    Preparation of Pro-Forma Project Description for Scoping

    Accomplished EIA Coverage & Requirements Screening Checklist (ECRSC)

    Description and NAMRIA Map of Projects Tentatively Identified Impact Areas

    Preliminary List of Stakeholders and Partial List of Invitees to the Public Scoping

    Request for Scoping with EMB

    Review Team Formation, Scheduling of Three-Level Scoping Activity

    Conduct of Three-Level Scoping Activity

    a. 1st Level: Project Briefing Meeting with Review Team

    b. 2nd Level: Public Scoping with Community

    3 d L l T h i l S i ith R i T

    Program of Works for the Prepa

    Constru ct ion/Rehabil i tat ion/Imp rovement o f Dumalon-Zambales-Baluno

    Scoping Checklist for the Project

    SCREENING & SCOPING (SCOPING/PROCEDURAL SCREENING CHECKLIST)

    Summary Matrix of Accomplished IEC/Social Preparation Activities with List of

    Issues & Proponents Response

  • 7/30/2019 ECC Requirements

    2/38

    c 3rd Le el Technical Scoping ith Re ie Team

    Review proper by Review Team (EMB CH, EIARC, RP)

    1st Review Team Meeting

    Public Hearing (PH), Public Consultation (PC), or Site Visit (SV)

    2nd & 3rd Review Team (RT) Meeting

    Submission of EIARC Report by EIARC Chair

    EMB Evaluation of EIARC recommendations/Endorsement of Recommendaton

    Sign-off/Issuance of Decision Document

    Transmittal of ECC to Concerned Gas/LGUs

    Reconvening of Review Team & Distribution of EIA Report Copies to RT member

    Submission of Review Process Report (RPR)/Recommendation byEMB Case Handler

  • 7/30/2019 ECC Requirements

    3/38

  • 7/30/2019 ECC Requirements

    4/38

    Expected Output

    Pro-Forma PDS Completed

    ECRSC Accomplished

    Description and NAMRIA Map of

    Projects Tentatively Identified Impact

    Areas Completed

    Preliminary List of Stakeholdersand Partial List of Invitees to the

    Public Scoping Completed

    Summary Matrix of Accomplished

    IEC/Social Preparation Activities

    with List of Issues & Proponents

    Response CompletedScoping Checklist for the Project

    AccomplishedLetter Requesting Scoping with

    EMB completed and forwarded to

    EMB Reg'l Director

    EIARC Formed and date and

    venue of scoping activity confirmedThree-level Scoping Activity

    Completed

    NO. OF WORKING DAYS(within

    proponent control)

    ration of Environmental Impact Statement for the

    -Capisan-Malagutay-San Roqu e-Calarian-Cawit-Sinu nuc -Maasin Water Syst em Projec

    55 6035 40 45 505 10 20 30 615 25

  • 7/30/2019 ECC Requirements

    5/38

    EIA Report Copies distributed to RT

    members

    EIARC Review Report & Review

    Process Report CompletedAdditional Information (AI)

    Consolidated

    PH or PC/SV Completed

    Response by Proponent for every AI

    Submitted EIARC Report

    RPR/Recommendation by EMB CaseHandler Submitted

    EMB Review Process Report (RPR)

    and draft decision

    completed/Recommendation

    forwarded to EMB Chief/Director

    Sworn Statement of Full

    Responsibility on ECC Conditions

    prior to the official release of the ECC

    ECC Received by Concerned Gas /

    LGUs

  • 7/30/2019 ECC Requirements

    6/38

    4-Nov-12

    9-Nov-12

    14-Nov-12

    19-Nov-12

    24-Nov-12

    29-Nov-12

    4-Dec-12

    9-Dec-12

    14-Dec-12

    19-Dec-12

    24-Dec-12

    29-Dec-12

    3-Jan-138-Jan-13

    13-Jan-13

    18-Jan-13

    23-Jan-13

  • 7/30/2019 ECC Requirements

    7/38

    outside proponent control

    95 100 105 11080 85 9070 75

  • 7/30/2019 ECC Requirements

    8/38

  • 7/30/2019 ECC Requirements

    9/38

    EIS SCOPING AND PROCEDURAL SCREENING CHECKLIST

    PROJECT NAME: PROPOSED DUMALON WATER SYSTEM

    PROPONENT NAME: ZAMBOANGA CITY WATER DISTRICTYPROPONENT CONTACT PERSON: Leonardo Rey D. Vasquez

    EIA CONSULTANT: Planning & Design Division

    EIA CONSULTANT CONTACT PERSON: Anne Aubrey R. De Guzman-Bugtong

    Project Fact Sheet

    ~2-3 pages: Information highlights from

    Executive Summary on Project Description;

    Project Specific EIA Process, Baseline Profile,

    Key Impacts, Key environmental Management

    measures and monitoring plans; includ0.25

    page of project regional site location on

    Philippine map inset

    Table of Contents~9-10 pages: include all sections of the EIS for

    procedural screening

    1.0 Brief Project Description

    ~ 3 pages (tabulated): project location & area

    (0.25 - 0.50 page project regional location onPhilippine map inset), rationale, components,

    project phases/stages, process/technology (as

    applicable) products and production capacity

    GENERAL CONTENTS REQUIREMENTS SPECIFIC CONTENTS/ REQUIREMENTS

  • 7/30/2019 ECC Requirements

    10/38

    PROJECT LOCATION: DUMALON, ZAMBOA

    PROPONENT ADDRESS: Pilar Street, ZamboanPROPONENT MEANS OF CONTACT: Telephone Number 99

    CONSULTANT ADDRESS: Old Reservoir, Scout Li

    CONSULTANT MEANS OF CONTACT: 955-4235

    FOR SCOPING USE

    CLARIFICATIONS/CHANGES/SPECIAL

    INSTRUCTIONS BY EIA RC/EMB

    PAGE/S IN THE

    EIA REPORT REMARKS

    VALIDATED

    ACCEPTABLEBY EMB CASE

    HANDLER?

