+ All Categories
Home > Documents > DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR...

DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR...

Date post: 17-Jul-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
7
6/9/2014 1 D ESIGN C RITERIA FOR T ERMINAL S TORAGE R ESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano, P.E. May 29, 2014 Joint Booster Pump Station #3 Reservoir | TFMA PROJECT BACKGROUND Integrated Pipeline Project 149 miles of pipeline 3 booster pump stations 3 lake pump stations 4 reservoirs Joint Booster Pump Station #3 Reservoir (JB3R) Figure provided by Tarrant Regional Water District Joint Booster Pump Station #3 Reservoir | TFMA JB3R OVERVIEW
Transcript
Page 1: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

1

DESIGN CRITERIA FORTERMINAL STORAGE

RESERVOIRS

Joint Booster Pump Station #3 Reservoir

Nicole Rutigliano, P.E.May 29, 2014

Joint Booster Pump Station #3 Reservoir | TFMA

PROJECT BACKGROUND

Integrated Pipeline Project

• 149 miles of pipeline• 3 booster pump stations• 3 lake pump stations• 4 reservoirs

Joint Booster Pump Station #3 Reservoir (JB3R)

Figure provided by Tarrant Regional Water District

Joint Booster Pump Station #3 Reservoir | TFMA

JB3R OVERVIEW

Page 2: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

2

Joint Booster Pump Station #3 Reservoir | TFMA

APPLICABLE DESIGN CRITERIA

• Texas Commission on Environmental Quality (TCEQ) design criteria

• Probable Maximum Flood (PMF)

• 100-year storm event

• Pumped inflows

Joint Booster Pump Station #3 Reservoir | TFMA

TCEQ REQUIREMENTS

• JB3R is classified as a dam

• Requirements for design of new dams:

– Design Storm (PMF)

– Wave Runup

– Freeboard

– Erosion Protection

– Seepage Protection

Joint Booster Pump Station #3 Reservoir | TFMA

TCEQ – SIZE AND HAZARD CLASSIFICATION

High-Hazard Dam• More than 3 habitable structures• FM 877• JB3 pump station

Small Size Dam• Max height: 30 feet• Max storage: 291 acre-feet

Inundation mapping resulting from a simplified breach analysis.

Page 3: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

3

Joint Booster Pump Station #3 Reservoir | TFMA

TCEQ REQUIREMENTS – DESIGN STORM/PMF

• Probable Maximum Flood – Greatest possible theoretical flood in a

geographical area

• Texas Administrative Code 299.15 requires a small size, high-hazard dam to pass 75% of the PMF

Joint Booster Pump Station #3 Reservoir | TFMA

TCEQ RESULTS – WAVE RUNUP/FREEBOARD

• Wave runup at maximum operating elevationo 1.39 feet

• Results in minimum overflow weir crest elevationo 533 ft-msl + 1.39 ft = 534.39 ft-msl

(weir crest elevation set at 535 ft-msl)

• Wave runup must also be considered during PMF event

Joint Booster Pump Station #3 Reservoir | TFMA

TCEQ RESULTS – DESIGN STORM

Wave runup during PMF event = 0.71 feet

Peak elevation during PMF event less than:

537 feet-msl – 0.71 feet = 536.29 feet-msl

RESULTS:

Exterior weir crest length – 10 feet

Interior weir crest length – 5 feet

Page 4: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

4

Joint Booster Pump Station #3 Reservoir | TFMA

100-YEAR DISCHARGES

• Avoid flooding downstream due to dam presence

• 100-year water surface elevation in reservoir = 534 feet-msl(below minimum weir crest elevation determined by wave runup analysis)

• No discharges from the reservoir will occur

Joint Booster Pump Station #3 Reservoir | TFMA

DO WE STOP WITH TCEQ MINIMUMS?

• Regulatory obligation has been met, but what about obligation to protect downstream residents and property?

Joint Booster Pump Station #3 Reservoir | TFMA

CASE STUDY: TAUM SAUK RESERVOIR FAILURE

http://www.waterpowermagazine.com/news/newsrcc-2009-short-course-and-tour

Page 5: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

5

Joint Booster Pump Station #3 Reservoir | TFMA

CASE STUDY: TAUM SAUK RESERVOIR FAILURE

• December 14, 2005

• Reynolds County, MO

• Taum Sauk Hydroelectric Power Station

• No emergency spillway

• Water level readings incorrect; embankment overtopped

• 600-foot section of reservoir failed, 1.5 billion gallons of water released

• No fatalities, but several injuries, damage

Joint Booster Pump Station #3 Reservoir | TFMA

PUMPING SCENARIOS

• Normal operating conditions– JB3R will receive pumped inflows from upstream

in the IPL system– Discharges from the reservoir will be made via the

JB3 pump station

• Operational errors are possible

Pumping Scenario Inflow (MGD) Inflow (cfs)

Initial Buildout(one pipeline)

350 542

Two Pipelines 700 1,083

Ultimate Buildout(three pipelines)

1,050 1,625

Joint Booster Pump Station #3 Reservoir | TFMA

PUMPING SCENARIOS - RESULTS

Design CriteriaInflow(MGD)

Inflow(cfs)

Weir crest length (ft)

Pumping Duration(h:mm)

Initial Flows(one pipeline)

350 54210 0:4065 ∞

Two Pipelines 700 1,08310 0:20

125 ∞Final Buildout

(three pipelines)1,050 1,625

10 0:15185 ∞

Page 6: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

6

Joint Booster Pump Station #3 Reservoir | TFMA

WEIR CREST ELEVATION/LENGTHS

Design Criteria Minimum Weir Length (ft)

Minimum Weir Crest Elevation (ft-msl)

Wave Runup at Maximum Operating Elevation

N/A 534.39

TCEQ – PMF Event (including wave runup)

10 535

100-Year Event N/A 534

Pumping Scenario –Initial Flows

65 535

Pumping Scenario –Two Pipelines

125 535

Pumping Scenario –Final Buildout

185 535

Joint Booster Pump Station #3 Reservoir | TFMA

ULTIMATE WEIR DESIGN

• Based on pumped inflows

– Weir crest length – 185 feet

– Weir elevation – 535 feet-msl

• Uncontrolled discharges through weir, but no breach of embankment

Joint Booster Pump Station #3 Reservoir | TFMA

CONCLUSIONS

• Meeting minimum regulatory requirements may not result in most appropriate design

• Weir crest length = relatively small impact on overall cost

• Protection of downstream residents, homes, and roads must be top priority

Page 7: DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS · 2018-04-14 · 6/9/2014 1 DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano,

6/9/2014

7

Joint Booster Pump Station #3 Reservoir | TFMA

QUESTIONS

QUESTIONS


Recommended