+ All Categories
Home > Documents > ECG524-Topic 2a-Asphaltic Concrete Pavement Design

ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Date post: 02-Oct-2014
Category:
Upload: adikaazwan
View: 107 times
Download: 1 times
Share this document with a friend
Popular Tags:
68
Pavement Engineering ECG 524 TOPIC 2.0 Asphaltic Concrete Pavement Design
Transcript
Page 1: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Pavement Engineering

ECG 524TOPIC 2.0

Asphaltic Concrete Pavement Design

Page 2: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

2.1 Hot Mix Asphalt Mixture Design Methodology

2.2 Marshall mixture design method

2.3 Superpave mix design method

2.4 Design of Flexible Pavement

2.5 Overlay design and surface dressing

Topic Outlines

Page 3: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

3

At the end of the lecture, students should be

able to:

Perform design mix according to either Marshall

or Superpave Method .(CO2-PO3, CO2-PO4)

To understand the element of thickness design,

material requirements, mixture requirements,

traffic loading and JKR Design Method.(C02-

PO4)

Learning Outcomes

Page 4: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

4

Topic 2.1

Hot Mix Asphalt Mixture Design Methodology

Page 5: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Introduction

History of asphalt mix design dated backfrom 1860s (Crawford)

First binder used was TAR (1868 and1873)

Aggregate proportioning not understood,hence no proper mixing processedmechanized

Page 6: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Introduction

Clifford Richardson, an asphalt technologistdiscovered that material selection is important,especially the role of aggregate fractions

His documentations include the importantprinciples of HMA design including voids inmineral aggregate (VMA) and air void content

The first test to determine OBC of HMA mix is the “Pat Test”

Still used till early 1920s – visual assessments

Page 7: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Hubbard-Field method in the middle of 1920s

Marshall and Hveem mix design methodswere used between 1940s and mid 1990s

In 1939, Bruce Marshall developed theearliest version of Marshall mix designmethod

Controlling factor is the correspondence betweendensity achieved in field under traffic and thatproduced in the lab with specified compactive effort,hence only by knowing field conditions can properadjustments be made in the lab to replicate fieldconditions

Introduction

Page 8: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Hveem mix design method – FrancisHveem

Hveem developed stabilometer in 1959,a procedure to measure cohesivestrength of compacted specimen

Developed simple portable apparatusfor designing asphalt mixtures forairfield pavements

Introduction

Page 9: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Hot Mix Asphalt Design

History

Binder

HMA

Specimen

Aggregates

Page 10: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Hot Mix Asphalt Concrete (HMA)

Mix Designs

Objective:

– Develop an economical blend of aggregates and

asphalt binder that meets design requirements

Historical mix design methods

– Hubbard-Field, Hveem, Marshall (1920 – 1940)

New

– Superpave Mix Design Method (1995 - present)

– Srategic Highway Research Programme (SHRP)

Page 11: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

No matter which design procedure is going to be usedthe HMA mixture that is placed on the roadway mustmeet certain requirements.

Sufficient asphalt binder to ensure a durable pavement

- To ensure durable, compacted pavement by thoroughly coating, bonding and waterproofing the aggregate

Sufficient stability under traffic loads

- To satisfy the demands of traffic without displacement or distortion (rutting)

Requirements in Common

Page 12: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Sufficient air voids

-to prevent excessive environmental damage

should be low enough to keep out harmful air and moisture

-to allow room for initial densification due to traffic

should have sufficient voids to allow compaction under

traffic

loading without bleeding and loss of stability

Sufficient workability

-Enough workability to permit placement and proper

compaction without segregation

Requirements in Common

Page 13: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Resistance to Permanent DeformationMix should not distort or displace when subjected to traffic. The

resistance to permanent deformation (rutting) becomes critical

at elevated temperatures during hot weather when the viscosity

of the bitumen is low and traffic load is primarily carried by

aggregate structure. Hence, selecting quality aggregate is

important with proper gradation.

