Draft EIA Report
1
Executive Summary
1. Introduction
Indian Oil Corporation Limited (IOCL) operates one of its largest oil refineries at Koyali
(near Vadodara) in Gujarat, Western India. The refinery was commissioned in the year
1965 with a capacity of 3.0 MMTPA. Over the years, the capacity of the refinery has
gradually been increased to 13.7 MMTPA with augmentation of old primary Atmospheric
Units (AU-I, AU-II and AU-III) and addition of new primary units viz. Atmospheric Unit-IV
in 1978 and AU-V in 1999 as well as augmentation of AU-IV in 2000.
Gujarat refinery IOCL owned a land of 434 Acres at survey no 771 to 795 at Dumad
with Existing facilities of LPG marketing terminal commissioned during Nov 2002 and
IOTL white oil terminal commissioned in the year 2012.
LPG marketing Terminal occupies land of approximately 62 Acres in 434 Acres at
Dumad Village, Vadodara Savili Road, Dumad. It is about 3 Km from Dumad Approx ~8
Kms away from Gujarat Refinery (GR) of IOCL and situated between Vadodara-Savli
Road. The operating processes carried out at the Terminal are receipt of LPG bulk, its
storage in 6 mounded storage vessels having max storage capacity of 8300 MT,
distribution of bulk LPG by loading Tank trucks and filled LPG cylinder after their filling
at carousel machines. The quantity of LPG to be handled in existing facility is 0.50
MMTPA. The existing plant is under operation with GPCB consent obtained vide: AWH
68449, valid up to 18/11/2019 & PESO license obtained vide S/HO/GJ/03/498(S2126),
Valid up to 31 March 2019.
IOTL Terminal occupies approximately 48 Acres of 434 Acres land. The existing
terminal obtained EC in 2001 from MoEF vide: J-11011/8/2001-IA-II (I).The facility
comprises of storage tanks for 5 No Gasoline Tanks, 4 No Diesel tanks, 3 No Kerosene
Tank, 3 No Ethanol Tanks. The nearest railway station is Pilol 1.4 km towards NNE.The
existing plant is under operation with GPCB consent obtained vide: AWH 65930, valid
Draft EIA Report
2
up to 02/09/2019& PESO license obtained vide P/WC/GJ/15/2323(P-12298) (PESO)
Valid Up to: - 31/12/2020.
2. Environmental Sensitive Areas
The existing complex is located at Dumad, Vadodara District, Gujarat State. The site is
located ~20 Km from Vadodara city towards South-South-West. The site is located
approximately≈ 14 Km towards East from Gujarat Refinery. Vishwamitri River is flowing
adjacent to site boundary in East direction. Google image showing 15, 10, 5 and 1 Km
radius from project boundary is shown in Figure 1.
The Environmentally Sensitive Areas within 15km from Project Boundary is provided in
Table-1.
Table-1 Environmentally Sensitive Areas within 15km from Project Boundary
S.No Areas Distance & Direction from project boundary1 Areas protected under
international conventions,national or local legislationfor their ecological,landscape, cultural or otherrelated value
None within 15 km Radius
2 Areas which are important orsensitive for ecologicalreasons – Wetlands,Watercourses or other waterbodies, coastal zone,biospheres, mountains,forests
None within 15 Km radius
3 Areas used by protected,important or sensitivespecies of flora or fauna forbreeding, nesting, foraging,resting, over wintering,migration
None within 15 Km radius
4 Inland, coastal, marine orunderground waters None within 15 Km radius
5 State, National boundaries None within 15 Km radius
Draft EIA Report
3
6 Routes or facilities used bythe public for access torecreation or other tourist,pilgrim areas
None within 15 Km radius
7 Defence installations Nil8 Densely populated or built-up
area (Nearest Town, City,District)
Dumad area is surrounded by small villages likeVirod~0.8 km (ESE), ASOJ ~0.9 Km (NNW),Sisva ~1.4 Km (W), Ganpatpura ~1.1 km (SSW).However, most part of theVadodara city, will fall within15 Km, which ishaving population more than 16 lakhs.
9 Areas occupied by sensitiveman-made land uses(hospitals, schools, places ofworship, community facilities)
S.No.
