+ All Categories
Home > Documents > Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register...

Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register...

Date post: 02-Feb-2018
Category:
Upload: lythuy
View: 219 times
Download: 0 times
Share this document with a friend
28
Deltek Acumen 6.1 Release Notes June 24, 2015
Transcript
Page 1: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Deltek Acumen 6.1 Release Notes

June 24, 2015

Page 2: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Release Notes ii

While Deltek has attempted to verify that the information in this document is accurate and complete, some typographical or technical errors may exist. The recipient of this document is solely responsible for all decisions relating to or use of the information provided herein.

The information contained in this publication is effective as of the publication date below and is subject to change without notice.

This publication contains proprietary information that is protected by copyright. All rights are reserved. No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, or translated into another language, without the prior written consent of Deltek, Inc.

This edition published June 2015.

© 2015 Deltek, Inc.

Deltek’s software is also protected by copyright law and constitutes valuable confidential and proprietary information of Deltek, Inc. and its licensors. The Deltek software, and all related documentation, is provided for use only in accordance with the terms of the license agreement. Unauthorized reproduction or distribution of the program or any portion thereof could result in severe civil or criminal penalties.

All trademarks are the property of their respective owners.

Page 3: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Release Notes iii

Contents Overview .......................................................................................................................................... 1

Custom Programming ................................................................................................................. 1

New Features and Enhancements .................................................................................................. 2

Compare Two Or More Scenarios Using Risk Driver Analysis ................................................... 2

Use Mitigation Steps to Compare Scenarios .............................................................................. 3

Display Duration Risk Output in Hours ........................................................................................ 4

Context-Sensitive Online Help .................................................................................................... 4

RiskBook Is Now Kona Risk ........................................................................................................ 4

Schedule/Cost Activity Overlay Tooltip ....................................................................................... 5

Risk Register Import Enhanced .................................................................................................. 5

Grouping by Fields Enhanced on the S2 // Diagnostics Tab ...................................................... 6

Ribbons Enhanced on the S2 // Diagnostics Tab ....................................................................... 8

Reorder Metrics in the Ribbon and Phase Analyzer ................................................................... 8

Export User-Defined Fields to MSP and Primavera P6 .............................................................. 8

Primavera P6 Project Selection Dialog Box Includes a Flat View .............................................. 9

Software Issues Resolved ............................................................................................................. 10

Appendix A: For Additional Information ......................................................................................... 23

Customer Care Connect Site .................................................................................................... 23

Available Documentation for this Release ................................................................................ 23

Page 4: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Overview

Release Notes 1

Overview Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain a summary of the following:

New Features and Enhancements

Software Issues Resolved

For system requirements and the Compatibility Matrix, see the Deltek Acumen Technical Installation Guide.

Custom Programming If you have custom programs or reports that use the Acumen API, then before you upgrade:

Review all existing custom report work prior to your intended go-live date.

Pay particular attention to any Acumen API changes that may impact your custom work.

When upgrading, Deltek strongly recommends that you first deploy an instance of Acumen to test your customizations (if any) prior to moving into production.

Deltek’s Technical Services team is available to support you as you plan for this upgrade. We offer both technical and custom services, ensuring the best possible Deltek experience. Contact [email protected].

Page 5: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 2

New Features and Enhancements

Compare Two Or More Scenarios Using Risk Driver Analysis The new Risk Driver Comparison view displays several cost / schedule risk driver result sets on the same chart. This allows you to compare risk driver results and analyze risk mitigation benefits.

Each result set is summed either by activity or by risk. You can use the Activities or Risk Events menu options to specify how the result sets are summed. In addition, you can use the Copy to Clipboard feature to copy the graph or table and paste them into another application, such as MS Excel.

Sort by impact Edit or rename

the result set

Specify which results sets to display on the

graph

Select a different

color

Remove a result set from the

chart

Copy the table or graph

Compare multiple risk driver result

sets

Page 6: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 3

Use Mitigation Steps to Compare Scenarios Risk mitigation allows you to reduce or eliminate the risks associated with a project.

Before making any changes to a project, you may want to assess if mitigation will reduce project risk and if the improvement will be worth the investment.

