+ All Categories
Home > Documents > Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure...

Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure...

Date post: 07-Apr-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
28
Draft EIA Report 1 Executive Summary 1. Introduction Indian Oil Corporation Limited (IOCL) operates one of its largest oil refineries at Koyali (near Vadodara) in Gujarat, Western India. The refinery was commissioned in the year 1965 with a capacity of 3.0 MMTPA. Over the years, the capacity of the refinery has gradually been increased to 13.7 MMTPA with augmentation of old primary Atmospheric Units (AU-I, AU-II and AU-III) and addition of new primary units viz. Atmospheric Unit-IV in 1978 and AU-V in 1999 as well as augmentation of AU-IV in 2000. Gujarat refinery IOCL owned a land of 434 Acres at survey no 771 to 795 at Dumad with Existing facilities of LPG marketing terminal commissioned during Nov 2002 and IOTL white oil terminal commissioned in the year 2012. LPG marketing Terminal occupies land of approximately 62 Acres in 434 Acres at Dumad Village, Vadodara Savili Road, Dumad. It is about 3 Km from Dumad Approx ~8 Kms away from Gujarat Refinery (GR) of IOCL and situated between Vadodara-Savli Road. The operating processes carried out at the Terminal are receipt of LPG bulk, its storage in 6 mounded storage vessels having max storage capacity of 8300 MT, distribution of bulk LPG by loading Tank trucks and filled LPG cylinder after their filling at carousel machines. The quantity of LPG to be handled in existing facility is 0.50 MMTPA. The existing plant is under operation with GPCB consent obtained vide: AWH 68449, valid up to 18/11/2019 & PESO license obtained vide S/HO/GJ/03/498(S2126), Valid up to 31 March 2019. IOTL Terminal occupies approximately 48 Acres of 434 Acres land. The existing terminal obtained EC in 2001 from MoEF vide: J-11011/8/2001-IA-II (I).The facility comprises of storage tanks for 5 No Gasoline Tanks, 4 No Diesel tanks, 3 No Kerosene Tank, 3 No Ethanol Tanks. The nearest railway station is Pilol 1.4 km towards NNE.The existing plant is under operation with GPCB consent obtained vide: AWH 65930, valid
Transcript
Page 1: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

1

Executive Summary

1. Introduction

Indian Oil Corporation Limited (IOCL) operates one of its largest oil refineries at Koyali

(near Vadodara) in Gujarat, Western India. The refinery was commissioned in the year

1965 with a capacity of 3.0 MMTPA. Over the years, the capacity of the refinery has

gradually been increased to 13.7 MMTPA with augmentation of old primary Atmospheric

Units (AU-I, AU-II and AU-III) and addition of new primary units viz. Atmospheric Unit-IV

in 1978 and AU-V in 1999 as well as augmentation of AU-IV in 2000.

Gujarat refinery IOCL owned a land of 434 Acres at survey no 771 to 795 at Dumad

with Existing facilities of LPG marketing terminal commissioned during Nov 2002 and

IOTL white oil terminal commissioned in the year 2012.

LPG marketing Terminal occupies land of approximately 62 Acres in 434 Acres at

Dumad Village, Vadodara Savili Road, Dumad. It is about 3 Km from Dumad Approx ~8

Kms away from Gujarat Refinery (GR) of IOCL and situated between Vadodara-Savli

Road. The operating processes carried out at the Terminal are receipt of LPG bulk, its

storage in 6 mounded storage vessels having max storage capacity of 8300 MT,

distribution of bulk LPG by loading Tank trucks and filled LPG cylinder after their filling

at carousel machines. The quantity of LPG to be handled in existing facility is 0.50

MMTPA. The existing plant is under operation with GPCB consent obtained vide: AWH

68449, valid up to 18/11/2019 & PESO license obtained vide S/HO/GJ/03/498(S2126),

Valid up to 31 March 2019.

IOTL Terminal occupies approximately 48 Acres of 434 Acres land. The existing

terminal obtained EC in 2001 from MoEF vide: J-11011/8/2001-IA-II (I).The facility

comprises of storage tanks for 5 No Gasoline Tanks, 4 No Diesel tanks, 3 No Kerosene

Tank, 3 No Ethanol Tanks. The nearest railway station is Pilol 1.4 km towards NNE.The

existing plant is under operation with GPCB consent obtained vide: AWH 65930, valid

Page 2: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

2

up to 02/09/2019& PESO license obtained vide P/WC/GJ/15/2323(P-12298) (PESO)

Valid Up to: - 31/12/2020.

