of 21
7/28/2019 Electrical Generator Transfer Switch
1/21
Quality Program LessonElectrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
2/21
At the end of this lesson you will understand the
requirements for electrical systems, generator installationsand the use of Transfer Switches for site protection. You will
achieve an understanding of transfer switch installations and
be able to recognize their proper installation and that they
are in accordance with manufacturer specs.
Objectives
7/28/2019 Electrical Generator Transfer Switch
3/21
Electrical/Generator/Transfer Switch
Introduction
Electrical component installation
Electrical routing and termination
Generator, fuel tank and associated signage
Generator receptacle
Automatic transfer switch (ATS)
Lighting
DC power cables
7/28/2019 Electrical Generator Transfer Switch
4/21
Electrical component installation Verify all interior & exterior electrical components
(conduit, outlets, switches, work boxes, breakers, pullboxes, junction boxes, and panels etc.) are properly
installed, anchored and grounded.
Verify that cables, lugs, etc. are correctly installed,
routed, supported, secured, protected, crimped, andlabeled.
Verify that clear heat shrink has been installed in
electrical cable lugs.
Verify that the DC breakers in shelter room are thecorrect size:
DC Fan 5A
DC Smoke 5A
DC Lights 10A
7/28/2019 Electrical Generator Transfer Switch
5/21
Generator, fuel tank and associated signage
Verify the emergency generator, associated fuel tanksand signage have been installed where required by the
construction drawings and/or project specifications.
Fuel tank will have an AT&T designation label.
Generator pad free of cracks and defects. Fixed generator is properly grounded
Solid ground leads (min. 2) attached to generator with
the correct lug No-Ox is applied and paint removed at contact point.
Fixed generator doors and fuel filler cap/box locked, if
applicable.
7/28/2019 Electrical Generator Transfer Switch
6/21
Generator receptacle
Verify site is equipped with AT&T Mobility standard
generator receptacle (cam-lock), if required. Verify cam-lock is grounded.
Automatic transfer switch (ATS)
ATS is required on sites with a fixed generator only.
May be contained in the Intersect PTLC (AC breaker panel)
or equivalent.
Verify ATS has been installed and is labeled per the
construction drawings and/or project specifications andtested.
Generator / ATS Testing & Commissioning
If in scope, verify that the generator and ATS have been
tested and commissioned.
7/28/2019 Electrical Generator Transfer Switch
7/21
Lighting
Insure all lighting (indoor/outdoor) is
functional, including DC powered lights if
equipped. Insure the lighting in the equipment areas is
adequate and in good repair.
Verify emergency lamps are workingproperly.
7/28/2019 Electrical Generator Transfer Switch
8/21
DC power cables
Verify that all DC power cables are the proper
type. Verify that all DC power cables are correctly
routed, supported, secured and protected.
Verify that all DC power cables are correctlycolor coded for voltage per specs.
Verify that all DC power cable lugs are the
correct type & size, are correctly installed and clear
heat shrink is used.
Verify that all indoor DC power cables enter /
exit cable ladder racks over the side (waterfall) and
not through ladder rungs.
7/28/2019 Electrical Generator Transfer Switch
9/21
What do you see? Good? Not good?
Electrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
10/21
Electrical/Generator/Transfer Switch
What do you see? Good? Not good?
7/28/2019 Electrical Generator Transfer Switch
11/21What do you see? Good? Not good?
Electrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
12/21
Electrical/Generator/Transfer Switch
What do you see? Good? Not good?
7/28/2019 Electrical Generator Transfer Switch
13/21What do you see? Good? Not good?
Electrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
14/21What do you see? Good? Not good?
Electrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
15/21
What do you see? Good? Not good?
Electrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
16/21
Electrical/Generator/Transfer Switch
What do you see? Good? Not good?
7/28/2019 Electrical Generator Transfer Switch
17/21What do you see? Good? Not good?
Electrical/Generator/Transfer Switch
7/28/2019 Electrical Generator Transfer Switch
18/21
Electrical/Generator/Transfer Switch
What do you see? Good? Not good?
7/28/2019 Electrical Generator Transfer Switch
19/21
Electrical/Generator/Transfer Switch
What do you see? Good? Not good?
7/28/2019 Electrical Generator Transfer Switch
20/21
Electrical/Generator/Transfer Switch
What do you see? Good? Not good?
/ /
7/28/2019 Electrical Generator Transfer Switch
21/21
Electrical/Generator/Transfer Switch