List of Sensitive AreasDistance
(≈km)Directi
on
1 The Maharaj SayajiRao University of Baroda
8.22 SSW
2 Madurai Kamraj University 10 SSW3 GSFC University 6.42 WSW4 Medical College of Baroda 10.28 SSW5 Navrachana School Sama 6.89 SSW
6 Sanskriti School ofBusiness
4.85 SSE
7 MS Patel Institute ofManagement
8.43 SSW
8 Cygnus world school 5.6 SSE9 Bright day school 6.7 SSE
10 American School ofBaroda
9.6 SE
11 Bright School 8.28 S12 Ganga –Jamna Hospital 9.69 SW
13 Bhailal-Amin GeneralHospital
8.9 SW
14 SSG Hospital 10.14 S
15 Metro-Hospital & ResearchInstitute
6.85 S
16 Satyam Hospital 5.95 SW17 Tapovan Mandir 8.37 WSW18 EME temple 7.52 SSW
19 Shree SwaminarayanTemple
8.64 S
20 Surya Narayan Temple 10.89 S21 Kirti Mandir 9.89 SSW
10 Areas containing important, No
Draft EIA Report
4
high quality or scarceresources, (groundwaterresources, surfaceresources, forestry,agriculture, fisheries, tourism,minerals)
11 Areas already subjected topollution or environmentaldamage (those whereexisting legal environmentalstandards are exceeded)
No
12 Areas susceptible to naturalhazard which could causethe project to presentenvironmental problems,(earthquakes, subsidence,landslides, erosion orextreme or adverse climaticconditions)
No
Figure-1 Google image showing 15, 10, 05 and 01 Km radius from projectboundary
Draft EIA Report
5
3. Proposed Facilities
For KAHSPL & TTL project the following are proposed
a. Existing 18” dia Underground line in Koyali – Dumad ROW for HSD pipeline
transfer (PLT) from JR & tanks at Dumad
b. Existing 10” dia & 14” dia underground line in Koyali-Dumad ROW for MS
and SKO PLT from JR and tanks at Dumad
c. Proposed new 12” dia underground line in Koyali-Dumad ROW for ATF PLT
from JR and tanks at Dumad
d. Proposed new 12” dia underground line in Koyali-Dumad ROW for PCK PLT
from JR and Tanks at Dumad
e. Proposed new 12” dia underground line in Koyali-Dumad ROW for pumping
of fresh water from JR to Dumad
f. New 10” dia & 6” dia LMW & HMW underground line from JR to Dumad in
existing Koyali-Dumad ROW
g. Proposed Tanks with Capacities are given in Table- 2.
Table- 2 Proposed Tanks with Capacities
S. No Product Capacity(KL) Number of Tanks
TotalCapacity
(KL)1 HSD 30000 4 (2 in operation + 1 receiving + 1 M&I) 1,20,0002 MS 25000 3 (1 in operation + 1 receiving + 1 M&I) 75,0003 ATF 10000 3 ( 1 in operation + 1 receiving + 1 M&I) 30,0004 PCK 10000 2 ( 1 in operation + 1 M&I) 20,0005 SKO 5000 2 ( 1 in operation + 1 M&I) 10,0006 LMW 5000 3 (1 in operation + 1 receiving + 1 M&I) 150007 HMW 5000 1 in operation/ Receiving 5000
8Fresh/
FireWater
6000 3 (1 in operation + 1 M&I) 24000
9 Servicewater 6000 1 in operation/ Receiving 6000
h. Provision of circulation pumps, compressors, Fire and safety systems and
miscellaneous facilities at Dumad
Draft EIA Report
6
i. Cross Country Pipelines
j. Pipeline terminal with Booster and mainline pumping station
k. 6 Bay Tank Truck Loading Facilities for LMW and HMW and Utilities etc.
l. Fire Station
Proposed Facilities for Acrylics/ Oxo Alcohol ProjectThe Major facilities proposed are PRU Unit, SYN Gas Unit, Oxo Unit AA unit and BA
Unit. The schematic diagram of the proposed project is shown below
Storage facilitiesThe following storage facilities are envisaged during the proposed expansion is given in
Table-3.
Table-3: Proposed Storage facilities for expansion project
S.No
Chemical Name Storage Type StoragePeriod/ Tank
Capacity(KL)
No ofTanks
1 N Butanol Internal Floating Roof 3 Days 1025 12 I-Butanol Internal Floating Roof 7 Days 232 23 Acrylic Acid Cone Roof 6 Days 1583 14 Butyl Acrylate Cone Roof 7 Days 3617 25 Propylene Mounded Bullets 7 Days 1410 16 Naptha Internal Floating Roof 3 Days 468 2
The product evacuation from Dumad has been considered by road only.