Fatigue Resistance

Mix should not crack when subjected to repeated loads over a

period of time.

Objectives and Elements of Mix Design

Page 14: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

DurabilityMix must contain sufficient bitumen to ensure adequate film

thickness around aggregate particles, thus minimizing binder

hardening or aging during production and in service.

Resistance to Moisture Induced Damage

Some HMA mix when subjected to moisture or water lose

adhesion between aggregate surface and binder. Aggregate

properties are primarily responsible for this phenomenon,

although some binder ar more prone to moisture damage

(stripping) than others. Antistripping agent should be use if a

HMA mix is prone to stripping to minimize problems or making

the mix impermeable

Objectives and Elements of Mix Design

Page 15: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Skid Resistance

This requirement is only applicable to surface mixes which must

be designed to provide sufficient resistance to skidding to permit

normal turning and braking movements to occur. Aggregate

characteristics such as texture, shape, size and resistance to

polish are primarily responsible for skid resistance. Mix should

not also contain too much binder that may cause mix to flush

and create slippery surface.

Workability

Mix must be capable of being placed and compacted with

reasonable effort. Workability problems are most frequently

discovered during the paving operations.

Objectives and Elements of Mix Design

Page 16: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

16

Topic 2.2

Marshall Mix Design Method

Page 17: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

MARSHALL

MIX

DESIGN

Page 18: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Marshall Mix Design

Developed by Bruce Marshall for the Mississippi Highway Department in the late 30’s

In 1943 for WWII – Developed simple portable apparatus for designing asphalt mixtures for airfield pavements

– Evaluated compaction effort

• No. of blows, foot design, etc.

• Decided on 10 lb.. Hammer, 50 blows/side

• 4% voids after traffic

Initial criteria were established and upgraded for increased tyre pressures and loads

Page 19: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Automatic Marshall Hammer

Mixtures designed in laboratory

using a variety of compactive

efforts in an attempt to produce

densities similar to field

One goal of lab compaction

study was to adopt a sample

preparation procedure that

would involve minimum effort

and time but would provide a

basis for selecting the proper

optimum binder content

Page 20: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Development and evolution of the Marshall method

concluded that two variables stand out in the design and

performance of HMA:

•Asphalt content

•Density

In the field, it is the highest satisfactory asphalt content at

a density achieved under traffic that is significant.

In laboratory, the important feature is selecting a

compaction procedure that represents traffic-induced

density and then selecting response properties that can be

averaged to yield as asphalt content that will produce

satisfactory performance.

Page 21: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Marshall Design Method

Advantages

– Attention on voids, strength, durability

– Inexpensive equipment

– Easy to use in process control/acceptance

Disadvantages

– Impact method of compaction

– Does not consider shear strength

– Load perpendicular to compaction axis

Page 22: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Marshall Mix Design Method

(ASTM D1559)

Steps:

– Step A: Aggregate Evaluation

– Step B: Binder/Bitumen Evaluation

– Step C: Preparation of Marshall Specimens

– Step D: Density-Voids Analysis

– Step E: Marshall Stability and Flow Test

– Step F: Tabulating & Plotting Test Results

– Step G: Determine Optimum Binder

Content (OBC)

Page 23: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step A: Aggregate Evaluation

A-1:

Determine acceptability of aggregate for use in HMA, construction;

tests often performed include LA abrasion, sulfate soundness, sand

equivalent, presence of deleterious substances, polishing, crushed

face count and flat & elongated particle

A-2:

If material is acceptable in A-1, then perform other required

aggregate tests: gradation, specific gravity and absorption

A-3:

Perform blending calculations, plot mid range gradation on FHWA

0.45 power gradation chart

A-4:

Prepare a specimen weigh-out table by multiplying the percent

aggregate retained between sieves times an aggregate weight of

approximately 1150g, then determine the cummualtive weights

starting with the material passing the 0.075 mm sieve

Page 24: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step A: Basic Aggregate Testing

