+ All Categories
Home > Documents > Design of Gas Handling Facilities for Shale Oil...

Design of Gas Handling Facilities for Shale Oil...

Date post: 16-Mar-2018
Category:
Upload: duonglien
View: 224 times
Download: 3 times
Share this document with a friend
22
DESIGN OF GAS HANDLING FACILITIES FOR SHALE OIL PRODUCTION Rocky Mountain Gas Processors Association 2015 Regional Conference Thursday November 19, 2015 Denver, CO Mike Conder and April Schroer
Transcript

DESIGN OF GAS HANDLING

FACILITIES FOR SHALE OIL

PRODUCTION

Rocky Mountain Gas Processors Association – 2015

Regional Conference

Thursday November 19, 2015 Denver, CO

Mike Conder and April Schroer

Overview

Trends in Gas Handling from Shale Oil Production

Designing with PVT Fluid Analyses

Simulating Gas Handling at Oil Production Facilities

Using GOR Data

Modeling Different Oils

Lift Gas Design & Sources

VRT Design & VRT/VRU System Value

Practical Tips for Facility Design

Trends in Gas Handling from Shale Oil Production

Single well pads transition to multi-well pad productionLow volume vertical wells to high volume horizontal wells

Change in Size & Complexity

Increase air emission requirements

Pushing threshold limits – esp. VOCs

Oil Price Boom to Slump MentalityBoom

Projects schedule driven

Projects not necessary based on long term economics

Little published on “more” complex designs and operation

Slump

Projects transitioning to “Cost” driven

“Critical” economic project drivers

Use “slump time” to improve facility designs

3

Transitioning from a

“Standardized Design”

to a

“Design in Progress”

Designs for Shale Oil/Gas Handling – “Traditional”

“Traditional” Well Pad typical flow sheet

4

Designs for Shale Oil/Gas Handling “4 Well Multi”4 –Well Multi-Well Pad Flow Sheet

5

GATHERING

Designing with PVT Fluid Analyses

PVT (Pressure-Volume-Temperature) fluid properties analysisMainly used for planning field exploitation by reservoir engineers

However, facilities engineers can use this information for equipment design

Predict gas handling requirements of the well and/or field

PVT samples are typically taken at surface separator Gas/Oil/Water samples taken & then recombined in the lab

GC results are carbon number (CN or “alkane – straight chain”) analysis

Typical range from C1 (methane ) to C36 with inerts

CN can be used in a process simulator for equipment sizing

Our work is based on VMG Sim “PIONA” (Paraffin's, Iso-paraffins,

Olefins, Naphthenes and Aromatics) new oil characterization Gives improved liquid property results

6

Simulating Gas Handling at Oil Production Facilities

Oil characterization by PIONA vs straight chain CN data

Little difference in gas production & analysis between two cases

Credible difference in oil properties

Need best oil properties for stabilization designs & meeting transport specs

Off gas flow from a stabilizer will impact facility & gas/handling design

7

Table 1CN (Alkane) Simulation PIONA Simulation

Process Simulation

ComparisonsHigh Press

Separator

Low Press

Separator

Recovered Tank

Flash

High Press

Separator

Low Press

Separator Recovered Tank Flash

OIL DATA Oil Production Oil Production

Oil Make, BPD, @ STD 609.1 463.1 454.8 596.3 451.3 443.0

API Grav @ STD 47.39 57.40 56.47 35.06 51.86 50.86

GAS DATA Gas Production Gas Production

Flow, MSCFD 512 36.1 11.6 517 34.3 11.6

Separator Gas SG 0.812 1.356 1.777 0.814 1.369 1.756

Heating value, BTU/SCF 1,350.0f 2,125.0 2,853.0 1,352.4 2,161.6 2,866.4

Total Heating value, BTU/SCF 1,431.1 1,432.9

Well Gas/Oil Ratio (GOR) 1,230.7 1,270.7

512 517

56.5 50.9

Using GOR Data

Reservoir engineers can provide gas-oil ratio (GOR) and type

curve (time vs. production)

Useful design tool for facilities engineer BUT “use with caution”

Normally developed from similar wells in the area (analogue wells)