2. Environmental Sensitive Areas

The existing complex is located at Dumad, Vadodara District, Gujarat State. The site is

located ~20 Km from Vadodara city towards South-South-West. The site is located

approximately≈ 14 Km towards East from Gujarat Refinery. Vishwamitri River is flowing

adjacent to site boundary in East direction. Google image showing 15, 10, 5 and 1 Km

radius from project boundary is shown in Figure 1.

The Environmentally Sensitive Areas within 15km from Project Boundary is provided in

Table-1.

Table-1 Environmentally Sensitive Areas within 15km from Project Boundary

S.No Areas Distance & Direction from project boundary1 Areas protected under

international conventions,national or local legislationfor their ecological,landscape, cultural or otherrelated value

None within 15 km Radius

2 Areas which are important orsensitive for ecologicalreasons – Wetlands,Watercourses or other waterbodies, coastal zone,biospheres, mountains,forests

None within 15 Km radius

3 Areas used by protected,important or sensitivespecies of flora or fauna forbreeding, nesting, foraging,resting, over wintering,migration

None within 15 Km radius

4 Inland, coastal, marine orunderground waters None within 15 Km radius

5 State, National boundaries None within 15 Km radius

Page 3: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

3

6 Routes or facilities used bythe public for access torecreation or other tourist,pilgrim areas

None within 15 Km radius

7 Defence installations Nil8 Densely populated or built-up

area (Nearest Town, City,District)

Dumad area is surrounded by small villages likeVirod~0.8 km (ESE), ASOJ ~0.9 Km (NNW),Sisva ~1.4 Km (W), Ganpatpura ~1.1 km (SSW).However, most part of theVadodara city, will fall within15 Km, which ishaving population more than 16 lakhs.

9 Areas occupied by sensitiveman-made land uses(hospitals, schools, places ofworship, community facilities)

S.No.

List of Sensitive AreasDistance

(≈km)Directi

on

1 The Maharaj SayajiRao University of Baroda

8.22 SSW

2 Madurai Kamraj University 10 SSW3 GSFC University 6.42 WSW4 Medical College of Baroda 10.28 SSW5 Navrachana School Sama 6.89 SSW

6 Sanskriti School ofBusiness

4.85 SSE

7 MS Patel Institute ofManagement

8.43 SSW

8 Cygnus world school 5.6 SSE9 Bright day school 6.7 SSE

10 American School ofBaroda

9.6 SE

11 Bright School 8.28 S12 Ganga –Jamna Hospital 9.69 SW

13 Bhailal-Amin GeneralHospital

8.9 SW

14 SSG Hospital 10.14 S

15 Metro-Hospital & ResearchInstitute

6.85 S

16 Satyam Hospital 5.95 SW17 Tapovan Mandir 8.37 WSW18 EME temple 7.52 SSW

19 Shree SwaminarayanTemple

8.64 S

20 Surya Narayan Temple 10.89 S21 Kirti Mandir 9.89 SSW

10 Areas containing important, No

Page 4: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

4

high quality or scarceresources, (groundwaterresources, surfaceresources, forestry,agriculture, fisheries, tourism,minerals)

11 Areas already subjected topollution or environmentaldamage (those whereexisting legal environmentalstandards are exceeded)

No

12 Areas susceptible to naturalhazard which could causethe project to presentenvironmental problems,(earthquakes, subsidence,landslides, erosion orextreme or adverse climaticconditions)

No

Figure-1 Google image showing 15, 10, 05 and 01 Km radius from projectboundary

Page 5: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

5

3. Proposed Facilities

For KAHSPL & TTL project the following are proposed

a. Existing 18” dia Underground line in Koyali – Dumad ROW for HSD pipeline

transfer (PLT) from JR & tanks at Dumad

b. Existing 10” dia & 14” dia underground line in Koyali-Dumad ROW for MS

and SKO PLT from JR and tanks at Dumad

c. Proposed new 12” dia underground line in Koyali-Dumad ROW for ATF PLT

from JR and tanks at Dumad

d. Proposed new 12” dia underground line in Koyali-Dumad ROW for PCK PLT

from JR and Tanks at Dumad

e. Proposed new 12” dia underground line in Koyali-Dumad ROW for pumping

of fresh water from JR to Dumad

f. New 10” dia & 6” dia LMW & HMW underground line from JR to Dumad in

existing Koyali-Dumad ROW

g. Proposed Tanks with Capacities are given in Table- 2.

