    Effective Qualification of Critical Utilities 

    Presented By Miguel Montalvo,President, Expert Validation Consulting, Inc.

    IVT Validation and cGMP Compliance Forum – San Juan, P.R.

    July 12th – 14th, 2011

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    2/148

     April 23, 2013 2

    FDA 21st Century Initiative –Effects on Facility and Utilities

    Qualifications

    !  Aseptic Processing Concept Paper from 2002 – Basis for 2004Final Guidance"  Goal – !build quality into products using science-based

    facility, equipment and systems design.”

     "  Ensure reliable and robust product protection through

    adequate design and control.” "  Advantages of Automation and Isolation Concepts - Innovation"  Consistent with Agency efforts to harmonize with international

    regulatory standards (ISO-14644 Classifications)!

      Agency intent to integrate quality systems and risk management  approaches into existing programs with the goal of encouragingthe adoption of modern and innovative manufacturingtechnologies

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    3/148

    3

    ICH-Q7A - cGMPs for APIManufacturing

    !  HVAC Systems – These systemsshould be designed andconstructed to minimize risks ofcontamination and cross-

    contamination”

     !  Qualification of Critical Equipment

    and Ancillary Systems

    "  Design Qualification

    "  Installation Qualification

    "  Operational Qualification

    "  Performance Qualification

    !  Periodical Review of ValidatedSystems

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    4/148

     April 23, 2013 4

    Quality Systems Approach toPharmaceutical GMP

     

    s –

    Guidance from FDA (9/29/06)!  The guidance describes a comprehensive quality systems (QS) model, 

    highlighting the model's consistency with the CGMP regulatoryrequirements for manufacturing human and veterinary drugs, includingbiological drug products. The guidance also explains how

    manufacturers implementing such quality systems can be in fullcompliance with parts 210 and 211.

     

    !  Implementation of Quality Systems, when coupled with manufacturingprocess and product knowledge, can handle changes without a needfor regulatory submissions - changes in facility, equipment or evenprocesses

    !  Change Control – managing change to prevent unintended

    consequences

    !  According to CGMP regulations, the QCU has the responsibility ofreviewing and approving all initial design criteria and procedurespertaining to facilities and equipment and any subsequent changes(see 211.22(c))!” 

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    5/148

     April 23, 2013 5

    Quality Systems Approach toPharmaceutical GMP

     

    s –

    Guidance from FDA (9/06)

    !  Quality by Design Concept:"  Quality by design means designing and developing

    manufacturing processes during the product development stage

    to consistently ensure a predefined quality at the end of themanufacturing process. A quality system provides a soundframework for the transfer of process knowledge fromdevelopment to the commercial manufacturing processes andfor post-development changes and optimization

     

    "  Quality should be built into the product, and testing alonecannot be relied on to ensure product quality.

     

    "   A quality system can provide the necessary framework forimplementing quality by design (building in quality from thedevelopment phase and throughout a product 

     

    s life-cycle),continuous improvement, and risk management in the drugmanufacturing process. This concept is being developed underthe ICH Q8 Pharmaceutical Development Expert Working

    Group.”

     

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    6/148

     April 23, 2013 6

    Effects on Equipment/SystemsQualifications – Quality Systems

    Approach

    !  Design Qualification/Review

    !  Purchasing Controls

    "  Vendor/Contractor Selection is Key” to an Effective

    Qualification/Project Implementation

    !  Monitoring and Control – Master Project Plan"  It is the responsibility of the designer, construction manager

    and plant engineer in charge of the project that all agreed

    upon”

     design requirements are met during:!  During Construction

    !  Start-Up and Commissioning

    "  Qualification and Routine Monitoring

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    7/1487

    ISPE Efforts and Impact

    Baseline Engineering Guides – Volume #5

    Enhanced DesignReview Concepts

    !  Structured DesignReview

    "  System Impact and

    Components CriticalityLevels and Applications

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    8/148 April 23, 2013 8

    Scope of the ISPECommissioning

    and Qualification Guide

    Design

    Development

    Engineering Change Management

    Enhanced DesignReview

    Scope of Guide

    ProcessValidation

    IQ & OQ

    commissioning PQ

    Design for Impact

    Impact Assessment

    QA Change Control

    GEP Contribution

    Of Interest to the Regulatory

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    9/148 April 23, 2013 9

    ISPE – Impact Concepts andApplication

    !  FDA cooperation with development of these concepts for new manufacturingfacilities and modifications to existing. It does not mean acceptance by FDA.Guidelines still prevail – Process Validation Guideline from 1987 whichincludes qualification requirements.

    !  Scope – Facilities, Utilities, Equipment!  Key Concepts:

    "  Direct Impact Systems – impact on product quality

    Qualification required

    "  Indirect Impact Systems – not expected to have an impact on productquality

    Commissioning may be enough (Enhanced Commissioningdocumentation)

    "  No Impact Systems

    !  Basis – GEP application, Enhanced Design and Review and Commissioning

    !  System Impact Assessment is key (Risk) – rationales for decision are fully

    understood, documented and endorsed by QA function

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    10/14810

    Validation Life Cycle

    Design

    Verify

    Do

    Act

    Plan

    Qualification

    Continued System Verification

    Discontinuation

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    11/148

    Life-Cycle Phases

    Design

    "  User Requirements

    "  FunctionalRequirements

    "  Detailed Design

    Qualification

    Continued SystemVerification

    "  Monitoring

    "  Change Control

    "  Deviations/OOS

    "  Maintenance

    11

    Risk Management is appliedat every phase

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    12/14812

    Plan for Compliance

    !  Application of GEP s during the Design and Construction Phases

    !  Audits of vendors and suppliers"  Proactive Review of Turn-Over Packages/Forms

    !  Master Project Plan to include"  Basis of Design – Process/Product

    "  User/Functional Specifications

    "  Definition of Responsibilities

    "  Scope of Installation

    "  Cost/time considerations

    "  Quality Plan to Include:

    !  Design Review with pre-determined

    acceptance criteria

    !  FAT/SAT Requirements

    !  Start-Up and Commissioning

    !  Qualification Requirements

    (may be in parallel to VMP)

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    13/148 April 23, 2013 13

    Master Project Plan

    !  Applicable to New Facilities or Major Modifications/Projects

    !  Project is awarded:

    "  You may have User Requirements and FunctionalRequirements Specifications

    "  You may even have a Conceptual Designdocument

    !  Master Project Plan includes Quality Plan with

    Design Review and Change Control processes

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    14/148

    Project Phases

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    15/148 April 23, 2013 15

    Process Support Systems orUtilities Requirements – Direct

    Impact vs. Indirect Impact

    !  Direct Impact—raw material,product contact or directimpact on product quality

    "  Water For Injection

    "  HVAC System for CleanArea

    "  Clean Steam

    "  Clean Compressed Air

    !  IQ, OQ, and PQ required

    !  Indirect Impact—noproduct contact but mayhave indirect effect on

    product quality"  Vessel jacket heating/

    cooling

    "  Potable water forwashing/cleaning –not final rinse

    "  Vacuum for drying/coating

    !  IQ and OQ required

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    16/14816

    Approval of Suppliers/Vendors

    !  Approval is granted after all initial approvalrequirements have been met and all

    documentation has been gathered and reviewed!  Purchasing must not be allowed to enter into a

    contract or PO with a supplier/vendor that has notbeen approved – Approved Supplier List (forCritical, Major and Minor class Suppliers)

    !  Quality Agreement or Contract in place beforefirst order is issued for Critical or Major materials/services

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    17/14817

    Quality Agreements/Contracts

    !  Defined Requirements – specifications and otherneeds

    !  Communication – changes

    !  Giver versus Acceptor responsibilities

    !  Testing/standards/regulations to be applied

    !  Requirements for Qualification/Certification and impactof deviations/non-conformances

    "  Number of lots/batches and evaluation process

    !  Documentation

    !  Requirements for Sub-Contracting any step/process

    !  Dispute Resolution

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    18/148

    Quality Agreements/Contracts

    !  In the technical contract, both parties can agree upon a checklist,in which the company contracting the services lays down all therequirements for the supplier. A checklist with an extreme level of

    detail is necessary, and should be an attachment to the technicalcontract. For example, if there is a specific concern for crosscontamination, the list can put special emphasis on air handlingunits, hygienic control, environmental monitoring, etc.

