+ All Categories
Home > Documents > DØ Fiber Tracker Installation and Commissioning

DØ Fiber Tracker Installation and Commissioning

Date post: 05-Jan-2016
Category:
Upload: tom
View: 39 times
Download: 4 times
Share this document with a friend
Description:
DØ Fiber Tracker Installation and Commissioning. Don Lincoln DØ Collaboration Fermilab Director’s Review December 7, 1999. Fiber Tracker Overview. stereo. axial. stereo. axial. Scint Fibers 830m m Æ , multiclad 1.6-2.5m active length 10m clear waveguide to photodetector - PowerPoint PPT Presentation
40
D D Director’s Review Dec 1999 (DL) DØ Fiber Tracker Installation and Commissioning Don Lincoln DØ Collaboration Fermilab Director’s Review December 7, 1999
Transcript
Page 1: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

DØ Fiber Tracker

Installation and

Commissioning

Don LincolnDØ Collaboration

Fermilab

Director’s ReviewDecember 7, 1999

Page 2: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Tracker Overview

Scint Fibers m , multiclad 1.6-2.5m active

length 10m clear

waveguide to photodetector

rad hard (100 krad) (10yr @ 20cm @1032)

Fiber Ribbons 8 axial doublets 8 stereo doublets

(3o pitch)

Readout 77,000 channels VLPC readout run at low temp (9

K) fast pickoff for

trigger SVXII readout

end view

side view

axial

stereo

axial

stereo

Scintillating FiberOptical Connector

Waveguide Fiber

Mirror

Photodetector CassetteElectrical Signal Out

Cryostat

Page 3: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Prototype Commissioning

At Lab 3, a prototype cosmic ray test has been underway for about a year.

To date: Tested two cylinders (3A & 3B) Lightguides and connectors Prototype cassettes (final design) Cryogenics and control Prototype analog electronics boards

(‘stereo’ boards, with SVX-II readout) Standalone sequencer DAQ

Soon Final sequencers VRB readout

Eventually Final analog board (AFE) shakedown

Page 4: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cosmic Ray Test of CFT

110 cm

xvv

xvv

xvv

19.05 cm19.05 cm

Light GuidesLight Guides

88 cm

127 cm

Proportional Drift TubesProportional Drift Tubes

2(3 deg) Stereo Ribbons2(3 deg) Stereo Ribbons4 Axial Ribbons4 Axial Ribbons

4096 4096 VLPC pixelsVLPC pixels4 Cassettes4 Cassettes

CryostatCryostat

Forward and Forward and Central Preshower ModulesCentral Preshower Modules

110 cm

xvv

xvv

xvv

19.05 cm19.05 cm

Jadzia WarcholNotre Dame

Page 5: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

DAQ

CBDCBD82108210

CAMACCAMAC(TDCs for drift tubes)(TDCs for drift tubes)

DART eventDART eventin lab3sgi1in lab3sgi1

MVMEMVME162162Motorola 68kMotorola 68k

FE board on CassetteFE board on Cassette

Stand Stand Alone Alone SequencersSequencers

XVMEXVME200200((GENERATESGENERATESINTERRUPTINTERRUPT))

EthernetEthernet linklink

VME CRATEVME CRATE

Jadzia WarcholNotre DameStan Krzywdzinski

Page 6: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Prototype Commissioning

Cosmic Ray Test Installed two separate

cylinders (3A/3B) Tested lightguides Tested prototype

electronics Tested DAQ

Jadzia WarcholVolker BuescherJuan EstradaStefan Grunendahl

Page 7: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Pre-installation Commisisoning

At Lab 3, all components of the CFT will be tested.

Fiber positions are surveyed. During nesting, each cylinder

is aligned to the others on CMM.

CFT arrives at DAB as a single-piece unit.

Each VLPC cassette is qualified at Lab 3

Each lightguide is tested at ND or IU prior to shipping.

Page 8: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Necessary Components

Installation Support fixtures Installation fixtures Fiber bundles

Installation and Commission Cassettes Cryostat and cryogenics plant Electronics (readout,

temperature and voltage control, LEDs)

Gas system DA system Tracking code Examines, etc.

Pre-Installation and Pre-Commissioning

Page 9: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cryogenics

Two independent cryostats

Most material either in house or on order.

Fabrication 11/4/99 - 4/7/00 Installation 4/10/00 - 4/28/00 Shakedown 4/28/00 - 6/12/00

Prototype installed and running at Lab 3 7/15/97.

Russ RucinskiBob Barger

Cryostat positions, relative to DØ

(Nothing to Scale)

Page 10: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Lab 3 VLPC Cryostat

Test Cryostat - holds 4, full-size VLPC cassettes. Provided input to final cryo design

Fully Tested Meets specification

Russ RucinskiBob Barger

Page 11: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cryostat

Page 12: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Lightguide Production

Magnitude of the problem CPS 30 bundles of 256 fibers FPS 64 bundles of 256 fibers CFT 300 bundles of 256 fibers,

with each cylinder having a different connector

106 m of fiber (500 kg)

100 CFT bundles of unconnectorized fiber, pulled to correct length

Many CPS bundles under construction.