    FOR PROCEDURAL SCREENING USE

  • 7/30/2019 ECC Requirements

    11/38

    GA CITY, REGION IX

    a City1-1556

    mbaga St., Pasonanca, Zamboanga City

  • 7/30/2019 ECC Requirements

    12/38

    1. Purpose of Screening Proponent Self Screening for ECC CNC ECC Amendment

    EMB Screening for Validation Inquiry

    Site Inspection Report for: ECC/CNC/Amendment Project w/out ECC

    2. Project Name Construction/Rehabilitation/Improvement of Dumalon-Zambales-Baluno-Capisan-Malagutay-

    San Roque-Calarian-Cawit-Sinunuc & Maasin Water System Project

    3. Project Location

    4. Proponent Name Zamboanga City Water District

    5. Proponent Address Pilar Street, Zamboanga City

    6. Contact Person Anne Aubrey R. De Guzman-Bugtong

    Landline : 955-4235 Fax No. : 991-2799

    Mobile No. : E-mail : [email protected]

    8. Project Type Non-Environmentally Critical Projects (NECP) in Environmentally Critical Area (ECA)

    9. Project Status

    New Existing, for Operating without an Previously not covered

    Modification (w/ or ECC

    w/out Expansion

    Water System Project (Complete System)

    Pipelaying

    4. Sub-component # 3 7. Sub-component # 6

    10. Main Project's

    Components for both Multi-

    Component Single Project

    Applications and for Co-Located Project Applications

    7. Proponent Means of

    Contact

    1. Main Component:11. Project Size (Main Project

    component and sub

    Region

    IX

    A. SCREENING FOR EIA COVERAGE AND REQUIREMENTS

    Maasin

    Sitio Barangay/s City

    Malagutay

    San Roque

    Calarian

    CawitSinunuc

    Province/s

    Dumalon

    Zambales

    Baluno

    Capisan

    Zamboanga City

  • 7/30/2019 ECC Requirements

    13/38

    Single Project * Group II **

    (ECP) (NECP in ECA)

    Co-located Project (Group IV)Unclassified Project (Group V)

    * All new Projects are initially assumed located in ECA. Thus, there is no Grp II in the first level screening

    ** All new Projects are initially assumed located in ECA. Thus, there is no Grp III in the first level screening

    Group I12. Project Group based on

    Type of Threshold only

  • 7/30/2019 ECC Requirements

    14/38

    13. EIA Report Type

    EIS PEIS IEER PDR

    EPRMP PEPRMP IEEC Letter Request

    For EIA Report Types : Refer to Annex 2-1b for new projects, Annex 2-1c for modification, and

    Table 3 for further guidance

    - If a component has an EIA Report Requirement at a higher level than the main project component

    being applied for (e.g. EIS for a support component, IEE for main project, the component's report type

    should be adopted as the application document for the entire project.

    NOTE: FOR PROJECTS UNDER Group I (all with EIS requirement) and Group II with PDR-threshold level).

    there is no need to undertake ECA screening. Step 13 is the final screening step. For projects under Group

    II with EIS or IEE threshold, proponent is advised to go to Step # 14 if it wants the option to confirm the

    actual ECA status of the project for the purpose of determining non-coverage. If project location is

    confirmed non-ECA, project shall not be required any report type or ECC. A PDR is optional, except for

    Group II and III environmental enhancement and mitigation projects and for all Group V projects. A PDR in

    any group results to the issuance of a CNC except when a project is found to have comments fallin under

    EIS/IEE-threshold groupings in Group I or II.

    * If a Proponent opts to secure a CNC for either Group II project with PDR-threshold level or Group III

    projects, Proponent must submit a PDR. Otherwise, project has no need to secure an ECC or a CNC.

    Fill out Table 2b first as basis for filling out the ECA Summary Table 2a, then checkappropriate box below:

    ECA* NECA** Uncertain ***

    * Any one confirmed ECA among the 12 ECA categories renders the project location in ECA.

    ** All of the relevant ECA categories have to be confirmed by Proponent thru the mandated agencies as

    "not an ECA" the project is considered a NECA. See footnote of Table 2b on "relevance"

    determination

    *** If no response or data from agencies, the "uncertain" rating renders the project location as ECA.

    For ECA Categories

    14. Environmental Criticality of

    Location (ONLY FOR GROUPII PROJECTS W/ EIS & IEE-

    BASED THRESHOLDS &

    WANT TO KNOW NON-

    COVERAGE OPTION)

    Specific Category Legal Basis or Official Name of Specific ECA

    Category

  • 7/30/2019 ECC Requirements

    15/38

    - If a component has an EIA Report requirement at a higher level than the main projec being applied for

    (e.g. EIS for a support component, IEE for main project, the component's report type should be adopted as

    the application document for the entire project)

    EMB CO Director EIAMD Chair

    EMB RO Director EMB CO Director DENR Secretary

    19. Filing Fee

    Php ________________________

    17. Processing/Endorsing

    Authority

    18. Application Deciding

    Authority

  • 7/30/2019 ECC Requirements

    16/38

    (Note: Optional for Proponent for Pre-Scoping Preparations; Required for EMB if projects is required for Site Inspection Report

    prior to Substantive Review of procedurally-accepted application)

    * use Table 2bas basis for identification of environmental and social issues likely associated with the project's location in specific ECA category/ies. Otherwise,

    issues may be identied thru site inspection for a rapid screening/observation of the project environment.