    !  Process knowledge is also critical. Manufacturers must

    characterize all processes, monitor process variables (in real-time if possible), and anticipate how product and process willbehave in this multivariate environment

    18

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    19/148

    19

    Traceability Matrix Model

    User RequirementsSpec

    DesignSpecs

    System Build

    Installation Qualification

    Functional Specs OperationalQualification

    PerformanceQualificationVerifies

    Verifies

    Verifies

    Design Review

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    20/148

     April 23, 2013 20

    Specifications Purpose

    !  User Requirements – Describe clearly and preciselywhat you need the system to do? It must be driven by

    the business process needs.!  Functional Requirements Specifications – How the

    system will achieve the User Requirements in terms offunctionality characteristics?

    !  Design Specifications – What are the specific (detailed)

    attributes/characteristics for the system to be able tomeet the functions and user requirements?

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    21/148

     April 23, 2013 21

    Traceability Matrix Application/Relation to Design Qual./Review

    !  User Requirements Specifications – basis for theFunctional Requirements Specifications – basis

    for the Design Specifications and Drawings

    !  Design Qual./Review verifies the flow from one setof specifications to the next has been effective/complete and that all criteria/requirements are

    met by the design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    22/148

     April 23, 2013 22

    Design of a Process SupportSystem or Utility – Plan for

    Compliance

    !  Clear Design Specifications: User Requirements andFunctional Requirements

    Process Requirements – determine what are therequirements for your specific application (asepticconditions vs terminally sterilized products)

    !  Risk analysis.

    !  Facility Location – environment conditions and seasonal

    changes. Evaluate facility location in terms oftemperature/humidity worst case conditions

    !  Feed (if applicable)

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    23/148

     April 23, 2013 23

    Design of a Process SupportSystem or Utility – Plan for

    Compliance (Cont.)

    !  Initial Cost vs. Maintenance Costs – evaluate the options in terms oforiginal investment vs. maintenance costs.

    Other aspects to be considered – reliability, future growth/flexibility!  Average and Upper (peak) demand for utilities and environmental

    conditions

    !  Critical Parameters – set-points, alert and action limits

    !  Methods of Measurement, control, monitoring and documentation ofparameters

    !  Automation Control Costs – how much automation is desiredcompared to operating and initial cost

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    24/148

    24

    Process Requirements andConsiderations

    !  Potential for Contamination"

     

    Feed, Make-up air

    "  Equipment/Personnel

    "  Materials/Components

    "  Room Finishes

    Other Products!  Effects of exposure to extreme

    conditions - temperature,humidity

    !  Filtration requirements

    !  Safety Considerations

    !  Product requirements – sterile,

    particulate levels/classifications

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    25/148

     April 23, 2013 25

    Design Qualification/ReviewApplication

    !  New Facilities or Major Modifications to ExistingFacilities

    "  Direct Impact Systems – primary focus

    "  Indirect Impact – may select systems based on levelof impact

    "  Typical Direct Impact Systems – HVAC for ClassifiedEnvironments, Purified Water, Manufacturing

    Equipment/Systems

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    26/148

    What is Design Review?Is it the same as DesignQualification or Enhanced

    Design Review”

    ?

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    27/148

     April 23, 2013 27

    ISPE Baseline EngineeringGuide #5 – Section 7 on EDR

    !  Enhanced Design Review (EDR) – “a documented review of the

    design, at an appropriate stage in the project, for conformance to

    operational and regulatory expectations.” 

    “It is in the interests of all to reveal design or specificationproblems through a rigorous , structured and appropriate

    review process early in the project, rather than discover themlater !where a remedy might involve significant delay and

    expense.” 

    "   Avoiding the use of the term DQ

    !  EDR provides audit trail from conception of the project up to thecompletion of the detailed design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    28/148

     April 23, 2013 28

    ISPE Baseline EngineeringGuide #5 – Section 7 on EDR

    !  EDR aims to capture (organize) the design documents witha formal index and a process for their archival

    !  “EDR should be described in the Validation Master Plan

    (VMP) indicating intention, process to be followed,responsibilities of persons involved, and position of EDR

    with reference to GEP and Qualification Practices.” 

    "  Master Project Plan with a Quality Plan Section instead

    of the VMP

    !  Impact and complexity of the design will influence the depth

    of the review process. 

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    29/148

     April 23, 2013 29

    EDR Rationale

    !  To be included in Plan:

    "  What will be reviewed

    "  What method will be used – supporting data

    "  Who will be involved

    "  When?

    "  How will be documented?

    !  Could be in a standard procedure

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    30/148

    Steps in a Design Review

    !  Define scope and objectives of thereview, the methods to be followedand the outputs (SOP)

    !  Who will be involved (SOP)

    !  Identify and evaluate any potentialareas or items of noncompliance(checklist)

    !  Review the design documents anddrawings against the user/functional specifications and otherrequirements identified on thechecklist above

    !  Ensure that designs are modified toeliminate noncompliant features

    !  Prepare a brief report thatsummarizes the design-review process and

    obtain appropriateapprovals, includingquality assurance.

     April 23, 2013 30

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    31/148

     April 23, 2013 31

    When Should ChangeControl Be Implemented?

    !  Need a policy for Change Control Management which willinclude applications at different points

    !  Define application for new and/or modifications to facilities,utilities, equipment and systems

    !  Formal QA Change Control procedures MUST be implementedupon completion of the Qualification / Validation

    !  Implement change control for all Direct and Indirect Impactsystems – level of detail/depth of impact determination will becommensurate with the impact level of the system/process

    !  Once the system / equipment is identified and specified

    (approved documents), it falls under some level of changecontrol 

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    32/148

     April 23, 2013 32

    Change Control Levels early inProjects – Impact Determinations and

    Application of Risk

    !  Direct Impact Systems – more documentation requiredand a formal risk assessment done for changes

    !  Indirect Impact Systems – basic procedure and form to

    be completed. No need for formal risk assessment aspart of the change impact analysis.

    !  Responsibilities must be defined for each project

    phase!  User functions to be involved – Quality (at a defined

    level)

    R l ti hi b t D i

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    33/148

     April 23, 2013 33

    Relationship between DesignReview and Change ControlManagement during Design

    !  Team for Design Review is normally same teamthat will evaluate changes

    !  Documentation of Design Review will serve to

    document changes and their verification ofimplementation.

    !  The DQ process/meetings will provide theopportunity to complete any Change Control

    documentation required for the changes to DirectImpact and Indirect Impact Systems.

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    34/148

    34

    Construction

    !  Construction shall comply withdesign drawings andspecifications

    !  Changes shall be documented inaccordance to a change controlprocedure (defined in QualityPlan)

    !  Cleaning procedures and criteriafor acceptance of the work must

    be pre-defined!  Security and access procedures

    must be defined

    F t A t

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    35/148

    35

    Factory AcceptanceTesting (FATs)

     

    FATs are standard tests that areexecuted at the factory to verifyproper operations before thesystem leaves the plant. 