Draft EIA Report
7
Utilities
S. No Name of the Facility Demand1. Pet Coke Power plant 17 MW2. Boiler 200 TPH3. Cooling water system (5 x 4200 KLPH, 4 working + 1
standby) 16800 KLPH capacity16320 KLPH
4. Nitrogen 900 NM3/Hr 800 KLPH5. Raw water from IOCL Jack wells 400 KLPH6. Fire water Storage 1700 KLPH7. Flare 81000 NM3/Hr8. ETP of 190 & 150 TPH capacity ~212 TPH9. DG Set (Stand By) 1 x 1500 kVA
Piping CorridorThe following streams are needed to be transferred through new pipelines in Existing
koyali – Dumad ROW
i. LPGii. NAPTHAiii. Raw Water
4. Land Requirement
Proposed site layout is given in Figure 1. Land details are given in Table-4.
Table-4: Land details
Site Name Existing Land(Acres)
Proposed(Acres)
TotalAcres
LPG Terminal 62 -- 62IOTL Terminal 48 -- 48Proposed KAHSPL & TTL -- 79.8 79.8Proposed Oxo/ Acrylics Project -- 65.5 65.5Green Belt 33 111 144Vacant Land 291 -256.3 34.7Total Area Available at Dumad
Facility 434 434
Draft EIA Report
8
5. Water Requirement
Total water requirement of the existing facility is 24 KLD of which LPG terminal requires
19 KLD and IOTL white oil terminal requires 5 KLD.
The total additional water requirement for the proposed project is ~260 KLPH (say ~3
MGD) of which 2.7 MGD of raw water is required for operation of Oxo-Alcohol Project
and 0.3 MGD of raw water for KAHSPL and TTL project.
Detailed breakup of Existing and proposed water balance is summarized in Table -5.
Water Balance Diagram of Existing Terminals is given in Figure 2. Water balance
diagram of the Proposed Facility is given in Figure 3. CPP Water Balance is given in
Figure 4.
Draft EIA Report
9
Figure 1 Existing and ProposedSite Layout
Draft EIA Report
10
Table-5 Existing and Proposed Water Balance Diagram
S.No
Description
Existing (KLD) Proposed (KLPH) Total (KLPH)
RemarksTotalWater(a+b+
c)
FreshWater
(a)
CondensateUsed
(b)
ETPTreat
edWaterUsed
(c)
EffluentGenerat
edLos
s
TotalWater(a+b+
c)
FreshWater
(a)
CondensateUsed
(b)
ETPTreat
edWaterUsed
(c)
Effluent
Generated
LossTotalWater(a+b+
c)
Fresh
Water
(a)
CondensateUsed
(b)
ETPTreat
edWaterUsed
(c)
EffluentGenerat
edLoss
1 Raw WaterTreatment 0 0 0 0 0 0 97.5 97.5 0 0 97.5 0 97.5 97.5 0 0 97.5 0
2 Boiler 0 0 0 0 0 0 163 30.9 132.1 0 14.9 16 163 30.9 132.1 0 14.9 16
3DM PlantRegeneration
0 0 0 0 0 0 28.9 28.9 0 0 28.9 0 28.9 28.9 0 0 28.9 0
4 Domestic 13.5 13.5 0 0 12 1.5 15 15 0 0 13.5 1.5 15 15 0 0 13.5 1.5
5 Green Belt 19.5 0 0 19.5 0 19.5 110 0 30 80 0 110 110 0 30 80 0 110
Condensatefrom MEE isused for GB
6CylinderWashing/Testing
6 6 0 0 3.5 0.5 0 0 0 0 0 0 0 0 0 0 0 0
7 Coolingtower 0 0 0 0 0 0 430 335 - 95 50 380 430 335 - 95 50 380
ETP treatedwater sent tocooling tower
8 Fire waterMakeup 4.5 4.5 0 0 0 4.5 15 15 0 0 0 15 15 15 0 0 0 15
9 CPP 0 0 0 0 0 43 37.5 5.5 0 6.9 30.6 43 37.5 5.5 0 6.9 30.6
10 Ash PondQuanching 0 0 0 0 0 0 6.9 0 0 6.9 0 6.9 6.9 0 0 6.9 0 6.9 ETP treated
water usedTotal 43.5 24 0 19.5 15.5 26 902.4 559.8 167.6 175 211.7 553.1 902.4 559.8 167.6 175 211.7 553.1
Note: CETP = Combined Effluent Treatment Plant
Total Fresh water requirement after proposed expansion is ~560 KLPH
1 KL = 219.969 UK Gallon
So 219.969 * 560 KL/Hr* 24 Hrs/day / 10^6 = ~2.95 MGD (say 3 MGD)
Draft EIA Report
11
Figure 2 Water Balance Diagrams of Existing Terminals
Draft EIA Report
12
Figure 3 Water balance diagram of the Proposed Facility
Draft EIA Report
13
Figure 4 CPP Water Balance
Draft EIA Report
14
6. Wastewater Generation
Two Nos combined ETP (CETP) of 190 KLPH and 150 KLPH of ETPs is proposed.
