Capital Works Management Framework - Technical Briefing Paper
Popular Tags:
4
Davis Langdon PKS Technical Briefing Capital Works Management Framework Technical Briefing Government Procedures: The Capital Works Management Framework (CWMF) was published on www.constructionprocurement.gov.ie in mid-August 2009. The CWMF comprises of 4 Pillars which underpin the Government Initiative to reform public sector construction procurement. Reasons: The objective of the initiative is to achieve greater value for money, cost certainty and more efficient project delivery. Davis Langdon PKS were commissioned to prepare, in conjunction with the Department of Finance, a key suite of these documents. Challenges: All Public Sector Management\Personnel involved in the management and delivery of Building and Engineering Capital Projects must comply with these new best practice Guidance Notes. NUI Galway, Engineering Building, RMJM\T Architects
Transcript
Page 1: Dlpks Cwmf Technical Briefing

Davis Langdon PKS Technical Briefing

Capital WorksManagementFramework

Technical Briefing

Government Procedures: The Capital Works Management Framework (CWMF) was published on www.constructionprocurement.gov.ie in mid-August 2009. The CWMF comprises of 4 Pillars which underpin the Government Initiative to reform public sector construction procurement.

Reasons: The objective of the initiative is to achieve greater value for money, cost certainty and more efficient project delivery. Davis Langdon PKS were commissioned to prepare, in conjunction with the Department of Finance, a key suite of these documents.

Challenges: All Public Sector Management\Personnel involved in the management and delivery of Building and Engineering Capital Projects must comply with these new best practice Guidance Notes.

NUI Galway, Engineering Building, RMJM\T Architects

Page 2: Dlpks Cwmf Technical Briefing

Capital Works Management Framework

This Technical Briefing is aimed at giving an introduction to the overall structure of the Capital Works Management Framework (CWMF).

The Capital Works Management Framework (CWMF) consists of a suite of documents that constitutes the four pillars of the Framework.

Pillar 1 Public Works Contract

A suite of standard forms of construction contracts and associated model forms, dispute resolution rules, model invitations to tender, forms of tender and schedules;

Pillar 2 Conditions of Engagement

The standard conditions of engagement for consultants;

Pillar 3 Cost Planning and Control

Standard templates to record data in an appropriate way, to enable analysis, future comparison and ease of retrieval.

Pillar 4 Guidance Notes

Extensive guidance notes covering the various activities in a project delivery lifecycle.

Previously Published Contracts

There has been guidance note material and industry training rolled out in relation to the documentation contained in Pillars 1 & 2 (Contracts & Conditions of Engagement). The principle source for the Department of Finance sponsored information is on:

www.constructionprocurement.gov.ie

Substantive New Guidance Notes and Templates

The second half of the CWMF (Pillars 3 & 4) hasjust recently been published on the above website.Davis Langdon PKS have been directly involved inPillar’s 3 and 4 where we were commissioned bythe Department of Finance to develop a number ofthe key Guidance Note documents and to create theCost Planning and Control document templates.

These key Guidance Notes relate to the critical“Planning; Developed” and “Implementation” stages;

Project Management

Design Development Process

Planning and Control of Capital Costs

Procurement Process for Works Contractors

Implementation Process

Project Review

WORKS MAN

AGEM

ENT

CA

PIT

AL

FRAME WORK

Pillar 3 Pilla

r 4

Pi

llar 1 Pillar 2

Terminal II Dublin AirportNational Rehabilitation Centre

Page 3: Dlpks Cwmf Technical Briefing

Project Structure

There are a number of key new components which are utilised throughout the Guidance Notes contained in Pillar 4. These are;

Project Coordinator

Project Execution Plan

Risk & Value Management

Project Reviews

Project Coordinator

The formal introduction of a Project Coordinator to the Project Team Structure is a key development and will have a pivotal role in leading the project.

Project Execution Plan

The creation of a Project Execution Plan at the project outset establishes clear project objectives, references a defined scope of works and puts in place formal team structures with defined roles and responsibilities.

This provides a solid footing for the team to manage the project going forward and for the project and team performance evaluation on completion.

Risk & Value Management

Risk & Value Management are constant themesthroughout the new Best Practice Procedures andthe CWMF requires that these processes are implemented at the various project stages.

Project Reviews

A series of defined Red and Amber project reviewshave been established with clear procedures as tothe steps to be taken to move to the next stage.Red are those that require submission of a reportand Sanctioning Authority approval in writing prior to proceeding.

Amber require reporting to and review by the SponsoringAgency who in turn should inform the SanctioningAuthority. The project can proceed once theSanctioning Authority has been informed.

Capital AppraisalStage

Conditionsof EngagementStages

Main ProjectActivities

Building

Project Review 1

Project Review 2

Project Review 3

Project Review 5

Project Review 4

Project Review 6

Project Review 7

Make expert appointments(design studies) and appointPSDP (if required)

Develop Definitive Project Brief

Determine procurement strategy

Appoint Design Team

Design Team assesses outputrequirements, constraints, budget

Outline Sketch Scheme

Developed Sketch Scheme

Detailed Design(not design-and-build)

Submit for statutory approval

Conduct Tender process

Award contract

Administer Contract

Supervise management ofconstruction process

Manage the Post Project Review

Stage (i)Feasibility Study\Preliminary Report

1 Planning Initial

2 Planning Developed

3 Implementation

4 Review

Stage (ii)Design

Stage (iii)Tender

Stage (iv)Construction

Stage (v)Handover

University of Limerick Indoor Pitch Arena

Page 4: Dlpks Cwmf Technical Briefing

Capital Works Management Framework

Are you involved in Public Sector Capital Projects?

Are you aware of all the documentation governing the Capital Works Management Framework?

Do you understand your roles and responsibilities and those of other partiesinvolved in projects, under the new Capital Works Management Framework?

Have you reviewed your processes and procedures to maximise efficiency,project success and compliance with the CWMF?

If you have a requirement for assistance in the adoption of the CWMF pleasecontact Davis Langdon PKS who have a dedicated Public Sector ManagementTeam. Davis Langdon PKS can work with Sanctioning Authorities and SponsoringAgencies to establish sector and project specific CWMF Implementation Plans. Inaddition we can offer bespoke training for staff and those charged with theimplementation of the CWMF.

Contact:

Tomás Kelly

Davis Langdon PKSConstruction ConsultantsHeritage Hall, Kirwan’s LaneGalway

Tel + 353 91 530199Fax + 353 91 530198Email: [email protected]

Davis Langdon PKS Construction ConsultantsContact Information

DLPKS Dublin Office 24 Lower Hatch StreetDublin 2

Phone + 353 1 676 3671FAX + 353 1 676 3672Email [email protected]

DLPKS Galway Office Heritage HallKirwan’s LaneGalway

Phone + 353 91 530 199FAX + 353 91 530 198Email [email protected]

DLPKS Limerick Office Mezzanine SuiteRiverpointLower Mallow StreetLimerick

Phone + 353 61 318 870FAX + 353 61 317 871Email [email protected]