    Prepared by Proponent: Signature over Printed Name Date of Signing (MM/DD/YYYY)

    Received by EMB: Signature over Printed Name Date of Receipt (MM/DD/YYYY)

    Remarks by EMB:

    SIGN-OFF PAGE FOR EMB (For Purposes # 2,3,4)

    Prepared by EMB Region Office IX: Signature over Printed Name Date of Signing (MM/DD/YYYY)

    Remarks by EMB Regional Office:

    Remarks by EMB Central Office:

    _________________________________________

    __________________________________________

    LEONARDO REY D. VASQUEZ

    General Manager

    ___________________________________________

    ___________________________________________

    Land

    Water

    Air

    People

    Site Specific (ECA/Non-ECA) Potential Key Environmental Issues

    Environmental Components Potential Issues

    B. RAPID SCREENING FOR ENVIRONMENTAL ISSUES

  • 7/30/2019 ECC Requirements

    17/38

  • 7/30/2019 ECC Requirements

    18/38

    Table 1. Project Types (in bold letters) and sub-types (Put check in appropriate boxes )

    GROUP I (ECPs in both GROUP II (NECPs in ECAs) GROUP III (NECPs in NECAs)

    ECAs and NECAs)

    o A. Golf Course Projects o A. Heavy Industries o All Group II Projecto A.1 Golf course projects/complex o A.1 Iron and Steel Mills Types/Sub Types in NECA

    o B. Heavy Industries o A.2 Non-Ferrous Metal Industries

    o B.1 Iron and Steel Mills o A.3Petroleum and Petrochemical Industries

    o B.2 Non-Ferrous Metal Industries o A.4 Smelting Plants

    o B.3 Petroleum and Petrochemical o B. Resource Extractive Industries

    Industries o B.1 Fishery Projects - Dikes for / and

    o B.4 Smelting Plants fishpond Development Projects

    o C. Resource Extractive o B.2 Forestry Projects

    Industries o B.3 Minor Mining and Quarrying Projectso C.1 Fishery Projects - Dikes for o C. Infrastructure Industries

    / and Fishpond o C.1 Minor Dams

    Development Projects o C.2 Minor Power Plants

    o C.2 Forestry Projects o C.3 Minor Reclamation Projects

    o C.3 Mining and Quarrying o C.4 Minor Roads & Bridges

    o projects o C.5 Other Power Plant (not listed in

    o D. Infrastructure Projects ProclamationNo. 2146)

    o D.1 Major Dams o D. Agriculture Industry

    o D.2 Major Reclamation Projects o D.1 Agricultural Plantation (e.g. orchards,o D.3 Major Roads and Bridges including rubber plantation)

    o D.4 Major Power Plants o D.2 Agricultural Processing Facilities

    o D.3 Cut-flower industry/Projects

    o D.4. Livestock Production

    o E. Buildings, Storage Facilities and

    other Structures

    o E.1 Cemetery

    o E.2 Commercial, (Business centers with

    residential units (mixed use) malls,

    supermarkets, public markets)

    Fast food/Restaurant Projects

    Commercial Eestablishments (i.e.

    showrooms

  • 7/30/2019 ECC Requirements

    19/38

    materials, substances or products

    o E.15 Subdivision and housing projects,

    resettlement projects, economic and

    socialized housing project, open

    market housing and other similar

    (horizontal) land development projects

    o E.16 Telecommunication Projects

    o F. Chemical Industries

  • 7/30/2019 ECC Requirements

    20/38

    GROUP I (ECPs in both GROUP II (NECPs in ECAs) GROUP III (NECPs in NECAs)

    ECAs and NECAs)

    o F.1 Manufacturing, processing and/or use

    of substances inclded in the Priority

    Chemical List

    o F.2 Manufacture of explosives, propellants

    and industrial gases

    o F.3 Manufacture of agri-chemicals and

    other industrial chemicals not in the PCL

    o F.4 Pharmaceutical industries and

    manufacture of soap and detergents

    health and beauty products, and other

    consumer products.

    o F.5 Surface coating industries (paints,

    pigments, varnishes, lacquers, anti-capacity fouling coating, printing inks)

    o G. Cottage Industries

    o H. Demonstration and Pilot Projects

    o I. Environmental Enhancement and

    o Environmental Mitigation Projects

    o I.1 Artificial Reef

    o I.2 Pollution Control devices or facilities

    required under the ECC condition/s of

    the "main" project/s covered underGroups I and II

    o I. 3 Pollution Control devices or similar

    facilities intended to prevent emissions

    and/or discharges beyond allowable limits

    (e.g. For compliance with Clean Air Act or

    Clean Water Code).

    o I.4 Preventive or proactive measures

    against potential natural hazards (such

    as shore protection, river embankment,river stabilization, seawall, etc.)

    o I.5 Reforestation Projects

    o J. Food and Related Industries

    o J1 A i l P d t i (fi h/ t

  • 7/30/2019 ECC Requirements

    21/38

    pollutants except from domestic wastes

    and occupying a space equal to or less

    than limits specified in Group I or II for

    infrastructure or other applicable project

    components needed in the service industry.

