake
Lake
Gull L.
Beaverhill
Lac Ste.
Sullivan
Lake
Lake
Buff
alo
Anne
PARK
PROV.
Stony Plain
I.R. 135
O’Chiese
Big Horn
I.R. 202
I.R.
O’Chiese
I.R. 203
203
203A
Sunchild
O’Chiese Cemetery
I.R.
I.R. 144A
PARK
BANFF
NATIONAL
JASPER
PARK
NATIONAL
LOUGHEED
PROV. PARK
PETER
PARK
WILDERNESS
WILLMORE
W HITECOURT
BANFF
CANMORE
GRANDE CACHE
EDSON
DRAYTON
HINTON
FOX CREEK
MAYERTHORPE
V ALLEY
61
16 14
58
51
8
59
9
54
17 1320 18
57
52
53
11 10
56
19 12
60
15
62
55
Brazeau
Brazeau
akt
l
n
Rocky
River
e
s
River
o
River
cB
R.
a
River
S a
Athabasca
n
River
wan
h
No
s
Saskatche
R.
Nort
h
b
Atha
basca
r
McLeod
North
t
At
a
R.
t
c
h
wa e
h
k
ac
River
McLeod
a
s
L.
Jasper
L.
Talbot
Canal
BrazeauReservoir
Brazeau
Chip Lake
Lake
AbrahamLake
Brule
ELBOW-SHEEP
WILDLAND
KAKW A WILDLAND
PROV. PARK
Whitecourt
I.R. 232
I.R. 234
CardinalRiver
Elk RiverI.R. 233
Utikoomak Lake
I.R. 213
215
I.R.
Duncans
I.R. 228
209
Drift Pile River
I.R.
Lake
Bistcho Lake
I.R. 150F
I.R. 150D
Boyer
I.R. 154A
I.R. 154B
I.R. 152B
I.R. 212
I.R. 151A
Creek
Amber River
I.R. 226
I.R. 210
I.R. 154
Pakashan
Woodland Cree
I.R. 211
I.R. 164A
John D’Or
Woodland CreeI.R. 227
Clear Hills
Jackfish
Woodland Cree
I.R. 150C
Assineau River
I.R.
Sucker
Upper Hay River
Child Lake
Lakes
Sturgeon
I.R. 152C
Swan River
Point
I.R. 163
I.R. 214
Lake
Horse
Sturgeon Lake
Hay
I.R. 150E
I.R. 150
I.R. 187
Halcro
150A
William McKenzie
Sturgeon Lake
I.R. 155B
I.R. 207
I.R. 151K
I.R. 164
Carcajou Settlement
Zama Lake
PrairieBushe River
PRAIRIE
GRANDE
RN
A
SH
DE
XI
MT
II
FALHER
RIV ER
V ALLEYV IEW
MANNING
HIGH
HIGH
LAKE LEV EL
SEXSMITH
RAINBOW
PEACE
W EMBLEY
FAIRV IEW
McLENNAN
BEAV ERLODGE
PRAIRIE
RIV ER
GRIMSHAW
SPIRIT
71
20
5
13
64
99
12
84
79
19
63
85
13
80
18
118
24
17
8
93
108
120
3
90
11
77
74
7
96
118
65
7
8
97
24
128
9
191
67
204
7
16
1517
105
87
94
115
126
16
9
116
69
102
110
4
13
8
117
82
1425
2
104
125
11
91
72
119
66
510
11
101
86
63
111
23
76
98
23
112
89
92
73
12
81
6
109
107
124
11
122
75
14 9
78
10
83
12
22 21
22
121
9
10
123
114
10
100
262
113
70
21
95
88
15
103
River
River
Smoky
River
River
River
Wapiti
Wapiti
Smoky
Smoky
Peace
iPeace
River
r
aec
P
ev
R
e
Bison
L.
Buffalo Bay
W inagami
Lake
Kimiwan
Lake
Bear L.
L.
Cardina
l
L.
Lake
SaskatoonL.
Lake
Eva
Lubicon
Hay
Wadlin
Giroux
L.
Bay
Auger
Bay
L
g
Zama
rtk
Mr
a
Lake
e
a
ea
Lake
Utikuma
Bistcho Lake
LakeLesser Slave
Utikoomak LakeI.R. 155 Utikoomak
LakeI.R. 155A
I.R. 231Grouard
Freeman I.R. 150BGrouard I.R. 229
Grouard I.R. 230
Tallcree
I.R. 173
Tallcree
I.R. 173A
Fort Vermilion I.R. 173B
Beaver RanchI.R. 163B
BeaverRanch
I.R. 163ABeaver Ranch
I.R. 173C
Wadlin Lake
I.R. 221
131
Dog Head
Clearwater
I.R. 166C
I.R. 174B
I.R. 175
I.R. 194
I.R. 150G
Allison Bay
Sand
Gregoire Lake
Lake
I.R. 166D
Gambler
Chipewyan
I.R. 201G
I.R. 218
Chipewyan
I.R. 166
I.R. 201C
Chipewyan
Wabasca
166A
Charles Lake
Point
I.R. 162
I.R. 224
I.R.
I.R. 176B
I.R. 176
Fox
Cold
Gate
I.R. 225
I.R.
Sawridge
Indian Cemetery
Wabasca
Lake
Chipewyan
Lake
Colin Lake
Old Fort
Namur River
201F
I.R. 150H
Devil’s
I.R. 201E
Fort McKay
I.R.
I.R. 201D
Chipewyan
Chipewyan
I.R. 219
Gregoire
I.R. 167
Wabasca
Chipewyan
Namur River
Gregoire Lake
I.R. 166B
I.R. 176A
I.R. 201A
Beaver
Cornwall Lake
I.R. 217
I.R. 201B
I.R. 220
I.R. 223
I.R. 174A
Wabasca
Jean Baptiste
I.R. 174
Heart Lake
Sawridge
I.R. 183
House River
Janvier
I.R. 178
Wabasca
Lake
I.R. 149B
I.R.