Page 25: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Mix Type Wearing

Course

Wearing

Course

Binder Course

Mix

Designation

AC10 AC14 AC28

BS Sieve Size Percentage Passing by Weight

28.0

20.0

14.0

10.0

5.0

3.35

1.18

0.425

0.150

0.075

100

90-100

58-72

48-64

22-40

12-26

6-14

4-8

100

90-100

76-86

50-62

40-54

18-34

12-24

6-14

4-8

100

72-90

58-76

48-64

30-46

24-40

14-28

8-20

4-10

3-7

JKR Gradation Limits

Page 26: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Aggregate Blending

How many percentage from each stockpile to

achieve a blend that conform to PWD mid-gradation,

example ACW 14?

Page 27: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Blending of Aggregates

Agg. BAgg. A

Blend Target

Material

%

Passing

%

Passing

% Used

Sieve (mm)%

Batch

%

Batch

10

5

3.35

1.18

0.425

0.15

0.075

14

90

30

7

3

1

0

0

100

100

100

88

47

32

24

10

100

Page 28: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Blending of Aggregates

Agg. BAgg. A

Blend Target

Material

%

Passing

%

Passing

% Used

Sieve (mm)%

Batch

%

Batch

10

5

3.35

1.18

0.425

0.150

0.075

14

45

15

3.5

1.5

0.5

0

0

100

100

100

88

47

32

24

10

100

50 %50 %

First Try

(remember trial & error)

90

30

7

3

1

0

0

50

90 * 0.5 = 45

30 * 0.5 = 15

7 * 0.5 = 3.5

3 * 0.5 = 1.5

1 * 0.5 = 0.5

0 * 0.5 = 0

0 * 0.5 = 0

100 * 0.5 = 50

80 - 100

65 - 100

40 - 80

20 - 65

7 - 40

3 - 20

2 - 10

100

Page 29: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Blending of Aggregates

Agg. BAgg. A

Blend Target

Material

%

Passing

%

Passing

% Used

Sieve (mm)%

Batch

%

Batch

10

5

3.35

1.18

0.425

0.150

0.075

14

80 - 100

65 - 100

40 - 80

20 - 65

7 - 40

3 - 20

2 - 10

100

45

15

3.5

1.5

0.5

0

0

100

50

50

44

23.5

16

12

5

50

50 %50 %

90

30

7

3

1

0

0

50

95

65

47.5

25

16.5

12

5

100

100

100

88

47

32

24

10

100

Let’s Try

and get

a little closer

to the middle of

the target values.

Page 30: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Blending of Aggregates

Agg. BAgg. A

Blend Target

Material

%

Passing

%

Passing

% Used

Sieve (mm)%

Batch

%

Batch

10

5

3.35

1.18

0.425

0.150

0.075

14

80 - 100

65 - 100

40 - 80

20 - 65

7 - 40

3 - 20

2 - 10

100

27

9

2.1

0.9

0.3

0

0

100

70

70

61.6

32.9

22.4

16.8

7

70

70 %30 %

90

30

7

3

1

0

0

30

97

79

63.7

33.8

22.7

16.8

7

100

100

100

88

47

32

24

10

100

Page 31: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Aggregate Blending to Meet Specifications Given the gradation of aggregates A, B and C, determine the required percent of

