+ All Categories
Home > Documents > Decision 2012-310 ATCO Gas and Pipelines Ltd. - AUC · AUC Decision 2012-310 (November 22, 2012)...

Decision 2012-310 ATCO Gas and Pipelines Ltd. - AUC · AUC Decision 2012-310 (November 22, 2012)...

Date post: 13-Feb-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
27
Decision 2012-310 ATCO Gas and Pipelines Ltd. Asset Swap Application November 22, 2012
Transcript
  • Decision 2012-310

    ATCO Gas and Pipelines Ltd.

    Asset Swap Application November 22, 2012

  • The Alberta Utilities Commission

    Decision 2012-310: ATCO Gas and Pipelines Ltd.

    Asset Swap Application

    Application No. 1608166

    Proceeding ID No. 1723

    November 22, 2012

    Published by

    The Alberta Utilities Commission

    Fifth Avenue Place, Fourth Floor, 425 First Street S.W.

    Calgary, Alberta

    T2P 3L8

    Telephone: 403-592-8845

    Fax: 403-592-4406

    Web site: www.auc.ab.ca

    http://www.auc.ab.ca/

  • AUC Decision 2012-310 (November 22, 2012) • i

    Contents

    1 Introduction ........................................................................................................................... 1

    2 Background ........................................................................................................................... 3

    3 Issues ...................................................................................................................................... 5

    4 Discussion of issues ............................................................................................................... 6 4.1 Depreciation ................................................................................................................... 7

    4.1.1 Commission finding .......................................................................................... 7 4.2 Tranche timing and non-monetary adjustment .............................................................. 8

    4.2.1 Commission finding .......................................................................................... 9

    4.3 Income tax and other costs ........................................................................................... 10 4.3.1 Commission finding ........................................................................................ 11

    4.4 Conclusion ................................................................................................................... 12

    4.5 Other - board directions ............................................................................................... 14

    5 Order .................................................................................................................................... 15

    Appendix 1 – Proceeding participants ...................................................................................... 17

    Appendix 2 – Summary of Commission directions .................................................................. 18

    Appendix 3 – Tranche Timing and Asset Swap Map .............................................................. 19

    List of tables

    Table 1. Asset values to be swapped......................................................................................... 8

  • AUC Decision 2012-310 (November 22, 2012) • 1

    The Alberta Utilities Commission

    Calgary, Alberta

    Decision 2012-310

    ATCO Gas and Pipelines Ltd. Application No. 1608166

    Asset Swap Application Proceeding ID No. 1723

    1 Introduction

    1. ATCO Gas and Pipelines Ltd. (AGPL), carrying on business under the trade name ATCO Pipelines (AP), filed an application with the Alberta Utilities Commission (AUC or

    Commission) on February 15, 2012, requesting approval, pursuant to Section 26(2)(d) of the Gas

    Utilities Act, RSA 2000, c. G-5 to transfer certain assets to NOVA Gas Transmission Ltd.

    (NGTL) in exchange for assets of approximately equal net book value from NGTL consistent

    with the terms of an integration agreement between AP and NGTL dated April 7, 2009.

    Integration combines AP and NGTL’s physical assets in Alberta under a single rates and service

    structure that operates assets under a single integrated system. The asset transfer exchanges and

    realigns facilities between AP and NGTL to align asset ownership with their respective operating

    areas.1

    2. The legal requirement for AUC approval of the asset dispositions involved is found in Section 26(2)(d) of the Gas Utilities Act. Section 26(2)(d) of the Gas Utilities Act provides:

    (2) No owner of a gas utility designated under subsection (1) shall

    (d) without the approval of the Commission,

    (i) sell, lease, mortgage or otherwise dispose of or encumber its

    property, franchises, privileges or rights, or any part of it or them,

    or

    (ii) merge or consolidate its property, franchises, privileges or rights,

    or any part of it or them,

    and a sale, lease, mortgage, disposition, encumbrance, merger or

    consolidation made in contravention of this clause is void, but nothing in this

    clause shall be construed to prevent in any way the sale, lease, mortgage,

    disposition, encumbrance, merger or consolidation of any of the property of

    an owner of a gas utility designated under subsection (1) in the ordinary

    course of the owner’s business.

    3. The Commission and its predecessor, the Alberta Energy and Utilities Board (EUB), have traditionally applied a “no harm test” in assessing an application for the disposition of utility

    property under Section 26(2)(d) of the Gas Utilities Act. In the present case, application of the no

    harm test requires the Commission to consider whether any of service quality, service reliability

    or customer rates are likely to be adversely affected by the transfer by AP of assets of

    1 Once integration is completed, AP will own and operate assets located primarily around the Calgary –

    Edmonton corridor (AP Footprint), while NGTL will own and operate assets located in the balance of Alberta

    (NGTL Footprint).

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    2 • AUC Decision 2012-310 (November 22, 2012)

    approximately $114.6 million in net book value in exchange for NGTL assets of approximately

    $115.6 million in net book value.

    4. In this decision, the Commission considers this no harm test in deciding whether to approve this asset transfer; but the cost implications of the application on AP’s revenue

    requirement associated with the exchange or transfer of assets between AP and NGTL is subject

    to further scrutiny in AP’s next general rate application. AP’s rate base and the implications of

    such for rate-making purposes is not determined in this decision but rather will be decided at the

    time of AP’s next rate application.

    5. On February 17, 2012, the Commission issued notice of this application. Any party who wished to intervene in this proceeding was required to file a statement of intent to participate

    (SIP) with the AUC by March 2, 2012.

    6. The Commission received an SIP from the following parties:

    BP Canada Energy Company

    NGTL

    Encana Corporation

    Canadian Association of Petroleum Producers (CAPP)

    Office of the Utilities Consumer Advocate (UCA)

    ATCO Gas, a division of ATCO Gas and Pipelines Ltd.

    The City of Calgary

    7. In their SIP, each of BP Canada Energy Company and Encana Corporation indicated that it had no issues with the application but reserved the right to participate. NGTL supported AP’s

    application and reserved the right to participate. The UCA submitted that it neither opposed nor

    supported the application and expected to file information requests and submit final argument.

    As well, the UCA indicated that it was uncertain whether it would file evidence but reserved the

    right to do so. CAPP, ATCO Gas and The City of Calgary did not object to the application.

    8. Based on the submissions received from parties, the Commission determined that a written proceeding was suitable. Through a series of letters,2 the Commission established a

    process schedule, with argument and reply argument due July 19, 2012 and August 2, 2012

    respectively.

    9. On July 4, 2012, the Commission received an email from Lacombe County that raised concerns regarding the novation of existing crossing agreements applicable to the pipeline assets

    in Lacombe County being exchanged between AP and NGTL.

    10. In a letter dated July 11, 2012, the Commission requested that Lacombe County file a statement of intent to participate if it wanted its July 4, 2012 email to be included and considered

    on the public record of Proceeding ID No. 1723 (ATCO Pipelines Asset Swap application).

    11. In an email dated July 11, 2012, Lacombe County filed its SIP with the AUC. Inadvertently, the SIP was not placed onto the public record of Proceeding ID No. 1723. As a

    result, on October 25, 2012, the AUC requested that Lacombe County refile its SIP.

    2 Exhibits 13.01, 18.01 and 24.01.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 3

    12. On October 26, 2012, Lacombe County refiled its SIP, along with documentation on crossing agreements.

    13. On October 30, 2012, the Commission established a process schedule to address the concerns raised by Lacombe County’s October 26, 2012 SIP regarding the novation of existing

    crossing agreements applicable to the pipeline assets in Lacombe County being exchanged

    between AP and NGTL.

    14. Both NGTL and AP were afforded an opportunity to file a reply submission to address Lacombe County’s SIP and standing in the current proceeding, and provide submissions on

    further process by November 1, 2012. Lacombe County was also given an opportunity to reply to

    any submissions from NGTL and AP by November 5, 2012.

    15. The Commission received a submission from AP on October 31, 2012, followed by a reply from Lacombe County dated November 6, 2012.

    16. Based on the review of submissions from Lacombe County and AP, the Commission ruled on Lacombe County’s submission. In its November 9, 2012 ruling, the Commission found

    that AP’s October 31, 2012 response provided Lacombe County with the assurance sought in its

    SIP, in addition to that already extended in AP’s Landowner Package,3 that novations or

    assignments of such agreements needed for the ongoing operation of the pipeline assets being

    transferred to AP will be properly affected in the ordinary course of conveyancing.

    17. The Commission considers that the record for this proceeding closed on November 9, 2012.

    18. In reaching the determinations contained within this decision, the Commission has considered all relevant materials comprising the record of this proceeding, including the

    evidence and argument provided by each party. Accordingly, references in this decision to

    specific parts of the record are intended to assist the reader in understanding the Commission’s

    reasoning relating to a particular matter and should not be taken as an indication that the

    Commission did not consider all relevant portions of the record with respect to that matter.