For example, if you spend $1,000,000 to move a risk from Very High to High but it only saves you a few days, you may decide that it is not worth it. On the other hand, if you can spend $10,000 and save three weeks, it may be a worthwhile investment.

The new Risk Register mitigation steps allow you to set up and run risk analysis that compares different mitigation scenarios to see the impact on the project.

In the example below, risk analysis with mitigation has been performed three times, once with all three mitigation steps, once with the first two, and once with only the first step selected. The Risk Exposure chart displays the results of the three scenarios.

Use the grid to hide a step in the graph, change color, edit the name, or

remove step data

Create mitigation steps for a risk event in the Risk Register

Include or exclude overhead

in mitigation steps

Page 7: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 4

Display Duration Risk Output in Hours The Risk Drivers and Risk Driver Comparison reports display duration in days by default; however, you now have the option to display the duration in hours and vice versa by changing the display settings on the S1 // Projects tab (Activities menu » Activity View » Display Settings » Duration Time Unit).

Context-Sensitive Online Help Acumen now includes online help that is context-sensitive to the tab and dialog box level. Click the help icon in the corner of the Acumen window to display the help page for the current tab, or click the help icon in the corner of a dialog box to display the help page for the dialog box.

RiskBook Is Now Kona Risk RiskBook has been renamed to Kona Risk.

Display in days or hours

Click the help icon to display the help page for the current tab

or dialog box

Page 8: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 5

Schedule/Cost Activity Overlay Tooltip The S3 // Risk tab Activity Schedule Overlay column now displays additional tooltip information when you hover over a cell.

If you overlay with an activity, the tooltip displays the cost estimate ID and description, the overlaid activity ID and description, and the project to which the activity is associated.

If you overlay with a WBS, the tooltip displays the cost estimate ID and description, the overlaid WBS ID and description, and the project to which the WBS is associated.

If you overlay with a project or scenario, the tooltip displays the cost estimate ID and description and the project ID and description.

Risk Register Import Enhanced

Maintain Existing Risk Events Duration and Cost When you import a risk register from Kona Risk, it maintains existing risk event mitigation duration and cost data.

Mitigation Steps Combined Risk Register risk events can have multiple mitigation steps. When you import such a risk register back into Acumen from Kona Risk, the mitigation steps are combined into a single step on the Risk Register Mitigation Steps tab. The mitigation step Duration and Cost fields display the sum total of all of the original individual steps.

Hover over a cell in the Activity Schedule

Overlay column to display additional information

Page 9: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 6

New Risk Events Maintained in the Risk Register When you add new risks in Acumen after you have exported the risk register to Kona Risk, and you then import that risk register back into Acumen, the new risks are maintained in the risk register.

Grouping by Fields Enhanced on the S2 // Diagnostics Tab Grouping by fields on the S2 // Diagnostics tab includes a number of enhancements:

The available fields in the Fields » Selected Field drop-down menu in the Ribbons menu group are now grouped into three sub-menus: General, Inputs, and Outputs.

Interval size is now automatically set based on the number of ribbons you select in the Number of Intervals field.

If the selected field is a string, the activities are distributed as evenly as possible across the ribbons.

If the selected field is a date, the minimum and maximum values define the range and the dates are rounded to the nearest enclosing day, month, or year.

If the selected field is a number, the minimum and maximum values define the range and the numbers are grouped to the nearest round numbers.

For example, if the numbers are in the range from 0 to 99 and the number of ribbons is four, the ribbons will be called >= 0, > =25, >= 50 and >= 75. If the number of ribbons is five, the ribbons will be >= 0, >= 20, >= 40, >= 60, and >= 80

Duration and Cost are maintained when you import a risk register

Imported risk register combines mitigation

steps and sums Duration and Cost

New risk events added in Acumen maintained when risk register is

imported

Page 10: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 7

The default fields grouping type for new workbooks is now Number of Intervals:7.

After grouping your ribbons, you can double-click on a ribbon to drill-down or click on Properties to view name and value information. Click the Home button to return to the top-level view.

Fields are grouped into three sub-menus

Default setting for new workbooks

Double-click on a ribbon to drill

down

Click Properties for more information

Click Home to return to the

top-level

Page 11: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 8

Ribbons Enhanced on the S2 // Diagnostics Tab When you have many values or ranges, the ribbon now lists them with a >= sign instead of a range.

