+ All Categories
Home > Documents > Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015....

Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015....

Date post: 12-Nov-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
26
Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen - Germany)
Transcript
Page 1: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Usage of existing power plants

as synchronous condenser

Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen - Germany)

Page 2: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 2

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Conversion of existing power plants

to synchronous condenser units

Increased need of reactive power

Available solutions

Electrical and mechanical works;

examples Biblis and Ensted

Your advantage

Page 3: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 3

Public © Siemens Osakeyhtiö 2015. All rights reserved.

New challenges for power plants and power grids by a steady increase in

renewable power

Reduction of nuclear and fossil power is causing

stability problems in the HV-grid

(Reduction of short circuit power and voltage dips stability)

Increase of renewable energy

(wind parks in the north / PV in the south)

means stress to power grid

International transit trade of electricity causes additional

stress to transmission network

Page 4: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 4

Public © Siemens Osakeyhtiö 2015. All rights reserved.

• Lack of short circuit power capacity in the grid

• Voltage and frequency swings in the grid

• Grid capacity has reached its limit due to increased power transport

from one side of a country to the other side of the country

• Lack of generators for reactive power

• Power factor (cos φ) difficult to control

New challenges for power plants and power grids

by a steady decrease of fossil power generation.

Synchronous condensers as solution.

Impacts on the grid:

Page 5: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 5

Public © Siemens Osakeyhtiö 2015. All rights reserved.

New business model:

profitable growth by generation or reactive power

Page 6: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 6

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Conversion of existing power plants

to synchronous condenser units

Increased need of reactive power

Available solutions

Electrical and mechanical works to be done;

examples Biblis and Ensted

Your advantage

Page 7: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 7

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Synchronous generator as optimal solution for synchronous condenser

G

APFC

(Option 1)

APFC

(Option 2)

Active Power

Reactive Power

Reacti

ve P

ow

er

Synchronous generator working as

synchronous condenser5….1.500 MVAr (+/-)

Capacitor banks

working as condenserContinuous MVAr-regulation

up to 200 MVAr (+/-)

Transformer combination

working as phase shifterup to 1.000 MVAr (+/-)

System with

inductive

load

Three-phase

generator working

as a Synchronous

Condenser

Three-phase

Generator

G

3~

G

3~

Substation “A“

Substation “B“

Tap 4

Phase angle -7.5°

Power flow without

synchronous condenser

for compensation

Power flow with

synchronous condenser for

compensation

Page 8: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 8

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Synchronous generator working as

synchronous condenser

Conversion of power plants

to synchronous condenser units

or

New built synchronous condensers

Page 9: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 9

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Synchronous generator as optimal solution for synchronous condenser

Synchronous generator

working as synchronous

condenser

Transformer combination

working as phase shifterCapacitor bank working as

synchronous condenser

Investment cost per

MVArlow mid. high

Additional short circuit

current (rotating mass) Yes No No

Short delivery time Yes No No

Re-use of existing

componentsYes No No

Yes No NoOptimal solution

Page 10: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 10

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Charges for reactive energy*

CountryReactive Tariff

(Y/N)

Penalty

(Y/N)Tariff

Bosnia and

HerzegovinaY N 5,56€ / MVArh

Croatia Y N 20,90€ / MVArh

France N Y 13,3€ / MVArh

Germany Y/N Y/N 8,70€ / MVArh

Serbia Y Y 1,22€ / MVArh

Switzerland Y N 7,80€ / MVArh

Two charging schemes for reactive energy exist:

• Reactive Tariff: A regular tariff rate is applied to each MVArh of reactive energy produced and/or consumed.

• Penalty: Reactive energy produced and/or consumed is charged only if some pre-defined conditions are met. Examples can be excesses

of energy off-taken/fed-in during a given period or excess levels of cos φ or tg φ.

* ENTSO-E Overview of transmission tariffs in Europe Synthesis June 2014

Page 11: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 11

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Example amortization time for

synchronous condenser

Ownermax. reactive

power (MVAr)Tariff Project cost Amortization time

Germany

RWE800MVAr 8,70€ / MVArh 5,5M€ <24 month

… … … … …

Investment

Profit

Page 12: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 12

Public © Siemens Osakeyhtiö 2015. All rights reserved.

New tasks for old power plants means

advantages for all involved parties

Minimum costs due to use of existing plants.Written-off assets will be reactivated!

Extended lifetime of a power plantgenerates additional income

Grid is in an optimum range of operation due to improved cos φ and increase of short circuit capability; Decreased danger for blackouts

Page 13: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 13

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Conversion of existing power plants

to synchronous condenser units

Increased need of reactive power

Solutions

Electrical and mechanical works to be done;

examples Biblis and Ensted

Your advantage

Page 14: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 14

Public © Siemens Osakeyhtiö 2015. All rights reserved.

NPP Biblis: Generator in use for power-factor correction

Generator: 1500 MVA, 27 kV, 1500 rpm

Reactive Power: -450 … +850 MVAr

Start operation: 2012

Page 15: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 15

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Mechanical Works:

Conversion to synchronous condenser in few steps

Example: NPP Biblis

• Check and recalculation of generator design

(electrical and mechanical)

• Decoupling of generator and turbine

and dismantling of low pressure turbine part

• Modification and extension of generator shaft

• New / additional axial bearing

• New hydraulic motor

(in case of brushless excitation)

• New oil pumps and piping

Page 16: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 16

Public © Siemens Osakeyhtiö 2015. All rights reserved.

