WORKSHOPS
Yaoundé CAMEROUN30/04/2016
WORKSHOPSSteel structures
2/730/04/2016
WORKSHOPSErection on site l
30/04/2016 3/7
WORKSHOPSErection on site ll
30/04/2016 4/7
WORKSHOPSErection on site IV
30/04/2016 5/7
WORKSHOPSOutside view
30/04/2016 6/7
WORKSHOPS
Production: 4 weeksErection on site: 4 weeksNb of containers: 4x 40’
Yaoundé CAMEROUN
Nb of containers: 4x 40’Surface: 750 m2.Supervisors: 2 peopleWorkforce: 8 people
7/730/04/2016