    2 Background

    19. In order to streamline the provision of natural gas transmission services and address competitive pipeline issues in Alberta, AP and NGTL entered into the Alberta System

    Integration Agreement dated April 7, 2009 (Integration Agreement).4 The Integration Agreement

    requires AP and NGTL, subject to necessary regulatory approvals, to exchange ownership of

    certain physical assets within distinct operating territories or “footprints” in Alberta (Asset

    Swap), and to work together in Alberta under a single rates and services structure, while

    maintaining separate ownership, management and operation of their own assets (Integration).

    NGTL would be the party that interfaces contractually with customers for regulated gas

    transmission services using the combined regulated AP and NGTL gas transmission systems

    within Alberta (collectively, the Alberta System). AP’s approved revenue requirement would be

    3 Exhibit 20.01, AUC-AP-9(a) attachment.

    4 On September 8, 2008, ATCO Ltd. issued a news release indicating that AP and NGTL had reached a proposed

    agreement to provide seamless natural gas transmission service to customers.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    4 • AUC Decision 2012-310 (November 22, 2012)

    included in NGTL’s revenue requirement through a monthly charge from AP to NGTL. The total

    Alberta System revenue requirement would therefore be composed of the AP revenue

    requirement approved by the Commission and charged to NGTL plus the NGTL revenue

    requirement approved by the National Energy Board (NEB).5 This would form the basis for the

    determination of Alberta System rates and tariffs for all customers. As part of the

    implementation of the Integration, all AP contracts would be transitioned to Alberta System

    contracts with NGTL.

    20. On June 26, 2009, AP filed an application (Integration Application) with the AUC that sought a number of approvals from the Commission with respect to Integration and a request to

    approve AP’s revenue requirement for each of 2010, 2011 and 2012. On April 29, 2009, the

    Commission approved AP’s request to negotiate the revenue requirements for 2010, 2011 and

    2012 and the parties reached a negotiated settlement on the requirements.

    21. In its Integration Application, AP requested that the Commission:

    (i) issue an Order, pursuant to section 22 of the Gas Utilities Act, declaring that Integration is in the public interest and furthers the convenience of the public and to

    provide approval for AP to proceed with implementing Integration

    (ii) approve, pursuant to section 36 of the Gas Utilities Act:

    (a) the AP revenue requirements for 2010, 2011 and 2012, as set out in the

    Negotiated Settlement

    (b) the AP charge payable by NGTL to AP as of the Integration implementation date

    and equal to the AP revenue requirement as approved under (a)

    (iii) approve the transitioning of AP contracts to NGTL Alberta System contracts,

    effective on the Integration implementation date, in accordance with the Integration

    Application, pursuant to sections 22 and 36 of the Gas Utilities Act

    (iv) approve, the sale of AP assets to NGTL to effect a swap of assets between AP and

    NGTL, as reflected in the Integration Agreement; and provide such further and other

    relief as AP may request or the Commission may deem appropriate, pursuant to

    section 26 of the Gas Utilities Act6

    22. In Decision 2010-228,7 the Commission approved AP’s 2010-2012 Negotiated Settlement (Settlement) with regard to its 2010-2012 General Rate Application (GRA) Phase I and

    concluded that the proposal to integrate regulated gas transmission services in Alberta involving

    the AP and NGTL systems was in the public interest and furthered the convenience of the public.

    23. Decision 2010-228 also approved the proposed AP-NGTL asset swap in principle.8 The transitioning of AP contracts to NGTL Alberta System contracts effective on the implementation

    of integration, and a swap of certain assets between AP and NGTL were to be determined in a

    separate proceeding. Contract transitioning was approved in Decision 2011-1609 and the transfer

    5 NGTL is regulated by the NEB.

    6 Proceeding ID No. 223, ATCO Pipelines Alberta, System Integration Application, page 19. 7 Decision 2010-228: ATCO Pipelines 2010-2012 Revenue Requirement Settlement and Alberta System

    Integration, Application No. 1605226, Proceeding ID. 223, May 27, 2010. 8 Decision 2010-228, page 46, paragraph 167.

    9 Decision 2011-160: ATCO Pipelines Contract Transition, Application No. 1606374, Proceeding ID No. 732,

    April 20, 2011. In paragraph 151 Decision 2011-260, AP was directed to notify the Commission of the date that

    AP contracts cease to exist and customer contracts are transitioned to NGTL. In a letter dated August 23, 2011,

    AP advised the Commission that the Integration Implementation date was October 1, 2011.

    http://www.auc.ab.ca/applications/decisions/Decisions/2010/2010-228.pdfhttp://www.auc.ab.ca/applications/decisions/Decisions/2011/2011-160.pdf

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 5

    of certain assets to implement a portion of the asset swap is the subject of the current

    proceeding10 before the Commission.

    24. On August 12, 2010, the NEB also approved Integration in Decision RHW-1-2010. In May 2011, AP and NGTL applied to the Federal Competition Bureau for an advisory opinion

    (and Advance Ruling Certificate) under the Competition Act. On July 8, 2011, the Federal

    Competition Bureau issued a standard “No Action” letter, with no conditions regarding

    Integration and the Asset Swap and requesting notification of the closing date.

    25. AP’s integration with NGTL was effective on October 1, 2011. As of this date, AP no longer invoices customers directly, but instead invoices NGTL monthly, based on AP’s approved

    revenue requirement.11

    26. AP and NGTL entered into an Asset Swap Agreement dated June 15, 2011 (Asset Swap Agreement).12 The key components of the Asset Swap Agreement are as follows:

    it provides for the overall asset transfer to be conducted in one or more tranches (closings)

    it provides for a due diligence process on behalf of the transferee

    it provides for non-monetary adjustments for closings prior to the final closing to ensure no harm to the rate base of either party as a result of the timing and selection of assets for

    each closing

    it provides for monetary adjustments at the final closing for: (i) any difference in aggregate net book value of the assets received by a party; (ii) any expenditures in respect

    of the assets not already included in the value of the assets; and (iii) any abandonment

    costs relating to the assets already collected by the transferee13

    Upon completion of the operational review of all assets within each tranche applications to

    approve transfer of pipeline and facility licenses will be made to the AUC and the NEB

    respectively. The close of each tranche will occur upon the completion of the license transfer of

    each respective tranche.

    3 Issues

    27. Before reaching a determination with respect to approval of AP’s asset transfer and related dispositions, the Commission must address “the no harm test” and the specific concerns

    raised by the UCA:

    1. the treatment of information that will allow accurate depreciation costs to be calculated in the future

    10

    Application No. 1608166, Proceeding ID No. 1723. 11

    Decision 2011-494: ATCO Pipelines 2011 Final Revenue Requirements, Final Rates Filing and Deferral

    Account, Application No. 1607451, Proceeding ID No. 1314, December 20, 2011, page 2. 12

    A copy of the executed Asset Swap Agreement is provided as Attachment 2 to the application. 13

    Exhibit 1, application, page 5, paragraph 15.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    6 • AUC Decision 2012-310 (November 22, 2012)

    2. the potential that AP will earn an additional return on mid-year rate base as a result of the timing of asset tranche transfers

    3. AP income tax treatment under the Asset Swap Agreement

    4 Discussion of issues

    28. The no harm test considers the proposed transaction in the context of both potential financial impacts and service level impacts to customers and has been reviewed in several EUB

    and Commission decisions. The test was summarized in Decision 2000-4114 when the EUB

    stated:

    The Supreme Court of Canada has stated that the Board’s jurisdiction to “safeguard the

    public interest in the nature and quality of the service provided to the community by

    public utilities” is “of the widest proportions.”15

    The Board has also noted that its

    governing legislation provides no explicit guidance for the exercise of the Board’s

    discretion in approving an asset disposition by a designated owner of a public utility.16

    The Board has held that its discretion under essentially similar provisions of the GU Act

    must be exercised according to a “no harm” standard. More specifically, the Board has

    held that it must be satisfied that customers of the utility will experience no adverse

    impact as a result of the reviewable transaction.17

    The Board believes that its duty to ensure the provision of safe and reliable service at just

    and reasonable rates informs its authority to approve an asset disposition by a public

    utility pursuant to Section 91.1(2) of the PUB Act. Therefore, the Board is of the view

    that, subject to those issues which can be dealt with in future regulatory proceedings …,

    it must consider whether the disposition will adversely impact the rates customers would

    otherwise pay and whether it will disrupt safe and reliable service to customers. As

    already noted, the Board also accepts that it must assess potential impacts on customers

    in light of the policy reflected in the EU Act, namely the unbundling of the generation,

    transmission and distribution components of electric utility service and the development

    of competitive markets and customer choice. As a result, rather than simply asking

    whether customers will be adversely impacted by some aspect of the transactions, the

    Board concludes that it should weigh the potential positive and negative impacts of the

    transactions to determine whether the balance favours customers or at least leaves them

    no worse off, having regard to all of the circumstances of the case. If so, then the Board

    considers that the transactions should be approved.