    o N. Textile, Wood, Rubber Industries

    o N.1 Textile, Wood, Rubber Industries

    o N.2 Wood and Metal Furniture Assembly

  • 7/30/2019 ECC Requirements

    22/38

    GROUP I (ECPs in both GROUP II (NECPs in ECAs) GROUP III (NECPs in NECAs)

    ECAs and NECAs)

    o O. Tourism Industry

    o O.1 Resorts and other Tourism/leisure projects

    o P. Transport Terminal Facilities

    o P.1 Airportso P.2 Land transport terminal (for buses,

    jeepneys and other modes of

    transportation)

    o Q. Treasure Hunting Projects in NIPAS

    o R. Waste Management Projects

    o R.1 Compost/fertilizer making

    o R.2 Domestic wastewater treatment facility

    o R.3 Hazardous waste treatment, recycling,

    and/or disposal facilities (for recyclingof lead, see details in Group I - Heavy

    Industries)

    o R.4 Industrial and hospital waste (non-

    hazardous) materials treatment facilities

    o R.5 Landfill for industrial and other wastes

    o R.6 Materials Recovery Facilities

    o R.7 Recovering facilities, paper, plastic, and

    other materials recycling

    oR.8 Sanitary landfill for domestic wastes only

    o S. Water Supply, Irrigation or Flood

    Control Projects

    o S.1 Impounding System or Flood Control

    Project

    o S. 2 Irrigation system (Distribution System

    only)

    o S.3 Water Supply Systems (Complete

    System)

    o S.4 Water Supply System (Distribution only)

    o T. Wildlife Farming or any related

    projects as defined by PAWB

    o Group IV (Co-located Projects)

  • 7/30/2019 ECC Requirements

    23/38

  • 7/30/2019 ECC Requirements

    24/38

    Table 2b. ECA Related Issues Screening Checklist for ENVIRONMENTALLY CRITICAL AREAS (ECAs)

    A.

    B. Areas set aside as aesthetic, potential tourist spots

    1.

    Ag

    te

    n

    a.) State specific official

    declaration of ECA

    b.) List of specific ECA at the

    project (e.g. Slope)

    Basis

    Technical Description of Twelve (12) ECA Categories

    yes no uncertain

    The projects falls within ECA

    description

    Indeterminate species shall refer to plant or animal species which are apparently

    endangered but where data currently available are insufficient for a reliable

    assessment

    The laws referred to by this provision are Pres. Decree No. 705, as amended, otherwise

    called as the "Revised Forestry Code," Republic Act No. 7586 or the National

    Integrated Protected Areas System (NIPAS) Act, and other issuances including other

    proclamations, executive orders, local ordinances and international commitments and

    declarations,

    A "national park" is defined under Section 4 (c) of the NIPAS Act as a "forest

    reservation essentially of natural wilderness character which has been withdrawn from

    settlement, occupancy or any form of exploitation except in conformity with approved

    management plan and set aside as such exclusively to conserve the area or preservethe scenery, the natural and historic objects, wild animals and plants therein and to

    provide enjoyment of these features in such area."

    A "wildlife sanctuary" is defined under Section 4 (m) of the NIPAS Act as "an area,

    which assumes the natural conditions necessary to protect naturally significant species,

    groups of species, biotic communities or physical features of the environment where

    these may require specific human manipulations for their perpetuation."

    Areas declared by law as national parks, watershed reserves , wildlife reserves,and sanctuaries

    This refers to areas considered as wilderness areas and areas identified by the

    Protected Areas and Wild Bureau (PAWB) to be natural habitats of endangered or

    threatened, rare and indeterminate species of flora and fauna

    Pasonanca Natural Park,

    Presidential Proclamation No.

    132 dated July 22, 1999

  • 7/30/2019 ECC Requirements

    25/38

    2.

    3.

    4.

    D. Areas of unique history, archeological, geological, or scientific interest

    E. Areas which are traditionally occupied by cultural communities or tribes

    F. Areas frequently visited and or hard-hit by natural calamities

    The area shall be so characterized if any of the following conditions exist

    1.

    2.

    3.

    NM

    This refers to areas which are more than 100 years old and declared by the National

    Historical Institute, National Museum or National Commission for Culture and the Arts,

    through national or local laws or ordinances as areas of cultural, historical and scientific

    significance to the nation, e.g. declared national historical landmarks, geological

    monuments, and paleontological and anthropological reservations.

    Threatened species shall refer to any plant or animal species that is likely to become

    endangered species within the foreseeable future throughout all or just a significant

    portion of its range.

    Rare species shall refer to plant or animal species, which are not under immediate

    threat of extinction but occurs in small numbers

    Endangered species shall refer to plant or animal species which are already actively

    threatened with extinction and whose survival are unlikely without protective

    measures.

    Areas frequently visited or had-hit by typhoons: This shall refer to all areas where

    typhoon signal no. 4 was hoisted for at least twice (2x) a year during the last five (5)

    years prior to the year of reckoning. For example, a determination made in 2007 willconsider the weather records from 2002 to 2006.

    This refers to all ancestral lands of National Cultural Communities identified in Sec. 1 ofP.D. No. 410 and settlements designed, implemented and maintained by the PANAMIN

    for national minorities (non-Muslim hill tribes referred to in P.D. No. 719) as may be

    amended by Republic Act No. 8371 the Indigenous People's Rights Act of 1997 (IPRA)

    and its IRR.