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    36/148

    36

    Start-Up and Commissioning

    !  Adequate Installation/Construction Documentation - as per GEP s:

    "  Design Concepts

    "  Design Schematics

    "  As Installed drawings

    "  Instrumentation Calibrations

    "  Test records

    "  Operation and Maintenance Manuals

    "  Statutory inspection Reports

    "  Material Certificates, FATs

    "  Duct Installation and Cleaning documentation

    "  Changes are properly managed

    and documented during construction

    "  Training of personnel

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    37/148

     April 23, 2013 37

    $ $ 

    Design Purchasing 

    Construction

    Installation 

    Start-up 

    Validation 

    V

    Project Phases

    C i i i L d

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    38/148

     April 23, 2013 38

    Commissioning Leadsto IQ/OQ for Indirect and

    Direct Impact Systems"  Documents created and collected during

    Commissioning are incorporated into thevalidation package

    "  During construction, a review of current status

    of installed equipment and walk through canhelp ensure validation criteria are kept on target—avoid unnecessary delays

    "  Start-up/field testing may address the needs of

    IQ/OQ criteria

    Key Question:

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    39/148

     April 23, 2013 39

    Key Question:Is Commissioning going to beconsidered part of Validation

    Effort?!   Yes!

    "  Define Commissioningprocess and documentationin Project/Quality Plan andin Master Validation Planand how they will relate tofurther qualification of

    systems

    !  No

    "  CompleteCommissioning

    "  Will need to repeatsome tests forQualification

    "  Still need to describe

    Commissioningrequirements inPlans

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    40/148

     April 23, 2013 40

    Commissioning as part ofMaster Validation Plan

    !  Advantages:"  Pre-qualification determination if system is reliable/

    operates according to specifications

    "  Avoid redundancy

    !  Requirements:"  Pre-defined/documented test requirements

    "  Training of personnel executing the tests

    "  Adequate documentation practices

    "  Quality review

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    41/148

     April 23, 2013 41

    Equipment Qualification Levels

    !  Historical:

    "  Installation

    Qualification"  Operational

    Qualification

    "  PerformanceQualification

    Suggested – applying Risk Assessment/Analysis:"  Direct Impact System:

    !  Product Failure Hazard Level:

     –  Level I – Sterile/Biological/Critical MedicalDevices!  Installation – more detail

    !  Operational Qualification – basic operational

    functions, controls, alarms, Challenge ParameterRanges and Worst Cases – extremes

     –  Level II – Oral Solid/Liquids!  Installation – adequate detail

    !  Operational Qualification – Basic OperationalFunctions, Controls, Critical Alarms

    "  In-direct Impact System:!  Installation – not detailed

    Basic Operational Functions - only those which couldimpact the product quality

    "  No Impact – Enhanced CommissioningDocumentation

    !  PQ – no change. Only for critical direct

    impact systems.

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    42/148

     April 23, 2013 42

    Questions to be Answered

    !  Which sections of a system need to be qualified?

    !  Which parameters to test and at what level – Does

    an OTC/Cosmetic system/equipment/facilityneeds to test all systems at Worst case” or theextreme parameter limits?

    !  How many runs/tests?

    !  Decisions on criteria - equipment specificationsversus process needs?

    R i t f I t ll ti

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    43/148

     April 23, 2013 43

    Requirements for InstallationQualification – In-direct Impact

    System!  Main Components Verification – critical components only

    "  Base decision on risk assessment

    !  Drawings Verification

    !  Utilities Verification!   Availability of Support Documentation – Manuals, Specifications,

    Design Review Documents, PO’s, Commissioning Documents

    !  Procedures and corresponding training – Operation, Maintenance,Cleaning

    !  Calibrations – critical instruments

    "  based on risk assessment

    !  Hardware/Software Configuration and Set-up Information

    !  Filter Verification (if applicable)

    R i f I ll i

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    44/148

     April 23, 2013 44

    Requirements for InstallationQualification – Direct Impact

    System (Level II – Oral Solid/Liquids)!  Main Components Verification as per design/drawings including controls/

    instrumentation"  Base list of main components on risk assessment

    !  Drawings Verification to be As-Built

    !  Materials of Construction – product contact only!  Lubricant List!  Utilities Verification – Electrical, Water, Compressed Gases

    !  Review Support Documentation – Manuals, Specifications, FAT reports,Design Review Documents, PO

     

    s, Commissioning Documents

    !  Procedures and corresponding training – Operation, Maintenance,

    Cleaning!  Calibrations – critical instruments

    "  Base list of instruments on risk assessment 

    !  Hardware/Software Configuration and Set-up Information!  Input/Output Loop Verification

    !  Filter Verification (if applicable)

    Requirements for Installation

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    45/148

     April 23, 2013 45

    Requirements for InstallationQualification – Direct Impact System

    (Level I – Sterile/Biological/

    Critical Medical Devices)!  Main Components Verification as per design/drawings including controls/

    instrumentation"  Base list of main components on risk assessment

    !  Drawings Verification to be As-Built!  Materials of Construction – product contact only!  Lubricant List and Spare Parts List

    !  Utilities Verification – Electrical, Water, Compressed Gases!  Review Support Documentation – Manuals, Specifications, FAT reports, Design

    Review Documents, PO 

    s, Commissioning Documents!  Procedures and corresponding training – Operation, Maintenance, Cleaning!  Calibrations – critical instruments

    "  Base list of instruments on risk assessment

    !  Hardware/Software Configuration and Set-up Information – applicable procedures

    for back-up, restore

    !  Input/Output Loop Verification!  Construction completion documentation such as:

    "  Piping pressure and leak testing"  Pipe slope verification"  Pipe insulation"  Instrument loop checks

    !  Filter Verification (if applicable)

    R i t f O ti l

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    46/148

     April 23, 2013 46

    Requirements for OperationalQualification – In-direct Impact

    System

    !  Verify the basic Operational Functions - only thosewhich could impact the product quality"  Functional Tests – critical parameters at nominal values

    and verifying only critical responses or characteristics"  Controls Verification"  Motor verification

    "  Sequence Verification (if applicable)

    !  Select the parameters from risk assessment/analysis–select number of tests for each

    !  Select the responses or resulting characteristics to beverified from risk assessment/analysis

    R i t f O ti l

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    47/148

     April 23, 2013 47

    Requirements for OperationalQualification – Direct Impact

    System (Level II – Oral Solid/Liquids)!  Verify the basic Operational Functions including critical

    alarms"  Functional Tests – parameters at operational limits and

    verifying critical responses or characteristics"  Controls Verification"  Motor verification"  Sequence Verification (if applicable)"  Critical Alarms – verification and reporting

    !  Select the parameters to be challenged from risk

    assessment/analysis – select number of tests for each!  Select the responses or resulting characteristics to be

    verified from risk assessment/analysis

    Requirements for Operational

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    48/148

     April 23, 2013 48

    q p

    Qualification – Direct Impact System (Level I – Sterile/Biological/

    Critical Medical Devices)

    !  Verify the operational functions and critical alarms.Challenge Parameter Ranges and Worst Cases – extremes

    "  Functional Tests – parameters at operational extreme limits and

    verifying critical responses or characteristics"  Controls Verification – more detailed

    "  Motor verification

    "  Sequence Verification (if applicable)

    "  Critical Alarms – verification and reporting

    !  Select the parameters to be challenged from riskassessment/analysis – select number of tests for each

    !  Select the responses or resulting characteristics to beverified from risk assessment/analysis