    ________________

    15 ATCO Ltd. v. Calgary Power Ltd. [1982] 2 S.C.R. 557, at 576 (per Estey J.)

    16 Decision U99102, p.7

    17 See Decision U98084, NOVA Corporation, et al., Application for Regulatory Approvals in

    Connection with a Proposed Merger of NOVA Corporation and TransCanada Pipelines

    Limited (May 19,1998), p. 6; Decision U98097, Westcoast Energy Inc. et al., Sale of Shares

    in Centra Gas Alberta Inc. from Westcoast Energy Inc. to AltaGas Services Inc. (June 29,

    1998), p.3; Decision U99102, supra, p.8

    14

    Decision 2000-41: TransAlta Utilities Corporation, Sale of Distribution Business, Application No. 2000051,

    File No. 6404-3, July 5, 2000, pages 7 and 8.

    http://www.auc.ab.ca/applications/decisions/Decisions/2000/2000-41.pdf

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 7

    4.1 Depreciation

    29. In its information request UCA-AP-3(b), the UCA questioned whether AP was aware of the depreciation procedures used by NGTL with respect to the assets being transferred from

    NGTL to AP.15 AP’s response was that AP is generally aware of the depreciation procedures

    NGTL uses to depreciate its assets but has not done an analysis of the specific procedure used in

    relation to the assets to be transferred. AP added that it will be engaging a depreciation expert to

    perform a depreciation study to incorporate the NGTL assets into AP’s asset base.16

    30. The UCA submitted that there is a clear risk that when AP and its depreciation expert(s) conduct future depreciation studies, they will discover the information required for estimating

    the historical and forecast life and net salvage is deficient, incomplete, or otherwise needs to be

    supplemented by information currently held by NGTL.17

    31. The UCA noted that following a similar failure to scrutinize asset data after the transfer of assets from TransAlta to Aquila Networks Canada (Alberta) Ltd. (ANCA), the Commission’s

    predecessor stated in EUB Decision 2003-019:18

    The Board notes ANCA’s comments that it was unaware of the deficiencies in the

    required data for a depreciation study. The Board considers that it was the responsibility

    of ANCA to take all reasonable steps available to it, to ensure that it was able to provide

    a depreciation study when it made the commitment to its customers and stakeholders that

    it would do so.

    32. The UCA argued that AP should at least be requesting NGTL to provide all available information needed to ensure the data being incorporated into AP’s depreciation data matches

    and has integrity. The UCA requested that the Commission make clear in any decision approving

    this application that any associated future harm to customers, such as delayed or expensive

    depreciation studies, incomplete or imprecise estimations of life and net salvage, or ad hoc

    depreciation methods for the transferred assets, will be at the expense of AP and not its

    customers.19

    33. In reply argument, AP submitted that it is taking all prudent steps to acquire and ensure the accuracy of the information and data required to perform a depreciation study and discounted

    the UCA’s concern that NGTL would not cooperate with AP on an ongoing basis with respect to

    matters affecting the Alberta System. AP argued that the Integration Agreement specifically

    contains a “Further Assurances” clause committing the parties to continue working together once

    Integration is implemented.20

    4.1.1 Commission finding

    34. The Commission recognizes that the Asset Swap and its depreciation implications for AP have not been subject to an extensive review by a depreciation expert. Consistent with Decision

    2003-019, the Commission considers that any deficiencies in the data required to conduct a

    15

    Exhibit 16.02, page 4. 16

    Exhibit 21.01. 17

    Exhibit 31.01 UCA argument, paragraph 13. 18

    Decision 2003-019: Aquila Networks Canada (Alberta) Ltd., 2002/2003 Distribution Tariff, Application No.

    1250392, February 28, 2003, page 62. 19

    Exhibit 31.01, UCA argument, paragraph 17. 20

    Exhibit 33, AP reply argument, pages 1-2.

    http://www.auc.ab.ca/applications/decisions/Decisions/2003/2003-019.pdf

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    8 • AUC Decision 2012-310 (November 22, 2012)

    depreciation study, the depreciation method previously employed by NGTL, and the impact of

    any required future adjustments to depreciation costs, estimations of life, or net salvage are to be

    borne by AP’s shareholders, unless AP is able to justify why customers should bear any

    subsequent adjustments. The Commission directs AP to advise the Commission of any material

    adjustments to depreciation under consideration or being made (including changes to

    environmental liabilities and abandonments) in its next general rate application.

    35. The Commission considers that any adverse future consequences resulting from this concern raised by the UCA may be dealt with more effectively in AP’s next general rate

    application. Accordingly the Commission is not persuaded that depreciation matters raised by the

    UCA are likely to result in harm to AP customers.

    4.2 Tranche timing and non-monetary adjustment

    36. The Asset Swap transfers assets of approximately equal net book value between AP and NGTL in four tranches (see Appendix 3) over an 18-month period to align asset ownership with

    the respective operating areas.21 The value of each of these tranches as at December 31, 2010, is

    provided below (these are preliminary values which will be updated at the time of each closing).

    Table 1. Asset values to be swapped

    NGTL Assets transferring to AP ($millions) AP Assets transferring to NGTL ($millions)

    Tranche Historic

    cost Accumulated depreciation

    Net book value

    Tranche Historic

    cost Accumulated depreciation

    Net book value

    1 12.9 -6.1 6.8

    1 28.4 -10.8 17.6

    2a 96.5 -52.6 43.9

    2 32.5 -13.4 19.1

    3 19.9 -9.5 10.4

    3 6.3 -2.2 4.1

    4a 100.3 -45.8 54.5

    4 96.3 -22.5 73.8

    Total 229.6 -114 115.6

    163.5 -48.9 114.6

    37. The Asset Swap Agreement also provides for adjustments for tranche closings prior to the final closing to prevent harm to the rate base of either party as a result of the timing and

    selection of assets for each tranche closing. These consist of monetary adjustments for

    differences in aggregate net book value and also abandonment costs related to the assets already

    collected by the transferee. Further, any adjustments required for differences in line pack with

    respect to transferred assets will be made pursuant to Article 7.2(b) of the Asset Swap

    Agreement.

    38. The UCA argued that AP’s proposed asset swap in four tranches could result in rate base additions for AP greater than its retirements during the calendar year. As such, the annual return

    could be over and above the amount that would be earned absent the asset swap.22

    39. The UCA submitted that it remained unclear how the mechanics of the bilateral agreement between AP and NGTL would affect AP’s filings before the Commission. As shown

    in Ms. Radway’s evidence and information request responses on behalf of the UCA, depending

    on how the regulatory information is filed, and notwithstanding the presence of the Non-

    Monetary Adjustment in the Asset Swap Agreement, the UCA stated that it is possible for AP to

    21

    Exhibit 1, Application, Attachment 4 Schedule A & Schedule B, pages 19-21. 22

    Exhibit 31.01, UCA argument, paragraph 18.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 9

    earn an increased return based on the actual mid-year rate base additions, amounting to between

    $1 million and $1.5 million.23 The UCA submitted that to avoid any extra return, inadvertently or

    otherwise, and to ensure transparency in the years where the assets are transferred, the AUC

    should include a condition preventing AP from earning an increased return as a result of transfer

    timing. The UCA added that AP should also be directed to include the reconciliation of the

    tranche transfers in subsequent annual regulatory filings. The UCA further submitted that to

    ensure transparency, such a reconciliation table should include the capital additions and

    retirements on an actual basis as separate line items.24

    40. AP submitted that the Non-Monetary Adjustment mechanism would eliminate any differences in the net book value of the rate base additions and retirements as part of the Asset

    Swap Agreement. AP stated that the only time when rate base would be impacted by a difference

    in the tranche values is at the time of the final asset swap tranche.

    41. AP noted that Section 3.3(b) of the Asset Swap Agreement states:

    The Non-Monetary Adjustments are intended to ensure no harm to the rate base of either

    Party as a result of the timing and selection of Transferred Assets at each Closing.

    (emphasis added by AP).

    42. AP argued that the Non-Monetary Adjustment mechanism allows the value of the tranches being swapped to be equalized prior to the completion of the Asset Swap and ensures

    that the rate bases of AP and NGTL remain unchanged. The UCA’s evidence should therefore be

    rejected.25

    4.2.1 Commission finding

    43. The Commission is satisfied that the Non-Monetary Adjustment mechanism will negate any increased return that might result from the timing of asset tranche transfers with varying net

    book values prior to completion of the Asset Swap. The Commission finds that the rebuttal

    evidence submitted by AP26 satisfactorily demonstrates that the Non-Monetary Adjustment

    mechanism will operate to offset the cumulative difference in the tranche values so that rate base

    remains unchanged after the first three tranches. Any difference in rate base will only occur after

    the final tranche is completed as a result of the difference between the $115.6 million transferred

    from NGTL to AP and the $114.6 million being transferred from AP to NGTL. This will result

    in a net $1 million increase in rate base for AP. Even if the Commission were to accept the

    UCA’s evidence, any increased return that might occur should be weighed against the forecast

    benefit or savings27 associated with Integration. Given the expected monetary benefit of

    Integration, the Commission expects any resulting marginal increase in return will be immaterial.

