+ All Categories
Home > Documents > Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project...

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project...

Date post: 18-Oct-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
30
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President
Transcript
Page 1: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Dulles Corridor Metrorail Project

Phase 1 & Phase 2 Updates

May 31, 2018

Charles W. Stark

Senior Vice President

Page 2: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Phase 1

Page 3: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Expenditures

(Nov 17 thru Apr 18)

$ 4.0 Million

Total Expenditures

(Thru Apr 30, 2018)

$ 2.908 Billion

Forecast at Completion $ 2.982 Billion

Phase 1 Cost Summary

Page 4: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Phase 1 Update

• Closeout of VDOT Comprehensive Agreement

There are two categories of work that must be performed: remediation

of all remaining VDOT facility deficiency items and the Old Meadow

Road intersection lane widening.

Bechtel and MWAA signed an agreement share costs to perform the

concrete pipe remediation.

MWAA will remediate the remainder of the deficiencies.

• Task Order Contract Status

Task Orders with Notice To Proceed (NTP): 36 issued, including Old

Meadow Road Design; 30 have been completed.

Upcoming activities include: Americans with Disabilities Act sidewalk

repair, storm drain remediation, manhole/structure repair, Chain

Bridge Road drainage design, DCR Median Stormwater runoff

repairs, underdrain remediation, and Dulles Connector Road left

shoulder modification.

Page 5: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Old Meadow Road Schedule

• The final design is nearing completion for the realignment.

100% design is scheduled to be completed by June 29.

A traffic study now underway to be completed by June 30.

• Utility Issues:

Numerous utility facilities require minor relocation work, but significant

coordination and time effort for management, design and construction.

11 utility agencies/companies are involved.

Utility relocation scheduled to begin July 18.

• Plans Moving Forward:

Construction to begin upon completion of the utility relocation.

Construction scheduled to be complete 4th quarter 2018.

Page 6: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Phase 2

Package A 82% Complete

Package B 82% Complete

Page 7: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Phase 2 Cost Summary

Expenditures

(Nov 17 thru Apr 18)

$ 195.4 Million

Total Expenditures $ 1.733 Billion

Total Budget $ 2.778 Billion

Total Forecast $ 2.778 Billion

Page 8: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Guideway & Stations

Design-Build Activities

Current

• All Design Packages complete and issued for construction.

• 97 Identified Design and Field Changes in Progress:

42 yet to be submitted by CRC

29 in Review process (MWAA Ball in Court = 7)

26 in Issued for Permit/Issued for Construction production

process

31 reviewed/processed by MWAA last month

• Three Design Revisions approved by MWAA Building Codes

Department & three by the Department of General Services

last month.

• 119 Supplier Submittals reviewed/processed last month.

• 43 Non-Conformance Reports resolved last month.

Page 9: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Upcoming

• Electricians have received and set all Traction Power Substation

(TPSS) and Tie Breaker Station (TBS) buildings and are

continuing to connect these facilities with communication and

power cables to the guideway and stations.

• East Stations – Continue roofing, escalator installation, and

electrical and plumbing and set rail ties and track through the

stations. Reston Station platform paver installation is ongoing and

Loudoun Gateway and Ashburn Stations vault structural steel

welding and painting continues.

• Track – Ballasted rail and switch installation continues on the east

through the at-grade stations and along the guideways; the contact

(Third) rail is being installed in advance of the Systems electrical

work on the track.

Guideway & Stations

Design-Build Activities

Page 10: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Alkali Silica Reaction (ASR) Issue

• Universal Concrete Products (UCP) fabricated the At

Grade Station Precast Concrete Elements:

On May 16 the US Department of Justice unsealed a Qui

Tam complaint against UCP. The complaint contains a

previously unknown allegation that UCP used a concrete

aggregate that does not meet the specified alkali-silica

reaction requirements. This reaction can be deleterious to

the service life of concrete structures.

CRC has been notified that it must address this issue.

The Project is working with its engineering consultants to

investigate and determine if this is an actual concern.

Page 11: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Canopy Ceiling Framing in Reston Station Mezzanine

Page 12: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Set Storm Water Retention Cistern Precast Risers at Reston South Pavilion Area

Page 13: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Relocating Underground Communications Services along Sunrise Valley Drive

Page 14: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Roofing

South Pavilion Steel Installation Herndon Station

Page 15: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Placing Concrete for Barrier Walls at Herndon Station Kiss & Ride

Page 16: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Installation of Aerial Guideway Track Third Rail Cover Boards

Page 17: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Electricians Terminating Switch Power and Control Cables on Aerial Guideway

Page 18: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Pulling Wire for Electrical Systems Under Dulles Station Platform

Page 19: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Hanging Elevator Cladding

Dulles

Station

Painting Station Curtain Wall Beams

Page 20: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Testing AC Switch Gear at Loudoun Gateway Station

Page 21: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

WMATA Rail Yard & Maintenance Facility

Design-Build Activities

Current Construction

• Paving, final grading, seeding/stabilization and utility installation

continues.

• Interior buildouts continue in the Service and Inspection Building

(SIB), Maintenance of Way Building (MWB), Transportation

Building and Warehouse Building.

• Running rail installation to be complete soon, third rail installation

underway.

• Permanent power provided April 30.

Page 22: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

WMATA Rail Yard & Maintenance Facility

Design-Build Activities

Other Ongoing – Non-Construction Activities

• Gas crossing under Route 606 to begin soon.

• HP obtaining VDOT permit for the sanitary sewer crossings

under Route 606.

• Developing final testing and acceptance plans and procedures.

• Construction permit inspection and testing ongoing.

• Interface coordination with Package A continues.

Page 23: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Installing Truck Turntables in SIB High Bay Area

Page 24: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Installing Power Distribution Panels

Page 25: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Bumping Post at the Train Crew Platforms

Page 26: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Preparing to Test SIB Main Switchgear

Page 27: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

HVAC Installation in MWB Upper Mezzanine

Page 28: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Installing the Water Supply Line

Page 29: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

Tie Extender and Third Rail Installation

Page 30: Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates · Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President . Phase

DULLESMETRO.COM


Recommended