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    49/148

     April 23, 2013 49

    Additional Areas to be coveredduring the qualification

    !  Process Parameters vs. Equipment Design -Verify that the equipment is capable ofoperating at the desired process parametersindependently of the equipment design

    !  Flexibility, Reliability, Future Growth

    H d i lifi i

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    50/148

     April 23, 2013 50

    How to determine qualificationrequirements - Steps

    !  Procedure/Policy to describe the evaluation processand documentation requirements

    !  Impact Assessment – ISPE Baseline Engineering Guide

    Volume #5 Commissioning and Qualification concepts!  Hazard Level determination for Direct Impact systems

    !  Risk Assessment on system parameters andspecifications

    !  Protocol development including results from Risk

    Assessment and rationale for decisions

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    51/148

     April 23, 2013 51

    Protocol Requirements –General Outline

    !  Approvals

    !  Objective/Purpose

    !  Scope/Boundaries

    !  System Description

    "  Overview

    "  Basis of Design

    "  Flow Diagrams

    !  Qualification Approach:policies, procedures,references

    !  Responsibilities

    !  Pre-Requisites

    !  Definitions

    !  Test requirements

    "  Record of Signatures

    "  Test Instruments –Calibrations

    "  Qual. Tests

    !  Acceptance Criteria

    !  Documentation/ Handlingof deviations or exceptions

    !  Attachments

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    52/148

     April 23, 2013 52

    Integrated PLC Qualification

    !  Qualification should encompass all aspectsthat could affect the operation of a system

    "  Program code

    "  Wiring

    "  Labeling

    "  Instrument enclosures

    "  Transmitters

    "  Recorders

    "  Monitors

    "  Final control elements

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    53/148

     April 23, 2013 53

    PLC IQ/OQ

    !  Review of Program Code

    !  Display/Graphics/ControlPanel Verification

    Operator InterfaceChallenges

    !  Review of SoftwareDevelopment proceduresand Test Protocols

    !  Design review of allperipheral equipment

    !  Tests to verify that all wireshave been correctlyterminated

    !  Reports Accuracy

    !  Verification that the systemhas been installed andlabeled in accordance withthe Process and

    Instrumentation drawings!  Review of security features

    !  Fault tree analysis toidentify unwantedoperations activities

    !  Review of all anticipated

    operation activities andmaintenance activities

    !  Control SoftwareBack-up/Recovery Test

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    54/148

     April 23, 2013 54

    BMS, DCS or SCADA(Supervisory Control and Data

    Acquisition)!  Stand-Alone Systems that provide additional tools:

    "  Recipe Manager (Specification, Stages, Alarms limits)"  Reporting Tools" 

    Screen Builders"  Software Package Design Constraints"  Data usually acquired without operator action"  Data available for later retrieval, reporting, analysis, and

    archiving"  Communication with the PLC"

      Program timing

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    55/148

     April 23, 2013 55

    BMS, DCS and SCADA

    Validation Issues!  Field Device Calibration

    !  Field Device Maintenance

    !  Cabling Changes!  PLC Maintenance (HW&SW)

    !  Software and Hardware Upgrades

    Legacy Systems Key

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    56/148

     April 23, 2013 56

    Legacy Systems – KeyQuestions

    !  How much documentation is available fromoriginal purchase/design/installation?

    !  Change Control System – How good is it?

    Have changes to the system beendocumented and tested properly?

    !  How critical is my system to the operation?

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    57/148

     April 23, 2013 57

    Legacy Systems - IQ

    !  Documentation Available:"  Similar to new equipment in

    terms of Specifications,drawings, manuals, PO

     

    s.

    "  Verify history of changes

    "  Inspect/Verify calibrations,utilities installations, majorcomponents, materials ofconstruction

    "  Required SOP s and training

    "  Software/Hardwareinstallation, configuration

    !  Documentation not available:"

     

    Need to create specifications forsystem as installed.

    "  Verify drawings are created and/or up-to-date.

    "  Create/review operational andmaintenance procedures.

    Document history of equipmentoper. and maintenance. Verifytraining on those procedures.

    "  Inspect/Verify calibrations,utilities installations, major

    components, materials ofconstruction

    "  Software/Hardware installation,configuration

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    58/148

     April 23, 2013 58

    Legacy Systems - OQ

    !  Parameter Ranges – in the absence ofspecifications, use actual operationalparameters

    !  Testing to be done similar to new system.

    !  Retrospective is not a concept for

    equipment qualification. Limitations andrisks are much higher for trying to defendthis position(History, Quality of Operationaland Maintenance Documentation, ChangeControl)

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    59/148

    59

    Performance Qualification(PQ) – Direct Impact Systems

    !  Test quality at use points fora pre-determined period

    !  Criteria as per specifications

    !  Verify/document operational

    data during the test period

    !  Operational and PM SOP sare effective and followed

    Qualification Summary

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    60/148

    60

    Qualification SummaryReports - Outline

    !  Approvals

    !  Objective

    !  Data Summary

    !  Analysis of Deviations orExceptions

    "  Cause

    "  Effect on Study

    "  Conclusion

    "  Approval By QualityFunction

    !  Conclusions

    Facilities

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    61/148

    61

    FacilitiesRequirements – New

    !  Electrical supply system

    !  Terminations—walls,ceilings, floors, drains

    !  Access controls!  Pest controls

    !  Usually handled through afacilities protocol

    Design of an HVAC System

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    62/148

     April 23, 2013 62

    Design of an HVAC System –Plan for Compliance

    !  Clear Design Specifications:"  User Requirements"  Functional Requirements

    !  Process Requirements – determine what are the

    requirements for your specific application:"  Potential for Contamination: Make-up air, Equipment/Personnel,

    Materials/Components, Room Finishes, Other Products

    "  Effects of exposure to extreme conditions - temperature,humidity

    "  Filtration requirements

    "  Safety Considerations

    "  Product requirements – sterile, particulate levels/classifications

    Design of an HVAC System

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    63/148

     April 23, 2013 63

    Design of an HVAC System –Plan for Compliance

    !  Facility Location – Evaluate in terms oftemp./humidity worst case conditions

    !  Automation Control Costs – how muchautomation is desired compared to operatingand initial cost

    !  Initial Cost vs. Maintenance Costs – originalinvestment vs. maintenance costs.

    !  Other aspects to be considered – reliability,

    future growth/flexibility!  Average and Upper (peak) demand for

    utilities and environmental conditions

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    64/148

     April 23, 2013 64

    Design Specifications

    !  General Purpose of Areas, Operations to be Carried out,Constraints, Specified Occupancy

    !  Layout and configuration of the installation

    !  Required Air Quality for each area!  Critical Parameters – set-points, alert and action limits. Worst case

    conditions

    !  Contamination Control Concept for each area/room/zone

    !  Controls/Instrumentation/Automation – Failure protection devices,

    alarms for critical parameters, BMS, documentation of parameterdata

    !  Dust Collection Systems (if applicable)

    !  Material/Equipment/Personnel Flow to minimize possibilities ofcontamination

    Premises for Classified/

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    65/148

     April 23, 2013 65

    Premises for Classified/Clean Rooms

    !  Surfaces must be smooth,impervious and unbroken inorder to minimize theshedding or accumulation of

    particles or microorganismsand to permit the repeatedapplication of cleaningagents!No uncleanablerecesses

     – EU Annex 1

    !  Sealed false ceilings

    Walls/ceiling/floorterminations – seamless androunded corners

    !  Utilities installations – norecesses, unsealed openings anddifficult to clean surfaces

    !  Pressure differential – warningsystem

    !  Changing rooms with physicalbarrier between class levels

    !  Air locks with interlocks

    !  Layout of equipment – considerergonomics and personnelcomfort and ease of movement

    !  Flow of personnel – limit entries

    and exits and the amount ofpersonnel

    !  Limit the activities/interventionsinto the aseptic processing area

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    66/148

    66

    Decisions on Parameters

    Parameter Suggested Values/Limits from Reg.Guidelines

    Industry Suggestions(PDA, Others)

    Air Velocity –HEPA Filters

    90ft/min is no longer required. It is suggested. FDAstatement is at a velocity sufficient to sweep particlesaway from the filling/closing area and maintain

    unidirectional airflow during operations.”