    The UCA’s recommendation regarding the inclusion of a condition preventing AP from earning

    an increased return as a result of transfer timing is therefore unnecessary and is rejected.

    44. The Commission concurs with the UCA’s submission that AP should file a reconciliation of each of the tranche transfers, similar in format to that shown in the tables included in AP’s

    23

    Exhibit 23.03, paragraph A10 and Exhibits 29.01 and 29.03 re: AUC-UCA-1(a) and (b). 24

    Exhibit 31.01, UCA argument, paragraphs 22-24. 25

    Exhibit 32.01, AP argument, paragraph 14. 26

    Exhibits 30.01 and 30.02. 27

    Exhibit 1, application, paragraph 11, net cumulative savings for the period from 2010 through 2017 to

    customers are $41.3 million.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    10 • AUC Decision 2012-310 (November 22, 2012)

    rebuttal evidence. This will help to monitor the progress of the asset swap and serve as a check

    that the Non-Monetary Adjustment mechanism is functioning as represented by AP. The

    Commission directs AP to submit the reconciliation of the tranche transfers upon the closing of

    each tranche and also as part of the subsequent general rate application(s) and the subsequent

    Rule 005: Annual Reporting Requirements of Financial and Operational Results (Rule 005)

    annual regulatory filings. To ensure transparency, the reconciliation tables should include the

    capital additions and retirements on an actual basis as separate line items.28

    4.3 Income tax and other costs

    45. The UCA expressed concerns that AP identified increased income tax as a consequence of the Asset Swap, due to different capital cost allowances between the incoming and exiting

    assets, and that AP proposed to capture these extra expenditures in the “Integration deferral

    account”.29 As part of its evidence30 the UCA submitted the following concerns with this

    proposal:

    It is not clear that the “Integration deferral account” currently exists.

    Decision 2010-228 notes that AP stated in an Information Request response that it “may” have an “Integration deferral account” in 2010 resulting from AP’s Negotiated

    Settlement with regard to its 2010-2012 General Rate Application (GRA) Phase I –

    but that is not the approval of an actual deferral account.

    The Settlement’s treatment of income taxes does not consider a deferral account.

    Using a deferral account to broadly capture income tax (or other material costs) without any sense of their magnitude does not allow the Commission to apply the “no

    harm test” to the transfer of a regulatory asset, required under s. 26(2)(d)(i) of the

    Gas Utilities Act .

    Upon disposition, a deferral account would represent an increased cost to AP ratepayers that will have to be paid at some point, contrary to the Alberta System

    Integration Agreement.

    46. In order to assess harm, the UCA submitted that there must be full disclosure and transparency in the sale of any regulated asset. The UCA argued that there must be full

    disclosure of costs included in AP’s Integration deferral account, and absent that transparency,

    costs such as income tax should not be approved for inclusion in AP’s Integration deferral

    account.

    47. To ensure that the Asset Swap’s benefits to customers are not significantly eroded, the UCA submitted that the Commission should condition any approval of the present application on

    the basis that increased AP customer costs, which are neither included in the application’s net

    present value calculation nor offset by a matching benefit from the NGTL system, should be

    borne by AP’s shareholders and not its customers.

    48. AP indicated that its proposed treatment of the increase in income taxes due to lower capital cost allowance deduction claims resulting from the Asset Swap is consistent with the

    spirit and intent of the Integration Agreement. Section 5.1(a) of the Integration Agreement states:

    The swap of assets will not affect the revenue requirement of either Party.

    28

    Exhibit 31.01, UCA argument, paragraphs 22-24. 29

    Exhibit 20.01, AUC-AP-7(f). 30

    Exhibit 25.03, UCA evidence A16 and A17.

    http://www.auc.ab.ca/acts-regulations-and-auc-rules/rules/Pages/Rule005.aspx

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 11

    AP added that Section 5.1(b) (ii) of the Integration Agreement further states:

    … the intent that neither Party is to be negatively impacted by such swap …

    49. AP argued that the charges in the deferral account will be completely offset by tax deductions for NGTL.31

    50. AP argued that the UCA’s submission was entirely inappropriate for a number of reasons. First, it amounted to requiring AP to “guarantee” the savings that will result from integration.

    That had never been part of the Integration equation, nor had AP’s return been premised on any

    such risk. Imposing such a risk would certainly have return implications. Further, the condition

    requested by the UCA places non-symmetrical risk on AP. AP submitted that the UCA was

    seeking to have the Commission make rate determinations that may affect a number of

    stakeholders. AP did not consider the current process was the proper forum to make such a

    determination and potentially affected parties had not had notice that such issues may be raised.

    The proper forum for determining AP's revenue requirement is a rate proceeding where all

    relevant facts are before the Commission and all interested parties have an opportunity to

    participate.32

    4.3.1 Commission finding

    51. Section 5.1(a) and Section 5.1(b) (ii) of the Integration Agreement indicates that neither party is intended to be impacted by the swap of assets between parties. The Commission is

    mindful of the submission of the UCA that “[u]sing a deferral account to broadly capture income

    tax costs (or other material costs) without any sense of their magnitude does not allow the

    Commission to apply the “no harm test” to the transfer of a regulatory asset,33 required under s.

    26(2)(d)(i) of the Gas Utilities Act (GUA)”. The Commission accepts AP’s contention that any

    increase in income taxes for AP as a result of reduced capital cost allowance deductions will be

    offset by a corresponding decrease for NGTL, all other things being equal. Even though this

    means that the revenue requirements for each of AP and NGTL may be affected by the Asset

    Swap, the overall combined revenue requirements are not likely to be materially impacted and it

    is this combined revenue requirement which is used in determining customers’ rates. As such,

    customers are not likely to be harmed by a potential increase in AP’s income taxes associated

    with the Asset Swap as the combined revenue requirement and rates are essentially unchanged.

    52. With respect to the UCA’s submission that it is not clear that an Integration deferral account was approved by the Commission, Decision 2010-228 states:

    “Flow through” items are items that either: (i) have offsetting revenues and expenses (e.g.

    franchise fees); or (ii) have the difference between the actual amount and forecast amount

    placed in a deferral account for collection from or refund to customers at a later time (e.g.

    hearing costs, Integration costs/savings).34

    53. Although Decision 2010-228 may not have explicitly approved an Integration deferral account, the Commission approved the Settlement as filed which contained the above section. As

    31

    Exhibit 32.01, AP argument, paragraph 20. 32

    Exhibit 33.01, AP reply argument, paragraph 21. 33

    Decision 2000-41, as cited in Exhibit 1, application, paragraph 52. 34

    Decision 2010-228, paragraph 37.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    12 • AUC Decision 2012-310 (November 22, 2012)

    a result, the Commission considers that creation of an Integration deferral account was therefore

    implicitly approved. The Commission is satisfied that AP’s proposal to capture the extra cost in

    the “Integration deferral account” is reasonable. The Commission and interested parties will be

    given the opportunity to examine and challenge any extra income tax expenditures when AP files

    application to settle the balance in the Integration deferral account. The Commission directs AP

    to clearly identify any increased income tax amounts resulting as a consequence of the Asset

    Swap in AP’s Integration deferral account approval application.

    4.4 Conclusion

    54. The Asset Swap Agreement provides for adjustments for tranche closings prior to the final closing to prevent harm to the rate base of either party as a result of the timing and selection

    of assets for each closing. These consist of monetary adjustments for differences in aggregate net

    book value and also abandonment costs related to the assets already collected by the transferee.

    Section 3.3(b) of the Asset Swap Agreement also includes Non-Monetary Adjustments intended

    to ensure no harm to the rate base of either party as a result of the timing and selection of

    transferred assets at each tranche closing. AP and NGTL also conducted province-wide

    landowner and stakeholder information publication and consultation efforts and no formal

    objections to the Asset Swap were recorded throughout the process.

    55. When evaluating AP’s asset transfer and considering whether the” no harm test” is satisfied, the Commission is mindful of the overall benefits of Integration when weighed against

    specific costs identified in the asset transfer approval application. In Decision 2010-228, the

    Commission concluded the following with respect to Integration:

    Integration eliminates stacked tolls for customers who transport gas in Alberta on both the AP and NGTL pipeline systems, eliminates the need for duplicative terms of service,

    and reduces the regulatory burden and costs which result when NGTL and AP compete

    for customers in Alberta, often leading to protracted and contentious regulatory

    proceedings.35

    Integration should enhance the orderly, efficient, and cost effective expansion of the Alberta System in that system planning for an expansion is anticipated to be performed

    on a coordinated basis.36

    The exclusive footprint areas should lead to efficiencies for facility applications.37

    The 2010-2012 GRA Phase I Settlement forecasted cost savings to AP’s customers due to Integration, and reduced business risk for AP.38

    Most customers requiring the use of both the AP and NGTL pipeline systems should benefit by the removal of dual or stacked tolls that inhibited cost effective transportation

    of gas in the province. However, the rate impact to individual customers will be explored

    in NGTL’s rate application to the NEB.39

    35

    Decision 2010-228, paragraph 131. 36

    Decision 2010-228, paragraph 131. 37

    Decision 2010-228, paragraph 131. 38

    Decision 2010-228, paragraph 131. 39

    Decision 2010-228, paragraph 132.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 13

    56. Based on its review of the evidence in this proceeding, the Commission is satisfied that AP has met the requirement of the no harm test, specifically as it relates to concerns regarding

    service quality, reliability, and increased costs to customers, which has been applied by the

    Commission in determining whether to approve a disposition under Section 26(2)(d) of the Gas

    Utilities Act. In reaching its finding on the “no harm test,” the Commission relied significantly

    on the assertions in AP’s application:

    In applying the no harm test, the Commission first considers if the disposition would

    disrupt safe and reliable service to customers or otherwise affect the quality and/or

    quantity of services being provided to ratepayers. It is respectfully submitted that the

    proposed disposition of the AP Swap Assets in conjunction with Integration will not

    disrupt safe and reliable service, nor will it adversely affect the quality and/or quantity of

    services being provided to ratepayers. On the contrary, the proposed swap will allow for

    the efficiencies and streamlining of service contemplated by Integration to be fully

    realized.

