ST. DISMAS ASSISTED LIVING FACILITY
Project DeliverablesType Occupancy No. of Rooms
Heavy Assisted Single 30
Light Assisted Single 20
Light Assisted Double 50
Project DeliverablesoBuilding Construction
o Living Room- TV, entertainment
o Bed Rooms
o Furniture Setup
oMedical Facility Setup
oGarden
oWalking Track
o Sheltered Connection
ConstraintsoTime Constraint: 7 months
(project duration)
oUnits Constraint: 100 units oLight Assisted: Most of single
occupancy rooms oConnectivity Constraint: New site has to be closer to appropriate location of the building
AssumptionsoHeavy Assisted: Given ->15-30 units Assumed -> 30 units oPopulation: Given -> 110 to 150 Assumed -> 150
Preliminary Level 1 Action PlanoPurchase land
oFinish initial paper works: oland registrationobuilding construction permission,o submit proposal to accreditation board
oDesign heavy & light assisted apartment plan
oConstruct BuildingoFurnish interiorsoSetup Medical FacilityoRecruit Staff
Dr.Fred -Project Manager?• Pros:
oMore control over the project
oDirect supervision
oQuick decision making in critical times
• Cons:
oNot able to completely focus on ALF project
oWill have other organization tasks to perform
oTrade off b/n ALF and other tasks: overloaded
RecommendationAppoint a Project Manager
• Reporting Frequency:
• 2 times/week
• Total: 56+ scheduled reporting
• Give decision making power for items,
which doesn’t require Fred’s direct
involvement