Chipewyan
201
AIR W EAPONS RANGE
COLD LAKE
NATIONAL
PARK
BUFFALO
W OOD
W OOD BUFFALO
D
H
M
AR
F T
H
U
D I
R
A N
IE
F I
I
O
N
T
F
E R
I
M
LAC
LAKE
FORT SMITH
LA BICHE
SLAV E
ATHABASCA
125
79
120
6
9
123
94
93
81
76
1
83
108
5
119
112
88
3
96
1
111
84
74
101
64
125
109
12
100
8
108
87
101
7
82
94
63
100
26
73
92
23
71
78
15
99
126
89
4
21
75
63
5
113
3
74
91
115
2
16
16
104
85
7
1320
67
65
107
80
3
64
106
96
118
11
116
19
89
9
69
66
5 4
109
25
103
15
110
104
23
124
121
126
99
17
91
24
95
8
65
121
22
118
73
17
98
97
14
70
6
19
72
107
22
7
106
95
114
84
122
105
3
79
24
122
11
78
86
2
70
87
97
86
18
71
124
85
82
105
75
5 4
76
1
14
111
115
1320
1
88
66
4
90
10
113
72
67
77
68
110
81
119
114
83
123
103
77
6
117
21
69
102
90
120
102
2
18
112
2
116
92
117
93
12
98
t
h
A
River
Atha
basca
Athabasca
t
b
er
a
River
Peace
River
sa
River
b
Atha
basca
v
c
a
River
a
hc
River
a
A
s
Ri
a
Rvr
iSla
ve
River
Slave
e
McClelland
Lake
L.
Pinehurst
Lake
Lake
Lakes
Fort
Wabasca
Lake
Lake
Lake
Touchwood
Sand
Arch
Colin
Andrew
Lake
L.
Legend
Seibert
Leggo
Lela
nd
Chipewyan L.
Cornwall
Heart
Willow Lake
Gardiner Ls.
Lake
Bay
Old
Conibear
English
Bay
NamL.
ur
Lake
L.
Muskwa
Lake
Beaver
Lake
Island
Thultue
South
Lake
Lake
Lake
Richardson
Lake
Lake
Rock
Charl
es
L.
Lake
st
Lake
Winefred
Baril
Gordon
ao
Peerless
Lake
Garson
Lake
Lake
Lake
Lake
Wentzel
Lake
rWab
cL.
Calling
Lake
ah
N
Graham
Mamawi
Biche
Lac
la
Claire
Lake
I.R. 149A
Winefred Lake
I.R. 194B
I.R. 194ACowper Lake
REGIONAL MUNICIPALITY OF
COLD
LAKE
Cold Lake
Cold
Lake
LEGAL
DRUMHELLER
BENTLEY
LA
KE
HILLSSW AN
S I X T H
M E R I D I A N
FORT MCMURRAY
95
52
AWN
Piikani
Piikani
Tsu T’ina
ATCO Pipelines
TCT
TCT (Nova Ventures)
TRANSMISSION LINES
Alliance Pipeline
INFORMATION THEREON IS MADE .
NO WARRANTY OR REPRESENTATION AS TO THE COMPLETENESS OF SAID MAP OR
PRODUCED BY ATCO Pipelines - GRAPHICS
M ap 1
M ap 3
M ap 2
M ap 4
M ap 5
M ap 10Set of 3
M ap 11
M ap 7
M ap 6
M ap 14
M ap 12
M ap 27
M ap 28M ap 23
M ap 24
M ap 31M ap 30
M ap 29
M ap 32
M ap 35
M ap 33
M ap 34
M ap 37
M ap 38
M ap 36
M ap 19
M ap 20
Set of 3
M ap 17
M ap 15
M ap 49
M ap 43M ap 44
M ap 46
M ap 40
M ap 48
M ap 21
M ap 22
M ap 18
M ap 51
M ap 47
M ap 53
M ap 52
M ap 54
M ap 55
56
M ap
REVISED:
Set of 6
Set of 3
Set of 2
M ap 57
M ap 58Set of 2
Integration Areas
Proposed ATCO Central Area Footprint
1
2
4
2a
4a
3
Proposed Tranches
Set of 2
(2011)INTEGRATION M APFINAL ATCO NGTL
SEPTEMBER 06, 2011
ATCONGTL
NGTLATCO
ATCONGTL
NGTLATCO
BLOCK VALVE
LAC LA NONNE
BLOCK VALVE
TCT TRANSMISSION
P
P
P
273m m MOP 7240kPa
15175
1517615174
PEERS
CREEK RECEIPT
FROM SOUTH CARROT
168m m
11452 11453
1145411455
25100
43 44
2
TO
PE
ER
S S
UC
TIO
N
FR
OM
PE
ER
S D
ISC
HA
RG
E
COMPRESSOR
03-33-53-13-W 5M
24176 26690
24177323m m MOP 6550kPa
16-02-57-3-W 5
12-23-41-19-W 4
273m m MOP 7240kPa
15-35-52-20-W 5
24820
24844
24851
24846 24847
SUNDANCE CREEK
COMPRESSOR
24848
24849
24852
24845
SUNDANCE CREEK
COMPRESSOR TIE-IN
N.E.35-52-20-W 5
273m m MOP 7240kPa
ATCO PipelinesAsset Swap Application - Attachment 3
February 15, 2012
Page 2 of 2
Asset Swap Application
ATCO Gas and Pipelines Ltd. Appendix 3 - Asset Swap Map Page 1 of 1
AUC Decision 2012-310 (November 22, 2012)