    ........ With respect to the potential for the proposed disposition to adversely impact the

    rates customers would otherwise pay, it is respectfully submitted that the proposed

    disposition will have no such adverse impact. The proposed disposition involves a swap

    of AP assets for NGTL assets of approximately equal value. As such, the respective rate

    bases of AP and NGTL remain unchanged as a result of the swap.40

    57. The Commission finds that the UCA’s concerns with respect to income tax, increased return due to tranche timing and differences in the net book value of assets transferred between

    NGTL and AP, and depreciation, have been adequately addressed by AP. Further the

    Commission is satisfied that AP’s landowner and stakeholder engagement adequately informed

    affected parties of the intended asset transfer by AP. Nevertheless, the implications of the Asset

    Swap for rate-making purposes should not be construed as approved by this decision and remain

    subject to further scrutiny and determination in AP’s next general rate application(s).

    58. The Commission is also satisfied that AP and NGTL have entered into four operating agreements “to ensure the safe and reliable operation of the pipeline system during the Asset

    Swap and on an ongoing basis once the Asset Swap is completed.” The agreements consist of the

    following:

    i. The Transitional Operating Agreement41

    ii. The Long-Term Operating Agreement

    iii. The Odourization Agreement

    iv. The Cathodic Protection Services Agreement42

    59. In response to CAPP-AP-5(i),43 AP explained that it will not be requesting further approvals for the Asset Swap, but will be applying for the required pipeline and facility license

    transfers 30 days in advance of the closing of each tranche. The Commission considers that AP’s

    40

    Exhibit1, application, paragraphs 53 -54. 41

    Once all assets are transferred, this agreement will no longer be in effect. 42

    Exhibit 1, application, page 14, paragraph 44. 43

    Exhibit 19.01.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    14 • AUC Decision 2012-310 (November 22, 2012)

    proposed timeline to address pipeline and facility license transfers is reasonable. The

    Commission directs AP to provide written notice to the AUC that the tranche is ready to close 30

    days prior to each tranche closing date in accordance with Section 6(f) of the Transitional

    Operating Agreement.

    60. AP’s asset transfer to NGTL and related dispositions are approved as filed pursuant to Section 26(2)(d) of the Gas Utilities Act.

    4.5 Other - board directions

    61. In Decision 2010-228, the Commission directed AP clarify the matter of outstanding directions in its future detailed application for the Asset Swap:

    The Commission has compiled a summary of outstanding directions from 2003 to the end

    of 2009 (refer to Appendix 5), many of which are ongoing and some applicable to a GRA

    Phase II. AP should review and identify those that will be become redundant in the event

    Integration receives universal approval and a GRA Phase II or other routine filings

    become unnecessary. AP is directed to clarify the matter of outstanding directions in its

    future detailed application for the Asset Swap.44

    62. The Commission is satisfied that AP’s application complies with the above direction from Decision 2010-228 because it clearly identified the proceedings wherein AP has complied

    with outstanding directions, where a direction continues to be an ongoing matter to be addressed

    in a future application, and the specific cases where Integration has made the direction moot.

    44

    Decision 2010-228, page 48, paragraph 179.

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 15

    5 Order

    63. It is hereby ordered that:

    (1) ATCO Gas and Pipelines Ltd.’s asset transfer to Nova Gas Transmission Ltd. and

    related disposition is approved as filed pursuant to Section 26(2)(d) of the Gas Utilities

    Act and subject to the Commission’s directions in this decision.

    Dated on November 22, 2012.

    The Alberta Utilities Commission

    (original signed by)

    Mark Kolesar

    Vice-Chair

    (original signed by)

    Anne Michaud

    Commission Member

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 17

    Appendix 1 – Proceeding participants

    Name of organization (abbreviation) counsel or representative

    ATCO Pipelines (AP)

    N. Gretener B. Jones S. J. Mah

    ATCO Gas (AG)

    A. Green M. Bayley

    BP Canada Energy Company

    C. G. Worthy The City of Calgary

    D. Evanchuk M. Rowe H. Johnson

    Canadian Association of Petroleum Producers (CAPP)

    R. Fairbairn K. Folkins

    Encana Corporation

    R. Powell D. Dunlop

    Lacombe County

    T. Hager

    NOVA Gas Transmission Ltd. (NGTL)

    L. Angus

    Office of the Utilities Consumer Advocate (UCA)

    R. B. Wallace M. Keen B. Shymanski

    The Alberta Utilities Commission Commission Panel

    M. Kolesar, Vice-Chair A. Michaud, Commission Member

    Commission Staff

    J. Petch (Commission counsel) M. McJannet R. Armstrong, P.Eng. N. Mahbub D. Mitchell L. Ou

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    18 • AUC Decision 2012-310 (November 22, 2012)

    Appendix 2 – Summary of Commission directions

    This section is provided for the convenience of readers. In the event of any difference between

    the directions in this section and those in the main body of the decision, the wording in the main

    body of the decision shall prevail.

    1. The Commission recognizes that the Asset Swap and its depreciation implications for AP have not been subject to an extensive review by a depreciation expert. Consistent with

    Decision 2003-019, the Commission considers that any deficiencies in the data required

    to conduct a depreciation study, the depreciation method previously employed by NGTL,

    and the impact of any required future adjustments to depreciation costs, estimations of

    life, or net salvage are to be borne by AP’s shareholders, unless AP is able to justify why

    customers should bear any subsequent adjustments. The Commission directs AP to advise

    the Commission of any material adjustments to depreciation under consideration or being

    made (including changes to environmental liabilities and abandonments) in its next

    general rate application. ................................................................................... Paragraph 34

    2. The Commission concurs with the UCA’s submission that AP should file a reconciliation of each of the tranche transfers, similar in format to that shown in the tables included in

    AP’s rebuttal evidence. This will help to monitor the progress of the asset swap and serve

    as a check that the Non-Monetary Adjustment mechanism is functioning as represented

    by AP. The Commission directs AP to submit the reconciliation of the tranche transfers

    upon the closing of each tranche and also as part of the subsequent general rate

    application(s) and the subsequent Rule 005: Annual Reporting Requirements of Financial

    and Operational Results (Rule 005) annual regulatory filings. To ensure transparency, the

    reconciliation tables should include the capital additions and retirements on an actual

    basis as separate line items. ............................................................................. Paragraph 44

    3. Although Decision 2010-228 may not have explicitly approved an Integration deferral account, the Commission approved the Settlement as filed which contained the above

    section. As a result, the Commission considers that creation of an Integration deferral

    account was therefore implicitly approved. The Commission is satisfied that AP’s

    proposal to capture the extra cost in the “Integration deferral account” is reasonable. The

    Commission and interested parties will be given the opportunity to examine and

    challenge any extra income tax expenditures when AP files application to settle the

    balance in the Integration deferral account. The Commission directs AP to clearly

    identify any increased income tax amounts resulting as a consequence of the Asset Swap

    in AP’s Integration deferral account approval application. ............................. Paragraph 53

    4. In response to CAPP-AP-5(i), AP explained that it will not be requesting further approvals for the Asset Swap, but will be applying for the required pipeline and facility

    license transfers 30 days in advance of the closing of each tranche. The Commission

    considers that AP’s proposed timeline to address pipeline and facility license transfers is

    reasonable. The Commission directs AP to provide written notice to the AUC that the

    tranche is ready to close 30 days prior to each tranche closing date in accordance with

    Section 6(f) of the Transitional Operating Agreement. ................................... Paragraph 59

    http://www.auc.ab.ca/acts-regulations-and-auc-rules/rules/Pages/Rule005.aspx

  • Asset Swap Application ATCO Gas and Pipelines Ltd.