each to result in a blend meeting the required specification requirements

Sieve Size

Aggregate

Specifications

Median of

SpecificationsA B C

1 inch 100 100 100 94-100 97

½ inch 63 100 100 70-85 78

No.4 (4.75 mm or 3/8 inch) 19 100 100 40-55 48

No.8 (2.36 mm) 8 93 100 30-42 36

No.30 (0.6 mm) 5 55 100 20-30 25

No.100 (0.150 mm) 3 36 97 12-22 17

No.200 (0.075 mm) 2 3 88 5-11 8

Desired

material

larger than

4.75mm

sieve is 52%

must come

from Agg. A

Desired

material

larger than

0.6 mm sieve

is 75% must

come from

Agg. A and B

percent of A = = 64 %81

52percent of B = 75 – 0.64(95) = 14 %

Page 32: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Sieve Size

Aggregate

Specification

s

Median of

SpecificationsA B C

1 inch 100 100 100 94-100 97

½ inch 63 100 100 70-85 78

No.4 (4.75 mm or 3/8 inch) 19 100 100 40-55 48

No.8 (2.36 mm) 8 93 100 30-42 36

No.30 (0.6 mm) 5 55 100 20-30 25

No.100 (0.150 mm) 3 36 97 12-22 17

No.200 (0.075 mm) 2 3 88 5-11 8

Desired

material

larger than

4.75mm

sieve is 52%

must come

from Agg. A

Desired

material

larger than

0.6 mm sieve

is 75% must

come from

Agg. A and B

percent of A = = 64 %81

52percent of B = 75 – 0.64(95) = 14 %

Based on these calculations, first estimate is :

Aggregate A : 64 %

Aggregate B : 14 %

Aggregate C : 22 %

Page 33: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Aggregate %

Used

Sieve Size

1 inch ½ inch No.4 No.8 No.30 No.100 No.200

A 64 64 40.3 12.2 5.1 3.2 1.9 1.3

B 14 14 8.8 2.6 1.1 0.7 0.4 0.3

C 22 22 13.8 4.2 1.7 1.1 0.7 0.4

Blend 100 100 62.9 19 7.9 5 3 2

Desired 97 78 48 36 25 17 8

Specification 94-100 70-85 40-55 30-42 20-30 12-22 5-11

FIRST TRIAL

A 71 71 44.7 13.5 5.7 3.6 2.1 1.4

B 21 21 21 21 19.5 11.6 7.6 0.6

C 8 8 8 8 8 8 7.8 7

Blend 100 100 73.7 42.5 23.2 23.2 17.5 9.0

SECOND TRIAL

A 66

B 28

C 6

Blend 100

Source : HMA Asphalt Materials, Mixture Design & Construction, NAPA

Page 34: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step B: Basic Asphalt Testing

B-1:

Determine appropriate binder grade for type and geographic

location of mixture being designed

B-2:

Verify specification properties are acceptable

B-3:

Determine binder specific gravity and plot viscosity data on a

temperature-viscosity plot

B-4:

Determine the ranges of mixing and compaction temperatures from

the temperature-viscosity plot:

– Mixing temperature should be selected to provide viscosity of 170 ±

20 centistokes

– Compaction temperature should be selected to provide a viscosity

of 280 ± 30 centistokes

Page 35: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step B: Basic Asphalt TestingAsphalt Properties Required by JKR Malaysia

Standard Tests Penetration Grades

60-80 80-100

Penetration @ 25oC 60-80 80-100

Loss on heating (%) <0.2 <0.5

Drop in penetration after heating (%) <20 <20

Retained penetration after thin-film

oven test (%)

>52 >47

Solubility in Carbon Disulphide or

Trichloroethylene (%)

>99 >99

Flash and fire point test (oC) >250 >225

Ductility test at 25oC >100 >100

Ring and Ball Softening Point test >48, <56 >45,<52

Page 36: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

.1

.2

.3

.5

1

10

5

100 110 120 130 140 150 160 170 180 190 200

Temperature, C

Viscosity, Pa s

Compaction Range

Mixing Range

Mixing/Compaction Temperatures

To establish mixing and compaction temperatures it is necessary to develop a temperature viscosity chart.

Determining the viscosity at two different temperatures - generally 135 C and 165 C. These two

viscosities are then plotted on the graph above and a straight line is drawn between the two points.

The desired viscosity range for mixing is between 0.15 and 0.19 Pa-s and 0.25 and 0.31 Pa-s for

compaction. Appropriate mixing and compaction temperatures are selected as the temperature where these

viscosity requirements are met. This information can be obtained from the suppliers.