GOR data can be misleading

GOR usually calculated from actual production data

Rarely adjusted for vapor recovery volumes

Measured separator oil density lower than final produced oil density

Make sure know how GOR is calculated

8

Using GOR Data (continued)

Design impacts

Well operating conditions strongly influence GOR calculations

Differences can range ± 25-50%

These differences can impact the equipment design

(stabilization)

9

Table 2 Alkane (CN) Simulation PIONA Simulation

Calculated GOR ValuesHigh Press

Separator

Low Press

Separator

Recovered Tank

Flash

High Press

Separator

Low Press

Separator

Recovered Tank

Flash

OIL DATA Oil Production Oil Production

Oil Make, BPD, @ T,P 617.7 477.0 467.8 601.5 461.6 452.6

Oil Make, BPD, @ STD 609.1 463.1 454.8 596.3 451.3 443.0

GAS DATA Gas Production Gas Production

Flow, MSCFD 512 36.1 11.6 517 34.3 11.6

GOR @ T,P 829 1,149 1,196 860 1,194 1,244

GOR @ STD 841 1,184 1,231 867 1,222 1,271841 1,184 867

46%

1,231 1,222 1,271

47%

Modeling Different Oils – Unit Based

3 typical oils (lt, med, hvy) modeled using PVT @ same

operating conditions

PVT reported API Gravities:

Oil B was used in the previous calculations

Table 3 Oil Production Gas Production, MSCFD

Process

Simulation for

Different OilsActual

BPD Standard BPD API Grav. RPV

From HP

Separator

From LP

Separator

From

VRT

Total Gas

Production

C2+ GPM Total

Gas

ECD Gas

Burned

Oil A 470.1 458.9 63.29 8.08 7,099.8 27.4 16.3 7,143.5 6.50 3.9

Oil B 467.9 458.9 41.53 7.05 548.7 22.9 14.3 585.8 9.08 2.4

Oil C 467.2 458.9 41.26 7.45 843.0 20.5 14.9 878.4 9.98 2.5

549

1193%

7,100

843

37.2

43.7

35.4

17 %

Oil A: 61.3; Oil B: 49.6; Oil C:35.8

Modeling Different Oils – (continued)

HPS production ranges +/- 1200%

Total LPS & VRT flash gas production only ranges +/- 25%

LPS/flash gas handling equipment sizing strongly dependent on total oil production

Less dependent on GOR

Simplifies design of gas handling facilitiesEquipment size based on oil production rates

The flash gas historically burnedState regulations require capturing flash gas for VOC control

Recent North Dakota regulations now require capturing most flash gas volumes

Modeling Different Oils – (continued)

Value of LPS & VRT flash gas not significant for single well

facilities, but very significant for multi-well pads

3-6% of total produced gas volume

10-14% of total gas revenue of the well

Adds ±$1/bbl. of the oil to the total wells revenue (Q1 Rocky Mtn. prices)

Table 4 Gas Production NGL Recovered

Btu Quantities & $/BBL

Values – flash gas 75 psig

basisHPS Gas,

MMBTU/D

LP Flash

MMBTU/D

VRT Gas

MMBTU/D

HPS Gas, NGL

GPD

LP Flash NGL

GPD VRT Gas NGL GPD

Case 1 - Light Oil 5,721.4 12.7 2.9 17,207 4 3

Case 2 – Med. Oil 717.3 15.3 3.4 1,125.0 164.6 184.9

Case 3 - Heavy Oil 36.5 1.2 0.8 2,501.6 184.8 226.9

Total Value, $/day Percent of Total Value

Case 1 - Light Oil 37,232 48 13 99.8% 0.1% 0.0%

Case 2 – Med.Oil 3,635 218 197 89.8% 5.4% 4.9%

Case 3 - Heavy Oil 2,629 189 230 86.3% 6.2% 7.5%

Total Value, $/BBL Oil Produced

Case 1 - Light Oil 81.13 0.10 0.03

Case 2 – Med.Oil 7.92 0.48 0.43

Case 3 - Heavy Oil 5.73 0.41 0.50

$0.91

$0.13

$0.91

Modeling Different Oils – Single Well (continued)