50% of waveguides 3/1 100% of waveguides 7/6

Notre DameIndiana University

Page 13: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing I

2-FRONT

CFWCFE

CENTERBEAM

FORWARD DETECTORS

FORWARD PRE-SHOWERICD

LEVEL ZERO

WAVE GUIDEPATCH PANEL

VLPC CRYOSTAT INSTALLATION

SEPT 98

WAVE GUIDE FIBERBUNDLE INSTALLATION

VLPC CASSETTE

VLPC CRYOSTAT

SILICON TRACKER POWER SUPPLIES

VLPC CASSETTE

VLPC CRYOSTAT

TRACKER CABLING SLOT

ECS

Waveguide bundles consist of 256 fibers in light-tight nylon sheath

Curved connector (256 ch.) at detector 2 128 ch. Connector at cassette end

Page 14: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing II

3-FRONT

4-FRONT

D3

-G4

B 1

5A 5B

E 3

R99.000

A2

-G5

A 2

G 5

C 3

E 4

C3

-E4

A 1

H 5

A1

-H5

B 2

F 4

123

ONE HALF CONNECTOR IN SECTOR 3 ONLY WITH FULL SHAREDCONNECTORS AT SECTORS 1 & 2, AND SECTORS 4 & 5.

4 5

B2

-F4

274

296

232

135

177

SECTORS 1 THRU 5 (5 SPLIT)CABLE ROUTES3/4 DIA. BUNDLES HELD AT R58 AND

CONTINUING ON TO THE TOP OF THE NOTCHES575eith3card.dwg

SCALE: 1/8(LOOKING AT SOUTH FACE OF CC)

B 3

H 6

B3

-H6

D4

-F5

D 4

F 5

B 5

B5

-H1

1

F 9

G 1 0

H 1 1

F9

-G1

0

D 7

E 8

D7

-E8

C 6

H 1 0

B1

-E3

C 2

F 3

H 4

D 2

C2

-H4

D2

-F3

D 3

G 4

C6

-H1

0

G 9

A 4

A4

-G9

E 7

G 3

H 3

G3

-H3

E2

-F2

E 2

F 2

F 8

E7

-F8

D 6

H 9

D6

-H9

C 5

G 8

C5

-G8

E 6

F 7

E6

-F7

B 4

H 8

B4

-H8

G 7

D 5

D5

-G7

A 3

F 6

A3

-F6

C 4

H 7

C4

-H7

E 5

G 6

E5

-G6

C1

-D1

C 1

D 1

E 1

F 1

G 1

H 1

H 2

G 2

E1

-G1

F1

-H2

G1

-H1

C.P.S

.

C.P.S

.

H 1 2

H 1 3

H 1 4

H 1 5

H 1 6

H 1 7

G 1 1

G 1 2

G 1 3

G 1 4

G 1 5

F 1 0

F 1 1

F 1 2

F 1 3

F 1 4

E 9

E 1 0

E 1 1

E 1 2

D 8

D 9

D 1 0

D 1 1

C 7

C 8

C 9

B 6

B 7

B 8

A 5

A 6

H 1 8

H 1 9

H 2 0

H 2 1

H 2 2

G 1 6

G 1 7

G 1 8

G 1 9

G 2 0

G 2 1G 2 2

F 1 5

F 1 6

F 1 7

F 1 8

F 1 9

F 2 0

E 1 3

E 1 4

E 1 5

E 1 6

E 1 7 E 1 8

D 1 2

D 1 3

D 1 4

D 1 5

D 1 6

C 1 0

C 1 1

C 1 2

C 1 3

C 1 3

B 9

B 1 0

B 1 1B 1 2

A 7

A 8

A 9

A 1 0

B 1 3

C 1 4

C 1 5

D 1 7

D 1 8

E 1 9

E 2 0

F 2 1

F 2 2

F 2 3

G 2 3

G 2 4

G 2 5

H 2 3

H 2 4H 2 5

H 2 6

H 2 7

H 2 8

B6

-C8

-F1

0-H

12

E9

-G1

1

Page 15: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing III

Page 16: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing IV

Page 17: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing V

Page 18: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing VI

Page 19: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing VII

Page 20: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Fiber Routing VIII

Page 21: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Waveguide Installation Manpower

Waveguide Installation 5/11/00 Duration 8 weeks

Physicists: Wayne 25%ND

Shepard 25% ND PostDoc 100% ND 1 student 100% ND Ray 50% Gutierrez 50%

Engineer: Cease 50%

Techs: (All Lab 3) Butler 100% Kubinski " Spartana " Garramone " Tolian " C. Davis " Flores "

Page 22: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cassettes

VLPC’s and most mechanical components in house

Four prototype cassettes have been built

Production manufacture has begun

50% completion 5/3/00 100% completion 9/13/00 2.5 cassettes/week

George GintherVolker BuescherGreg DavisDan Olis

Page 23: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cassette

Engineering Drawing Constructed Cassette

Page 24: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cassette Installation Manpower