• Installation of start-up frequency converter for start-up

• Modification of generator protection system and synchronizer

• Modification of excitation equipment

• Modification / connection to the generator bus duct

• Installation of Is-limiter

• Electrical installation, cabling

Conversion to synchronous condenser in few steps

Example: NPP Biblis

Electrical Works:

Page 17: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 17

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Residual works:

Mechanical / hydraulic works:

• Blocking Generator / Turbine Springs

• Check of hydraulic oil pumps

• Modification of hydraulic pipes

I&C / DCS works:

• Installation of new probes and sensors

• Modification of DCS and turbine controller

• Connection to Control Room

Erection Supervision

Commissioning

Training

Conversion to synchronous condenser in few steps

Example: NPP Biblis

Page 18: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 18

Public © Siemens Osakeyhtiö 2015. All rights reserved.

View of the

• Generator

• new electrical

components

on top of the

low pressure

turbine housing

• and the remaining

high pressure

turbines

Overview of the electrical parts in Biblis

Conversion to synchronous condenser in few steps

Example: NPP Biblis

Page 19: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 19

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Generator: 850 MVA, 21 kV, 3000 rpm

Reactive Power: -350 … +800 MVAr

Start operation: 2013

Power Plant Ensted: Converted to Synchronous Condenser Operation

Page 20: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 20

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Other references in 2013….

Huntington Beach, USA

4x 128 MW (2013)

GKM, Germany

Study (2013)

Bjaerveskov, Denmark

270 MVA (2013)

DK1 & DK2, Denmark

2x 150 MW (2013)

Page 21: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 21

Public © Siemens Osakeyhtiö 2015. All rights reserved.

SPPA-E3000 Electrical Solutions

Conversion of existing power plants to synchronous condenser units

G LP HP/MPMP HP

Gas-Turbines Steam-Turbines

Main differences between Gas-Turbine

and Steam-Turbine adaptation

G TurbineComressor

For a conversion from power shaft

to synchronous condenser,

there is NO difference!There is always a direct connection to the

Generator which has to be removed.

Page 22: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 22

Public © Siemens Osakeyhtiö 2015. All rights reserved.

SPPA-E3000 Electrical Solutions

Conversion of existing power plants to synchronous condenser units

Possible disconnection ways

Disconnecting the generator

by moving the turbine

[2” (5cm) needed]

Disconnecting the generator

by removing the distance ring

between generator and turbine

Disconnecting the generator

by complete removal of the

LP-turbine (compressor)

TurbineCompressorG

Moving

turbine if

possible

TurbineCompressorG

Removing

distance ring

TurbineG

Removing

compressor/

LP-turbine

Page 23: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 23

Public © Siemens Osakeyhtiö 2015. All rights reserved.

Conversion of existing power plants

to synchronous condenser units

Increased need of reactive power

Solutions

Electrical and mechanical works to be done;

examples Biblis and Ensted

Your advantage

Page 24: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 24

Public © Siemens Osakeyhtiö 2015. All rights reserved.

• Increased controlled reactive power in the grid

• Increased short circuit capacity of the grid

• Stability of the grid

• Stability of the grid voltage

• To settle grid system incidents

• Increased capacity (load flow) of the HV power grid

• To keep old power plants alive

• To earn money

Conversion of existing power plants

to synchronous condenser units

Your advantages:

Page 25: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 25

Public © Siemens Osakeyhtiö 2015. All rights reserved.

SPPA-E3000

Synchronous Condenser

Thank you!

Page 26: Dipl.-Ing. Alexander Deecke / Siemens AG (Erlangen ...€¦ · Public © Siemens Osakeyhtiö 2015. All rights reserved. Usage of existing power plants as synchronous condenser Dipl.-Ing.

Page 26

Public © Siemens Osakeyhtiö 2015. All rights reserved.

To obtain further information, please contact:

[email protected]

Published by and Copyright 2015:

Siemens AG

Energy Sector

Fossil Power Generation

Instrumentation, Controls & Electrical

Siemensallee 84

76187 Karlsruhe, Germany

Tel.: + 49 721 / 595 - 69 43

Fax: + 49 721 / 595 - 67 21

www.siemens.com/energy/sppa-e3000

Subject to change without prior notice.

The information in this document contains general descriptions of the

technical options available which do not always have to be present in

individual cases. The required features should therefore be specified

in each individual case at the time of closing the contract.

SPPA-E3000 Electrical Solution

PG IE

AL:N ECCN:N

This document contains forward-looking statements and information – that is, statements related to future, not past, events. These statements

may be identified either orally or in writing by words as “expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words

of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks

and uncertainties. A variety of factors, many of which are beyond Siemens’ control, affect its operations, performance, business strategy and

results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results,

performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise,

among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction

of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens

worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in

Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and on the SEC’s website, www.sec.gov. Should

one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from

those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected.

Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ

from those anticipated.

Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their respective owners.


Recommended