HPS operating pressure affects LPS & VRT flash gas volumes

Volume and total BTU production increases with HPS pressure

75 psig HPS pressure : flash gas 5% of total flow and 8% BTU value

250 psig HPS pressure : flash gas 16% of total flow and 25% BTU value

13

0%

5%

10%

15%

20%

25%

30%

35%

40%

50 100 150 200 250 300 350 400

HPS Pressure, PSIG

Flash Gas % of Total Flow

Flash Gas % of Total MMBTU/day

8%

5%

25%

16%

Lift Gas Design

Most shale oil wells need artificial lift to produce the wells

Gas lift is a common method of artificial lift

High pressure gas stream is injected into well bottom

Assists in driving produced water/oil to the surface

Single Well Site Iift gas compression

Plus: uses HPS gas compressed by pad compressors

Plus: easy installation; minimal facilities investment

Minus: requires many temporary units, one on each site

Minus: high $/hp for small units

Minus: no back-up for downtime

14

Lift Gas Design (continued)

Centralized lift gas compressionPlus: permanent gas lift compression facilities

Plus: lower $/HP

Plus: back-up for downtime

Plus: simple to add new wells; extend pipe

Minus: requires installation of gas lift lines & larger gathering systems

Minus: potential liquid drop problems in pipe and at well pads

Dew point units can be installed to prevent liquid problems Removing gas liquids increases net gas production from wells

Dry lift gas strips light ends from the oil

Helps stabilize the oil

15

Vapor Recovery Tower (VRT)

VRT introduced into well pad designs 2012/13

Provides a positive suction pressure to VRUs

Act as a liquid seal to prevent air ingress (O2) into the flash gas

Previously connected VRUs to tanks directly to tanks

<1 psig inlet pressure, create vacuum and pulls air into the flash

gas

Result O2> 10 ppm exceeding pipeline and facilities specs

Downstream operators installing O2 meters and will

shutdown on high O2

Increase risk of corrosion and solids with H2S present

16

Vapor Recovery Tower (VRT) - Continued

Vertical Vessel

• 30” to 60” dia. x 30’-40’ tall

• Internal dip tube

• Oil enters top

• Flows to bottom

• Fills vessel

• Pressure pushes oil up the dip tube to oil tanks

• Flash gas leaves top to VRU

17

OIL TANK

Flash Gas to VRU

Oil

VRT Design Continued

Original VRU design Approximately 5 feet above oil tanks

Problem upset downstream equipment (VRU)Blow out seal and limited pressure control (<2 psig pressure)

VRT design optimizationSnap acting dump valves upset downstream equipment operation (VRU/ VRT liquid levels)

Install a large K/O drum on the VRU

Increase the overall height of the VRT10 feet above tanks and some up to 20 feet above tanks

Convert to throttling dump valves

Install PCV to vent or flare on the VRU to avoid blowing VRT seals

Operate VRT at 2-4 psig for good control, prevent air ingress

18

VRT/VRU System Value – Not Always Economic

ASSUMPTIONS- $225k installation cost

- $2,500/mo. VRU lease

- 450 BPD IP Rate

- 35 psi secondary separator pressure

- $ 0.41/BBL gross value of VRT flash gas

- 85/85 POP gathering & processing fee

- Value is sensitive to HP and LP flash pressures

19

- Value is sensitive to HP and LP flash pressures

Tips on Shale Oil Gas Handling Facility Design

Heavy gas condenses, can build large recycleMaintain higher temps from VRU coolers with temperature controller

Use HPS gas for compressor recycle; helps clear out heavy gas

Air ingress can bust oxygen specificationUse HPS gas for VRU recycle, keep VRU running (no on/off operation)

NEVER use VRU’s to pull vapors from storage tanks

20

Tips on Shale Oil Gas Handling Facility Design

(continued)

ECD capacity VRT/VRU’s capture 90-95% of flash gas

ECD’s sized to handle low volume, also full VRU/VRT volume when VRU down

Design for flexibility Peak vs decline operation

Strategic drilling (offset) to optimize facility sizing and cost

21

Closing & Questions

Overall there are many opportunities available to better design and operate gas handling equipment.

During this low-price oil environment, it is critical to use this time and available resources to minimize the capital cost of these production facilities and improve the economics of the well.

Questions ???

22


Recommended