     EU stillincludes a range at working level of 0.36-0.54 m/s as a

    guidance value”

    .

    No limit established - Optimumair velocity is highly dependenton the configuration of the HVAC

    system and the productionfacilities.

    Air ExchangeRates

    FDA - 20 Room Air Changes for Class D (ISO #8) zoneswould be typically acceptable.

     EU has no suggestions.No specific number. Standardpractice NLT 50 for Class A/B(ISO 5/6) and 20 for Class D (ISO

    8)

    Pressure

    Differentials

    FDA - at least 12.5 Pa (0.05 inches water gauge) should

    be maintained between classified and un-classifiedareas and between the aseptic processing room and

    adjacent rooms.

    EU - guidance values”

     of 10-15 Pa between areas ofdifferent classifications

    PDA - Pressure Differentials

    between 0.03-0.05 inches ofwater are effective.

    Temperature andRH%requirements

    FDA and EU – no suggestions (comfort)

    Additional Tests to be Included

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    67/148

     April 23, 2013 67

    Additional Tests to be Includedin Commissioning

    !  Static tests – installation of systemcomponents

    !  Dynamic tests – verification of fan

    volumes, checking heating/cooling coilperformance

    !  System Balance and Testing

    "  Including room pressure/air flowverifications

    "  Room Air Changes Calculations

    !  HEPA filter certification tests

    Q lifi i R i

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    68/148

     April 23, 2013 68

    Qualification Requirementsfor an HVAC System

    !  Installation, Operational and PerformanceQualification of the HVAC System including IntegratedControl Systems (such as PLC

     

    s)

    !  Separate protocols for Stand-Alone Systems such as a

    BMS or other supervisory control systems

    !  Basic Documents – protocol, report for each segmentor combined if appropriate (IQ and OQ into one IOQ

    protocol)

    R i t f I t ll ti

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    69/148

     April 23, 2013 69

    Requirements for InstallationQualification of the System

    !  Main Components Verification as per design/drawingsincluding controls/instrumentation

    !  Drawings Verification to be As-Built

    Materials of Construction!  Utilities Verification – Electrical, Chilled Water, Steam/Hot

    Water

    !  Review Support Documentation – Manuals, specifications,FAT reports, Design Review/Qual. Documents, PO

     

    s, DuctCleaning Documents, Commissioning Documents

    !  Procedures and corresponding training – Operation,

    Maintenance, Cleaning

    !  Calibrations

    !  Filter Verification 

    Requirements for Operational

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    70/148

     April 23, 2013 70

    Requirements for OperationalQualification of the System

    !  Controls/Alarms Verification

    !  Sequence of Operation

    !  Interlocks testing

    !  Reports

    !  System Security/Data Retrieval

    !  Temperature/Humidity Control Verification – minimum offive days for continuous monitoring. Longer for frequentchecks during the day.

    !  Power Loss and Recovery Testing!  Sterile Operations – Air velocity, Pressure Differentials, Air

    Flow/Laminar Flow Verification as per design. PressureDifferentials for five days if continuous or longer forfrequent checks during the day.

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    71/148

    71

    Performance Qualification

    !  System operating under normalconditions (SOP

     

    s are effectiveand monitoring is in place) Thisincludes cleaning andsanitization procedures.

    !  Particulate Counts – three timesper location (twice per shift –

    beginning and end of operation)during a week period for eachcondition

    !  Viable Counts – air, surface.Three results in a week for eachcondition. Aseptic areas require

    testing per shift.!  Static vs. Dynamic Conditions

    !  Challenge is for EnvironmentalControl System – not only theHVAC

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    72/148

    Water System Design andSpecifications

    72

    Guide to Inspections of High

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    73/148

    PurityWater Systems, FDA 1993

    !  System Design"  Application based – type of product. UF as an option for Biotech WFI

    "  Loop Temperature (70-80ºC) versus sanitization – cost vs risk

    "  Quality level – risk. Reliability of the system.

    !  Microbial Limits – sample of 100ml minimum for WFI

    "  Specific contaminant versus counts

    "  Biofilm

    !  Water for Injection Systems

    "  Pretreatment – monitoring of feed water

    "  Still, Heat Exchangers, Holding Tanks(Vent Filters), Pumps, Piping(Steel vs PVDF), Reverse Osmosis

    "  Proper Operation and Maintenance

    Guide to Inspections of High

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    74/148

    PurityWater Systems, FDA 1993

    !  Purified Water Systems

    !  Process Water

    Inspection Strategy"  Data review – micro

    !  Investigation reports and actions

    "  Maintenance records

    "  System Drawing

    "  System Validation

    !  Description, Specifications, Documentation, Drawings

    !  Procedures – operation, cleaning, flushing, sanitization, sampling/testing

    74

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    75/148

    Variety of PharmaceuticalProducts

    !  Potable Water: Manufacture of substances and initialcleaning of equipment

    !  Purified Water: For use onsite in manufacture ofingredients of official preparations; not for parenterals

    !  WFI: For use onsite in manufacture of parenterals

    !  Internal Specification and Quality Requirements for

    specific needs

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    76/148

    What else does FDA expect?

    !  Feed water must meet EPA Drinking Water Standards

    "  May use WHO standards for international

    applications

    !  Microbial expectationsPurified Water NMT 100 cfu/ 100 mLWFI NMT 10 cfu/100 mL

    Sample size

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    77/148

    Industry References

    !  ISPE Baseline Engineering Guide – Volume 4

    !  PDA Technical Reports and additional references

    ASTM Standards!  ASME Standards – Bioprocessing Equipment

    !  Books:

    "  Pharmaceutical Water: System Design, Operation

    and Validation”

     by William V. Collentro"  Pharmaceutical Water Systems” by Theodore A.

    Meltzer

    77

    ISPE Baseline Engineering

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    78/148

    ISPE Baseline EngineeringGuide – Volume 4 Water and

    Steam Systems

    !  Pre-Treatment Options

    !  Final Treatment Options

    !  Instrumentation

    !  Storage/Distribution

    !  Qualification/Validation

    !  Appendix

    78

    F d Ch t i ti

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    79/148

    Feed Characterization

    !  Ground Water vs

    Surface Water!  Chemical and

    MicrobiologicalLoads

    !  Seasonal Variations!  Volume and effects

    of peak usage

    Zero In On User Requirements

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    80/148

    Zero In On User Requirements – System Planning

    !  Multi-DisciplinaryTeam Approach

    Define User Needs:"  Water Quality

    "  Use PointsRequirements

    "  System Criteria

    Water System Design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    81/148

    Water System Design

    !  Water Quality Specifications - related to the typeof product to be manufactured

    !  Clear Design Specifications: User Requirementsand Functional Requirements

    !  Water Source Quality and Characteristics

    "  Private Well, Public Well or City Potable Water

    "  Seasonal variations

    "  Location of Well (if applicable)

    !  Quality and Performance Criteria for each

    component of the system including capacity

    Water System Design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    82/148

    Water System Design

    !  System Operational and Maintenance Costs - SanitizationFrequencies, Cleaning, Filter Replacement among others

    !  Facility Location – environment conditions and seasonal changes

    !  Evaluate facility location in terms of temperature/humidity worstcase conditions

    !  Industry Common Practices and Regulatory Input

    !  Recirculation Loop – Hot or Cold

    "  Hot loop reduces sanitization requirements – beware of heat

    exchangers

    "  Sanitization for cold loops – daily?