Cassette Installation - First 50 4/26/00 Duration: 5 weeks

Physicists: All University of Rochester Ginther 25% Buescher 50% G. Davis 50% J. Estrada 50% F. Canelli 50%

Engineer: Anderson 20% Fogelsong 25%

Techs: B. Davis 100% Lab 3 Barger 20% Electronics 50% From MJ

Page 25: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cassette Installation Manpower

Cassette Installation - Last 50 8/15/00 Duration: 5 weeks

Physicists: All University of Rochester Ginther 25% Buescher 50% G. Davis 50% J. Estrada 50% F. Canelli 50%

Engineer: Anderson 20% Fogelsong 25%

Techs: B. Davis 100% Lab 3 Barger 20% Electronics 50% From MJ

Page 26: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Electronics Status

In House: prototype stereo boards (used in Lab3 CRT)

AFE ordered 3/8/00 AFE 10 boards available 5/3/00 AFE all available 8/11/00

DFE ordered 12/15/99 DFE 10 boards available 5/10/99 DFE all available 9/1/00

Mixer boards ordered 5/31/00 Mixer boards available 7/27/00

First crate operational 5/17/00

Marvin Johnsonand crew

Page 27: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Tracking Test

Current Code can track single muons as long as impact parameter is not too big.

Run I algorithms allowed larger impact parameter

Kin YipNorm Graf

Page 28: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

EXAMINE/Data Integrity

Code exists and is ready for data

Andrei MayorovIndiana University

Page 29: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Cosmic Ray Manpower

Cosmic Ray Run 7/15/00Duration: 8 w Physicists: Warchol 100% ND PostDoc

100% Mayorov 100% Lincoln 25% ND Students 100%

Techs: Electronics 25%

From MJ

Page 30: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

FullDAQ Startup

CFT Timeline

2000 2001 J F M A M J J A S O N D J F

FT install/hookup

1st CFT crate

operational

Waveguide production

SMT install/ hookup

Roll

in

Beam-

ready

Ribbon Mounting

Cryo Install/Shakedown

Support Design/Fabricate

Cassettes Installed

50%

50%

Assembly Complete

4/27

5/11

2/1 3/13 4/24

5/12 5/25

7/24

9/1

8

9/2

5

10/3

0

3/1 7/6

Cryo Fabrication4/7

4/10 4/28 6/12

Cassette Assembly

50% 5/3 9/13

5/1710/48/01

5/17

Full SystemTest

9/5 10/30

3/8 4/7

Commission CFT

6/12 10/30

Page 31: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Technician Manpower

Fiber Tracker Tech EffortFNAL

0

5

10

15

20

25

Jan-

99

Mar

-99

May

-99

Jul-9

9

Sep

-99

Nov

-99

Jan-

00

Mar

-00

May

-00

Jul-0

0

Sep

-00

Nov

-00

Jan-

01

FT

Es

All

Install.

Fiber Tracker

Note about the legend:

“All” - refers to effort assigned to all tasks in the relevant schedule

“Install.” - refers to effort assigned to a subset of those tasks flagged as installation tasks

Tech effort is sum of MTF112+ETF112

Page 32: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Summary

All components will be pre-tested and pre-commissioned, prior to arrival at DAB

Lightguide map is complete.

Manpower lists here are adequate for installation

Will need close cooperation with electronics group for cosmic ray commissioning

Page 33: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Ribbons

Page 34: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Ribbons

= 18.4 mAve. = 0.3 m

Page 35: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Ribbons - Optical Connectors

Have now received 50%

of curved connectors Material - Torlon Optical coupling efficiency > 90%

Cylinder 3 Stereo Connector

0.00.10.20.30.40.5

0.60.70.80.91.0

1 16 31 46 61 76 91 106 121

Fiber Number

Tra

nsm

issi

on

Outside Row

Inside Row

Page 36: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Mechanical Supports

WBS 1.1.2.7

Cylinder 850 meas. Along L

3.5 mil RMS

1 division = 6.25 mil

Page 37: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Ribbon Mounting

Ribbon 3S2 mounting radii

11.86811.87011.87211.87411.87611.87811.88011.88211.88411.88611.888

0 20 40 60 80 100

Axial position [inches]

Ou

ter

rad

ius

[in

ch

es

]

121.7 deg 126.7 131.7 136.7 141.7

G. GutierrezRon RayJohn Krider

Page 38: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Support Fixtures

Two (three?) fixtures at 3 & 9 o’clock (possibly one at 6)

Aluminum plates Connect to the FT between

layers 6-8

Design 2/1/00 - 3/13/00 Fabricate 3/14/00 - 4/24/00

Kurt Krempetz

Page 39: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

Installation Fixturing

Technique same as inserting solenoid

Use same (modified) fixturing

Design/fabricate installation fixture 2/18/00 - 4/14/00

CFT

Rollers

Solenoid

Page 40: DØ Fiber Tracker Installation  and  Commissioning

DD

Director’s ReviewDec 1999 (DL)

CFT Install Manpower

CFT moves to DØ 5/4/00 Duration: 1 week

Fnal Surveyors 100% Krempetz 50% D. Butler 100%


Recommended