The amount of wastewater generated and to be treated is ~211.7 KLPH.
The net sludge production is 7.85 T/d (moisture content 70%) and net Salt production
is 4.5 T/d (moisture content 10%). Sludge shall be largely composed of Calcium
Carbonate and Magnesium Hydroxide and a small amount of settled suspended
solids and Copper Hydroxide. The moisture content ranges between70% to 75%.
Salts shall majorly consist of Sodium and Potassium Salts of Sulphates, Chlorides
and Nitrates. The moisture content ranges between10% to 15%. Typical Block
diagram of the ETP is given in Figure 5.
Figure 5 Typical ETP block diagram
7. Power & Fuel Requirement
The power requirement for the existing facility is met from JR. For proposed project
the power requirement will be 17 MW to be sourced from proposed Captive power
plant. Power and fuel requirement details are given in Table -6.
Draft EIA Report
15
Table-6: Power and Fuel Requirement
DetailsCapacity
SourceExisting(LPG+IOTL) Proposed Total
PowerRequirement
Existingpowerrequirementis met byGujaratRefinery
17 MW 17 MW
Pet-coke based boiler.
Petcoke will be supplied by
JR. Natural Gas will be
sourced from GAIL/GSPC.
Adequate measures are
taken to control Air
Pollution through
installation of Electrostatic
Precipitators to limit the
solid particulate matter
from petcoke based CPP
will be limited to less than
50 mg/Nm3 and Fuel Gas
Desulphurisation (FGD) as
a part of CPP system
Fuel -14.26MTPH
(Pet Coke)
14.26MTPH
(Pet Coke) Gujarat Refinery
Diesel
40 LPH(IOTL)
+750 LPM
(LPGTerminal)
40 LPH(IOTL)
+750 LPM
(LPGTerminal)
40 LPH(IOTL)
+750 LPM
(LPGTerminal)
Gujarat Refinery
8. Manpower
The existing Terminals (IOTL & LPG) unit has a total of 72 permanent employees
and 195 contract workers. Approximately ~1700 contract labors are required during
construction phase based on various skills. Manpower details during construction
and operation is given in Table -7 and Table-8.
Table-7: During Construction Phase
Draft EIA Report
16
S. No. Terminal Proposed1 Acrylics/ Oxo Alcohol Terminal ~10002 KAhSPL & TTL ~700
Total ~1700
Table-8: During Operation PhaseS.No. Terminal Existing Proposed Total
Permanent Contract Security Permanent Contract1 LPG 46 76 39 -- -- 1612 IOTL 26 80 -- -- 1063 Acrylics/
OxoAlcoholTerminalandKAhSPL &TTL
-- -- --177+55
350+50
632
Grand Total 899
9. Solid Waste
During Construction PhaseDuring construction phase ~3TPD of solid waste is envisaged. It will be the scope of
the contractor to collect and dispose the solid waste generated during construction
phase as per PCB norms.
During Operation Phase
During Operation phase Total of 407.25 Kg/day of solid waste is generated of which
162.9 kg/Day of organic waste will be composted and remaining Inorganic waste will
be disposed through authorized vendors. Solid waste generation details for existing
and proposed are given in Table-9. Hazardous waste generation details for existing
and proposed are given in Table-10.