If using modified binders - it is recommended that you should contact the supplier to determine the mixing

and compaction temperatures.

Page 37: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step C: Preparation of Marshall Specimens

C-1:

Dry and sieve aggregates into sizes (preferably individual sizes) and

store in clean sealable containers. Separate enough material to make

18 specimens of approximately 1150 g each.

C-2:

Weigh out aggregate for 18 specimens placing each in a separate

container and heat to mixing temperature determined in Step B-4.

However, the total aggregate weight should be determined as

discussed in C-3.

C-3:

It is generally desirable to prepare a trial specimen prior to preparing all

aggregate batches. Measure the height of the trial specimen (h1) and

check against height requirement for Marshall specimens (63.5 mm). If

the specimen is outside this range, adjust quantity of aggregate

included in a specimen using the following formula:

Q = 63.5/h1 x 1150 g

Page 38: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step C: Preparation of Marshall Specimens

C-4:

Heat sufficient binder to prepare a total of 18 specimens. Three

compacted specimens each should be prepared at five different binder

content. Binder contents should be selected at 0.5% increments with at

least two asphalt contents above “optimum” and at least two below

“optimum”. See appropriate specifications for a guide on approximate

“optimum” binder content or the estimate of optimum can be based on

experience. Three loose mixture specimens should be made near the

optimum binder content to measure Rice specific gravity or theoretical

max density (TMD).

Table 4.3.4 : Design Bitumen Contents (JKR/SPJ/2008-S4)

AC 10 – wearing course

AC 14 – wearing course

AC 28 – binder course

5.0-7.0%

4.0-6.0%

3.5-5.5%

Page 39: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step C: Preparation of Marshall Specimens

C-5:

Review appropriate specifications to determine number of blows/side

and type of compaction equipment required for compaction of Marshall

specimen

C-6:

Remove the hot aggregate, place it on a scale and add the proper

weight of binder to obtain the desired binder content

C-7:

Mix binder and aggregate until all the aggregate is coated. It is helpful

to work on a heated table. Mixing can be by hand, but a mechanical

mixer is preferred

Page 40: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step C: Preparation of Marshall Specimens

C-8:

Check temperature of freshly mixed material; if it is above the

compaction temperature, allow it to cool to compaction temperature; if it

is below compaction temperature, discard the material and make a new

mix. (The mix can be placed back in the oven to be reheated which is

considered as curing time to better simulate what happens to the HMA

mix in the field. This curing time is especially important for aggregates

with high absorption since the asphalt absorbed into the aggregate

increases with time).

C-9:

Place a paper disc into an assembled, preheated Marshall mould and

pour in loose HMA. Check the temperature. Spade the mixture with a

heated spatula or trowel 15 times around the perimeter and 10 times

over the interior.

Page 41: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step C: Preparation of Marshall Specimens

C-10:

Remove the collar and mound materials inside the mould so that the

middle is slightly higher than the edges. Attach the mould and base

plate to the pedestal. Place the preheated hammer into the mould, and

apply the appropriate number of blows to the top side of the specimen

C-11:

Remove the mould from the base plate. Place a paper disc on top of

the specimen and rotate the mould 180o so that the top surface is on

bottom. Replace the mould collar and attach the mould and base plate

to the pedestal. Place the hammer in the mould and apply the same

number of blows to the opposite side of the specimen

C-12:

Remove the paper filters from the top and bottom of the specimens.

Cool the specimens and extrude from the mould using a hydraulic jack.

Place identification marks on each specimen and allow specimens to sit

at room temperature overnight before further testing

Page 42: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step C: Preparation of Marshall Specimens

C-13:

Determine the bulk specific gravity for each specimen by weighing in air.