    Water System Design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    83/148

    !  Initial Cost vs. Maintenance Costs – evaluate the options in termsof original investment vs. maintenance costs

    !  Other aspects to be considered – reliability, future growth/

    flexibility!  Average and Upper (peak) demand for utilities and environmental

    conditions

    !  Critical Parameters – set-points, alert and action limits

    !  Methods of Measurement, control, monitoring and documentation

    of parameters

    !  Automation Control Costs – how much automation is desiredcompared to operating and initial cost

    Water System Design

    Additional Requirements and

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    84/148

    Additional Requirements andConsiderations

    !  Potential for Contamination

    !  Remove higher level ofcontamination first

    Keep residual chlorine in as long aspossible – how to eliminate whennecessary

    "  Carbon filtration versus sodiumsulfite injection or UV

    !  Dead legs and slope to drain

    !  Keep distribution system simple

    !  Filtration requirements

    !  Safety Considerations

    W t S t

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    85/148

    Water Systems 

    !  Entire water systems needs to be considered

    "  Source (Feed) Water

    "  Production method – How much water will be used?

    "  Sampling and Testing – data to be collected

    "  SOPs

    "  Pre-treatment steps designed based on actual feed

    water evaluation!  Softener and carbon filter location will depend on

    organic content of incoming water

    W t S t D i

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    86/148

    Water System Design

    !  Pre-Treatment

    "  Multimedia Filter

    "  Softener

    "  Carbon Filter

    "  Cartridge Filters

    "  DI Columns

    "  RO Units

    "  UV Lamps

    !  Storage and Distribution

    !  Instrumentation

    "  TOC – On-Line

    "  Resistivity/Conductivity Meters

    "  pH

    Pre-Treatment

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    87/148

    Specifications

    !  Required quantity and quality of treated water for thefinal treatment process

    !  Temperature and microbial control approach

    !  Considerations for added substances” – chlorine,sulfite, acid

    !  Final treatment selected – cost vs risk of failure

    Quality of the feed water – need to consider spikes andseasonal variation (worst cases)

    !  Operational, maintenance, safety, validation, location/space, environmental and other requirements

    Impact on Final Treatment

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    88/148

    pCaused by Impurities

    Fouling -particulates

    Scaling –hardness andminerals

    Corrosion -chlorides

    Degradation -chlorines

    RO Large Large None Large - Membranedependent

    Other MembraneProcess

    Large - Moderate Large - Moderate None Large - Membranedependent

    Single Effect Still Moderate Moderate Moderate-Large Large

    Multi-Effect Still Large - Moderate Large - Moderate Moderate-Large Large

    VaporCompression Still

    Moderate Moderate Small Large

    88

    Micro Control in

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    89/148

    Pre-Treatment

    !  Micro Control Agent

    !  Periodic sanitization (heat or chemical)

    UV Lights!  Avoiding dead legs and stagnation

    !  Removal of control agent:

    "  Chlorine – simple (Carbon)

    "  Chloramines – much more complex (requiresseveral steps). Typically, RO is recommended beforeStill with pH controls/adjustments and sulfiteinjection to assure removal of chloramines and CO2 

    Final Treatment

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    90/148

    Final Treatment

    "  Significant shift from Ion Exchange basedsystems to membrane based systems forPW production (90% systems are RO basedtoday) due to costs, ease of operation/maintenance and quality of end product

    90

    P-8

    Standard Conventional Purified Water System Design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    91/148

    Multi-Media

    Softener 

    Carbon

    RO CDI/EDIP-7

    Storage Tank

    PumpHeat Exchanger 

    Typical Options for Purified

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    92/148

    Typical Options for PurifiedWater

    !  System A – Pre-treatment followed by off-site regenerated IX (ionexchange) – separate beds or mixed beds(Cations and Anions) orother configurations

    "  Feed Water analysis is key – focus on meeting Conductivity/TOC levels

    "  On-site handling of bulk regeneration chemicals – not desired

    !  System B – Pre-treatment followed by RO (single or double pass)and off-site regenerated IX for ionic polishing

    "  RO means more pre-treatment

    !  System C – Similar to B with CEDI replacing IX (no chemical

    regeneration)

    !  System D – pretreatment followed by distillation (meets WFI)

    "  Higher capital versus less downtime and maintenance (reliability)

    !  Sanitization considerations (heat resistance) or additional steps –UV or microbial filtration

    92

    System C

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    93/148

    System C

    93

    Recommended “HP" Purified Water System

    Design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    94/148

    Multi Media Carbon Softener  

    RO

    Storage Tank

    Pump

    Virgin Ion Exchange

    Mixed Beds

    Final filter TOC

    UV

    g

    Nitrogen Blanket

    R

    R

    F

    Totalizing Flow Meter 

    WFI – Purified Water as a

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    95/148

    feed to Still

    !  Pre- treament for Still is critical

    !  Will ease the operation/maintenance

    !  Reduce the possibility of contaminations andendotoxins in the product WFI

    !  Typical high volume systems will have RO as partof pre-treatment for Still

    95

    Still Design

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    96/148

    Still Design

    !  Volume and temperature driven

    !  Instrumentation and controls

    !  Materials of construction

    !  Vendor selection

    96

    Single Effect Multi-Effect VC

    Capacity Range(GPH) 1-100 25-3000 100-6000

    WFI Temperature

    Range (ºC)

    80-100 37-100 - Ambient

    - 80-100

    - Combination (hot/

    cold loops)

    Design Table – Technology

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    97/148

    Options for ME Still

    97

    For VC, RO or UF as Steps 5 and 6 is optional.

    Key Factors for Storage

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    98/148

    and Distribution

    !  Designed tomaintain waterquality and

    deliver to usepoints attemperature andflow required

    !  Capacity!  Continuous flow/

    movement

    !  Minimize Cost

    98

    Materials of Construction

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    99/148

    !  Non compendial:

    "  Polyvinyl Chloride (PVC)

    Polypropylene (PP)"  Polyvinyldene flouride (PVDF)

    !  Compendial water

    "  316 stainless is preferred but PVDF is an option

    !  Sanitary Fitting

    !  Consistent diameter where possible

    !  Orbital welding is preferred

    Other Considerations

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    100/148

    Other Considerations

    Points of Use Design – application ofZero Dead Leg

     Sanitary Valves

    !  Sloped to drain

    Maintained at positive pressure -constant

    !  Circulating Loop at 3 ft/second

    Microbial Controls

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    101/148

    Microbial Controls

    !  Ozone – periodically or continuously and UV toremove it

    !  Temperature Controls

    !  UV Lights for Microbial control – beware of issuesregarding UV such as cleaning/maintenance,intensity monitoring, flow vs contact time andtypical flora/bacteria present

    !  Filtration on Distribution System – microfiltrationor ultrafiltration

    101

    Qualification Pre-Requisites

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    102/148

    Qualification Pre-Requisites

    !  Well defined system and components specifications/functional requirements and drawings

    !  Well defined quality specifications

    !  Well defined sampling/testing procedures

    !  Training of personnel for water sampling/testing

    !  Operational and maintenance procedures (Draft)

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    103/148

    !  Installation Qual. – Pre-Requisites

    "  System description stating design intent

    "  Schematic drawing of the system (P&ID)

    !  Location and number of welds

    !  Relative elevation

    !  Slope of lines

    !  Point(s) of drainage

    "  System specifications

    Performance criteria

    !  Design parameters

    System boundaries

    "  Detailed design drawings

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    104/148

    !  Installation Qual. – Pre-Requisites

    "  Vendor manuals and drawings

    "  Field inspection and test reports

    Cleaning procedures and records

    !  Passivation procedures and records

    !  Weld parameter documentation and inspection reports

    Slope verification

    Verification of absence of dead-legs

    System commissioning test results!

