Development and Evaluation of Performance Tests to Enhance Superpave Mix Design and its Implementation in Idaho DTOS59-06-G-00029 (NIATT Project No. KLK479) ITD Project No. RP 181 (NIATT Project No. KLK483) Project Progress, May 6, 2008 1
Transcript

Development and Evaluation of

Performance Tests to Enhance Superpave Mix

Design and its Implementation in Idaho

DTOS59-06-G-00029 (NIATT Project No. KLK479)

ITD Project No. RP 181 (NIATT Project No. KLK483)

Project Progress, May 6, 2008

1

Team Fouad Bayomy (PI),

Dynamic properties, and overall project phases

SJ Jung, Fracture and Fatigue studies

Richard Nielsen, Reliability Studies

Thomas Weaver, Constitutive Modeling

Graduate Students Ahmad Abu Abdo Baek, Seung Il

ITD Coordinator (s) Mike Santi (Main Contact) Ned Parrish (Research Mgr) Others?? To be identified…..

USDOT Ashley Bittner / Ed Weiner,

COTR Paul Ziman (FHWA, Boise

Office) Others…

External Testing / Consulting Idaho Asphalt Supply, Inc. Image analysis (Masad at TTI) X-Ray Tomography (WSU or

UT, Austin) NIATT and CE Support

Judy LaLonde Don Parks Others

2

Presentation 1

Project Overview

F. Bayomy

3

Why this project?

ITD Moves towards SuperpaveSuperpave Mix Design System

Implementation of M-E DesignM-E Design guide at the national level

4

Project ObjectivesProject Objectives

Evaluate E* for Mixes that are commonly used in Idaho.

Determine E* vs. Temp for various binders used in Idaho, especially for polymer modified asphalts.

Develop constitutive models and develop procedure to estimate E* from given mix design properties.

Study of Gyratory Stability (GS) in relation to E*. Develop and evaluate mix fracture indicators for

ITD mixes. Incorporate reliability analysis.

5

Funding US DOT $ 280 k ITD $ 150 k UI Match (in kind) $ 154k

Total $ 584 k

6

Scope of Work

Phase A (Deformation study) Phase B (Fatigue and Fracture Study) Phase C (Implementation and Training) Phase D (Reporting)

7

Phase A: Mix Resistance to Deformation (E* and GS/CEI)

Tasks Literature Review Analytical Analysis Agg and Binders Evaluation Preparation and Evaluation of HMA

Mixtures Data Analysis Phase A Reports

8

Phase B: Mix Resistance to Fracture and fatigue Cracking

Tasks Literature Review Analytical Analysis Fracture Test Development Preparation and Evaluation of HMA

Mixtures Data Analysis Phase B Reports

9

Phases C and D: Implementation, Training & Reports

Tasks Work with ITD to Implement the Products Develop a training workshop to

disseminate the products Final Report / Peer Review

10

Progress

11

Phase / TaskQuarter

Month 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11

Task A1 – Review of previous studies and available data

10% 10% 2% 0% 2% 6% 0% 10% 40%

Task A2 – Analytical Analysis 12% 2% 4% 0% 7% 0% 5% 30%

Task A3 – Experimental Design, Binder and Agg. Eval.