    AUC Decision 2012-310 (November 22, 2012) • 19

    Appendix 3 – Tranche Timing and Asset Swap Map

    (return to text)

    Appendix 3 - Tranche Timing

    (consists of 3 pages)

    Appendix 3 - Asset Swap Map

    (consists of 1 pages)

  • - 4 -

    Phases Site Pre-Closing Activities Responsibilities Phase V-VII None anticipated Not applicable 9. Diagram of Pre-Closing Activities

    The following diagram illustrates the Pre-Closing Activities:

    Transferring Party is Owner

    Receiving Party is Owner

    Time

    Month 0

    Month 6

    Month 8

    Month 9

    AUC / NEBApproval

    PreliminaryEng. Design

    ATCO – TCPL Project Launch, Site

    discovery and Project Execution Plan

    Tranche 1

    Phase I -Tranche planning

    and detailed site Design

    Procurementbegins Phase II -

    ConfigurationFAT

    (Testing) Phase VI -AUC / NEB

    30 daynotification

    Phase III -Initial Acceptance

    Checklist-processed for

    each site

    Site FacilityOwnership

    Site FacilityOperator

    Phase VII -Tranche Closes

    Transferring Party is Operator Receiving Party is Operator

    Receiving Party is Operator

    Receiving Party is Operator

    Phase IV -Site

    Commissioning

    Phase V -Acceptance

    Checklist Processed

    Pre-Closing Activities

    Future Tranches 2-4...

    Diagram of Pre-Closing Activities

    Both Parties*Receiving Party is Operator

    Both Parties*

    Transferring Party is OperatorBoth Parties*

    Both Parties*

    Transferring Party is OperatorBoth Parties*

    Both Parties*Both Parties*

    Transferring Party is OperatorBoth Parties*

    Project KickoffProject Execution

    Plan start

    *Both Parties- During this time, Transferring Party operates equipment it owns; Receiving Party operates gas control and equipment installed during

    Pre-Closing Activities

    Project Close out

    Legend

    Transferring Party

    Receiving Party

    60-90 days per Tranche

    ATCO PipelinesAsset Swap Application - Attachment 4

    February 15, 2012

    Page 19 of 21

    Asset Swap Application

    ATCO Gas and Pipelines Ltd. Appendix 3 - Tranche Timing Page 1 of 3

    AUC Decision 2012-310 (November 22, 2012)

  • SCHEDULE “B”

    Tranche Map

    See attached page.

    ATCO PipelinesAsset Swap Application - Attachment 4

    February 15, 2012

    Page 20 of 21

    Asset Swap Application

    ATCO Gas and Pipelines Ltd. Appendix 3 - Tranche Timing Page 2 of 3

    AUC Decision 2012-310 (November 22, 2012)

  • - 2 -

    ATCO PipelinesAsset Swap Application - Attachment 4

    February 15, 2012

    Page 21 of 21

    Asset Swap Application

    ATCO Gas and Pipelines Ltd. Appendix 3 - Tranche Timing Page 3 of 3

    AUC Decision 2012-310 (November 22, 2012)

  • NATIONAL PARK

    GLACIER

    PROV. PARK

    MACKLIN

    SPARW OOD

    KOOTENAY

    NATIONAL

    YOHO

    PARK

    NATIONAL

    PARK

    GLACIER

    PARK

    NATIONAL

    ELK LAKES

    THE W ORLD

    TOP OF

    PROV. PARK

    MARY’S

    PROV. PARK

    MT. ASSINIBOINE

    ST.

    PARK

    ALPINE

    PROV. PARK

    PROV. PARK

    GLACIER

    HAMBER

    PROV. PARK

    KOKANEE

    PROVINCIAL

    PARK

    PROVINCIAL

    MT. ROBSON

    PARK

    W ELLS GRAY

    CRANBROOKFERNIE

    CASTLEGAR

    KIMBERLEY

    ROSSLAND

    NELSON

    TRAIL

    CRESTON

    GOLDEN

    ST.JOHN

    DAW SON

    FORT

    CREEK

    RIVER

    CLEARW ATER

    PROVINCIAL PARK

    LAKEMEADOW

    PARKPROVINCIAL

    URANIUM

    FORT SMITH

    CITY

    River

    Saskatchewan

    River

    Lake

    Ministikwan

    Lake

    Bronson

    Reflex

    Lakes

    Bitter

    Lake

    Cabri Lake

    Manito

    L.

    Riv

    er

    Tho

    mpson

    River

    Colu

    mbia

    North

    River

    Fraser

    River

    River

    Kootenay

    River

    River

    Pend

    River

    Kootenay

    d’Oreille

    Kootenay

    Th

    om

    pso

    n

    Kootenay

    R.

    Reach

    ArmSullivan

    Bush

    Arm

    Arm

    Wood

    Columbia

    Adams

    Lake

    Duncan

    Upper

    Lake

    Lake

    Lake

    Slocan

    Arrow

    Koocanusa

    Lake

    Kootenay

    Lake

    Revelstoke

    Lake

    Kinbasket

    Kinbasket

    Lake

    Lake

    LakeRevelstoke

    Pine

    R.

    cP

    e

    ee

    Rvi

    a

    r

    Lake

    Kwokwullie

    Lake

    Buffalo

    Kotcho

    Lake

    Tazin

    R.

    R.

    Tazin

    Lake

    Preston

    Bartlett

    LakeArchibald

    L.

    Tsalwor Lake

    Vermette

    Carswell

    Lake

    L.

    Lloyd L.

    Forrest L.

    Patterson

    Dillon

    Lake

    Lake

    Tazin

    Lake

    Peter

    Pond

    Lake

    Primrose

    Lake

    La

    Loche

    Lac

    5

    5

    16

    16

    1

    1

    1

    54°

    53°

    52°

    51°

    50°

    49°

    110°111°112°113°114°115°

    53°

    52°

    51°

    50°

    49°

    120° 119° 118° 117° 116°

    55°

    60°

    59°

    58°

    57°

    56°

    121° 120° 119° 118° 117° 116° 115° 114° 113° 112° 111° 110° 109°

    60°

    59°

    58°

    57°

    56°

    55°

    54°

    W

    O

    S

    AC

    N A

    E

    K

    AH

    ST

    M

    N

    T N

    A

    AH OIW ASHINGTON D A

    AM

    R

    B

    I H

    I

    TS

    UC

    B

    O

    I

    L

    I

    T E

    L

    A

    S

    B

    I

    U

    WO

    I

    R

    R

    C

    M

    HT

    H

    B

    T

    S

    N

    O

    E

    A

    R

    W

    AS

    K

    R

    C

    N

    SETR

    H

    A

    T E IO

    S

    T

    I

    89

    26

    55

    14

    7

    3

    17 15

    13

    31

    40

    43

    17

    17

    51

    44

    21

    26

    321

    371

    232

    93

    23

    6

    95

    31

    95

    23

    93

    31

    23

    6

    31

    3A

    21

    3B

    23

    6

    3

    93

    9593

    1

    95

    3

    95

    3A

    93

    6

    93

    25

    3A

    95A

    31A

    29

    97

    1

    2

    97

    5

    5

    955

    955

    1

    1

    AT

    HA

    BA

    S C

    A

    16

    I.R. 123

    Louis Bull

    Lake

    128

    Valley

    I.R. 137

    I.R. 133A

    Wabamun

    Samson

    Ermineskin

    White

    Alexander

    Stoney

    139

    I.R. 147B

    Makaoo

    Cold

    Kehewin

    Wabamun I.R. 133B

    I.R. 138A

    I.R. 121

    Eden

    I.R. 148A

    Fish

    I.R. 216

    I.R. 138B

    I.R. 149

    I.R.

    Blood

    I.R.

    142 143 144

    Valley

    I.R. 216

    I.R. 137 Samson

    Alexis

    Eden

    Unipouheous

    I.R. 142B

    I.R. 120

    I.R.

    I.R. 133

    Stoney

    Puskiakiwenin

    Lake

    Montana

    Samson

    I.R. 134

    I.R. 138Buck Lake

    I.R. 137A

    I.R. 133C

    Pigeon Lake

    I.R. 122

    I.R. 125

    Saddle Lake

    I.R. 145

    Blood

    I.R. 147

    I.R. 146

    Siksika

    I.R. 148

    C.F.B.

    W AINW RIGHT

    SUFFIELD

    C.F.B.

    LAKES

    PARK

    ELK ISLAND

    NAT.