Draft EIA Report
17
Table-9: Solid waste generation details for existing and proposed.
S.No List of Items
Existing (Kg/day) Proposed (Kg/day)Total
(kg/Day)LPG Terminal & WhiteOil Terminal
Oxy Acrylics, KAHSPL& TTL
1 Organicwaste 49.14 113.76 162.9
2 Inorganicwaste 73.71 170.64 244.35
Total 122.85 284.4 407.25As per CPCB 0.45 kg/ capita/ day
10. Hazardous waste Management
Table-10: Hazardous waste generation details for existing and proposed.
S.No
List ofItems
WasteCategor
yExisting Propose
dRemarks
LPGTermin
al
WhiteOil
Terminal
Oxo/Acrylics,KAhSPL
& TTL
1Tank
BottomSludge
3.3 0.5 TPA 40 TPA 3 TPASent to AuthorizedVendors.CHWIF Site
2 Spend Oil(KLPA) 5.1 1.98 0.15 0.15 Sent to Authorized
Vendors.
3Discarded
Drums/Container
33.3 0.5MTPM
400Nos./Yea
r--
Collection storage anddecontaminationwithin Facility
4 Paints andCoating 21.1 0.14
T/Month -- --
Sent to AuthorizedVendors.(M/s. RecyclingSolutions Pvt. Ltd.(RSPL), Panoli
Draft EIA Report
18
5
Total Saltfrom ZLD
MEE(TPD)
35.3 -- -- 4.05
The net sludgeproduction is 7.85 T/d(moisture content70%) and net Saltproduction is 4.5 T/d(moisture content10%). Sludge shall belargely composed ofCalcium Carbonateand MagnesiumHydroxide and a smallamount of settledsuspended solids andCopper Hydroxide.The moisture contentranges between70%to 75%. Salts shallmajorly consist ofSodium andPotassium Salts ofSulphates, Chloridesand Nitrates. Themoisture contentranges between10%to 15%.Sent to AuthorizedVendors.
6 ETPSludge 35.3 -- -- 0.8
Sent to AuthorizedVendors.
7 Gypsumfrom CPP -- -- 130
To be used in cementmanufacturingprocess
8 SpentCatalyst 1.6 -- -- 50
Disposal as perGPCB/ CPCB norms
9 OxidationCatalyst 1.6 -- -- 140 MT/ 5
Yrs
Sent to authorizedvendors forlandfill/auction
10 CCUCatalyst 1.6 -- -- 4.8KL/ 3
Yrs
Sent to authorizedvendors forlandfill/auction
11. Project cost
Draft EIA Report
19
The estimated cost for the proposed projects is given in Table-11.
Table-11: The estimated cost for the proposed projects.S. No. Proposed Project Project Cost (Crores)
1 Oxo/Acrylics project 41572 KAHSPL project 9063 TTL Facilities 131
Total 5194
12. Baseline Study
Common Sampling Location Map (Nov-2017 to Jan 2018)
Draft EIA Report
20
I. Meteorological Environment
Meteorological scenario in and around the project site is an essential requirement
during study period for proper interpretation of baseline air quality status.
Meteorological data was collected during the study period; (November 2017 –
January 2018).The wind rose for the period of Nov 2017 to Jan 2018 is given in
Figure-6.
Figure-6: The wind rose for the period of Nov 2017 to Jan 2018.
II. Ambient Air Quality
The ambient air quality has been monitored at 8 locations for 12 parameters
including 12 parameters as per NAAQS, 2009 within the study area. The baseline
levels of PM10(48.2 - 92.4 µg/m³), PM2.5 (15.3 - 51.8µg/m³), SO2 (7.4-17.4 µg/m³),
NO2 (14.4- 44.9 µg/m³), CO (0.08—0.41 mg/m3), all the parameters are well within
the National Ambient Air Quality Standards for Industrial, Commercial and
Residential areas at all monitoring locations during the study period from November
2107 to January 2018.
Draft EIA Report
20
I. Meteorological Environment
Meteorological scenario in and around the project site is an essential requirement
during study period for proper interpretation of baseline air quality status.
Meteorological data was collected during the study period; (November 2017 –
January 2018).The wind rose for the period of Nov 2017 to Jan 2018 is given in
Figure-6.
Figure-6: The wind rose for the period of Nov 2017 to Jan 2018.