    This also refers to all areas that are occupied or officially claimed as ancestral lands or

    ancestral domains by indigenous communities as determined by the National

    Commission on Indigenous Peoples (NCIP). Proofs are the official applications or

    issuance of Certificate of Ancestral Domain Claim (CADC) or Certificate of Ancestral

    Domain Title (CADT) by NCIP.

    Geologic hazard areas: This refers to all areas identified by the Mines and

    Geosciences Bureau as geologic hazard areas.

    Flood-prone area: This shall refer to low-lying areas usually adjacent to large active

    water bodies experiencing inundation of at least 2 meters, twice (2x) a year for the

    last five (5) years prior to the year reckoning. For example, a determination made in

    2007 will consider the available records from 2002 to 2006.

  • 7/30/2019 ECC Requirements

    26/38

    4.

    G.

    H.

    I. Recharge areas of aquifers

    J.

    K.

    1. with primary pristine and dense young growth

    2. adjoining mouth or major river systems

    3. near or adjacent to traditional productive fry or fishing grounds;4.

    5.

    L. Coral Reefs: characterized by one or any combination of the following conditions:

    1. with 50% and above live coraline cover

    2. Spawning and nursery grounds for fish

    3. which act as natural breakwater of coastlines

    Areas prone to volcanic activities/earthquakes: This refers to all areas identified as

    such by Philippine Institute of Volcanology and Seismology(PHILVOLCS), e.g. areas

    within permanent exclusion zones of active volcanoes or areas within the required

    minimum buffer zones of fault zones as determined by PHILVOLCS4

    Areas with critical slope: This shall refer to all lands with slope of 50% or more

    classified as geohazard by MGB.

    Areas classified as prime agricultural lands: Prime agricultural lands shall refer to

    lands taht can be used for various or specific agricultural activities and can provide

    optimum sustainable yield with a minimum of inputs and development costs as

    determined by the Department of Agriculture (DA).

    Recharge areas of aquifers shall refer to sources of water replenishment where

    rainwater or seepage actually enters the aquifers

    Areas under this classification shall be limited to all local or non-national watersheds

    and geothermal reservations.Water Bodies: Water bodies shall refer to waters that are tapped for domestic

    purposes or those which support wildlife and fishery activities within declared protected

    areas, including the buffer zones

    Any one (1) confirmed ECA among the 12 EC categories renders the project location an ECA. However, before a project location is considered in a Non-ECA (NECA) all of t

    Coral reefs as an ECA category is not relevant for a project situated up in the mountains to have to be confirmed. Proponent thru the mandated agencies as "not an ECA." Sh

    on which people are dependent for their livelihood, pursuant to and taking into

    consideration Republic Act No. 7161 which prohibits the cutting of mangrove

    species

    Mangrove Areas: characterized by one or any combination of the following conditions:

    which act as natural buffers against shore erosion, strong winds and storm floods

  • 7/30/2019 ECC Requirements

    27/38

    certified by PHILVOCS as not critical, and such certification has been considered by the SC as proof of non-ECA status of the area.

  • 7/30/2019 ECC Requirements

    28/38

    Source Verification Activity Spring source (water) PDD

    PDD, Admin. &

    limit engine idling time

    allow for settling of dust over a

    period of time

    use of low sulfur and low

    aromatic fuel meeting the

    standards set motor vehicle asset by the Philippine Clean Air

    Act

    use of low-emitting Diesel

    engines meeting the

    Site inspection and source

    verification activities

    Ambient Air decrease in ambient air quality due to

    entrained dust from vehicles

    transporting personnel

    ensure regular preventive

    maintenance vehicles to

    prevent emission increases

    due to engine

    ZCWD Transport

    Maintenance Divi

    conflicting interests with lot/property

    owners

    identified proprietary rights of

    individuals over parcels of landthat will be affected by the

    project

    Lot acquisition for 300 m

    concrete ground tanks (2

    Property owner acquisition of a parcel of land which may

    or may not be acquired secure Special Land Use

    Permit from CENRO-West,

    DENR IX and Special Use

    Agreement in Protected Areas

    from the Protected Areas

    Management Board (PAMB)

    which has jurisdiction over the

    areas covered by theproposed project

    Lot Acquisition C

    (LAC)

    I. PRE-CONSTRUCTION PHASE

    disturbance of water quality, increase in

    turbidity

    limiting activities to measuring

    discharge of the source and

    sampling for water quality

    analysis

    Topographic Survey of the

    proposed pipe network

    Residents fear of displacement from present

    settlement among nearby settlers

    conducted meeting with

    affected settlers together with

    local barangay officials

    PDD, Baluno Bar

    Council

    IMPACT MANAGEMENT PLAN

    Construction/Rehabilitation/Improvement of Dumalon-Zambales-Baluno-Capisan-Malagutay-

    Sinunuc & Maasin Water SystemSitio Zambales, Barangay Baluno, Zamboanga City

    Project Phase/Environmental

    Aspect

    Environmental

    Component Likely to be Potential Impact

    Options for Prevention or

    Mitigation or Enhancement Responsible E

  • 7/30/2019 ECC Requirements

    29/38

    decrease in ambient air quality due to:

    ambient air quality

    generation of solid wastes Constructio

    Project

    Wind erosion of areas disturbed during

    construction activities;Use either water application or

    chemical dust suppressant

    application to control dust

    emissions from unpavedsurface travel and unpaved

    parking areas;