Table- 2 Proposed Tanks with Capacities

S. No Product Capacity(KL) Number of Tanks

TotalCapacity

(KL)1 HSD 30000 4 (2 in operation + 1 receiving + 1 M&I) 1,20,0002 MS 25000 3 (1 in operation + 1 receiving + 1 M&I) 75,0003 ATF 10000 3 ( 1 in operation + 1 receiving + 1 M&I) 30,0004 PCK 10000 2 ( 1 in operation + 1 M&I) 20,0005 SKO 5000 2 ( 1 in operation + 1 M&I) 10,0006 LMW 5000 3 (1 in operation + 1 receiving + 1 M&I) 150007 HMW 5000 1 in operation/ Receiving 5000

8Fresh/

FireWater

6000 3 (1 in operation + 1 M&I) 24000

9 Servicewater 6000 1 in operation/ Receiving 6000

h. Provision of circulation pumps, compressors, Fire and safety systems and

miscellaneous facilities at Dumad

Page 6: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

6

i. Cross Country Pipelines

j. Pipeline terminal with Booster and mainline pumping station

k. 6 Bay Tank Truck Loading Facilities for LMW and HMW and Utilities etc.

l. Fire Station

Proposed Facilities for Acrylics/ Oxo Alcohol ProjectThe Major facilities proposed are PRU Unit, SYN Gas Unit, Oxo Unit AA unit and BA

Unit. The schematic diagram of the proposed project is shown below

Storage facilitiesThe following storage facilities are envisaged during the proposed expansion is given in

Table-3.

Table-3: Proposed Storage facilities for expansion project

S.No

Chemical Name Storage Type StoragePeriod/ Tank

Capacity(KL)

No ofTanks

1 N Butanol Internal Floating Roof 3 Days 1025 12 I-Butanol Internal Floating Roof 7 Days 232 23 Acrylic Acid Cone Roof 6 Days 1583 14 Butyl Acrylate Cone Roof 7 Days 3617 25 Propylene Mounded Bullets 7 Days 1410 16 Naptha Internal Floating Roof 3 Days 468 2

The product evacuation from Dumad has been considered by road only.

Page 7: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

7

Utilities

S. No Name of the Facility Demand1. Pet Coke Power plant 17 MW2. Boiler 200 TPH3. Cooling water system (5 x 4200 KLPH, 4 working + 1

standby) 16800 KLPH capacity16320 KLPH

4. Nitrogen 900 NM3/Hr 800 KLPH5. Raw water from IOCL Jack wells 400 KLPH6. Fire water Storage 1700 KLPH7. Flare 81000 NM3/Hr8. ETP of 190 & 150 TPH capacity ~212 TPH9. DG Set (Stand By) 1 x 1500 kVA

Piping CorridorThe following streams are needed to be transferred through new pipelines in Existing

koyali – Dumad ROW

i. LPGii. NAPTHAiii. Raw Water

4. Land Requirement

Proposed site layout is given in Figure 1. Land details are given in Table-4.

Table-4: Land details

Site Name Existing Land(Acres)

Proposed(Acres)

TotalAcres

LPG Terminal 62 -- 62IOTL Terminal 48 -- 48Proposed KAHSPL & TTL -- 79.8 79.8Proposed Oxo/ Acrylics Project -- 65.5 65.5Green Belt 33 111 144Vacant Land 291 -256.3 34.7Total Area Available at Dumad

Facility 434 434

Page 8: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

8

5. Water Requirement

Total water requirement of the existing facility is 24 KLD of which LPG terminal requires

19 KLD and IOTL white oil terminal requires 5 KLD.

The total additional water requirement for the proposed project is ~260 KLPH (say ~3

MGD) of which 2.7 MGD of raw water is required for operation of Oxo-Alcohol Project

and 0.3 MGD of raw water for KAHSPL and TTL project.

Detailed breakup of Existing and proposed water balance is summarized in Table -5.

Water Balance Diagram of Existing Terminals is given in Figure 2. Water balance

diagram of the Proposed Facility is given in Figure 3. CPP Water Balance is given in

Figure 4.

Page 9: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

9

Figure 1 Existing and ProposedSite Layout

Page 10: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

10

Table-5 Existing and Proposed Water Balance Diagram

S.No

Description

Existing (KLD) Proposed (KLPH) Total (KLPH)

RemarksTotalWater(a+b+

c)

FreshWater

(a)

CondensateUsed

(b)

ETPTreat

edWaterUsed

(c)

EffluentGenerat

edLos

s

TotalWater(a+b+

c)

FreshWater

(a)

CondensateUsed

(b)

ETPTreat

edWaterUsed

(c)

Effluent

Generated

LossTotalWater(a+b+

c)

Fresh

Water

(a)

CondensateUsed

(b)

ETPTreat

edWaterUsed

(c)