II. Ambient Air Quality
The ambient air quality has been monitored at 8 locations for 12 parameters
including 12 parameters as per NAAQS, 2009 within the study area. The baseline
levels of PM10(48.2 - 92.4 µg/m³), PM2.5 (15.3 - 51.8µg/m³), SO2 (7.4-17.4 µg/m³),
NO2 (14.4- 44.9 µg/m³), CO (0.08—0.41 mg/m3), all the parameters are well within
the National Ambient Air Quality Standards for Industrial, Commercial and
Residential areas at all monitoring locations during the study period from November
2107 to January 2018.
Draft EIA Report
20
I. Meteorological Environment
Meteorological scenario in and around the project site is an essential requirement
during study period for proper interpretation of baseline air quality status.
Meteorological data was collected during the study period; (November 2017 –
January 2018).The wind rose for the period of Nov 2017 to Jan 2018 is given in
Figure-6.
Figure-6: The wind rose for the period of Nov 2017 to Jan 2018.
II. Ambient Air Quality
The ambient air quality has been monitored at 8 locations for 12 parameters
including 12 parameters as per NAAQS, 2009 within the study area. The baseline
levels of PM10(48.2 - 92.4 µg/m³), PM2.5 (15.3 - 51.8µg/m³), SO2 (7.4-17.4 µg/m³),
NO2 (14.4- 44.9 µg/m³), CO (0.08—0.41 mg/m3), all the parameters are well within
the National Ambient Air Quality Standards for Industrial, Commercial and
Residential areas at all monitoring locations during the study period from November
2107 to January 2018.
Draft EIA Report
21
III. Noise Environment
It is observed that the noise levels monitored at 8 locations. Day equivalent and night
equivalent noise levels at all locations are within prescribed CPCB standards
In industrial areas day time noise levels was about 62.1 dB(A) to 65.2 dB(A)
and 51.1 dB(A) to 52.8 dB(A) during night time, which is within prescribed limit
by MoEF&CC (75 dB(A) Day time & 70 dB(A) Night time).
In residential areas day time noise levels varied from 56.1 dB(A) to 58.4 dB(A)
and night time noise levels varied from 44.1 dB(A) to 49.1 dB(A) across the
sampling stations. The field observations during the study period indicate that
the ambient noise levels in Residential area are within prescribed the limit
prescribed by MoEF&CC (55 dB(A) Day time & 45 dB(A) Night time)
IV. Water Environment
Surface water quality
The summary of surface water quality monitored at 8 locations is summarized below
In the surface water the pH varies between 6.58-7.62
The Total Dissolved Solids range varies between 200 mg/l – 2481.58 mg/l
for the surface water.
The chloride content in the surface water for study area is ranges between
12.7 mg/l – 526 mg/l.
The sulphate content of the surface water of the study area varies between
6.829 mg/l – 386 mg/l meeting the desirable limit of the IS 10500: 2012.
The Total hardness ranges is between 102 mg/l – 1785.04 mg/l.
Ground Water Quality
A summary of analytical results ground water quality monitored at 8 locations are
presented below:
The ground water results of the study area indicate that the average pH
ranges are varied between 6.91-8.14
Draft EIA Report
22
The Total Dissolved Solids ranges is varied between 714 mg/l – 5845 mg/l
for the ground water and for few samples exceeded the permissible limits
of IS 10500: 2012.
The desirable limit of the chloride content is 250mg/l and permissible limit
is 1000 mg/l. The chloride content in the ground water for study area is
ranges between 105 mg/l – 1516 mg/l. Some samples are exceeding the
permissible limit.
The desirable limit of the sulphate content is 200mg/l and permissible limit
is 400mg/l. the sulphate content of the ground water of the study area is
varied between 38.7 mg/l – 1585 mg/l and some samples are not meeting
the desirable limit of the IS 10500: 2012.
The Total hardness ranges is between 184.8 mg/l – 2908.6 mg/l. for
ground water and for few samples exceeded the permissible limit of the IS
10500: 2012.
V. Soil Environment
Summary of analytical results of soil quality monitored at 8 locations are presentedbelow:
The pH of the soil samples ranged from 7.25-8.22. Indicating that the soils
are almost neutral in nature.