    PARK

    W ATERTON

    NATIONAL

    CYPRESS HILLS

    LLOYDMINSTER

    CAMROSE

    W ETASKIW IN

    RED DEER

    MEDICINE HAT

    ST. ALBERT

    LETHBRIDGE

    SASKATCHEW AN

    LEDUC

    GROV E

    AIRDRIE

    FORT

    SPRUCE

    CALGARY

    EDMONTON

    R

    I

    D

    M

    IA

    II

    IA

    TH

    DE

    N

    N

    F O U R T H

    FF

    R

    EM

    LAMONT

    OKOTOKS

    PICTURE

    PLAIN

    PASS

    ROCKY

    CASTOR

    MUNDARE

    GRANUM

    MAGRATH

    CREEK

    SEDGEW ICK

    CALMAR

    HIGH RIV ER

    REDCLIFF

    SMOKY

    HANNA

    BOW ISLAND

    DIDSBURY

    LAKE

    DEV ON

    NANTON

    CARSTAIRS

    V ERMILION

    COCHRANE

    STONY

    TOFIELD

    ELK POINT

    CLARESHOLM

    BUTTE

    RIMBEY

    BEAUMONT

    V ULCAN

    ST. PAUL

    MORINV ILLE

    REDW ATER

    CORONATION

    LAKE

    BLACK DIAMOND

    V EGREV ILLE

    SYLV AN

    THREE

    KILLAM

    HOUSE

    BRUDERHEIM

    PENHOLD

    COALDALE

    BLACKFALDS

    DAYSLAND

    ECKV ILLE

    BASSANO

    FORT

    HILLS

    PROV OST

    PINCHER

    V AUXHALL

    OLDS

    CROW SNEST

    BROOKS

    BARRHEAD

    COALHURST

    TW O HILLS

    LACOMBE

    TROCHU

    MILLET

    TURNER V ALLEY

    OYEN

    CHESTER

    MERE

    BASHAW

    STRATHMORE

    GIBBONS

    BO

    NN

    YVIL

    LE

    V IKING

    CROSSFIELD

    BON

    BOW DEN

    W AINW RIGHT

    SUNDRE

    HARDISTY

    CARDSTON MILK RIV ER

    MACLEOD

    ACCORD

    TABER

    RAYMOND

    STETTLER

    STAV ELY

    INNISFAIL

    MOUNTAIN

    W ESTLOCK

    PONOKA

    217

    24

    28

    20

    9

    44

    6

    31

    10

    2

    50

    18

    15

    56

    45

    35

    3

    11

    47

    47

    43

    5

    6

    33

    14

    18

    1

    41

    8

    26

    52

    49

    55

    60

    3

    56

    19 16

    46

    11

    19

    1

    25

    9

    6

    27

    62

    2

    17

    8

    14

    5

    3

    18

    38

    23 41

    37

    39

    20

    5

    2

    34

    46

    20

    19

    4

    4

    59

    11

    8

    16

    36

    22 21

    13

    53

    10

    62

    6

    15

    6

    12

    27

    29

    26

    42

    59

    61

    54

    11

    4

    58

    3

    37

    1

    28

    21

    7

    24

    48

    36

    115

    35

    45

    17

    32

    57

    29

    31

    24

    49

    27

    40

    14

    20

    30

    28

    53

    22

    26

    7

    50

    28

    4

    39

    7

    51

    48

    51

    93

    3

    15

    5

    43

    44

    34

    4

    7

    33

    29

    25

    10

    58

    25

    60

    27

    8

    61

    18

    13

    12

    30

    7

    55

    2312

    57

    21

    22

    13

    12

    5

    136

    19

    1416

    10

    54

    32

    21

    17

    26

    40

    2 1

    23

    4

    k

    h

    River

    c

    a

    Deer

    h

    Bow

    a

    h

    River

    n

    S

    h

    River

    Riv

    er

    w

    Deer

    c

    S

    Old

    man

    t

    a

    e

    River

    Bow

    North

    South

    t

    O

    w

    c

    s

    Deer

    d

    a

    n

    River

    t

    River

    River

    River

    Red

    River

    k

    wa

    n

    s

    R.

    n

    s

    Red

    River

    Deer

    ka

    t

    l

    Red

    Red

    m

    a

    n

    e

    a

    Sout

    h

    River

    a

    S

    e

    River

    a

    a

    ka

    w

    S

    s

    a

    Bow

    ec

    Nort

    h

    RiverOldman

    n

    GarnerL.

    L

    Elkwater L.

    gikoC

    Keho Lake

    Reservoir

    St. Mary

    L.

    Gleniffer

    .o

    L.Stobart

    L.

    L.Kehiwin

    Marion

    LakeMoose

    Lake

    Gough

    Lake Res.

    LakeGoodfish

    LakeWhitefish

    LakeDowling

    Travers Reservoir

    Little Bow

    Tide Lake

    Res.

    Sylvan Lake

    WabamunLake

    Lake

    Ne

    well

    Sounding

    Lake

    Frog

    McGregor

    Pakowki

    Lake

    Muriel

    Lake

    Lake

    Lake

    Pigeon

    Lake

    Lake

    Gull L.

    Beaverhill

    Lac Ste.

    Sullivan

    Lake

    Lake

    Buff

    alo

    Anne

    PARK

    PROV.

    Stony Plain

    I.R. 135

    O’Chiese

    Big Horn

    I.R. 202

    I.R.

    O’Chiese

    I.R. 203

    203

    203A

    Sunchild

    O’Chiese Cemetery

    I.R.

    I.R. 144A

    PARK

    BANFF

    NATIONAL

    JASPER

    PARK

    NATIONAL

    LOUGHEED

    PROV. PARK

    PETER

    PARK

    WILDERNESS

    WILLMORE

    W HITECOURT

    BANFF

    CANMORE

    GRANDE CACHE

    EDSON

    DRAYTON

    HINTON

    FOX CREEK

    MAYERTHORPE

    V ALLEY

    61

    16 14

    58

    51

    8

    59

    9

    54

    17 1320 18

    57

    52

    53

    11 10

    56

    19 12

    60

    15

    62

    55

    Brazeau

    Brazeau

    akt

    l

    n

    Rocky

    River

    e

    s

    River

    o

    River

    cB

    R.

    a

    River

    S a

    Athabasca

    n

    River

    wan

    h

    No

    s

    Saskatche

    R.

    Nort

    h

    b

    Atha

    basca

    r

    McLeod

    North

    t

    At

    a

    R.

    t

    c

    h

    wa e

    h

    k

    ac

    River

    McLeod

    a

    s

    L.

    Jasper

    L.

    Talbot

    Canal

    BrazeauReservoir

    Brazeau

    Chip Lake

    Lake

    AbrahamLake

    Brule

    ELBOW-SHEEP

    WILDLAND

    KAKW A WILDLAND

    PROV. PARK

    Whitecourt

    I.R. 232

    I.R. 234

    CardinalRiver

    Elk RiverI.R. 233

    Utikoomak Lake

    I.R. 213

    215

    I.R.

    Duncans

    I.R. 228

    209

    Drift Pile River

    I.R.

    Lake

    Bistcho Lake

    I.R. 150F

    I.R. 150D

    Boyer

    I.R. 154A

    I.R. 154B

    I.R. 152B

    I.R. 212

    I.R. 151A

    Creek

    Amber River

    I.R. 226

    I.R. 210

    I.R. 154

    Pakashan

    Woodland Cree

    I.R. 211

    I.R. 164A

    John D’Or

    Woodland CreeI.R. 227

    Clear Hills

    Jackfish

    Woodland Cree

    I.R. 150C

    Assineau River

    I.R.

    Sucker

    Upper Hay River

    Child Lake

    Lakes

    Sturgeon

    I.R. 152C

    Swan River

    Point

    I.R. 163

    I.R. 214

    Lake

    Horse

    Sturgeon Lake

    Hay

    I.R. 150E

    I.R. 150

    I.R. 187

    Halcro

    150A

    William McKenzie

    Sturgeon Lake

    I.R. 155B

    I.R. 207

    I.R. 151K

    I.R. 164

    Carcajou Settlement

    Zama Lake

    PrairieBushe River

    PRAIRIE

    GRANDE

    RN

    A

    SH

    DE

    XI

    MT

    II

    FALHER

    RIV ER

    V ALLEYV IEW

    MANNING

    HIGH

    HIGH

    LAKE LEV EL

    SEXSMITH

    RAINBOW

    PEACE

    W EMBLEY

    FAIRV IEW

    McLENNAN

    BEAV ERLODGE

    PRAIRIE

    RIV ER

    GRIMSHAW

    SPIRIT

    71

    20

    5

    13

    64

    99

    12

    84

    79

    19

    63

    85

    13

    80

    18

    118

    24

    17

    8

    93

    108

    120

    3

    90

    11

    77

    74

    7

    96

    118

    65

    7

    8

    97

    24

    128

    9

    191

    67

    204

    7

    16

    1517

    105

    87

    94

    115

    126

    16

    9

    116

    69

    102

    110

    4

    13

    8

    117

    82

    1425

    2

    104

    125

    11

    91

    72

    119

    66

    510

    11

    101

    86

    63

    111

    23

    76

    98

    23

    112

    89

    92

    73

    12

    81

    6

    109

    107

    124

    11

    122

    75

    14 9

    78

    10

    83

    12

    22 21

    22

    121

    9

    10

    123

    114

    10

    100

    262

    113

    70

    21

    95

    88

    15

    103

    River

    River

    Smoky

    River

    River

    River

    Wapiti

    Wapiti

    Smoky

    Smoky

    Peace

    iPeace

    River

    r

    aec

    P

    ev

    R

    e

    Bison

    L.

    Buffalo Bay

    W inagami

    Lake

    Kimiwan

    Lake

    Bear L.

    L.

    Cardina

    l

    L.

    Lake

    SaskatoonL.