EffluentGenerat

edLoss

1 Raw WaterTreatment 0 0 0 0 0 0 97.5 97.5 0 0 97.5 0 97.5 97.5 0 0 97.5 0

2 Boiler 0 0 0 0 0 0 163 30.9 132.1 0 14.9 16 163 30.9 132.1 0 14.9 16

3DM PlantRegeneration

0 0 0 0 0 0 28.9 28.9 0 0 28.9 0 28.9 28.9 0 0 28.9 0

4 Domestic 13.5 13.5 0 0 12 1.5 15 15 0 0 13.5 1.5 15 15 0 0 13.5 1.5

5 Green Belt 19.5 0 0 19.5 0 19.5 110 0 30 80 0 110 110 0 30 80 0 110

Condensatefrom MEE isused for GB

6CylinderWashing/Testing

6 6 0 0 3.5 0.5 0 0 0 0 0 0 0 0 0 0 0 0

7 Coolingtower 0 0 0 0 0 0 430 335 - 95 50 380 430 335 - 95 50 380

ETP treatedwater sent tocooling tower

8 Fire waterMakeup 4.5 4.5 0 0 0 4.5 15 15 0 0 0 15 15 15 0 0 0 15

9 CPP 0 0 0 0 0 43 37.5 5.5 0 6.9 30.6 43 37.5 5.5 0 6.9 30.6

10 Ash PondQuanching 0 0 0 0 0 0 6.9 0 0 6.9 0 6.9 6.9 0 0 6.9 0 6.9 ETP treated

water usedTotal 43.5 24 0 19.5 15.5 26 902.4 559.8 167.6 175 211.7 553.1 902.4 559.8 167.6 175 211.7 553.1

Note: CETP = Combined Effluent Treatment Plant

Total Fresh water requirement after proposed expansion is ~560 KLPH

1 KL = 219.969 UK Gallon

So 219.969 * 560 KL/Hr* 24 Hrs/day / 10^6 = ~2.95 MGD (say 3 MGD)

Page 11: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

11

Figure 2 Water Balance Diagrams of Existing Terminals

Page 12: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

12

Figure 3 Water balance diagram of the Proposed Facility

Page 13: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

13

Figure 4 CPP Water Balance

Page 14: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

14

6. Wastewater Generation

Two Nos combined ETP (CETP) of 190 KLPH and 150 KLPH of ETPs is proposed.

The amount of wastewater generated and to be treated is ~211.7 KLPH.

The net sludge production is 7.85 T/d (moisture content 70%) and net Salt production

is 4.5 T/d (moisture content 10%). Sludge shall be largely composed of Calcium

Carbonate and Magnesium Hydroxide and a small amount of settled suspended

solids and Copper Hydroxide. The moisture content ranges between70% to 75%.

Salts shall majorly consist of Sodium and Potassium Salts of Sulphates, Chlorides

and Nitrates. The moisture content ranges between10% to 15%. Typical Block

diagram of the ETP is given in Figure 5.

Figure 5 Typical ETP block diagram

7. Power & Fuel Requirement

The power requirement for the existing facility is met from JR. For proposed project

the power requirement will be 17 MW to be sourced from proposed Captive power

plant. Power and fuel requirement details are given in Table -6.

Page 15: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

15

Table-6: Power and Fuel Requirement

DetailsCapacity

SourceExisting(LPG+IOTL) Proposed Total

PowerRequirement

Existingpowerrequirementis met byGujaratRefinery

17 MW 17 MW

Pet-coke based boiler.

Petcoke will be supplied by

JR. Natural Gas will be

sourced from GAIL/GSPC.

Adequate measures are

taken to control Air

Pollution through

installation of Electrostatic

Precipitators to limit the

solid particulate matter

from petcoke based CPP

will be limited to less than

50 mg/Nm3 and Fuel Gas

Desulphurisation (FGD) as

a part of CPP system

Fuel -14.26MTPH

(Pet Coke)

14.26MTPH

(Pet Coke) Gujarat Refinery

Diesel

40 LPH(IOTL)

+750 LPM

(LPGTerminal)

40 LPH(IOTL)

+750 LPM

(LPGTerminal)

40 LPH(IOTL)

+750 LPM

(LPGTerminal)

Gujarat Refinery

8. Manpower

The existing Terminals (IOTL & LPG) unit has a total of 72 permanent employees

and 195 contract workers. Approximately ~1700 contract labors are required during

construction phase based on various skills. Manpower details during construction

and operation is given in Table -7 and Table-8.

