+ All Categories
Home > Documents > Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build...

Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build...

Date post: 09-Mar-2021
Category:
Upload: others
View: 14 times
Download: 0 times
Share this document with a friend
24
Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® October 14, 2020 2020 Short Course
Transcript
Page 1: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Design-Build Programmatic UpdatesJoe Adams, PMP®

October 14, 20202020 Short Course

Page 2: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Table of contents

2

8-11

12-15

16-22

23-24

3-7Overview

New and Modified Relief

Risk Sharing

New Risk Sharing Concepts

Other Items

1

2

3

4

5

Page 3: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Overview

Page 4: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Major Programmatic Changes - DBC

Reallocation of risks associated with certain delays

DBE requirements for work done by Utilities

Evaluation factors

– Bidding Capacity

– Experience working with DBEs

– Proposer requests for SUE

Move toward increased use of electronic submittals

Insurance requirements

4

For additional details please refer to the Programmatic

Documents V4.0

Page 5: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Revising Programmatic Documents - Sources

5

Alternative Delivery Projects

Changes to the Design-Build Specifications

Electronic submittals requirements

Environmental approval commitments

Non-Project TxDOT

DBE experience reporting and reference forms

Bidding Capacity

Maintenance Management Plan requirements

FHWA and Industry

FHWA– Geotechnical and pavement

requirements– Intersection operational

requirements

Industry Feedback

– Risk Reallocation

V 4.0 incorporates more than 500 changes to V 3.1

Page 6: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020 6

Revising Programmatic Documents - Process

Alternative Delivery Projects Non-Project TxDOT Sources FHWA and Industry

Statewide Programmatic Working Group

Programmatic Working Group

SCMSection Director

Project-Specific Documents

UpdatedProgrammatic

Documents

Draft Programmatic

Documents

Director of Planning and Development

Page 7: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Collaboration with Industry

Delay risk and relief events– TxDOT is assuming greater responsibility for certain events outside of

DB Contractor’s control

Project Overhead– Project Overhead only applies to certain delays where DB Contractor

gets schedule relief– Daily Rate set during project procurement (8.5% to 10%)– DB Contractor can claim actual costs

New risk sharing concepts– Delay Deductible Aggregate Cap– Qualifying Delay Late Fee

7

Page 8: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

New & Modified Relief

Page 9: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Delay Event Cost Relief Schedule Project Overhead

Shared Risk

Differing Site Conditions Delay

Eminent Domain Delay

Force Majeure Delay

Uncooperative Utility Delay

Utility Owner Delay

Unidentified Utility Delay

New & Modified Relief – Qualifying Delays

9

Refer to Programmatic Documents V4.0 for details

Page 10: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

New & Modified Relief – Nonqualifying Events

10

Event Cost Relief Schedule Project Overhead

Shared Risk

Supply Chain Disruptions Delay

Railroad Documents

Railroad Agreement Delays

Special Events Delay

New Third Party Agreements

3rd Party Agreements Changes

Karst Features Delay

Unknown Karst Mitigation

New Utilities

New Drainage Permits

Refer to Programmatic Documents V4.0 for details

Page 11: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Risk Sharing

Page 12: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Tiered Risk Sharing Mechanism

12

Details of risk sharing mechanism varies across events

Day in Tiers can be either event specific or cumulative

Days can be subject to event specific caps

Not all events have risk sharing

Page 13: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Risk Sharing Mechanism

13

Basics of risk sharing mechanism

DB Contractor takes 100% of risk for X days

DB Contractor and TxDOT share next Y days of delay 50/50

TxDOT takes 100% of risk for each X+Y days

Events can be either per occurrence or cumulative

Risk sharing mechanism varies by event

Page 14: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

3 - Tiered Risk Sharing Mechanism – Force Majeure Event Delay

14

Tier 1: Cumulative Days 1 – 30 DB Contractor bears 100% of delay risk

No schedule relief or project overhead for first 30 days

Tier 2: Cumulative Days 31 – 90 Parties share delay risk equally, 2 days of delay = 1 day of relief

Maximum relief to DB Contractor in this tier is 30 days

Tier 3: Cumulative Days over 90 TxDOT bears 100% of the risk

DB Contractor is eligible for schedule relief and project overhead for every day of delay beginning on day 91

Page 15: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

4 - Tiered Risk Sharing Mechanism – Utility Owner Delay

15

Tier 1: Cumulative Days 1 – 60 DB Contractor bears 100% of delay risk

No schedule relief or project overhead for first 60 days

Tier 2: Cumulative Days 61 – 120 Parties share the delay risk equally, 2 days of delay = 1 day of relief

DB Contractor eligible for schedule relief, but not project overhead

Tier 3: Cumulative Days 121 - 180 Parties share the delay risk equally, 2 days of delay = 1 day of relief

DB Contractor eligible for schedule relief and project overhead

Tier 4: Cumulative Days over 180 TxDOT bears 100% of delay risk

DB Contractor eligible for schedule relief and project overhead for every day, beginning on day 181

Page 16: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

New Risk Sharing Concepts

Page 17: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

New Risk Sharing Concepts

17

Qualifying Delays

Delay Deductible

Delay Deductible Aggregate Cap

Qualifying Delay Late Fee

Refer to Programmatic Documents V4.0 for details

Page 18: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Qualifying Delays

18

Delays to the Critical Path

caused by the following events

• Uncooperative Utility Delay• Utility Owner Delay• Unidentified Utility Delay• Differing Site Conditions Delay• Force Majeure Delay• Eminent Domain Delay

Risk Sharing (Qualifying Days)

• Delay Deductible: DB Contractor does not get schedule relief and/or project overhead

• Relief days: DB Contractor gets schedule relief and/or project overhead

Page 19: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Delay Deductible & Delay Deductible Aggregate Cap

19

Delay Deductible• Qualifying days that DB Contractor does not

get schedule relief and/or project overhead

• Days contribute to the Delay Deductible Aggregate Cap

Delay Deductible Aggregate Cap

• 10% to 25% of the number of days from NTP1 to Substantial Completion deadline

• Determined on project by project basis

• TxDOT provides schedule relief and overhead for qualifying delays above Delay Deductible Aggregate Cap

Page 20: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Delay Deductible & Relief

20

Days Above Cap

Days At or Below Cap

Qualifying Delays

Delay Deductible Days Compensable Delays

Qualifying Delay Late Fee

Change OrderDelay

Deductible Aggregate

Cap

Page 21: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Qualifying Delay Late Fee

21

Daily late fee for failure to achieve Substantial Completion due to Qualifying Delays

Delay Late Fee applies to days after missed Substantial Completion

Not to exceed the number of days in the Delay Deductible Aggregate Cap

50% of amount set for liquidated damages for delay to Substantial Completion per day

Full Liquidated Damages for Delay apply for Substantial Completion exceeding Delay Deductible days

Page 22: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Other Items

Page 23: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020

Other Programmatic Changes

Sole discretion List of Reference Information Documents Advanced relocation utility agreements Utility investigation Utility adjustments Pre-proposal utility commitments Local approvals Level A SUE

23

For additional details please refer to the Programmatic Documents V4.0

Page 24: Design-Build Programmatic Updates...Design-Build Programmatic Updates October 14, 2020 Design-Build Programmatic Updates Joe Adams, PMP ® 2020 Short Course October 14, 2020 Design-Build

Design-Build Programmatic Updates October 14, 2020 24

Questions


Recommended