Date post: | 29-Dec-2015 |
Category: |
Documents |
Upload: | domenic-kennedy |
View: | 228 times |
Download: | 0 times |
DOW RESTRICTED - For internal use only
Material Verification for Piping
Positive Material Identification in Texas Operations
MyLearning Course Code 281258
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Introduction
• The intent of Positive Material Identification (PMI) for pipe systems is to reduce the likelihood of process safety risks by verifying that the installation of alloy and low alloy steel piping materials is consistent with engineering specifications.
• This discipline applies to Maintenance, Small Projects Construction Group (SPCG), and Engineering Solutions Construction.
You were invited to this training because your role has responsibilities in the PMI process.
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Desired Outcomes
In this session we will; 1. Explain what Positive Material Identification for piping (PMI) is.2. Explain why we’re formalizing a PMI process.3. Provide an overview of the PMI process.4. Review role responsibilities.5. Review process steps.6. Review next steps.
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
TXO Operating Discipline Development Team
Sponsors• Wayne Muil, Site Maintenance Leader• Dave Rizzo, Engineering Solutions Construction Leader
Team• David Barber, Maintenance Technology Center• Mike Groth, Engineering Solutions• Gary Parker, Site Maintenance• Donny Stamps, Site Maintenance• Mike Stepien, Site Reliability
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Dow’s Corporate Loss Prevention Principles indicate that we will use appropriate materials in our piping systems such that risks are managed.
• Our Process Safety efforts continue this thought through the Global Mechanical Integrity Safety Standard (GMISS) stating the use of proper materials in our piping systems.
• General guidance for verification of proper material usage follows the API recommended practice 578.
• EMETL Specification G8S-5002-03 Material Verification Program - Piping
Material Verification Program - Piping
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Why add another requirement?Events
Exxon Coker – substitution of material resulted in Coker fire and fatalities
BP Texas City – wrong material re-installed resulted in major fire and equipment damage
Dow Chlor-Alkali Events (~$7MM impact)• Freeport ($600M replacement & 60MM lbs AC loss)• Plaquemine (EH&S incident (PS) & 12MM lbs AC loss)
Marsh Limited Insurance Audit Feedback (April 2008)
“We would therefore recommend that the site amends its material identification procedures (typically only depending on mill certificate checks) to include physical verification sampling of key alloys arriving at the warehouse and/ or the construction field.”
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
• The installation of alloy and low alloy steel piping materials shall be verified to be consistent with engineering specifications.
• This process applies to installation of new piping and work on existing piping.
• Pipe • Pipe Fittings (tees, elbows, reducers, blinds, plugs, stub ends, and
special pipe components)• Flanges, for lap joint stub ends, both the ring flange and piping
stub end will be analyzed.• Welds and consumables (electrodes & filler metal)• Special forgings• Process valve bodies (including control valves) and relief devices• Expansion joints and bellows
Scope
Material Verification Program - Piping
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
How was the PMI level established?
Business Tech Centers (using criteria in G8S-4001-65) determined Positive Material Identification (PMI) Inspection Levels;
• Level 1 – Sampling• Level 2 – Full Finished• Level 3 – Full in Process
Note: These inspection levels will be explained later in this presentation
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
(5) Considering (1) – (4) is more verification needed?
(4) Business Risk – LOPC or Reactive Chemical
(3) NFPA (Fire) Hazard Rating 3 or greater
(2) GMISS hazard class assigned or corrosive substance?
(1) Alloy or Low Alloy Steel Pipe Spec?
IF YES, the Business Tech Center:1. Determines the required inspection level.
2. Adds a standard note to the pipe spec.
IF No, no change.
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
What was the result of PMI criteria application?
The Impact
Out of ~1570 total pipe specs in CPPS, 700 are alloy pipe specs and of those 148 have Level 1 – 3 requirements (to-date)
Inspection Level Table (example on next page)
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Material Verification Log Example
Some Level 3 Inspection Levels for Chlor Alkali
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Chlor Alkali Example
PMI Inspection Level Note
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Material Verification Inspection Requirements
Level 1 - Sampling• PMI by X-ray fluorescence or spark OES* for 25% of welds …• At least 1 test of each welder• At least 2 tests per pipe weld• A nonconformance will escalate testing coverage …• Piping removed and reinstalled must be PMI tested for verification
or labeled appropriately in the field
Technologies with L1 Requirements Identified include (but not limited to) Chlorinated Organics, Chlorohydrin Oxides & Glycols, Energy Systems, Hydrocarbons, Polycarbonate, Polyethylene, Polypropylene
* Optical Emission Spectrometer
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Material Verification Inspection Requirements
Level 2 – Full Finished• PMI by X-ray fluorescence or spark OES for 100% of finished
welds …• Four readings 90 degrees apart for 3” NPS and larger, 2” and
less require 2 tests per weld• Piping removed and reinstalled must be PMI tested for
verification or labeled appropriately in the field
Technologies with L2 Requirements Identified include (but not limited to) Contract Manufacturing, EDC/VCM, Chlorinated Organics, Specialty Alkanolamines, Environmental, Energy Systems, Hydrocarbons, Styrene Monomers
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Material Verification Inspection Requirements
Level 3 – Full in Process• PMI by X-ray fluorescence or spark OES for 100% of root passes …• Root pass tests will require 1 test per nominal inch …• Only 1 material shall be in the welder’s possession and tested.• Piping removed and reinstalled must be PMI tested for verification or
labeled appropriately in the field
Technologies with L3 Requirements Identified include (but not limited to) Chlor Alkali, EDV/VCM, Chlorinated Organics, Specialty Alkanolamines, Environmental, Polycarbonate, Styrene Polymers
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Piping repairs must be requested against the
proper Equipment Group, Pipe Spec, Equipment ID
P01 Piping (Non Hazardous)
P02 Classified Piping
I80 Control Valves
P72 Valves
Maintenance Example for Executing Positive Material Identification
Continued on next slide
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Plan for the required PMI
Level
Maintenance Example for Executing Positive Material Identification
Continued on next slide
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Fabricate/Test or Repair/Test per PMI Level
Qualified Inspector1. Confirms testing2. QC DocumentationProvided by the PMI Technician
Maintenance Example for Executing Positive Material Identification
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
TXO Operating Discipline for Positive Material Identification
L3G (Level 3 Geographic) Texas Operations document
Positive Material Identification for Piping in Texas Operations
In this session we will review;
1. Role Responsibilities
2. Process steps for Maintenance, Engineering Solutions / Small Projects Construction Group
3. Measurements
4. Gap Resolution
DOW RESTRICTED - For internal use only
What does success look like?
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Weld Map (and Component Map)
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
PMI Inspection Report
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
X-RAY FLUORECSCENCE ANALYZERUsed for majority of PMI inspections 40 TO 50 Kv x-ray tube or < 50 mCi source
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
• Number of readings determined by pipe size
• PMI of root required for level 3
PMI OF PIPE WELD
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Results Display
• Gives composition and alloy match
• Results data logged
PMI For Texas Operations \ MyLearning 281258
M. Stepien September 2010 DOW RESTRICTED - For internal use only
Next Steps
1. DAS’s to focus on role specific tasks in Network meetings.
2. Review and acknowledge MOC Number: 11111112010110001, Positive Material identification for Piping in Texas Operations.
3. Complete My Learning Course 281258 in December.
4. Positive Material Identification in-effect on January 1, 2011.
DOW RESTRICTED - For internal use only
Questions?
PMI For Texas Operations \ MyLearning 281258Revision History
Date Name Description
10/28/2014 Bruce Raiff Document Made
DOW RESTRICTED