+ All Categories
Home > Documents > Discussion with LHCC Referees November 18, 2008

Discussion with LHCC Referees November 18, 2008

Date post: 24-Jan-2016
Category:
Upload: gwylan
View: 41 times
Download: 1 times
Share this document with a friend
Description:
Discussion with LHCC Referees November 18, 2008. Memo sent to LHCC by LHCf Answers to Michelangelo’s questions Open point left from the previous meetings with referees Winter activities. LHCf Memo: Main points. - PowerPoint PPT Presentation
Popular Tags:
21
Discussion with LHCC Referees Discussion with LHCC Referees November 18, 2008 November 18, 2008 Memo sent to LHCC by LHCf Memo sent to LHCC by LHCf Answers to Michelangelo’s questions Answers to Michelangelo’s questions Open point left from the previous Open point left from the previous meetings with referees meetings with referees Winter activities Winter activities
Transcript
Page 1: Discussion with LHCC Referees November 18, 2008

Discussion with LHCC RefereesDiscussion with LHCC RefereesNovember 18, 2008November 18, 2008

Memo sent to LHCC by LHCfMemo sent to LHCC by LHCfAnswers to Michelangelo’s questionsAnswers to Michelangelo’s questionsOpen point left from the previous Open point left from the previous

meetings with refereesmeetings with refereesWinter activitiesWinter activities

Page 2: Discussion with LHCC Referees November 18, 2008

LHCf Memo: Main pointsLHCf Memo: Main points1. Our plan for the 2008/2009 winter shutdown is to continue working, focusing the

activities mainly on the DAQ software and analysis programs. We do not plan to remove the detectors from the TAN during this shutdown, but we will adapt them to the Remote Handling System.

2. As is clearly stated in the LHCf TDR, our experiment has been designed to take data at 14 TeV center of mass energy, at low luminosity (<1031 cm-2 s-1).

3. If it happens that the luminosity will exceed this limit during 5+5 TeV operation in 2009, then LHCf will have to be removed from the TAN to avoid excessive radiation damage.

4. We are extremely interested in the 7+7 TeV running since only then can we completely fulfill our physics task, which was approved by LHCC.

5. If the LHCf has been removed during 2009 operation because the luminosity has exceeded 1031 cm-2 s-1, we strongly hope to have the possibility to re-install LHCf in the TAN region during the 2009/2010 winter shutdown, and then complete our physics program early in 2010 (in the commissioning phase of the 7+7 TeV running).

6. We therefore kindly ask to the LHCC to investigate this possibility, and we strongly hope that the committee will reconfirm our original request, described in the TDR, for a LHCf data taking period at 7+7 TeV.

Page 3: Discussion with LHCC Referees November 18, 2008

Answers to Michelangelo’s Answers to Michelangelo’s questionsquestions

1. Is there a chance that with the current detectors you can take data already in 2009, regardless of the energy, and still preserve their functionaility for a final run at the highest energy in 2010? Could this be achieved by simply allowing for their removal after some integrated luminosity? I would find it really odd that you give up data taking in 09 simply because the energy is not at the highest value and you want to wait until that is available.

We completely agree with your opinions. It is very necessary to take data in 2009, and will try again the data taking at the highest energy in 2010.

Page 4: Discussion with LHCC Referees November 18, 2008

2. Is there a value in taking data at 10 TeV? 10 TeV instead of 14 should reduce only by a factor of 2 the equivalent CR energy at which you will be probing the production properties (E_CR ~ E^2/mp). Is a factor of 2 gain in energy so critical in the tuning of the MCs that you are willing to postpone by 1 year the possible analysis of data?

Yes, there is a strong value in taking data at 10 TeV. It is our unexpected good chance to get data at different energies. It will bring us not only important results on the energy dependence, but on the reliability of the results. Moreover, from the scientific point of view, we may expect CGC (Color Glass Condensation), a new hint to supress very low-x gluons recently discussed for HERA data among hadron theorists, that may link to composition measurement in UHECRs.

They are discussing that it would be more important at LHC energy. We think they may appear also in LHCf as increasing energy, maybe near 14TeV. This is also a good motivation for taking data also at 10TeV as a reference (and also 450 GeV!).

Page 5: Discussion with LHCC Referees November 18, 2008

Composition Composition fromfrom

Auger Auger

Xmax favors heavy primary

Anisotropy favors light primary (if we trust in the AGN correlation)

4

E>5.7.10E>5.7.101919 eV eV

Page 6: Discussion with LHCC Referees November 18, 2008

3. If indeed taking data in 2009 caused the detectors to fry and not be usable any longer in 2010 at the highest energy, is it conceivable to rebuild them?

We are planning to remove the detector during the high luminosity run. If it will not be possible, we are preparing to replace the plastic scintillators and the scintillating fiber belts, which might be damaged by a radiation dose greater than 10K rad.