Conductivity of the soil samples ranged from 100.5-245 μS/cm. As the EC
value is less than 2000 μS/cm, the soil is found to be non-saline in nature
The water holding capacity of the soil samples varied from 15-42 (%).
Nitrogen content ranged from 42 kg/ha to 142 kg/ha
Phosphorous ranged from 15.7 kg/ha to 63.3 kg/ha
Potassium content ranges from 62.4 to 197 kg/ha
Draft EIA Report
23
VI. Biological Environment
Trees and shrubs play an essential role in maintaining an ecological equilibrium and
improving the livelihood of people in the dry regions. Vegetation of a particular area
depends upon the interaction of various natural biotic and abiotic factors including
Temperature, Rain fall, Humidity, Soil type, plants, animals, micro-organisms of that
particular area in which they grow live and influence one another. The study area is
moderately rich in vegetation. The review of the study area indicated that 174 floral
species have been identified within the vicinity of the project site (refer Table 3-20 of
EIA report). The bio diversity richness map of the study area is given in Figure-7.
Figure-7: The bio diversity richness map of the study area
VII. Socio Economic Environment
Vadodara District is a district in the eastern part of the state of Gujarat in western
India. The city of Vadodara (Baroda), in the western part of the district, is the
administrative headquarters. Vadodara District covers an area of 7526 km². It had a
population of 3,641,802 with population growth of 19.87% as of 2001 census. As of
Draft EIA Report
24
2011 it is the third most populous district of Gujarat (out of 33) with 4,165,626, after
Ahmadabad (7,214,225) and Surat (6,081,322). The district is bounded by
Panchmahal and Dahod districts to the North, Anand and Kheda districts to the West,
Bharuch and Narmada districts to the South and Chhota Udaipur to the East.
A socio-economic study was undertaken in assessing aspects which are dealing with
social and cultural conditions, and economic status in the study area. The study
provides information such as demographic structure, population dynamics,
infrastructure resources, and the status of human health and economic attributes like
employment, per-capita income, agriculture, trade, and industrial development in the
study area. The study of these characteristic helps in identification, prediction and
evaluation of impacts on socio-economic and parameters of human interest due to
proposed project developments. The parameters are:
Demographic structure
Infrastructure Facility
Economic Status
Health status
Cultural attributes
Awareness and opinion of people about the project and Industries in the area.
VIII. Anticipated Environmental Impacts
a. Water Environment
The total raw water requirement is 560 TPH (considering the requirement of
integrated project at Dumad). Raw water storage pond of total 10 days storage of
water was considered for sizing the pond. Raw water treatment facilities include:
chemical dosing system, multi grade filter, activated carbon filter and Reverse
Osmosis plant.
Total 211.7 KLD of effluent of is anticipated and will be treated in dedicated proposed
combined ETP’s of 190 KLPH and 150 KLPH. Treated water will be passed through
RO and Permeate is used for Cooling tower and greenbelt.
Draft EIA Report
25
b. Air Environment
Adequate measures will be taken to control Air Pollution through installation of
Electrostatic Precipitators and Fuel Gas Desulphurisation (FGD) as a part of CPP
system. Following will be measured through installation of online analysers to
measure SOx, NOx, CO, Hydrocarbons and Particulate Matter.Total Maximum GLCs
from the proposed Stack Emissions are given in Table-12.
Table-12: Total Maximum GLCs from the proposed Stack Emissions
Pollutant
Max Baseline Conc.
(µg/m3)
predictedConc. at
source (µg/m3)
TotalConc.
(µg/m3)
NAAQstandar
d
% Increment inConcentration
Levels
PM10 92.4 2.108 94.508 100 2.28SO2 41.5 7.031 48.531 80 16.94NOx 44.9 7.301 52.201 80 16.26
It was observed that the maximum incremental concentration observed due to
proposed expansion for PM, SO2 and NOx are 2.108 µg/m3, 7.031 µg/m3 and 7.301
µg/m3. So it can be concluded that even after the expansion of the plant the impact
envisaged is minimum. Vehicular modelling was also carried out but since the
number of vehicles increased is marginal per day and no major impact envisaged on
Air environment.
c. Noise Environment
All equipment in the plant produce 40 to 55 dB(A) after control measures and
equipment are designed/operated to have a noise level not exceeding 85 to 90 dB(A)
as per the requirement of Occupational Health and Safety Administration Standard
(OHSAS). In addition, since most of the noise generating equipment would be in
closed structures, the noise transmitted outside would be still lower and for any other
case of higher noise sufficient safety ear plugs and ear muffs will be provided to the
employees.
d. Land Use
The proposed expansion is within the existing IOCl Dumad complex and the
proposed activity doesn’t change the land use classification of the site.