    Exhaust from automobiles and trucks

    used by workers to commute to the

    construction site;

    Pipelaying works including

    Operation of heavy

    equipments and other

    construction equipments,

    including hydrotesting and

    disinfection works, installation

    of valves/fittings and

    interconnection works;

    Installation of five (5) units of75 mm fire hydrants and

    barricade; installation of four

    (4) unit of blow-off assembly

    land prevention on site,

    segregation of waste

    according to recyclables,

    reusables and non-re-

    usable/recyclable; all such

    solid waste generated shall be

    gathered at the temporary

    facility; non-

    reusable/recyclable forappropriate disposal after

    determination of whether

    classified as hazardous/toxic

    waste

    cover all trucks hauling soil,

    sand and other loose

    materials, or require all trucks

    to maintain at least two feet of

    freeboard

    limit traffic speeds on unpaved

    surfaces at 40 kph

    Final Staking/Lay-outing/Line

    and Grade

    dust entrained during site preparation

    and grading/excavation at theconstruction site

    operational measures, such as

    limiting engine idling time andshutting down equipment

    when not in use

    ZCWD Tran

    MaintenancConstructio

    Project Engdust entrained during onsite travel on

    unpaved surfaces regular preventive

    maintenance to prevent

    emission increases due to

    engine problems

    exhaust from the Diesel construction

    equipment used for site preparation,

    grading, and excavation

    II. CONSTRUCTION PHASE

    Mobilization and Hauling of

    Materials

    Ambient Air

    Entrained dust from material delivery

    trucks traveling on unpaved

    roadsdecrease in ambient air quality

    allow for settling of dust over a

    period of time

    ZCWD Tran

    Maintenanc

    Constructio

    Project Engdust entrained during aggregate and soil

    loading and unloading operations

    use water flushing of unpaved

    road every interval to reduce

    entrained dusts in theatmosphere and to remove

    control dust emissions

  • 7/30/2019 ECC Requirements

    30/38

    ground tank

    nearest water body

    Abandonment of pipelines Engineerin

    IV. ABANDONEMENT PHASE

    land where pipelines

    have been installed

    soil contamination due to corrosion of

    pipesnatural treatment of trace

    elements due to corrosion of

    Regular maintenance of

    ground tank and source

    disturbance of water quality due to

    increase in turbidity as a result of

    maintenance activities

    allow settling to occur after

    maintenance activity has been

    performed as natural

    treatment for turbidity

    Production

    c/o O

    Construction of pipe support

    on creek crossings

    creeks and other nearby

    water bodies

    temporary disturbance in water quality

    because of human activities and

    contruction of pipe support

    cement preparation will be

    made some distance from the

    creek to avoid contamination

    of water body and to allow

    natural treatment of the creek

    before resumption of domestic

    use

    Constructio

    Project

    III. OPERATION PHASE

    Constructio

    Project

    creek, spring or other

    adjoining or nearby

    water bodies,

    underground water

    decrease in water quality due to

    temporary disturbances due to

    construction activities or introduction of

    wastewater from disinfection works

    which may increase turbidity levels and

    temporarily alter chemical

    characteristics of the water body

    concerned

    monitoring of water quality by

    taking sample for analysis at

    the laboratory or conducting

    on-site testing before and after

    the hydrotesting and

    disinfection of pipes

    Constructio

    Project

    or design

    P

    use of low-emitting Diesel

    engines meeting the

    standards set by PCAA

    exhaust from diesel-powered electric

    generators, air compressors, water

    pumps, etc.

    Ambient sounds increase in ambient noise levels at

    project site due to use of heavy

    equipments such as backhoe, dump

    truck, welding machine, bar cutter,

    hydrotesting machine, tamper hammer)

    strategic location of project

    site allows for buffer zones;

    machine operators adviced to

    use ear plugs to avoid

    damage to hearing

    exhaust from the diesel construction

    equipment used for site preparation,

    grading, excavation, and construction

    site of source collection box and

    entrained dusts from construction

    workers transportation while traveling on

    unpaved roads during construction and

    pipelaying

    regular preventive

    maintenance to prevent

    emission increases due to

    engine

  • 7/30/2019 ECC Requirements

    31/38

    Method Frequency Location

    nearby water bodies increased siltation caused

    by assessment, evaluationand monitoring activities on

    the water body

    water quality grab sampling and

    laboratory analysis

    monthly N 07 03' 9.54" E

    122 01' 54.84"

    Researcher-

    Analyst A, PD

    Station 1 Dumalon

    Creek N 07 03' 10.97"

    E 122 01' 55.57"

    Station 2 ZAMBAME

    N 07 02' 20.82" E

    122 01' 47.27"

    Station 3 Bandera GT

    Project Site N

    07 00' 00.71" E

    122 01' 40.51"

    Station 4 Baluno-

    Bandera Road

    N 07 00' 00.46" E122 01' 27.29"

    Station 5 Baluno GT

    Project Site

    as may be

    needed

    High Volume -

    Gravimetric

    Method for PM 10;