Table-7: During Construction Phase

Page 16: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

16

S. No. Terminal Proposed1 Acrylics/ Oxo Alcohol Terminal ~10002 KAhSPL & TTL ~700

Total ~1700

Table-8: During Operation PhaseS.No. Terminal Existing Proposed Total

Permanent Contract Security Permanent Contract1 LPG 46 76 39 -- -- 1612 IOTL 26 80 -- -- 1063 Acrylics/

OxoAlcoholTerminalandKAhSPL &TTL

-- -- --177+55

350+50

632

Grand Total 899

9. Solid Waste

During Construction PhaseDuring construction phase ~3TPD of solid waste is envisaged. It will be the scope of

the contractor to collect and dispose the solid waste generated during construction

phase as per PCB norms.

During Operation Phase

During Operation phase Total of 407.25 Kg/day of solid waste is generated of which

162.9 kg/Day of organic waste will be composted and remaining Inorganic waste will

be disposed through authorized vendors. Solid waste generation details for existing

and proposed are given in Table-9. Hazardous waste generation details for existing

and proposed are given in Table-10.

Page 17: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

17

Table-9: Solid waste generation details for existing and proposed.

S.No List of Items

Existing (Kg/day) Proposed (Kg/day)Total

(kg/Day)LPG Terminal & WhiteOil Terminal

Oxy Acrylics, KAHSPL& TTL

1 Organicwaste 49.14 113.76 162.9

2 Inorganicwaste 73.71 170.64 244.35

Total 122.85 284.4 407.25As per CPCB 0.45 kg/ capita/ day

10. Hazardous waste Management

Table-10: Hazardous waste generation details for existing and proposed.

S.No

List ofItems

WasteCategor

yExisting Propose

dRemarks

LPGTermin

al

WhiteOil

Terminal

Oxo/Acrylics,KAhSPL

& TTL

1Tank

BottomSludge

3.3 0.5 TPA 40 TPA 3 TPASent to AuthorizedVendors.CHWIF Site

2 Spend Oil(KLPA) 5.1 1.98 0.15 0.15 Sent to Authorized

Vendors.

3Discarded

Drums/Container

33.3 0.5MTPM

400Nos./Yea

r--

Collection storage anddecontaminationwithin Facility

4 Paints andCoating 21.1 0.14

T/Month -- --

Sent to AuthorizedVendors.(M/s. RecyclingSolutions Pvt. Ltd.(RSPL), Panoli

Page 18: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

18

5

Total Saltfrom ZLD

MEE(TPD)

35.3 -- -- 4.05

The net sludgeproduction is 7.85 T/d(moisture content70%) and net Saltproduction is 4.5 T/d(moisture content10%). Sludge shall belargely composed ofCalcium Carbonateand MagnesiumHydroxide and a smallamount of settledsuspended solids andCopper Hydroxide.The moisture contentranges between70%to 75%. Salts shallmajorly consist ofSodium andPotassium Salts ofSulphates, Chloridesand Nitrates. Themoisture contentranges between10%to 15%.Sent to AuthorizedVendors.

6 ETPSludge 35.3 -- -- 0.8

Sent to AuthorizedVendors.

7 Gypsumfrom CPP -- -- 130

To be used in cementmanufacturingprocess

8 SpentCatalyst 1.6 -- -- 50

Disposal as perGPCB/ CPCB norms

9 OxidationCatalyst 1.6 -- -- 140 MT/ 5

Yrs

Sent to authorizedvendors forlandfill/auction

10 CCUCatalyst 1.6 -- -- 4.8KL/ 3

Yrs

Sent to authorizedvendors forlandfill/auction

11. Project cost

Page 19: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

19

The estimated cost for the proposed projects is given in Table-11.

Table-11: The estimated cost for the proposed projects.S. No. Proposed Project Project Cost (Crores)

1 Oxo/Acrylics project 41572 KAHSPL project 9063 TTL Facilities 131

Total 5194

12. Baseline Study

Common Sampling Location Map (Nov-2017 to Jan 2018)

Page 20: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

20

I. Meteorological Environment

Meteorological scenario in and around the project site is an essential requirement

during study period for proper interpretation of baseline air quality status.

Meteorological data was collected during the study period; (November 2017 –

January 2018).The wind rose for the period of Nov 2017 to Jan 2018 is given in

Figure-6.

Figure-6: The wind rose for the period of Nov 2017 to Jan 2018.