15% 15% 10% 5% 15% 0% 5% 10% 75%

Task A4 – Prep and Evaluation of Asphalt Mixtures 5% 5% 10% 15% 20% 15% 15% 85%

Task A5 – Data Analysis 10% 0% 5% 15%

Task B1 – Literature Review 10% 15% 5% 5% 5% 5% 0% 5% 50%

Task B2 – Finite Element Analysis 5% 5% 5% 5% 15% 5% 40%

Task B3 – Development of the Fracture Test Procedure

12% 2% 5% 16% 35%

Task B4 – Prep and Evaluation of Asphalt Mixtures 0% 15% 10% 25%

Task B5 – Data Analysis 0%

Task B6 – Reliability Analysis 0%

Task C1 – Development of Implementation Plan 0%

Task C2 – Training Program for ITD Personnel 0%

Tasks A6, B7 and C3 – Quarter Reports for USDOT R1 R2 R3 R4 R5 R6 R7 Final 0%

Task D1: External peer review of the final report 0%

Task D2: Final report review by ITD 0%

Task D3: Final Report Submittal 0%

Phase C: Implementation of Research Products and Training

Reporting

Phase D: Final Report Review and Submittal

Phase A: Evaluation of Mix Resistance to Deformation

Phase B: Evaluation of Mix Resistance to Fracture and Fatigue Cracking

Q1 Q2 Q3 Q4

Calendar Yr 2007 Calendar Yr 2008 Calendar Yr 2009

Year 1 Year 2 Year 3

Tot

al %

Tas

k

Com

ple

tedQ1 Q2 Q3 Q4

Progress

12

Phase / TaskQuarter

Month 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11

Task A1 – Review of previous studies and available data

10% 10% 2% 0% 2% 6% 0% 10% 40%

Task A2 – Analytical Analysis 12% 2% 4% 0% 7% 0% 5% 30%

Task A3 – Experimental Design, Binder and Agg. Eval.

15% 15% 10% 5% 15% 0% 5% 10% 75%

Task A4 – Prep and Evaluation of Asphalt Mixtures 5% 5% 10% 15% 20% 15% 15% 85%

Task A5 – Data Analysis 10% 0% 5% 15%

Task B1 – Literature Review 10% 15% 5% 5% 5% 5% 0% 5% 50%

Task B2 – Finite Element Analysis 5% 5% 5% 5% 15% 5% 40%

Task B3 – Development of the Fracture Test Procedure

12% 2% 5% 16% 35%

Task B4 – Prep and Evaluation of Asphalt Mixtures 0% 15% 10% 25%

Task B5 – Data Analysis 0%

Task B6 – Reliability Analysis 0%

Phase A: Evaluation of Mix Resistance to Deformation

Phase B: Evaluation of Mix Resistance to Fracture and Fatigue Cracking

Q1

Calendar Yr 2007 Calendar Yr 2008

Year 1 Year 2Q1 Q2 Q3 Q4

Budget Status – KLK483

Budget Category

FY08 Adjusted Budget

Year to Date Encumbered/ Projected Costs

01-Salaries 80,141.00$ 17,036.80$ -$ 63,104.20$ 79%

02-Fringes 15,859.00$ 3,880.05$ -$ 11,978.95$ 76%

03-Irregular Help 10,000.00$ -$ -$ 10,000.00$ 100%

04-Travel 4,000.00$ 741.73$ -$ 3,258.27$ 81%

05-Other Expense 12,748.70$ 10,112.94$ 17.97$ 2,617.79$ 21%

06-Capital > 5K -$ -$ -$ -$

07-Capital Outlay < 5K 2,251.30$ 2,251.30$ -$ -$ 0%

08-Reserve -$ -$ -$ -$

09-Overhead 25,000.00$ 6,804.55$ 18,195.45$ -$ 0%

10-Tuition/stipends -$ -$ -$ -$

Total 150,000.00$ 40,827.37$ 18,213.42$ 90,959.21$ 61%

Balance

Budget Status – KLK479

Budget Category

FY08 Adjusted Budget

Year to Date Encumbered/ Projected

Costs

01-Salaries 63,009$ 22,513$ 4,337$ 36,159$ 57%

02-Fringes 2,985$ 106$ 58$ 2,821$ 94%

03-Irregular Help 5,000$ 1,105$ 2,415$ 1,480$ 30%

04-Travel 7,700$ -$ -$ 7,700$ 100%

05-Other Expense 19,921$ 567$ 94$ 19,260$ 97%

06-Capital > 5K 100,000$ 60,822$ 25,000$ 14,178$ 14%

07-Capital Outlay < 5K -$ -$ -$ -$

08-Reserve -$ -$ -$ -$

09-Overhead 45,659$ 11,247$ 34,412$ -$ 0%

10-Tuition/stipends 22,998$ 9,900$ 94$ 13,004$ 57%

Total 267,272$ 106,259$ 66,411$ 94,602$ 35%

Balance

Reports

Monthly_ ITD Form 771 http://www.webs1.uidaho.edu/niatt/research/P

roject_Descriptions/KLK483.htm

Quarterlyhttp://www.webs1.uidaho.edu/bayomy/klk479-483/qreports.htm