    Impinger -Pararosaniline

    Colorimetric

    Method for SOx

    and Impinger -

    Griess Saltzman

    Reaction Method

    for NOx

    Republic of the Philip

    ZAMBOANGA CITY WATE

    Planning and Design D

    I. PRE-CONSTRUCTION PHASE

    Key Envi ronmenta l

    Aspects per Project

    Phase

    Potential Imp acts per

    Envt ' l Sector

    Parameter to be

    Monitored

    Sampling & Measuremen t Plan

    Lead Person

    SELF-MONITORINCONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

    ambient air quality air qualityair pollution caused by

    vehicle emissions

    Researcher-

    Analyst A, PD

  • 7/30/2019 ECC Requirements

    32/38

    noise nuisance due to noise

    generation

    presence or absence of

    complaints

    auditory sensing as may be

    necessary

    above sited project

    sites

    Researcher-

    Analyst A, PDD

    people enhanced employmentand/or livelihood

    opportunities

    presence or absence ofcomplaints

    public consultation during projectplanning and prior

    to project

    implementation

    directly affectedbarangays of the

    project

    ZCWDmanagement/H

    R Division

    increase in traffic volume presence or absence of

    complaints

    consultation during conduct of

    site inspection

    identified project sites Researcher-

    Analyst A, PDD

    disturbance to wildlife and

    vegetation due to

    construction activities

    compliance with the

    conditions under the

    SAPA-MOA and SLUP

    ocular inspection

    and monitoring

    quarterly above sited project

    sites when applicable

    project

    PCO/Engineer

    change in

    surface/landform/topograph

    y/terrain/slope as a result of

    pipelaying and construction

    activities

    regular inspection of

    slope protection

    measures in erosion

    prone areas; inspection

    for new eroded areas

    near the project site

    ocular inspection

    and monitoring

    bi-quarterly above sited project

    sites when applicable

    project

    PCO/Engineer

    soil/land contamination due

    to improper solid waste

    disposal

    volume and

    classification of solid

    waste generated

    grab sampling and

    volumetric

    measurement

    daily above sited project

    sites

    project

    PCO/Engineer

    land impairement of visual

    aesthetics;

    regular inspection of

    landscaping and other

    beautification activities

    and monitoring of buffer

    occular inspection

    and monitoring

    monthly above sited project

    sites

    project

    PCO/Engineer

    land

    II. CONSTRUCTION PHASE

  • 7/30/2019 ECC Requirements

    33/38

    Depletion of water

    resources for downstream

    users

    volume volumetric

    measurement

    monthly Dumalon Creek N 07

    03' 10.97" E 122

    01' 55.57"

    project

    PCO/Engineer

    Station 1 Dumalon

    Creek N 07 03' 10.97"

    E 122 01' 55.57"

    Station 2 ZAMBAME

    N 07 02' 20.82" E

    ' "Station 3 Bandera GT

    Project Site N

    07 00' 00.71" E

    ' "Station 4 Baluno-

    Bandera Road

    N 07 00' 00.46" E

    ' "Station 5 Baluno GT

    Project Site

    N 06 59' 56.15" E

    122 01' 17.15"

    noise nuisance due to noise

    generation during project

    implementation and

    operation of construction

    equipments

    presence or absence of

    complaints

    auditory sensing as needed above sited project

    sites

    project

    PCO/Engineer

    displacement of residents in

    the project site and within

    its vicinity

    presence or absence of

    complaints

    consultation with

    concerned

    residents to be

    displaced

    when necessary upstream areas of the

    tapping point;

    identified sites for

    construction of 300

    cubic meter capacity

    Lot Acquisition

    Committee

    enhanced employment

    and/or livelihood

    opportunities

    presence or absence of

    complaints

    consultation with

    the LGU

    during project

    planning and prior

    to project

    im lementation

    directly affected

    barangays of the

    project

    ZCWD

    management

    enhanced delivery of public

    services

    presence or absence of

    complaints

    consultation with

    the LGU

    during project

    planning and prior

    to project

    im lementation

    directly affected

    barangays of the

    project

    ZCWD

    management

    Air once project

    PCO/Engineer

    Air quality degradation due

    to construction activities

    and equipment

    air quality;

    absence/presence of

    complaint;

    High Volume -

    Gravimetric

    Method for PM 10;Impinger -

    Pararosaniline

    Colorimetric

    Method for SOx

    and Impinger -

    Griess Saltzman

    Reaction Method

    people

  • 7/30/2019 ECC Requirements

    34/38

    presence of visually

    significant structures

    ensuring that structures

    are still visually

    aesthetic

    ocular inspection

    and monitoring

    regular exposed G.I. Pipeline,

    concrete ground tank

    sites and site of intake

    facility

    Designated

    PCO

    water increased siltation due to

    operational and

    maintenance activities

    water quality grab sampling and

    laboratory analysis

    regular Dumalon Creek N 07

    03' 10.97" E 122

    01' 55.57"

    Designated

    PCO

    competition in water use;

    possible depletion of water

    resources for downstream

    users

    streamflow of the water

    source

    volumetric

    measurement

    monthly from tapping point at N

    07 03' 10.97" E

    122 01' 55.57" to the

    whole downstream

    intake facility

    operator

    noise nuisance due tomaintenance activities

    especially when using

    generator set and other

    heavy equipment when

    presence or absence ofcomplaints

    tolerance-based regular where maintainanceactivities are being

    conducted

    maintenancepersonnel/des

    gnated PCO

  • 7/30/2019 ECC Requirements

    35/38

    No. Function/Activities Performance Indicator

    1st

    QTR

    2nd

    QTR

    3rd

    QTR

    4th

    QTR

    1.0Organizational Meeting, election/designation

    of officers/Executive Committee and

    Sectora/Committee members

    Officers elected and

    committees formed

    2.0 Training-Workshop on the Preparation of the

    MMT Manual of Operations (MOO) MMT MOO

    3.0

    Training-Workshops on the preparation and

    use of the customized MMT Compliance

    Monitoring and Validation Report (CMVR)