     

    Reported as related to acceptance criteria

    Verification of automated functions

    Verification of temperature controls

    Verification of distribution system velocity

    !  Initial water quality determination

    Installation Qualification

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    105/148

    Documents

    !  System/Components/Equipment Installation Qualification

    "  Incoming components specifications and inspection

    "  Installation verification

    "  Utilities installation

    "  Critical instrumentation calibration

    "  Software Configuration

    "  PM procedures

    "  As installed system drawings

    "  SOPs

    "  Summary report and conclusion

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    106/148

    Qualification Documents

    !  Operational Qualification

    "  Operational Verification

    !  Sequences – System/components cleaning/sanitization/flushing/regeneration proceduresand frequency

    !  Critical parameters – data collection

    "  Procedures may be in draft or operational

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    107/148

    Qualification Documents

    !  Operational Qualification

    "  Sampling points

    !  Source water

    After each critical step in the purification process

    !  Storage tank (temperature profile and water quality)

    Circulation loop (temperature profile only)

    !  At each POU (temperature profile and water quality)

    "  Sampling procedures

    "  Testing requirements

    "  Testing methods

    "  Acceptance criteria

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    108/148

    Qualification Documents

    !  Operational Qualification

    "  Documentation

    "  Summary report and conclusion

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    109/148

    Qualification Documents

    Performance Qualification"  Critical instrumentation calibration

    "  Operational Data Review – System is operating under approved

    SOP 

    s"  Sanitization/Cleaning/Regeneration/Flushing data review

    "  Sampling plan

    "  Sampling points

    Source water initially, then weekly

    !  After each critical step in the purification!

     

    Storage tank (temperature profile and water quality

    Recirculation loop (temperature profile only)

    !  At each POU (temperature profile and water quality)

    Qualification Documents

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    110/148

    Qualification Documents

    !  Performance Qualification

    "  Sampling procedures

    "  Testing requirements

    "  Testing methods

    "  Acceptance criteria

    "  Documentation

    "  Summary report and conclusions

    Sampling Plan

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    111/148

    Sampling Plan

    !  Phase 1 (OQ):

    During the initial phase the operational parameters and cleaning/sanitation procedures and frequencies will be developed.Sampling should be daily after each step in the purification

    process and at each point of use for two to four weeks. Thesampling procedures for point of use should reflect how they aretaken, e.g. use of hose, and time for flushing. At the end of thetwo (2) to four (4) weeks of sampling, the firm should havedeveloped its SOPs for operation and maintenance of the water

    system."  Develop operating ranges

    "  Develop and finalize operating, cleaning, and maintenanceprocedures

    "  Demonstrate production and delivery of in-spec water

    Sampling Program

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    112/148

    Sampling Program

    Phase 2 (PQ – Phase 1):

    The second phase of the water system validation is to

    demonstrate that the system will consistently produce thedesired water quality when operated in conformance withSOPs. The sampling is performed as in the initial phase andfor the same period . At the end of this phase the datashould demonstrate that the system will consistently

    produce the desired quality of water."  Demonstrate consistent operation within established

    ranges

    "  Demonstrate consistent production and delivery ofquality water

    Sampling Program

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    113/148

    Sampling Program

    Phase 3 (PQ – Phase 2):

    The third phase of validation is designed to demonstrate that

    when the water system is operated, in accordance with theSOPs, over a long period of time it will consistently producewater of desired quality. Any variations in quality of thefeedwater, that could affect the operation and ultimately thewater quality, will be noticed during this phase of thevalidation.

    "  Demonstrate extended performance"  Evaluate seasonal variation

    "  For Water for Injection systems samples should be takendaily from a minimum of one point of use, with all pointsof use tested weekly.

    Sampling Program

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    114/148

    Sampling Program

    FDA Requirements:

    "  The validation of the water system is completedwhen the firm has collected data for a full year.

    "  The FDA states that while the above validationscheme is not the only way a system can bevalidated, it contains the necessary elements forvalidation of a water system.

     

    Microbiological/Chemical Limits

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    115/148

    Chemical Limits

    Tests Potable

    Water

    Purified

    Water

    Water for Injection

    pH N/A 5.0 - 7.0 5.0 - 7.0

    TOC N/A 500 ppb C/liter 500 ppb C/literConductivity N/A 1.3 S/cm @ 25ºC

    1.1 S/cm @ 20ºC

    1.3 S/cm @ 25ºC

    1.1 S/cm @ 20ºC

    Bacteria 500 cfu/mL 100 cfu/mL 10 cfu/100mL

    Endotoxins N/A Not Specified 0.25 EU/mL

    cfu; = Colony Forming Units

    USP Limits

    Water Systems CriticalQuality Attributes (CQA s)

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    116/148

    Quality Attributes (CQA 

    s)

    !  TOC

    !  Conductivity

    !  Temperature

    !  Flow

    !  Pressure

    !  Rapid Microbiological Enumeration and ID – off-line

    !  On-Line Microbial rate of growth – laser technology!  On-line Endotoxin (Future)

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    117/148

    Design and Qualification ofOther Utilities

    Specific Requirements—C S

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    118/148

     April 23, 2013 118

    Clean Steam

    Design Aspects:"  Stainless steel boiler

    "  Deionized water feed

    "  Sufficient blowdown level

    "  Diaphragm valves not recommended

    Specific Requirements—Cl St

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    119/148

    119

    Clean Steam (cont d)

    !  Clean steam:"  IQ:

    ! Control valves andsteam traps checked

    ! Flushing, cleaning,passivation logs/records reviewed

    "  OQ:! Temperature/pressure

    "  PQ:!

     Pure steam condensate= USP WFI

    CLEAN STEAMSPECIFICATIONS

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    120/148

    120

    SPECIFICATIONS

    Table: Microbiological/Chemical Limits

    Tests Clean Steam

    pH 5.0 - 7.0

    TOC 500 ppbConductivity USP 2? Specifications/

    method

    Bacteria 10 cfu/100mL

    Endotoxins 0.25 EU/mL

    cfu; = Colony Forming Units 

    Specific Requirements—

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    121/148

    121

    Compressed Gases

    !  Compressed gas use as:

    "  Oxygen supply forbioreactors

    Nitrogen purge toremove oxygen

    "  Clean air for asepticoperations

    !  Quality must meet product

    specifications

    Specific Requirements—C d G

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    122/148

     April 23, 2013 122

    Compressed Gases (cont d)

    !  Product contact air:"  Filtered at points of

    use"  Supplied by oil-free

    compressor"  Dried (to -40ºF)

    !  Filter list"  Air intake filter

    (protect thecompressor)

    "  Prefilter on desiccantdryer

    !  Filter list (cont d) "  After filter (for

    retention of desiccantparticles)

    "  Carbon bed"

      Point of use filter(s)with integritycertification

    !  Controls andinstrumentation w/calibration check

    "  Pressure relief valve

    "  Temperature andpressure gauges

    Specific Requirements—C G

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    123/148

     April 23, 2013 123

    Compressed Gases (cont d)

    !  OQ:

    "  SOPs for operation and maintenance

    "  Proper operation of controls and indicators(compressor start or tank—bank switching)

    "  Alarms and interlocks

    "  Line pressure (throughout distribution piping)

    Air temperature

    PQ: Process (Clean)C d Ai

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    124/148

    124

    Compressed Air 

    !  Dew point

    !  Hydrocarbons!  Viable/non-viable

    particulates

    COMPRESS GAS SYSTEMSTEST PROGRAM

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    125/148

     April 23, 2013 125

    TEST PROGRAM

    !  Sample Site and FrequenciesDetermination 

    "  For compress gas systemssamples should be taken daily froma minimum of one point of use,with all points of use tested weekly.