Reorder Metrics in the Ribbon and Phase Analyzer On the S2 // Diagnostics tab, you can now drag and drop (reorder) the ribbon and phase analyzer metrics. Click on a metric and drag left/right (Ribbon Analyzer) or up/down (Phase Analyzer) to reorder.

Export User-Defined Fields to MSP and Primavera P6 When you export an Acumen project as a Microsoft Project XML file or an Oracle Primavera P6 XER file, any existing user-defined fields are now included in the export and are available for use in MSP and Primavera respectively.

>= sign displays when there are many values or ranges

Click on a metric and drag left or right to

a new location

Click on a metric and drag up or down to a

new location

Exporting as an MSP XML or P6 XER file

includes user-defined fields

Page 12: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

New Features and Enhancements

Release Notes 9

Primavera P6 Project Selection Dialog Box Includes a Flat View When you import a project from Primavera P6 Web Services, you can now browse through the projects on the Project Selection dialog box using a new Flat view or the existing view which is now called Enterprise Project Structure (EPS).

The Flat View tab includes all available project codes and allows you to group and filter. Using this view, you can:

Sort by clicking on a column header.

Drag a column header up to the “group by” bar above to group. If you drag first one and then a second, you can add a sub-level group. For example, if you drag Current Phase and then Business Process up to the “group by” bar, the projects are grouped first by Current Phase and then by Business Process.

Click on a column header to display filter options to filter by specific data. The filter selection displays at the bottom of the dialog box. Remove the filter by clicking the X next to the filter at the bottom of the dialog box.

Click on a column header

to sort

Two different views for browsing

through projects

Click next to column header to display and select filters

Click X to remove filter

Use checkbox to enable or

disable filter

Drag column header to “group by” bar to

group

Page 13: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 10

Software Issues Resolved S1 // Projects

Defect 504112

Description: Acumen crashed when you clicked the "Convert Snapshot to Project" button.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494138

Description: Acumen hung when you created a scenario from a Primavera P6 XER project.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Views

Defect 494805

Description: An error message displayed when you added the "Advice" field to the Sorting Fields panel.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Import

Defect 519428

Description: There was inconsistency when you tried to import a duplicate project across platforms.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Import » Filters

Defect 494341

Description: CTRL+V was not working in the Search box.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 14: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 11

S1 // Projects » Activity Grid

Defect 494122

Description: The selected tab did not remain selected when you switched between the rows

in the Activity grid.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494343

Description: The Gantt chart bar displayed across the Activities grid.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494475

Description: The ID Name for WBS rows displayed “…” at the end of the name when you

imported a project from Oracle Primavera P6 Services.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Activity Details

Defect 494120

Description: The Resource Assignment tab displayed the contents of the Costs tab when

you selected a project summary row.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494264

Description: When you changed the activity calendar in the grid, it didn’t immediately change

in the Details Pane.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 15: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 12

Defect 494728

Description: The relationship “Go To”button did not work in a flat view mode.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Scenario Generation

Defect 494727 Description: Early Start date was incorrect in retained logic mode for activities that had in-progress start-to-start predecessors with an early start greater than Time Now.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Get External Data From » Deltek Open Plan Import

Defect 494045 Description: An exception error displayed when you renamed an OPP project in Acumen and attempted to import a new project with the same name.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494494 Description: The Open Plan import failed when it tried to import a project that used multiple resources with the same name.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 500580

Description: All externals subprojects were loaded when you selected the "Include external subprojects if they are already opened..." option.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 501933

Description: The Open Plan import was not processing the Actual units correctly.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 16: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 13

Defect 501934

Description: Resource Names displayed invalid characters when you imported the Open Plan project.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Get External Data From » Safran

Defect 494083 Description: A Safran import did not handle calendar non-holiday exceptions.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494093

Description: A Safran import did not handle directly adjacent non-working periods.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494134

Description: The Safran import crashed when the link referenced a nonexistent calendar.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494412 Description: The Safran import was not handling quotes correctly in the .SP files.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494693 Description: Acumen crashed when you imported a Safran project twice.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 17: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 14