Submerge the samples in water and allow to saturate prior to getting submerged

weigh in SSD condition. Remove the sample and weigh in air in saturated

surface dry condition. This test is conducted in accordance with AASHTO T166

C-14:

Measure the Rice specific gravity on the loose HMA mix samples in accordance

with AASHTO T209 (ASTM D2041). This specific gravity is required for voids

analysis. If the mix contains absorptive aggregate it is recommended to place

the loose mix in an oven (maintained at the mix temp) for 4 hours so that the

asphalt binder is completely absorbed by the aggregate prior to testing. Keep

the mix in a covered container while in the oven. If the test is run in triplicate on

the mix containing near optimum binder content, average the three results,

calculate the effective specific gravity of the aggregate, and then calculate the

Rice specific gravity or TMD for the remaining mixes with different binder

content. If one TMD test is conducted on each mix containing a different binder

content, then calculate the effective specific gravity of aggregate in each case.

Calculate the average effective specific gravity and then calculate the TMD

values using the average for all five mixes.

Page 43: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Mixing

Place pre-heated aggregate in bowl & add hot bitumen

Place bowl on mixer & mix until aggregate is well-coated (1minute mixing time)

Place funnel on top of mould & place mix in mould. Take carenot to allow the mix to segregate

Place another paper on top of mix. Tamp along circumference &centre. Wait for specimen to cool down to compactiontemperature. Begin compaction.

Page 44: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Compaction

Marshall Hammer (impact) @50 or 75 blows each face

Page 45: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step D: Density and Voids Analysis

D-1:

For each specimen, use the bulk specific Gravity (Gmb) from

Step C-13 and Rice Specific gravity (Gmm) from C-14 to

calculate the percent voids or VTM

D-2:

Calculate the density of each Marshall specimen as follows:

Density (g/ml) = Bulk Specific Gravity (Gmb) x δw

1001

mm

mb

G

GVTM

Page 46: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step D: Density and Voids Analysis

D-3:

Calculate the VMA for each Marshall specimen using the bulk

specific gravity of the aggregate (Gsb) from Step A-2, the bulk

SG of the compacted mix (Gmb) from Step C-13, and the binder

content by weight of total mix (Pb)

D-4:

Calculate the VFA (voids filled with asphalt) for each Marshall

specimen using the VTM and VMA as follows :

VMA

VTMVMAVFA 100

sb

bmb

G

PGVMA

)1(1100

Page 47: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step E: Marshall Stability and Flow Test

E-1:

Heat the water bath to 60oC and place specimens to be tested in the

bath for at least 30 but not more than 40 minutes. Place specimens in

the bath in a staggered manner to ensure that all specimens have been

heated for the same length of time before testing. Use waterbath large

enough to hold all specimens prepared for the mixture design

E-2:

After heating for the required amount fo time, remove a specimen from

the bath, pat with towel to remove excess water, and quickly place in

the Marshall testing head

E-3:

Bring the loading ram into contact with the testing head. Zero the pens

if using a load-deformation recorder or zero flow gauge, and place the

gauge on the rod of the testing head. Apply the load

Page 48: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Marshall Stability and Flow

Page 49: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step E: Marshall Stability and Flow

Tests

test for Marshall Stability & flow at 60OC

The applied load must be corrected when thickness of

specimen is other than (2½ in.) or 63.5mm by using the

proper multiplying factor from Table below

Page 50: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Stability correlation ratio (ASTM D1559)

Page 51: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Lab Mix – Marshall Form

Page 52: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step F: Tabulating and Plotting Test

Results

F-1:

Tabulate the results from testing, correct the stability values for

specimen height (ASTM D1559), and calculate the average of each set

of 3 specimens

F-2:

Prepare the following plots:

Asphalt Content versus density (or unit weight)

Asphalt content versus Marshall stability

Asphalt content versus air voids (or VTM)

Asphalt content versus VMA

Asphalt content versus VFA

Page 53: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Step F: Tabulating and Plotting Test

Results

F-3:

Review the plots for the following trends:

Stability versus asphalt content can follow two trends:

(a)Stability increases with increasing asphalt content, reaches a peak and

then decreases

(b)Stability decreases with increasing asphalt content and does not show

a peak. This curve is common for some recycled HMA mixtures

Flow should increase with increasing asphalt content

Density increases with increasing asphalt content, reaches a peak, and then

decreases. Peak density usually occurs at a higher asphalt content than

peak stability

Percent air voids should decrease with increasing asphalt content

Percent VMA decreases with increasing asphalt content, reaches a

minimum and then increases

Percent VFA increases with increasing asphalt content

Page 54: ECG524-Topic 2a-Asphaltic Concrete Pavement Design
Page 55: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

OBC is the mean of bitumen contents that give an optimum value of density, stability

and 4% air voids

Peak curve taken from stability graph

Flow equals to 3mm from the flow graph

Peak curve taken from bulk specific graph

VFB equals to 75% for wearing course and 70% for binder course from the VFB

graph

VIM equals to 4% for wearing course and 5% for binder course from the VIM graph

The individual test values at the mean OBC shall then be read from the plotted smooth

curves and shall comply with the design parameters given in Table 4.3.5

The individual test values at the mean OBC shall then be read from the plotted

smooth curves and shall comply with the design parameters given in Table 4.3.5

Step G: Optimum Binder Content

Determination (JKR)

Page 56: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

1. Determine the binder content which corresponds to the specification’s

median air void content (4 % typically). This is the optimum binder content.

2. Determine the following properties at this optimum binder content by

referring to the plots: Marshall Stability

Flow

VMA and

VFA

3. Compare each of these values against the specification values and if all are

within the specification, then the preceding optimum binder content is

satisfactory. If any of these properties is outside the specification range, the

mixture should be redesigned

Step G: Optimum Binder Content

Determination NAPA Procedure

Page 57: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

1. Determine :(a) Binder content a maximum stability

(b) Binder content at maximum density

(c) Binder content at mid point of specified air void range (4% typically)

2. Average the three asphalt contents selected above.

3. For the binder content, go to the plotted curves and determine the following

properties: Stability

Flow

Air voids

VMA

4. Compare values from Step 3 with criteria for acceptability given in

specifications

Step G: Optimum Binder Content

Determination Asphalt Institute Method

Page 58: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Table 4.3.5 : Test and Analysis Parameters

(JKR/SPJ/2008-S4)

Parameter Wearing

Course

Binder

Course

Stability, S

Flow, F

Stiffness, S/F

Air voids in mix (VIM)

Voids in aggregate filled with bitumen

(VFB)

>8000 N

2.0-4.0 mm

>2000 N/mm

3.0-5.0 %

70-80%

>8000 N

2.0-4.0 mm

>2000 N/mm

3.0-7.0 %

65-75%

Page 59: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Lab Mix – OBC Determination

2.320

2.330

2.340

2.350

2.360

2.370

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Density (

g/c

u.c

m)

800

900

1000

1100

1200

1300

1400

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Sta

bili

ty (

kg)

2.0

3.0

4.0

5.0

6.0

7.0

8.0

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

VTM

(%

)

55.0

60.0

65.0

70.0

75.0

80.0

85.0

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

VF

B (

%)

c

a

d

b

Page 60: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

OBC =(a + b + c + d)/4 = e

Check parameters @ OBC

3.00

3.50

4.00

4.50

5.00

5.50

6.00

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Flo

w (

mm

)

100

150

200

250

300

350

400

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Stiffn

ess (

kg/m

m)

Lab Mix – OBC Determination

Page 61: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Lab Mix – Value @ OBC

2.320

2.330

2.340

2.350

2.360

2.370

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Density (

g/c

u.c

m)

800

900

1000

1100

1200

1300

1400

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Sta

bili

ty (

kg)

2.0

3.0

4.0

5.0

6.0

7.0

8.0

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

VTM

(%

)

55.0

60.0

65.0

70.0

75.0

80.0

85.0

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

VF

B (

%)

e e

e e

Page 62: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Lab Mix – Value @ OBC

3.00

3.50

4.00

4.50

5.00

5.50

6.00

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Flo

w (

mm

)

100

150

200

250

300

350

400

4.0 4.5 5.0 5.5 6.0 6.5 7.0

Bit. Content (%)

Stiffn

ess (

kg/m

m)

Compare parameters with JKR/SPJ/2008-S4 Specifications

Pass? @ OBC = e

If FAIL, then redesign

e e

Page 63: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Why are the Marshall criteria important?

