Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday...

Date post: 04-Jan-2016
Category:
Upload: marybeth-della-morgan
View: 215 times
Download: 0 times
Share this document with a friend
Popular Tags:
10
Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development Snapshot”
Transcript
Page 1: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

Dr Chris Whitaker

Chairman, James Point Pty Ltd

SW Corridor Strategic Planning afternoon

Thursday January 29th 2009

James Point Port at Kwinana:

“Development Snapshot”

Page 2: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

Who?

What?

Where?

When?

Why?

What next?

www.jamespoint.com.au

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 3: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHO? - JPPL at a glance …

www.jamespoint.com.au

• WA-based private company

• Significant capability and expertise, including:- maritime design and engineering- maritime construction- project management- rock and fill resources- financing

• Early 2008: Chris Whitaker appointed as Chairman, and Ian Hutton as Chief Executive

1 2 3 4 5 6 7 8 9 10 11 12 13

• Formed in 1997 to respond to EoI and then RFP from WA Government

Page 4: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHAT?

www.jamespoint.com.au

• Operating Agreement to build, own and operate new port infrastructure in the Outer Harbour

• Stage 1: a new bulk facility• Stage 2: a new international container facility• Further stages possible

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 5: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHERE?

www.jamespoint.com.au

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 6: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHEN?

www.jamespoint.com.au

• Stage 1: a new bulk facility … 2 years

• Stage 2: a new international container facility … 5-6 years

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 7: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHY? Market demand for additional common-user bulk berths:

www.jamespoint.com.au

1 2 3 4 5 6 7 8 9 10 11 12 13

• Clinker, slag, gypsum, coal, iron ore, pig iron, dolomite, LPG etc - all currently use KBB2 @ Kwinana Bulk Terminal, operated by FPs• Some significant delays (44% of ships in 2007/8), demurrage costs, and economic impacts• Is worsening as demand increases • Will soon need about 2.5 x current capacity• JPPL Stage 1 addresses this need• Strong support from cargo owners

Page 8: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHY? Market demand for additional container facilities

www.jamespoint.com.au

• Significant demand: growth @ 10% pa since 1990

• 580,345 TEUs handled at Inner Harbour 2007/8• Differing views on ultimate capacity• Landside connections are the main constraint to

further growth• Three proposals: two from FPs, one from JPPL• But only one will be developed in the foreseeable

future• Long lead times - therefore require decision now

on who will provide it

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 9: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHY JAMES POINT?

www.jamespoint.com.au

• Will bring competition in- provision of port infrastructure- provision of port services- price- service and innovation

• Less dredging than alternatives, and other environmental advantages

• Less cost• Less public debt• Reduced risk for Government

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 10: Dr Chris Whitaker Chairman, James Point Pty Ltd SW Corridor Strategic Planning afternoon Thursday January 29th 2009 James Point Port at Kwinana: “Development.

WHAT NEXT?

Getting land-side connections right is a“critical success factor”

www.jamespoint.com.au

• A Government responsibility under Operating Agreement

- Stage 1 addressed in some detail- Stage 2 addressed in concept

• Importance of long-term vision and planning• Opportunity remains to get it right• Dedicated freight routes (road and rail) linking to intermodal hubs• Implementation can be staged, as port grows