II. Ambient Air Quality

The ambient air quality has been monitored at 8 locations for 12 parameters

including 12 parameters as per NAAQS, 2009 within the study area. The baseline

levels of PM10(48.2 - 92.4 µg/m³), PM2.5 (15.3 - 51.8µg/m³), SO2 (7.4-17.4 µg/m³),

NO2 (14.4- 44.9 µg/m³), CO (0.08—0.41 mg/m3), all the parameters are well within

the National Ambient Air Quality Standards for Industrial, Commercial and

Residential areas at all monitoring locations during the study period from November

2107 to January 2018.

Draft EIA Report

20

I. Meteorological Environment

Meteorological scenario in and around the project site is an essential requirement

during study period for proper interpretation of baseline air quality status.

Meteorological data was collected during the study period; (November 2017 –

January 2018).The wind rose for the period of Nov 2017 to Jan 2018 is given in

Figure-6.

Figure-6: The wind rose for the period of Nov 2017 to Jan 2018.

II. Ambient Air Quality

The ambient air quality has been monitored at 8 locations for 12 parameters

including 12 parameters as per NAAQS, 2009 within the study area. The baseline

levels of PM10(48.2 - 92.4 µg/m³), PM2.5 (15.3 - 51.8µg/m³), SO2 (7.4-17.4 µg/m³),

NO2 (14.4- 44.9 µg/m³), CO (0.08—0.41 mg/m3), all the parameters are well within

the National Ambient Air Quality Standards for Industrial, Commercial and

Residential areas at all monitoring locations during the study period from November

2107 to January 2018.

Draft EIA Report

20

I. Meteorological Environment

Meteorological scenario in and around the project site is an essential requirement

during study period for proper interpretation of baseline air quality status.

Meteorological data was collected during the study period; (November 2017 –

January 2018).The wind rose for the period of Nov 2017 to Jan 2018 is given in

Figure-6.

Figure-6: The wind rose for the period of Nov 2017 to Jan 2018.

II. Ambient Air Quality

The ambient air quality has been monitored at 8 locations for 12 parameters

including 12 parameters as per NAAQS, 2009 within the study area. The baseline

levels of PM10(48.2 - 92.4 µg/m³), PM2.5 (15.3 - 51.8µg/m³), SO2 (7.4-17.4 µg/m³),

NO2 (14.4- 44.9 µg/m³), CO (0.08—0.41 mg/m3), all the parameters are well within

the National Ambient Air Quality Standards for Industrial, Commercial and

Residential areas at all monitoring locations during the study period from November

2107 to January 2018.

Page 21: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

21

III. Noise Environment

It is observed that the noise levels monitored at 8 locations. Day equivalent and night

equivalent noise levels at all locations are within prescribed CPCB standards

In industrial areas day time noise levels was about 62.1 dB(A) to 65.2 dB(A)

and 51.1 dB(A) to 52.8 dB(A) during night time, which is within prescribed limit

by MoEF&CC (75 dB(A) Day time & 70 dB(A) Night time).

In residential areas day time noise levels varied from 56.1 dB(A) to 58.4 dB(A)

and night time noise levels varied from 44.1 dB(A) to 49.1 dB(A) across the

sampling stations. The field observations during the study period indicate that

the ambient noise levels in Residential area are within prescribed the limit

prescribed by MoEF&CC (55 dB(A) Day time & 45 dB(A) Night time)

IV. Water Environment

Surface water quality

The summary of surface water quality monitored at 8 locations is summarized below

In the surface water the pH varies between 6.58-7.62

The Total Dissolved Solids range varies between 200 mg/l – 2481.58 mg/l

for the surface water.

The chloride content in the surface water for study area is ranges between

12.7 mg/l – 526 mg/l.

The sulphate content of the surface water of the study area varies between

6.829 mg/l – 386 mg/l meeting the desirable limit of the IS 10500: 2012.

The Total hardness ranges is between 102 mg/l – 1785.04 mg/l.

Ground Water Quality

A summary of analytical results ground water quality monitored at 8 locations are

presented below:

The ground water results of the study area indicate that the average pH

ranges are varied between 6.91-8.14

Page 22: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

22

The Total Dissolved Solids ranges is varied between 714 mg/l – 5845 mg/l

for the ground water and for few samples exceeded the permissible limits

of IS 10500: 2012.

The desirable limit of the chloride content is 250mg/l and permissible limit

is 1000 mg/l. The chloride content in the ground water for study area is

ranges between 105 mg/l – 1516 mg/l. Some samples are exceeding the

permissible limit.

The desirable limit of the sulphate content is 200mg/l and permissible limit

is 400mg/l. the sulphate content of the ground water of the study area is

varied between 38.7 mg/l – 1585 mg/l and some samples are not meeting

the desirable limit of the IS 10500: 2012.