Voids in the Mineral Aggregate (VMA)

VMA is the total volume of voids within the mass of the compacted aggregate.

This total amount of voids significantly affects the performance of mixture

If the VMA is too small, the mix may suffer durability problems, and if the VMA is

too large, the mix may show stability problems and be uneconomical to produce

VMA components divided into two : volume of voids filled with binder and volume

of voids remaining after compaction available for thermal expansion of the binder

during hot weather

The binder volume and aggregate gradation determines the thickness of binder

film around each aggregate particle

Without adequate film thickness, binder will oxidized faster, water easily penetrate

and tensile strength of mixture is adversely affected

The VMA of a mix must be sufficiently high to ensure there is room for binder plus

required air voids

Page 64: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Why are the Marshall criteria important?

Voids in Total Mix (VTM)

Suggested to range between 3 – 5 percent

However, air void content is for lab compacted samples and should not be

confused with field compacted samples

Void content must be approached during construction through the

application of compactive effort and not by adding binder to fill up the voids

High shear resistance must be developed in the HMA layers if adequate

performance is to be achieved

This high resistance must be present to prevent additional compaction

under traffic which could result in rutting in the wheel paths or flushing and

bleeding of the binder at the surface

Low air void contents minimize the aging of the binder films within the

aggregate mass and also minimize the possibility that water can get into

the mix, penetrate the thin binder film

The in-place air void content should initially be slightly higher than 3 to 5

percent to allow for some additional compaction

Page 65: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Why are the Marshall criteria important?

Density

The magnitude of the density achieved during compaction in the laboratory is

not so important. What is important is how close the density achieved in the

laboratory is to the density achieved in the field after several years of traffic

Density can be achieved by increasing compaction, increased binder content,

increased filler content or any method that reduces voids

Void content must be approached during construction through the application of

compactive effort and not by adding binder to fill up the voids

Density varies with binder content. Density increases as binder content

increases because the hot binder lubricates the particles allowing the

compactive effort to force them closer together.

The density reaches a peak and then begins to decrease because additional

binder produces thicker films around the individual aggregates, thereby pushing

the aggregate particles further apart and resulting in lower density

Page 66: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Why are the Marshall criteria important?

Stability

Marshall stability is defined as the maximum load carried by a compacted

specimen tested at 60oC

Generally a measure of the mass viscosity of the aggregate-binder mixture and

is affected significantly by the angle of internal friction of the aggregate and the

viscosity of the binder at 60oC

One of the easiest way to increase stability of aggregate mixture is to change to

higher viscosity grade of binder, also by selecting a more angular aggregate

Anything that increases the viscosity of binder increases Marshall stability

Marshall stability and field stability are not necessarily related. Stability in the

field is affected by the ambient temperature, types of loading, tyre contact

pressure and numerous mixture properties.

Primary use of stability is to aid selection of OBC and also useful in measuring

the consistency of a plant produced HMA

Page 67: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Why are the Marshall criteria important?

Flow

Flow is measured at the same time as the Marshall stability

Flow is equal to vertical deformation of the sample (measured from start

of loading to the point at which stability begins to decrease)

High flow values generally indicate a plastic mix that will experience

permanent deformation under traffic, whereas low flow value may indicate

a mix with higher than normal voids and insufficient asphalt for durability

and one that may experience premature cracking due to mixture

brittleness during the life of the pavement

Page 68: ECG524-Topic 2a-Asphaltic Concrete Pavement Design

Questions?


Recommended