    Customized CMVR

    Format for MMT

    Trained MMT

    Members on

    preparation of CMVR

    4.0 Preparation of Annual Work and Financial

    Plan (AWFP) - fully operational MMT AWFP

    5.0 Initial Compliance Monitoring and Reporting

    Activities

    CMVR for submission

    to EMB

    NO. Cost Item per Activity in the Work Plan Unit Cost Qty

    Days/

    No

    1st

    QTR

    2ND

    QTR

    3RD

    QTR

    4TH

    QTR TOTAL1.0

    1.1 Meals/venue 200.00 25 1 1 1 1 1 20,000.00 4

    1.2 Transportation Cost/Allowance 200.00 15 1 1 1 1 1 12,000.00 4

    1.3 Materials 150.00 25 1 1 1 1 1 15,000.00 447,000.00 #VALUE!

    2.0 #VALUE!2.1 Meals/venue 200.00 25 1 1 5,000.00 1

    2.2 Transportation cost/allowance 200.00 15 1 1 3,000.00 1

    2.3 Materials 150.00 25 1 1 3,750.00 12.4 Honoraria for Resource Persons 3,000.00 1 1 1 3,000.00 1

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    DRAFT WORK PLAN (MMT START UP)

    DRAFT FINANCIAL PLAN (MMT START-UP)

    Organizational Meetings, election/designation of officers/Executive Committee and Sectoral Committee

    Training-Workshop on the Preparation of the MMT Manual of Operations (MOO)

    CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-SAN ROQUE-

    CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM

  • 7/30/2019 ECC Requirements

    36/38

    NO.

    Cost Item per

    Activity in the Work

    Plan Unit Cost Qty Days/No 1st QTR

    2ND

    QTR

    3RD

    QTR 4TH QTR TOTAL

    1.0

    1.1 Meals/venue 200.00 25 1 1 1 1 1 20,000.00 41.2 Transportation

    Cost/Allowance 200.00 15 1 1 1 1 1 12,000.00 4

    1.3 Materials 150.00 25 1 1 1 1 1 15,000.00 4

    47,000.00 0

    2.0 0

    2.1 Meals/venue 200.00 25 1 5,000.00 1

    2.2 Transportation

    cost/allowance 200.00 15 1 3,000.00 1

    2.3 Materials 150.00 25 1 3,750.00 1

    2.4Honoraria for

    Resource Persons 3,000.00 1 1 3,000.00 1

    14,750.00 0

    3.0

    0

    3.1 Meals/venue 200.00 25 1 5,000.00 1

    3.2 Transportation

    Cost/Allowance 200.00 15 1 3,000.00 1

    3.3 Materials 150.00 25 1 3,750.00 1

    3.4 Honoraria for

    Resource Persons 3,000.00 1 1 3,000.00 1

    14,750.00 0

    4.0 0

    4.1 Meals/Venue 200.00 25 1 5,000.00 1

    4.2 Transportation

    cost/allowance 200.00 15 1 3,000.00 1

    4.3 Materials 150.00 25 1 3,750.00 1

    11,750.00 0

    5.0 0

    5.1 Document Review

    Meeting

    Meals/Venue 200.00 25 1 5,000.00 1

    5.2 Document review

    DRAFT FINANCIAL PLAN (MMT START-UP)

    Compliance Monitoring and Reporting Activities

    Organizational Meetings, election/designation of officers/Executive Committee and Sectoral Committee

    Training-Workshop on the Preparation of the MMT Manual of Operations (MOO)

    Training-Workshops on the preparation and use of the customized MMT Compliance Monitoring and

    Validation Report (CMVR)

    Preparation of the next year's Annual Work and Financial Plan (AWFP) - fully operational MMT

  • 7/30/2019 ECC Requirements

    37/38

    COMPOSITION

    EMB IX

    DENR IX

    ZCWD

    LGUs

    Baluno

    Capisan

    Dulian-Upper Pasonanca

    Malagutay

    San Roque

    CalarianCawit

    Sinunuc

    Maasin

    Acredited NGOs/POs

    Concerned Gov't Agencies

    Protected Areas Management BoardCENRO-West

  • 7/30/2019 ECC Requirements

    38/38

    Particulars cost date paid to whom paid Remarks

    EIS Review Fund 201,825.00Php 6-Feb-13

    PSME (third party

    fund manager) paid

    Application Fee 6,000.00Php 8-Aug-13 EMB IX paid

    Environmental Guarantee Fund - -

    third party fund

    manager

    amount to be fixed during

    the Review

    Environmental Monitoring Fund 100,500.00Php -

    third party fund

    manager

    amount based on draft

    AWFP for Dumalon Water

    System

    PD 1586 10,000.00Php - EMB IX amount requested

    Prepared by: Reviewed by: Noted by:

    ANNE AUBREY R. DE GUZMAN-BUGTONG MARIE CLAIRE C. BONGO

    Researcher-Analyst A (JO) Principal Engineer C

    MARLI P. ACOSTA-DE FIESTA

    OIC, Planning and Design Division

    Construction/Rehabilitation/Improvement of the Dumalon-Zambales-Baluno-Capisan-Malagutay-San Roque-Calarian-Cawit-Sinunuc & Maasin

    Water System

    Breakdown of Funds/Fees


Recommended