    Lake

    Eva

    Lubicon

    Hay

    Wadlin

    Giroux

    L.

    Bay

    Auger

    Bay

    L

    g

    Zama

    rtk

    Mr

    a

    Lake

    e

    a

    ea

    Lake

    Utikuma

    Bistcho Lake

    LakeLesser Slave

    Utikoomak LakeI.R. 155 Utikoomak

    LakeI.R. 155A

    I.R. 231Grouard

    Freeman I.R. 150BGrouard I.R. 229

    Grouard I.R. 230

    Tallcree

    I.R. 173

    Tallcree

    I.R. 173A

    Fort Vermilion I.R. 173B

    Beaver RanchI.R. 163B

    BeaverRanch

    I.R. 163ABeaver Ranch

    I.R. 173C

    Wadlin Lake

    I.R. 221

    131

    Dog Head

    Clearwater

    I.R. 166C

    I.R. 174B

    I.R. 175

    I.R. 194

    I.R. 150G

    Allison Bay

    Sand

    Gregoire Lake

    Lake

    I.R. 166D

    Gambler

    Chipewyan

    I.R. 201G

    I.R. 218

    Chipewyan

    I.R. 166

    I.R. 201C

    Chipewyan

    Wabasca

    166A

    Charles Lake

    Point

    I.R. 162

    I.R. 224

    I.R.

    I.R. 176B

    I.R. 176

    Fox

    Cold

    Gate

    I.R. 225

    I.R.

    Sawridge

    Indian Cemetery

    Wabasca

    Lake

    Chipewyan

    Lake

    Colin Lake

    Old Fort

    Namur River

    201F

    I.R. 150H

    Devil’s

    I.R. 201E

    Fort McKay

    I.R.

    I.R. 201D

    Chipewyan

    Chipewyan

    I.R. 219

    Gregoire

    I.R. 167

    Wabasca

    Chipewyan

    Namur River

    Gregoire Lake

    I.R. 166B

    I.R. 176A

    I.R. 201A

    Beaver

    Cornwall Lake

    I.R. 217

    I.R. 201B

    I.R. 220

    I.R. 223

    I.R. 174A

    Wabasca

    Jean Baptiste

    I.R. 174

    Heart Lake

    Sawridge

    I.R. 183

    House River

    Janvier

    I.R. 178

    Wabasca

    Lake

    I.R. 149B

    I.R.

    Chipewyan

    201

    AIR W EAPONS RANGE

    COLD LAKE

    NATIONAL

    PARK

    BUFFALO

    W OOD

    W OOD BUFFALO

    D

    H

    M

    AR

    F T

    H

    U

    D I

    R

    A N

    IE

    F I

    I

    O

    N

    T

    F

    E R

    I

    M

    LAC

    LAKE

    FORT SMITH

    LA BICHE

    SLAV E

    ATHABASCA

    125

    79

    120

    6

    9

    123

    94

    93

    81

    76

    1

    83

    108

    5

    119

    112

    88

    3

    96

    1

    111

    84

    74

    101

    64

    125

    109

    12

    100

    8

    108

    87

    101

    7

    82

    94

    63

    100

    26

    73

    92

    23

    71

    78

    15

    99

    126

    89

    4

    21

    75

    63

    5

    113

    3

    74

    91

    115

    2

    16

    16

    104

    85

    7

    1320

    67

    65

    107

    80

    3

    64

    106

    96

    118

    11

    116

    19

    89

    9

    69

    66

    5 4

    109

    25

    103

    15

    110

    104

    23

    124

    121

    126

    99

    17

    91

    24

    95

    8

    65

    121

    22

    118

    73

    17

    98

    97

    14

    70

    6

    19

    72

    107

    22

    7

    106

    95

    114

    84

    122

    105

    3

    79

    24

    122

    11

    78

    86

    2

    70

    87

    97

    86

    18

    71

    124

    85

    82

    105

    75

    5 4

    76

    1

    14

    111

    115

    1320

    1

    88

    66

    4

    90

    10

    113

    72

    67

    77

    68

    110

    81

    119

    114

    83

    123

    103

    77

    6

    117

    21

    69

    102

    90

    120

    102

    2

    18

    112

    2

    116

    92

    117

    93

    12

    98

    t

    h

    A

    River

    Atha

    basca

    Athabasca

    t

    b

    er

    a

    River

    Peace

    River

    sa

    River

    b

    Atha

    basca

    v

    c

    a

    River

    a

    hc

    River

    a

    A

    s

    Ri

    a

    Rvr

    iSla

    ve

    River

    Slave

    e

    McClelland

    Lake

    L.

    Pinehurst

    Lake

    Lake

    Lakes

    Fort

    Wabasca

    Lake

    Lake

    Lake

    Touchwood

    Sand

    Arch

    Colin

    Andrew

    Lake

    L.

    Legend

    Seibert

    Leggo

    Lela

    nd

    Chipewyan L.

    Cornwall

    Heart

    Willow Lake

    Gardiner Ls.

    Lake

    Bay

    Old

    Conibear

    English

    Bay

    NamL.

    ur

    Lake

    L.

    Muskwa

    Lake

    Beaver

    Lake

    Island

    Thultue

    South

    Lake

    Lake

    Lake

    Richardson

    Lake

    Lake

    Rock

    Charl

    es

    L.

    Lake

    st

    Lake

    Winefred

    Baril

    Gordon

    ao

    Peerless

    Lake

    Garson

    Lake

    Lake

    Lake

    Lake

    Wentzel

    Lake

    rWab

    cL.

    Calling

    Lake

    ah

    N

    Graham

    Mamawi

    Biche

    Lac

    la

    Claire

    Lake

    I.R. 149A

    Winefred Lake

    I.R. 194B

    I.R. 194ACowper Lake

    REGIONAL MUNICIPALITY OF

    COLD

    LAKE

    Cold Lake

    Cold

    Lake

    LEGAL

    DRUMHELLER

    BENTLEY

    LA

    KE

    HILLSSW AN

    S I X T H

    M E R I D I A N

    FORT MCMURRAY

    95

    52

    AWN

    Piikani

    Piikani

    Tsu T’ina

    ATCO Pipelines

    TCT

    TCT (Nova Ventures)

    TRANSMISSION LINES

    Alliance Pipeline

    INFORMATION THEREON IS MADE .

    NO WARRANTY OR REPRESENTATION AS TO THE COMPLETENESS OF SAID MAP OR

    PRODUCED BY ATCO Pipelines - GRAPHICS

    M ap 1

    M ap 3

    M ap 2

    M ap 4

    M ap 5

    M ap 10Set of 3

    M ap 11

    M ap 7

    M ap 6

    M ap 14

    M ap 12

    M ap 27

    M ap 28M ap 23

    M ap 24

    M ap 31M ap 30

    M ap 29

    M ap 32

    M ap 35

    M ap 33

    M ap 34

    M ap 37

    M ap 38

    M ap 36

    M ap 19

    M ap 20

    Set of 3

    M ap 17

    M ap 15

    M ap 49

    M ap 43M ap 44

    M ap 46

    M ap 40

    M ap 48

    M ap 21

    M ap 22

    M ap 18

    M ap 51

    M ap 47

    M ap 53

    M ap 52

    M ap 54

    M ap 55

    56

    M ap

    REVISED:

    Set of 6

    Set of 3

    Set of 2

    M ap 57

    M ap 58Set of 2

    Integration Areas

    Proposed ATCO Central Area Footprint

    1

    2

    4

    2a

    4a

    3

    Proposed Tranches

    Set of 2

    (2011)INTEGRATION M APFINAL ATCO NGTL

    SEPTEMBER 06, 2011

    ATCONGTL

    NGTLATCO

    ATCONGTL

    NGTLATCO

    BLOCK VALVE

    LAC LA NONNE

    BLOCK VALVE

    TCT TRANSMISSION

    P

    P

    P

    273m m MOP 7240kPa

    15175

    1517615174

    PEERS

    CREEK RECEIPT

    FROM SOUTH CARROT

    168m m

    11452 11453

    1145411455

    25100

    43 44

    2

    TO

    PE

    ER

    S S

    UC

    TIO

    N

    FR

    OM

    PE

    ER

    S D

    ISC

    HA

    RG

    E

    COMPRESSOR

    03-33-53-13-W 5M

    24176 26690

    24177323m m MOP 6550kPa

    16-02-57-3-W 5

    12-23-41-19-W 4

    273m m MOP 7240kPa

    15-35-52-20-W 5

    24820

    24844

    24851

    24846 24847

    SUNDANCE CREEK

    COMPRESSOR

    24848

    24849

    24852

    24845

    SUNDANCE CREEK

    COMPRESSOR TIE-IN

    N.E.35-52-20-W 5

    273m m MOP 7240kPa

    ATCO PipelinesAsset Swap Application - Attachment 3

    February 15, 2012

    Page 2 of 2

    Asset Swap Application

    ATCO Gas and Pipelines Ltd. Appendix 3 - Asset Swap Map Page 1 of 1

    AUC Decision 2012-310 (November 22, 2012)


Recommended