Page 7: Discussion with LHCC Referees November 18, 2008

Open points left from the Open points left from the previous previous

meetings with refereesmeetings with refereesMain point: Main point:

What happens to the spectra if we trigger on the What happens to the spectra if we trigger on the Double Arm Coincidence (for background rejection)?Double Arm Coincidence (for background rejection)?

We certainly expect that the We certainly expect that the and and 00 spectra will spectra will change.change.

We are studying by simulation how the spectra will beWe are studying by simulation how the spectra will beaffected.affected.

We hope to have some results in the first months of We hope to have some results in the first months of 20092009

Page 8: Discussion with LHCC Referees November 18, 2008

Winter activitiesWinter activities

Timing measurements for silicon Timing measurements for silicon Done Done Baking out of the paint in the TAN will not be doneBaking out of the paint in the TAN will not be done

– We will not remove the detectors from the TANWe will not remove the detectors from the TAN Remote Handling System (RHS) will be installedRemote Handling System (RHS) will be installed

– We will modify the LHCf handling system to comply with We will modify the LHCf handling system to comply with the RHSthe RHS

– We are producing safety boxes to be installed above LHCf We are producing safety boxes to be installed above LHCf to avoid damages to the detectorsto avoid damages to the detectors

• We will install the protection boxes before the end of 2008We will install the protection boxes before the end of 2008

Improvements of the DAQ and analysis softwareImprovements of the DAQ and analysis software– Improvement of the online analyzerImprovement of the online analyzer– Improvement of the full data analysis flow (from DAQ to Improvement of the full data analysis flow (from DAQ to

storage)storage)– Alignment studiesAlignment studies– Improve cluster finding on silicon partImprove cluster finding on silicon part

Cross check of MC (EPICS based) simulation with Cross check of MC (EPICS based) simulation with Fluka codeFluka code

Page 9: Discussion with LHCC Referees November 18, 2008

Most important slides from the Most important slides from the last LHCC presentationlast LHCC presentation

Page 10: Discussion with LHCC Referees November 18, 2008

InstallationInstallation

Final installation was completed in January Final installation was completed in January 20082008

No major problems have been found No major problems have been found – Quartz fiber for laser calibration has been re-Quartz fiber for laser calibration has been re-

installedinstalled

Both Arm1 and Arm2 are working fineBoth Arm1 and Arm2 are working fine No additional noise is found in the detectors, No additional noise is found in the detectors,

despite 200 m long power lines and signal despite 200 m long power lines and signal cables (for the scintillators)cables (for the scintillators)

Page 11: Discussion with LHCC Referees November 18, 2008

Front CounterFront Counter

2 fixed Front Counters 2 fixed Front Counters were installed in front were installed in front of Arm1 and Arm2of Arm1 and Arm2

They will not move They will not move with Arm1 and Arm2with Arm1 and Arm2

They are segmented They are segmented in 2 x and 2 y slicesin 2 x and 2 y slices

Very useful to check Very useful to check the beam quality and the beam quality and hence decide to move hence decide to move Arm1 and Arm2 in the Arm1 and Arm2 in the operating position operating position from the ‘garage’ from the ‘garage’ positionposition

Page 12: Discussion with LHCC Referees November 18, 2008

After the installation….After the installation….

After the installation was completed, a lot of work After the installation was completed, a lot of work on:on:– DAQDAQ

• New VME board to increase DAQ rate up to > 1 KHzNew VME board to increase DAQ rate up to > 1 KHz• Integration of all the subsystem (Using MIDAS frame)Integration of all the subsystem (Using MIDAS frame)• Analyzer to check the data quality and online monitorAnalyzer to check the data quality and online monitor

– Slow control software to control and monitor:Slow control software to control and monitor:• Power suppliesPower supplies• ManipulatorManipulator• Temperature monitorTemperature monitor

– LHC interface LHC interface • New NIM style board (CIBU) to send ‘PERMIT’ to LHC (KILL the New NIM style board (CIBU) to send ‘PERMIT’ to LHC (KILL the

beam in case of high rate)beam in case of high rate)• Handhshaking software signals (DIP standard) for Injection, Handhshaking software signals (DIP standard) for Injection,

Adjust and Beam DumpAdjust and Beam Dump• LHCf Physics information (beam position, rate, background LHCf Physics information (beam position, rate, background

etc.)etc.)

Page 13: Discussion with LHCC Referees November 18, 2008

Synchronization with AtlasSynchronization with Atlas To have the possibility to identify the events To have the possibility to identify the events

common with Atlas we implemented a common with Atlas we implemented a synchronization method based on the L1A signal synchronization method based on the L1A signal generated by Atlas. generated by Atlas.