Draft EIA Report
26
IX. Environmental Monitoring ProgramA monitoring schedule with respect to AAQ, Water, Wastewater quality, Noise Quality
as per CPCB/MoEF&CC/GPCB shall be maintained.
X. Pollution Control Measures
Fugitive air emissions from captive power plant will be controlled by ESP & FGD will
be provided to meet the norms as required by CPCB. Adequate stack height will be
provided.
Municipal solid waste will be composted within the facility.
Hazardous waste will be stored and disposed off to authorized vendors for landfill.
Fly ash will be disposed off to cement manufacturing processes.
The Industrial effluent generated will be treated in inhouse ETP. The sewage from
domestic use will be treated in ETP and treated water will be recycled back into the
system.
The proposed wastewater treatment system will be a Zero Liquid Discharge (ZLD).Hence, there will be no discharge to land environment.
XI. Greenbelt Development
Project site is an existing unit with shrubs and small trees. There will be clearance of
land envisaged for proposed projects. Existing Green belt is over a stretch of 33
Acres with approx 25000-30000 trees and adequate measures will be taken to
maintain the greenbelt of 111 Acres for the proposed expansion. The lists of species
suggested for green belt is given in Table-13. Green belt development scheme is
given in Table-14.
Draft EIA Report
27
Table-13: List of Suggested Species for green belt
S.No
Treesspecies
Commonname
Sensitive/
Tolerant
Height
(m)
Regeneration
GrowthRate
Canopysize(m2)
1.AbutilonIndicum Kanghi Tolerant 5 Through
seedsQuick
growing NA
2.Acacia
Auriculiformis
Australianwattle Tolerant 16 By
seedsQuick
growing 8548.22
3.Acacia
Catechu Khair Tolerant 3 Byseeds
Quickgrowing 108.42
4.Acacia
DealbataSilverwattle Tolerant 15 By
seedsQuick
growing NA
5.Acacia
FarnesianaWild
Babul Tolerant 5 Byseeds
Quickgrowing NA
6.Actinodaphn
eAngustifolia
Pisa Tolerant 13 Byseeds - -
7.Adina
Cordifolia Haldu Tolerant 20 Byseeds
Slowgrowing
148490.1
8.Aegle
Marmelos Boel Tolerant 12
Byseeds,
rootcuttings
Slowgrowing
26547.19
9.Aesculus
Indica Hook Bankhar Sensitive 20
Byseeds,
rootsuckers
Quickgrowing
10.AlbiziaAmara Tugli lalai Tolerant 10
Byseeds,
rootsuckers
Quickgrowing --
11.Anona
Reticulate Raamaphal Tolerant 10 Byseeds
Fastgrowing 2017.44
12.Anthocephalus Chinensis Kadamba Tolerant 20 By
seedsQuick
growing 52233.5
13.Azadiracta
Indica Neem tree Tolerant 20 Byseeds
Quickgrowthafter 1st
season
300445.3
Draft EIA Report
28
14.Balanites
Roxburghii Ingoriyo Tolerant 9 Byseeds
Quickgrowing
15.Bambusa
Arundinocia Wans Tolerant 20 Bycuttings
Quickgrowing --
16.BarringtoniaAcutangula
Samudraphol Tolerant 9-12 By
seedsQuick
growing --
17.Bauhinia
Racemosa Asundro Tolerant 5 Byseeds
Quickgrowing 136.9
18.BauhiniaVarigata Kavindara Tolerant 5 By
seedsQuick
growing 1769.52
Source: Guidelines for Developing Greenbelts- PROBES/75/1999-2000
Table-14: Green belt development scheme
S.No
Description Scheme of plantationTotal1st
Year2nd
year3rd
year4th
Year5th
Year
1 Area to Develop(Ha) 9.105 9.105 9.105 9.105 9.105 45.525
2 Plantion of Seeds/Saplings 13650 13650 13650 13650 13650 68250
3 Expenditure(Lakhs) 18 18 18 18 18 90
Note: 1500 Trees per Hectare