S1 // Projects » Get External Data From » Oracle Primavera Import

Defect 494352

Description: The P3 import included an activity that was deleted from the schedule.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Get External Data From » Microsoft Project Import

Defect 494160

Description: MSP native import didn’t resolve external links and tasks when possible.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494316

Description: MSP native import didn’t resolve external links and tasks when possible.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494756 Description: The MSP XML import was triggering multiple import wizards in Microsoft Project.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S1 // Projects » Publish » Export to Microsoft Project MPP

Defect 493028

Description: The Units column value was not displayed correctly when exporting an existing P6 XML project to a Microsoft Project XML file.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 499591

Description: An error message displayed when you exported the Safran project as an MSP XML file and the actual start date of the in-progress activity was after the project’s Time Now.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 18: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 15

Defect 518737 Description: The error message "The format for file is not a UN/CEFACT supported format..." displayed when you exported the file as a Microsoft XML file after a UN/CEFACT export.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S2 // Logic

Defect 494573

Description: The Print option was disabled for Logic trace.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 519020

Description: The Gantt chart did not display for a cleansed scenario.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S2 // Diagnostics

Defect 494690 Description: All activities were displayed as Critical in the Ribbon Analyzer when you created a scenario.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S3 // Risk

Defect 494326 Description: Grouping by cost/duration uncertainty was available in the Grouping and Sorting dialog box.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 19: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 16

Defect 494604

Description: Schedule impact mapping was set to zero when you mapped activities with a remaining duration of less than 1 day in the Hours display mode.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494605

Description: Turning the percentage based risk on/off corrupted the cost impacts for all activity/event mappings.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494606 Description: The cost Risk Drivers chart did not display values for risk events when you selected an activity.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494631 Description: The "Schedule Contribution" and "Criticality" options were available when you selected Cost Estimate.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494675 Description: The mitigated Max Cost was incorrect when you selected Absolute Mapping.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 495447

Description: Acumen crashed when you clicked the Risk Event icon.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 20: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 17

Defect 497994

Description: Duration and Cost values on the Risk Events tab were not converted to percent based values for a scenario.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 503886

Description: An error message displayed when you ran Risk Analysis on a copied scenario with activity correlation.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 503922 Description: The version store ran out of memory while trying to store the risk analysis database.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S3 // Risk » Views

Defect 502633 Description: A deleted activity was not removed from the Integrate Cost/Schedule Risk Uncertainty dialog box and the Activity Schedule Overlay column.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S3 // Risk » Views » Activities View

Defect 494152

Description: When you mapped cost elements to schedule elements, they mapped back to

the parent project instead of the scenario that you selected.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 21: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 18

S3 // Risk » Activities

Defect 494260

Description: You could not adjust the cost uncertainty slider for children until you ran risk analysis.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494267

Description: Neither Copy/Paste from the context menu nor Ctrl+V worked in the Risk Events mapping grid.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 498830 Description: Mapped checkboxes were checked for summary rows when all completed children activities were unchecked.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S3 // Risk » Analysis

Defect 494266 Description: The P100 cost was not calculated correctly for a Cost Estimate project.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494381

Description: An error displayed when you used the option to avoid CLT (Central Limit Theorem).

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 503912 Description: The deterministic value and yellow line in the histogram, did not match after running risk analysis.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 22: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 19

S3 // Risk » Publish

Defect 494305

Description: Relative duration/cost activity-risk impact did not import/export values and format correctly from/to MS Excel.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494476

Description: An error message displayed when you imported activity uncertainty containing duplicate IDs.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S3 // Risk » Risk Register » Publish to RiskBook

Defect 494225 Description: When you published a risk register to Kona Risk, sometimes it failed to export all risks.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S3 // Risk » Risk Comparison

Defect 494780 Description: The Risk Driver tornado chart displayed black bars for completed activities.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

S5 // Dashboard

Defect 494189 Description: The dashboard Relationship type chart overlapped the labels.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 23: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 20

Forensics

Defect 494297

Description: The calendar comparison was not available in Forensics.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494342

Description: The number for the Calendar forensic changes did not fit between the parentheses.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494411

Description: The project was not added to Forensics when you exported to a Primavera P6 XER file.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494470

Description: When you selected “Remaining duration,” the Forensics Screen got stuck in "Analyzing" mode.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 500588