The Total hardness ranges is between 184.8 mg/l – 2908.6 mg/l. for

ground water and for few samples exceeded the permissible limit of the IS

10500: 2012.

V. Soil Environment

Summary of analytical results of soil quality monitored at 8 locations are presentedbelow:

The pH of the soil samples ranged from 7.25-8.22. Indicating that the soils

are almost neutral in nature.

Conductivity of the soil samples ranged from 100.5-245 μS/cm. As the EC

value is less than 2000 μS/cm, the soil is found to be non-saline in nature

The water holding capacity of the soil samples varied from 15-42 (%).

Nitrogen content ranged from 42 kg/ha to 142 kg/ha

Phosphorous ranged from 15.7 kg/ha to 63.3 kg/ha

Potassium content ranges from 62.4 to 197 kg/ha

Page 23: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

23

VI. Biological Environment

Trees and shrubs play an essential role in maintaining an ecological equilibrium and

improving the livelihood of people in the dry regions. Vegetation of a particular area

depends upon the interaction of various natural biotic and abiotic factors including

Temperature, Rain fall, Humidity, Soil type, plants, animals, micro-organisms of that

particular area in which they grow live and influence one another. The study area is

moderately rich in vegetation. The review of the study area indicated that 174 floral

species have been identified within the vicinity of the project site (refer Table 3-20 of

EIA report). The bio diversity richness map of the study area is given in Figure-7.

Figure-7: The bio diversity richness map of the study area

VII. Socio Economic Environment

Vadodara District is a district in the eastern part of the state of Gujarat in western

India. The city of Vadodara (Baroda), in the western part of the district, is the

administrative headquarters. Vadodara District covers an area of 7526 km². It had a

population of 3,641,802 with population growth of 19.87% as of 2001 census. As of

Page 24: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

24

2011 it is the third most populous district of Gujarat (out of 33) with 4,165,626, after

Ahmadabad (7,214,225) and Surat (6,081,322). The district is bounded by

Panchmahal and Dahod districts to the North, Anand and Kheda districts to the West,

Bharuch and Narmada districts to the South and Chhota Udaipur to the East.

A socio-economic study was undertaken in assessing aspects which are dealing with

social and cultural conditions, and economic status in the study area. The study

provides information such as demographic structure, population dynamics,

infrastructure resources, and the status of human health and economic attributes like

employment, per-capita income, agriculture, trade, and industrial development in the

study area. The study of these characteristic helps in identification, prediction and

evaluation of impacts on socio-economic and parameters of human interest due to

proposed project developments. The parameters are:

Demographic structure

Infrastructure Facility

Economic Status

Health status

Cultural attributes

Awareness and opinion of people about the project and Industries in the area.

VIII. Anticipated Environmental Impacts

a. Water Environment

The total raw water requirement is 560 TPH (considering the requirement of

integrated project at Dumad). Raw water storage pond of total 10 days storage of

water was considered for sizing the pond. Raw water treatment facilities include:

chemical dosing system, multi grade filter, activated carbon filter and Reverse

Osmosis plant.

Total 211.7 KLD of effluent of is anticipated and will be treated in dedicated proposed

combined ETP’s of 190 KLPH and 150 KLPH. Treated water will be passed through

RO and Permeate is used for Cooling tower and greenbelt.

Page 25: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

25

b. Air Environment

Adequate measures will be taken to control Air Pollution through installation of

Electrostatic Precipitators and Fuel Gas Desulphurisation (FGD) as a part of CPP

system. Following will be measured through installation of online analysers to

measure SOx, NOx, CO, Hydrocarbons and Particulate Matter.Total Maximum GLCs

from the proposed Stack Emissions are given in Table-12.

Table-12: Total Maximum GLCs from the proposed Stack Emissions

Pollutant

Max Baseline Conc.

(µg/m3)

predictedConc. at

source (µg/m3)

TotalConc.

(µg/m3)

NAAQstandar

d

% Increment inConcentration

Levels

PM10 92.4 2.108 94.508 100 2.28SO2 41.5 7.031 48.531 80 16.94NOx 44.9 7.301 52.201 80 16.26

It was observed that the maximum incremental concentration observed due to

proposed expansion for PM, SO2 and NOx are 2.108 µg/m3, 7.031 µg/m3 and 7.301

µg/m3. So it can be concluded that even after the expansion of the plant the impact

envisaged is minimum. Vehicular modelling was also carried out but since the

number of vehicles increased is marginal per day and no major impact envisaged on

Air environment.

c. Noise Environment

All equipment in the plant produce 40 to 55 dB(A) after control measures and

equipment are designed/operated to have a noise level not exceeding 85 to 90 dB(A)

as per the requirement of Occupational Health and Safety Administration Standard

(OHSAS). In addition, since most of the noise generating equipment would be in

closed structures, the noise transmitted outside would be still lower and for any other

case of higher noise sufficient safety ear plugs and ear muffs will be provided to the

employees.

d. Land Use

The proposed expansion is within the existing IOCl Dumad complex and the

proposed activity doesn’t change the land use classification of the site.