    CLEAN AIRSPECIFICATIONS

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    126/148

    126

    SPECIFICATIONS

    Table: Microbiological/Chemical Limits

    Tests Compress Gas

    Dew Point < -10

    o

    CHydrocarbon as Oil

    Mist

    < 1 ppm

    Gas Content USP 23 Specifications/

    method for Purity

    Bacteria < 0.1 CFU/ft3 

    Non-Viable Particulate: Room Classificationcfu; = Colony Forming Units

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    127/148

    Maintaining a Compliant System

    127

    Monitoring Program

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    128/148

    Critical Parameter(s) Controls/Alarms

    "  Reports verification and review (procedure)

    "  Alert and Action Limits

    "  Handling of Alarms

    "  Process Deviations/Failure investigations

    !  Laboratory testing:

    "  Data handling

    "  Analysis of Trends (Quarterly?)

    "  Alert Limits and Action Limits

    "  Outside Limit Conditions/Failure Investigations

    Alarms

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    129/148

    129

    !  Critical parameters –temperature, RH%, PressureDifferential, Velocities/Filter

    Pressure Drop!  Critical to Program

    Adequate Alarm Limits andDelays

    !  Procedural Action Plan for

    Alarm Conditions

    Reports Verification and Review(Procedure)

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    130/148

     April 23, 2013 130

    (Procedure)

    !  Operations must review the data(recommendation – weekly)

    "  If system performs a review/trend and includes alarm

    reports, this is simpler"  If not, manual review is necessary

    !  Procedure requirement for review, documentationand archival (hard-copy or electronic)

    Process Deviations/FailureInvestigations

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    131/148

     April 23, 2013 131

    Investigations

    !  If Action Limits are exceeded, need a ProcessDeviation or similar form/documentation

    !  Procedure must indicate form, process, review,

    approvals and f/up.!  Risk Based Interpretation/Possible Effects -

    are the system controls working effectively?

    Data Handling/Review/Approval

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    132/148

     April 23, 2013 132

    Approval

    !  Documentation: Forms, rules, review/approval ina procedure

    !  Critical for Bioburden-based sterilization cycles

    !  Frequencies/samples need to be adjusted basedon actual results

    !  Product Release Criteria for Aseptically FilledManufacturing

    Training of LaboratoryPersonnel

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    133/148

     April 23, 2013 133

    Personnel

    !  Sampling Techniques

    !  Sample handling and testing

    !  Incubation Controls

    !  Media selection:"  Incubation conditions

    "  Growth promotion tests

    Analysis of Trends

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    134/148

     April 23, 2013 134

    !  Statistical Analysis – Control Charts with Alertand Action Limits

    !  Report to Responsible Management – Operations

    !  More critical for higher classifications

    Alert and Action Limits

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    135/148

     April 23, 2013 135

    !  Not specifications

    !  Alert – potential drift from normal operational conditions

    "  Based on historical information

    "  Include a documented f/up investigation

    "  May require corrective action and testing plan changes

    !  Action Limits – when exceeded, requires immediate f/upand corrective action

    !  Both levels should be re-examined at a defined frequency

    !  References:

    "  PDA Technical Report #13 (Revised) Fundamentals of an

    Environmental Monitoring Program” Sept./Oct 2002"  ISO-13048-1, Aseptic Processing of Health Care Products –

    Part 1: General Requirements”

     August, 1998!  Alert and Action Levels should be derived from and consistent

    with results obtained during the aseptic process validation.Historical data from routine monitoring may also be

    appropriate!”

     

    Outside Alert/Action LimitsConditions/Investigations

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    136/148

     April 23, 2013 136

    Conditions/Investigations

    !  Include review of:

    "  Area maintenance, Cleaning, SanitizationProcedures/documentation

    "  Operational Parameters

    "  Training of personnel in area

    Corrective Action may include:"  Training enforcement

    "  Additional testing/frequencies

    "  Additional Sanitization

    "  Additional product testing

    "  ID of Microbial Contamination and possible source

    "  Re-assess current procedures

    "  Revalidation

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    137/148

    Training Program forMaintenance

    d O ti P l

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    138/148

    and Operating Personnel

    cGMP 

    s

    !  DocumentationPractices

    Test Comprehension

    !  Change Control is Key

    Calibration ofInstrumentation

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    139/148

    NIST Traceability

    Calibration procedures pertype of instrument

    Control software/hardwaremaintained as per procedures

    Change Control

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    140/148

    !  Pre and Post Approvalof Change

    !  Impact of Change

    determined

    !  Documentation ofresults and modified

    documents anddrawings included inpackage

    !  Quality review 

    !  Training is Key forEffective Change Control

    !  Typical Changes affecting

    a Water System:

    "  Operational Procedures

    "  Sanitization/Cleaning

    Procedures"  Sampling/Testing

    Procedures

    Revalidation –Is it required?

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    141/148

    Is it required?

    !  DO NOT ESTABLISH TIME-BASEDREVALIDATION

    !  Base decision to revalidate on change control and

    monitoring procedures and controls (trending)

    141

    Auditing for Compliance

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    142/148

    Internal Audits

    "  Risk analysis for

    audit observations"  Remediation Plans

    and Closure

    Gap Analysis for

    Legacy Systems

    142

    Exercise : Variance andDeviations Investigations

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    143/148

    !  Carbon tank, 2 mixed bed resin tank, single effect still. Systemrequirement is for Purified Water. Action limit is TOC does notexceed 300 ppb. POU measurement is 1X/week. Successive weekslook like this:

    Week 1  100 

    Week 2  155 

    Week 3  95 

    Week 4  200 

    Week 5  290 

    Week 6  250 

    Week 7  275 

    Week 8  280 

    Week 9  270 

    Exercise : Variance andDeviations Investigations

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    144/148

    No specification have been exceeded.

    What does this data tell you?

    Is it time to investigate?

    !  What questions should be asked?

    !  Should any batches of product beinvestigated?

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    145/148

    Interactive Exercise:

    Based on a critical utility system descriptionto be provided, the participants will list thekey protocol requirements and tests for theOQ and PQ of these systems.

    Conclusions

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    146/148

    146

    Conclusions

    !  Facility and Utilities Design is dependent onseveral factors including feeds and desiredspecifications

    !  Design must also consider costs, flexibility,reliability. Options for system components are

    numerous

    !  Design Review for major systems is an FDAexpectation

    !  Validation must be considered early in theproject

    !  Sampling, routine monitoring and analysis of

    the data to determine system consistency is key

    !  Change Control is critical to maintain thesystem integrity and documentation for the FDA

    Questions?

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    147/148

    147

    THANK YOU!!!

  • 8/19/2019 Effective Qualification of Critical Utilities.pdf

    148/148

    Contact Info.:

    Miguel Montalvo

    Expert Validation Consulting, Inc.Mobile Phone +1(407) 587-6540

    Email: [email protected]

    www.expertvalcon.com