Description: The variance % and actual variance calculations were incorrect in Forensics when you selected different options.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 503930 Description: An error message displayed when you tried to compare calendars in Forensics.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 24: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 21

Forensics » Publish

Defect 494249

Description: When you exported forensics to MS Excel, it did not work correctly when there were multiple snapshots compared to a project.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 504219

Description: An error message displayed when you published a Forensic report to MS Excel.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Fields

Defect 494451

Description: There was an error when you mapped all projects in Code Fields.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494607

Description: The S1 // Project and S3 // Risk Description search box was not working properly.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

System and Configuration

Defect 494121

Description: The XER Import encoding was not working correctly when you imported a project using a Russian operating system.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 25: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Software Issues Resolved

Release Notes 22

Defect 494169

Description: The “Show release notes after upgrade” checkbox was still visible in the Deltek Acumen Options dialog box.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494572

Description: “The template file cannot be found.” error message displayed when you created a new project using the 6.0.0 offline installer.

Customers Impacted: All Acumen users using the 6.0.0 offline installer.

Workaround Before Fix: None

Defect 494680 Description: Acumen crashed when you copied the full distribution table to the clipboard.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Defect 494879

Description: The label in the Create a Kona Risk Register dialog box was updated.

Customers Impacted: All Acumen users.

Workaround Before Fix: None

Page 26: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Appendix A: For Additional Information

Release Notes 23

Appendix A: For Additional Information

Customer Care Connect Site The Deltek Customer Care Connect site is a support Web site for Deltek customers who purchase an Ongoing Support Plan (OSP).

The following are some of the many options that the Customer Care Connect site provides:

Download the latest versions of your Deltek products

Search Deltek’s knowledge base

Display or download product information, such as release notes, user guides, technical information, and white papers

Submit a support case and check on its progress

Transfer requested files to a Customer Care analyst

Use Quick Chat to submit a question to a Customer Care analyst online

Ask questions, exchange ideas, and share knowledge with other Deltek customers through the Deltek Connect Customer Forums

Subscribe to Deltek communications about your products and services

Receive alerts of new Deltek releases and hot fixes

For more information regarding Deltek Customer Care Connect, refer to the online help available from the Web site.

Access Customer Care Connect

To access the Customer Care Connect site, complete the following steps: 1. Go to http://support.deltek.com.

2. Enter your Customer Care Connect Username and Password.

3. Click Log In.

If you forget your username or password, you can click the Account Assistance button on the login screen for help.

Available Documentation for this Release The following table lists the Deltek documentation available for this release. Except where noted, all the user guides and quick reference guides listed in this table are available for download from the Deltek Customer Care Connect site.

Document Name Description

Deltek Acumen Online Help The online help system is available from within Acumen. It is context-sensitive to the tab and dialog box level and includes information about navigating, and steps for using, the Acumen

Page 27: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Appendix A: For Additional Information

Release Notes 24

Document Name Description

suite of products.

Deltek Acumen Technical Installation Guide

This contains technical installation and setup information for the staff at your company who maintain the hardware and software required to install Deltek Acumen.

Deltek Acumen API Guide This provides information about the Deltek Acumen API and how to integrate with different platforms to create custom reports.

Deltek Acumen Metric Developers Guide

This is a reference and guide for Acumen Software users looking to develop and customize advanced metrics within Acumen.

Deltek Acumen Kona Risk This includes information for setting up and using Kona Risk. Most of this information is also included in the online help.

Deltek Acumen Historical Release Notes

This includes information about features and resolved issues from previous releases.

Page 28: Deltek Acumen 6 - · PDF fileSchedule/Cost Activity Overlay Tooltip ..... 5 Risk Register Import Enhanced ... Welcome to Deltek Acumen 6.1 Release Notes. These release notes contain

Deltek is the leading global provider of enterprise software and information solutions for professional services firms, government contractors, and government agencies. For decades, we have delivered actionable insight that empowers our customers to unlock their business potential. Over 14,000 organizations and 1.8 million users in approximately 80 countries around the world rely on Deltek to research and identify opportunities, win new business, optimize resource, streamline operations, and deliver more profitable projects. Deltek – Know more. Do more.®

deltek.com


Recommended