We receive Atlas L1A and we store the time We receive Atlas L1A and we store the time stamp of this signal in our DAQ system.stamp of this signal in our DAQ system.

We can really correlate the Atlas events with the We can really correlate the Atlas events with the LHCf ones!LHCf ones!

Atlas Bunch ID – LHCf Bunch IdAtlas Bunch ID – LHCf Bunch Id

Page 14: Discussion with LHCC Referees November 18, 2008

00 mass reconstruction mass reconstruction

(MeV)

Prelim

inary!!!!

250 250 00 events triggered (in a quite big background) and on disk events triggered (in a quite big background) and on disk

Main problems: Main problems: – low photon energy (low photon energy (≥≥ 20 20

GeV) GeV) – Direct protons in the towersDirect protons in the towers– Multi hits in the same towerMulti hits in the same tower

m m ~ 8 MeV~ 8 MeVm/m m/m ~ 6%~ 6%

Page 15: Discussion with LHCC Referees November 18, 2008

ARM1 Position resolutionARM1 Position resolution

σx[m

m]

σy[m

m]

Nu

mb

er

of

even

tN

um

ber

of

even

t

x-pos[mm]

y-pos[mm]

200 GeV electrons

xx=172=172 mm

yy=159 =159 mm

E[GeV]

E[GeV]

Page 16: Discussion with LHCC Referees November 18, 2008

ARM2 Position ARM2 Position ResolutionResolution

Position Resolution X Side

0

20

40

60

80

100

120

0 50 100 150 200 250

Energy (GeV)

Re

so

luti

on

(m

icro

ns

)

Data

Simulation Spread Out

xx=40 =40 mm

x-pos[mm]

y-pos[mm]

200 GeV electrons

yy=64 =64 mm

Position Resolution Y Side

0

20

40

60

80

100

120

140

160

0 50 100 150 200 250

Energy (GeV)

Re

so

luti

on

(m

icro

ns

)

Data

Simulation Spread Out

Alignment has been taken into accountAlignment has been taken into account

Page 17: Discussion with LHCC Referees November 18, 2008

Preparation for data takingPreparation for data taking

FurnituresFurnituresTelephonesTelephonesAir conditionerAir conditionerNetworkNetworkComputersComputersPrintersPrinters…………

The LHCf control room has been prepared and fully The LHCf control room has been prepared and fully

equipped in the Atlas areaequipped in the Atlas area

Page 18: Discussion with LHCC Referees November 18, 2008

Dummy eventDummy event

Page 19: Discussion with LHCC Referees November 18, 2008

Communications with LHCCommunications with LHC

Experimental status (On/Off, Gain, etc.)Experimental status (On/Off, Gain, etc.) Detector position (Garage/Operating, position in mm, etc.) Detector position (Garage/Operating, position in mm, etc.)

Luminosity rate (Single and Double Arm)Luminosity rate (Single and Double Arm)– Front Counter rate (single Arm, double Arm coincidence)Front Counter rate (single Arm, double Arm coincidence)– Small tower rate (single Arm)Small tower rate (single Arm)– Big tower rate (single Arm)Big tower rate (single Arm)– Double Arm coincidence rate (FC.AND.Towers in opposite Double Arm coincidence rate (FC.AND.Towers in opposite

sides)sides)

Horizontal and Vertical position of the Beam (every 10000 Horizontal and Vertical position of the Beam (every 10000 events or in the whole RUN)events or in the whole RUN)

Injection InhibitInjection Inhibit Handshaking signals (Injection, Adjust, Beam Dump)Handshaking signals (Injection, Adjust, Beam Dump)

LHCf sends signals to LHC through the DIP system.LHCf sends signals to LHC through the DIP system.Link have been tested and it works fine!Link have been tested and it works fine!

Important for machine tuning! Important for machine tuning!

Page 20: Discussion with LHCC Referees November 18, 2008

We are ready for data takingWe are ready for data taking On September 10 we observed some signals on On September 10 we observed some signals on

Front Counters, with Arm1 and Arm2 in garage Front Counters, with Arm1 and Arm2 in garage position for safety reasonsposition for safety reasons– That day the Atlas BPTX signal was still not That day the Atlas BPTX signal was still not

available (no info on the real bunches in the available (no info on the real bunches in the Atlas zone)Atlas zone)

On September 11 Atlas gave us the synchronized On September 11 Atlas gave us the synchronized BPTX signals, and we could take Front Counter BPTX signals, and we could take Front Counter data by using this signal (still in garage position)data by using this signal (still in garage position)

We are measuring Beam-Gas from the Beam2 on We are measuring Beam-Gas from the Beam2 on Arm1 sideArm1 side

Page 21: Discussion with LHCC Referees November 18, 2008

Front Counter signalsFront Counter signals


Recommended