Development of Infrastructure Projects Public Consultation Sessions – Short List of Sites October 2015 Organics Processing Facility (OPF) and Materials Management Facility (MMF) Projects We are interested in receiving your feedback; speak with members of our Project Team and complete a comment form. Questions may be submitted prior to or following the presentation. Visit simcoe.ca/opf and simcoe.ca/mmf for more information. simcoe.ca Welcome Storyboard 1
Transcript
Page 1: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

Public Consultation Sessions – Short List of SitesOctober 2015

Organics Processing Facility (OPF) and Materials Management Facility (MMF) Projects

We are interested in receiving your feedback; speak with members of our Project Team and complete a comment form. Questions may be

submitted prior to or following the presentation.

Visit simcoe.ca/opf and simcoe.ca/mmf for more information.

simcoe.ca

Welcome

Storyboard 1

Page 2: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

Session Overview

Storyboard 2

2:00 - 2:30 Open House

• discussion with Project Team • opportunity to submit questions

2:30 - 3:00 Formal Presentation

• brief overview of project development • short-listed sites • moving forward

3:00 Question and Answer

Page 3: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

Session Overview

Storyboard 2

6:00 - 6:30 Open House

• discussion with Project Team • opportunity to submit questions

6:30 - 7:00 Formal Presentation

• brief overview of project development • short-listed sites • moving forward

7:00 Question and Answer

Page 4: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

Managing Your Waste 

Storyboard 3

• Solid Waste Management Strategy prioritizes the need to increase our diversion rate, reduce garbage, and securely manage our own transfer and processing capacity

• County will benefit from ownership and operation of its own facilities within its borders

• mandate to ensure secure and cost-effective management of diverted materials

Page 5: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

Why are we here? The purpose of this session is to:

• summarize project development to date

• present the short-listed sites for both the Organics Processing Facility and Materials Management Facility

• obtain feedback, comments, and questions in regards to the sites and potential to co-locate facilities

• outline next steps in the siting process

Storyboard 4

Page 6: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

What is a Materials Management Facility (MMF)?• integral part of a waste management system – the link between collection operations and final waste disposal/processing locations

• provides a location for transfer of garbage, organics, and blue box recycling to a final processor

• no long-term storage of materials or public drop-off

• replacing a private transfer facility in Barrie, estimated cost savings of $13M over the next 20 years

Storyboard 5

Page 7: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

MMF Siting Process

Storyboard 6

Up

com

ing

Fall 2015 Public and stakeholder consultation, further evaluation of short-listed sites

Early 2016 Preferred site presented to County Council

Next Steps:• commence engineering studies• approvals• construction • commissioning

2015

MarchCounty Council approves siting process and evaluation criteria

AprilRequest for Expression of Interest (RFEI) for willing vendor MMF sites released

June95 candidate sites evaluated

AugustShort list of sites released

2014

August Financial analysis determinesthat developing a MMF would be beneficial, Conestoga-Rovers & Associates retained as consultant for siting

Late 2014 $1.15 million in funding secured from Continuous Improvement Fund

December Public information sessions held

Page 8: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.caStoryboard 7

What is an Organics Processing Facility (OPF)? • a location where organics (green bin material, potentially materials such as leaf and yard waste, pet waste and diapers) are processed

• processing technology to be selected as the process continues

• valuable end products, such as compost or fertilizer, are produced and sold to market

Page 9: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

OPF Siting Process

Storyboard 8

Up

com

ing

Fall 2015 Public and stakeholder consultation, further evaluation of short-listed sites Early 2016 Preferred site presented to County Council

Next Steps:• commence engineering studies• select technology• approvals • construction • commissioning

2015

MarchCounty Council approves siting process and evaluation criteria

AprilRequest for Expression of Interest (RFEI) for willing vendor OPF sites released

June502 candidate sites evaluated

AugustShort list of sites released

2014

January County Council endorses phased project plan and timeline to develop OPF by 2018

May Conestoga-Rovers & Associates (CRA) selected as consultant June Public information sessions held

OctoberFormation of Community Engagement Committee (CEC) December Public information sessions held

Page 10: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

How were the short-listed sites selected?

Storyboard 9

Part 1 • defined the search area and developed the process to evaluate potential sites• public information sessions held in December 2014, feedback incorporated

Part 2 • identified a list of candidate sites and applied criteria to produce a short list of sites (7 for the OPF, 5 for the MMF)• Screen 1 criteria – was “must pass”, produced a long list of sites• Screen 2 evaluated long list in greater detail, particular consideration for land use and proximity of sensitive receptors

Page 11: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

simcoe.ca

Short-listed Sites

Storyboard 10

Nottawasaga Bay

Kempenfelt Bay

w

Organics Processing Facility Only Organics Processing Facility and/or Materials Management Facility

Page 12: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

simcoe.ca

Short-listed Sites - OPF Only

Storyboard 11

Flos Road 7 E

Penetanguishene Rd

Fairgrounds Rd N

Nottawasaga Sideroad 30 & 31

2249 Flos Road Seven East, Springwater 39 hectares / 96 acres

1637 Fairgrounds Road North, Clearview 23 hectares / 57 acres

Highly Vulnerable Aquifer

Medium Vulnerability Groundwater Recharge Area

Simcoe County Greenlands

High Vulnerability Groundwater Recharge Area

Canada Land Inventory - Soils Class 1- 3 Farmland

LEGEND

No Screen 1 or Screen 2 conflicts

Estimated footprint of OPF (to scale)*

* For illustration purposes only. Location of facility on the preferred site to be determined.

Page 13: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

simcoe.ca

Short-listed Sites - OPF and MMF

Storyboard 12

Line 5 N

Highway 400

Old Second South

High

way 11

Highway 400

Pen

etan

guis

hene

Rd

Gore Rd

Napoleon Rd

Rainbow Valley Rd E

Horseshoe Valley Rd W

Flos Road 3 E

1453 Flos Road Three East, Springwater

44 hectares / 109 acres

2976 Horseshoe Valley Road West, Springwater

84 hectares / 208 acres

540/528 Penetanguishene Road, Springwater

17 hectares / 42 acres

Line 5 North, Oro-Medonte

33 hectares / 82 acres

1473/1273 Old Second South, Springwater

91 hectares / 225 acres

Highly Vulnerable Aquifer

Medium Vulnerability Groundwater Recharge Area

Simcoe County Greenlands

High Vulnerability Groundwater Recharge Area

Canada Land Inventory - Soils Class 1- 3 Farmland

LEGEND

No screen 1 or screen 2 conflicts

Estimated footprint of facility (to scale)*

* For illustration purposes only. Location of facility on the preferred site to be determined.

Page 14: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

What’s Next?• public and stakeholder consultation on siting complete by November 2015

• we need your feedback by November to compile and incorporate into the consultant’s final evaluation

• sites will undergo further evaluation using all criteria – over 50 factors for consideration

• preferred site to be presented to County Council in early 2016 for direction

Storyboard 13

Page 15: Development of Infrastructure Projects Welcome · 2015-10-27 · Development of Infrastructure Projects simcoe.ca MMF Siting Process Storyboard 6 Upcoming Fall 2015 Public and stakeholder

Development of Infrastructure Projects

simcoe.ca

We’re Listening

We are planning for the future and would like your feedback.

Storyboard 14