Page 26: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

26

IX. Environmental Monitoring ProgramA monitoring schedule with respect to AAQ, Water, Wastewater quality, Noise Quality

as per CPCB/MoEF&CC/GPCB shall be maintained.

X. Pollution Control Measures

Fugitive air emissions from captive power plant will be controlled by ESP & FGD will

be provided to meet the norms as required by CPCB. Adequate stack height will be

provided.

Municipal solid waste will be composted within the facility.

Hazardous waste will be stored and disposed off to authorized vendors for landfill.

Fly ash will be disposed off to cement manufacturing processes.

The Industrial effluent generated will be treated in inhouse ETP. The sewage from

domestic use will be treated in ETP and treated water will be recycled back into the

system.

The proposed wastewater treatment system will be a Zero Liquid Discharge (ZLD).Hence, there will be no discharge to land environment.

XI. Greenbelt Development

Project site is an existing unit with shrubs and small trees. There will be clearance of

land envisaged for proposed projects. Existing Green belt is over a stretch of 33

Acres with approx 25000-30000 trees and adequate measures will be taken to

maintain the greenbelt of 111 Acres for the proposed expansion. The lists of species

suggested for green belt is given in Table-13. Green belt development scheme is

given in Table-14.

Page 27: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

27

Table-13: List of Suggested Species for green belt

S.No

Treesspecies

Commonname

Sensitive/

Tolerant

Height

(m)

Regeneration

GrowthRate

Canopysize(m2)

1.AbutilonIndicum Kanghi Tolerant 5 Through

seedsQuick

growing NA

2.Acacia

Auriculiformis

Australianwattle Tolerant 16 By

seedsQuick

growing 8548.22

3.Acacia

Catechu Khair Tolerant 3 Byseeds

Quickgrowing 108.42

4.Acacia

DealbataSilverwattle Tolerant 15 By

seedsQuick

growing NA

5.Acacia

FarnesianaWild

Babul Tolerant 5 Byseeds

Quickgrowing NA

6.Actinodaphn

eAngustifolia

Pisa Tolerant 13 Byseeds - -

7.Adina

Cordifolia Haldu Tolerant 20 Byseeds

Slowgrowing

148490.1

8.Aegle

Marmelos Boel Tolerant 12

Byseeds,

rootcuttings

Slowgrowing

26547.19

9.Aesculus

Indica Hook Bankhar Sensitive 20

Byseeds,

rootsuckers

Quickgrowing

10.AlbiziaAmara Tugli lalai Tolerant 10

Byseeds,

rootsuckers

Quickgrowing --

11.Anona

Reticulate Raamaphal Tolerant 10 Byseeds

Fastgrowing 2017.44

12.Anthocephalus Chinensis Kadamba Tolerant 20 By

seedsQuick

growing 52233.5

13.Azadiracta

Indica Neem tree Tolerant 20 Byseeds

Quickgrowthafter 1st

season

300445.3

Page 28: Draft EIA Report - Gujarat Pollution Control Board...radius from project boundary is shown in Figure 1. ... Provision of circulation pumps, compressors, Fire and safety systems and

Draft EIA Report

28

14.Balanites

Roxburghii Ingoriyo Tolerant 9 Byseeds

Quickgrowing

15.Bambusa

Arundinocia Wans Tolerant 20 Bycuttings

Quickgrowing --

16.BarringtoniaAcutangula

Samudraphol Tolerant 9-12 By

seedsQuick

growing --

17.Bauhinia

Racemosa Asundro Tolerant 5 Byseeds

Quickgrowing 136.9

18.BauhiniaVarigata Kavindara Tolerant 5 By

seedsQuick

growing 1769.52

Source: Guidelines for Developing Greenbelts- PROBES/75/1999-2000

Table-14: Green belt development scheme

S.No

Description Scheme of plantationTotal1st

Year2nd

year3rd

year4th

Year5th

Year

1 Area to Develop(Ha) 9.105 9.105 9.105 9.105 9.105 45.525

2 Plantion of Seeds/Saplings 13650 13650 13650 13650 13650 68250

3 Expenditure(Lakhs) 18 18 18 18 18 90

Note: 1500 Trees per Hectare


Recommended