+ All Categories
Home > Documents > Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Date post: 16-Feb-2016
Category:
Upload: sugar
View: 54 times
Download: 0 times
Share this document with a friend
Description:
Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013. Background. Australian Treasury is interested in electricity modelling in an economy-wide framework It has used: detailed consultant’s electricity model and - PowerPoint PPT Presentation
Popular Tags:
34
Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013
Transcript
Page 1: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Electricity in the GTAP model

Tony WiskichNational CGE Workshop 2013

Page 2: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Background• Australian Treasury is interested in electricity

modelling in an economy-wide framework • It has used:

– detailed consultant’s electricity model and– embedded Constant Elasticity of Substitution (CET)

production nest between generation technologies.

• Interested in macroeconomic impacts of adjustment in electricity generation

Page 3: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Motivation• NOT to replace detailed bottom-up electricity

model• Provide some insight using an alternative

approach to a CET nest structure based on a competitive electricity market

• Provide some insight into costs of adjustment

Page 4: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Model basics• GTAP model made recursive through simple

capital/investment dynamic• Single region, 8 sectors including electricity

Page 5: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-1

-0.9

-0.8

-0.7

-0.6

-0.5

-0.4

-0.3

-0.2

-0.1

0

Real GDP impact of a 1% decrease in Labour, Land & Nat Res efficiency

Temporary

Permanent

Page 6: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-0.45

-0.4

-0.35

-0.3

-0.25

-0.2

-0.15

-0.1

-0.05

0

Real GDP impact of a 1% decrease in Capital stock

Page 7: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Electricity Structure Assumptions

• Profit + Fixed + Variable Costs• Profit = Capital Cost (28%)• Fixed = Labour Cost (13%)• Variable = Intermediate (59%) (+ TAX)• Generators operate in a competitive electricity

market similar to Australia

Page 8: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Base case assumptions• Baseload, Mid and Peak generation• Same rate of return on investment between

generation types & other sectors• Same Fixed Cost per MW (MegaWatt) Capacity• Same Variable costs structure• Small load shedding period (demand > supply)

– Approx 3 hours per year

Page 9: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

M

2M

1Duration

Load Load duration curve

Page 10: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1

Capacity

Base

Mid

Peak

Duration

Page 11: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1

Capacity

BaseMidPeakDuration

Page 12: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1 Time

Price =Marginal Cost

BaseMidPeak

P_Base

P_Mid

P_Peak

Price CAP

Page 13: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1 Time

Price =Marginal Cost

BaseMidPeak

Base Capital + Fixed (Labour) Costs

Base Variable (Intermediate) Costs

P_Base

P_Mid

P_Peak

Price CAP

Page 14: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Base case assumptions/numbers

Var Cost

Electricity Gen share

Capacity share

Utilisation rate

Rev Share

Marginal generator

time share

Cost to build

per MW

Baseload 1 84.9% 66% 96% 79.3% 33% 1

Mid 1.5 15% 31% 36% 20% 62% 0.33

Peak 2 0.1% 3% 3% 0.7% 5% 0.28

Page 15: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Policy shock

• Introduce electricity output tax on Baseload electricity generation

• Two rates, initial Baseload variable cost = 1– Fast: incremental tax increase of 0.05 per year

• Mobile capital (consider immobile later)

Page 16: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10111213141516171819 20212223242526272829

-100

-90

-80

-70

-60

-50

-40

-30

-20

-10

0

Baseload generation % change

CES (elas=10)ELY

Page 17: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-100

0

100

200

300

400

500

600

700

Mid,Peak generation % change

Mid&Peak CESMid ELYPeak ELY

Page 18: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Back-of-envelope – ΔPrice• CES: Elasticity 10, approx 80% Base share• Price inc ~ 0.2*((1+0.8/0.2)10/9-1)-0.8 ~ 20%• ELY: Price inc ~ Base_varshare_as_marg_gen*

(Mid_varprice/Base_varprice-1)~14% * 0.5 ~ 7%

Page 19: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

2

4

6

8

10

12

14

16

18

20

Electricity price % change

CES (elas=10)ELY

Page 20: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Back-of-envelope - ΔGDP• CES: GDP impact ~

price_inc*ely_cost/GDP*dynamic_adj_factor ~ 20%* 2/56 * 1.5 ~ 1.1%• ELY: Price inc: (extra_var_cost –

cap_savings)/GDP*dynamic_adj_factor ~ (0.9*0.5 – 0.5*2/3)/GDP*dyn ~ 0.12/56*1.5 ~

0.3%

Page 21: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-1.2

-1

-0.8

-0.6

-0.4

-0.2

0

Real GDP % change

CES (elas=10)ELY

Page 22: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

200

400

600

800

1000

1200

GDP cost per Baseload unit reduction

CES (elas=10) ELY

tax

Page 23: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Fixed capital in generation• Baseload Depreciation – 30 years to vanish• No limit on capital increase (build in single

period)• Capital is decommissioned if profits < 0

Slow tax introduction• From 0.05 to 0.02 increment per year

Page 24: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-100

-90

-80

-70

-60

-50

-40

-30

-20

-10

0

Baseload: Fixed capital, Fast vs Slow tax introduction

fast Profit/MW

fast MW

fast GEN

Page 25: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-100

-90

-80

-70

-60

-50

-40

-30

-20

-10

0

Fast vs Slow: Baseload MW, Profit/MW , Gen % change

slow profit/MWslow MWslow GENfast Profit/MWfast MWfast GEN

Page 26: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

200

400

600

800

1000

1200

GDP Cost: ELY slow vs fast tax

fast tax

slow tax

fast cost

slow cost

Page 27: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 10 20 30 40 50 60 70 80 90 1000

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GDP cost vs Baseload reduction

Fast CET

Slow CET

% reduction in Baseload Generation

% re

ducti

on in

Rea

l GDP

Page 28: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 10 20 30 40 50 60 70 80 90 1000

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GDP cost vs Baseload reduction

Fast CET

Slow CET

Fast MOBILECAP

Slow MOBILECAP

% reduction in Baseload Generation

% re

ducti

on in

Rea

l GDP

Page 29: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 10 20 30 40 50 60 70 80 90 1000

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GDP cost vs Baseload reduction

Fast CET

Slow CET

Fast MOBILECAP

Slow MOBILECAP

Fast FIXCAP

Slow FIXCAP

% reduction in Baseload Generation

% re

ducti

on in

Rea

l GDP

Page 30: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Summing up• Competitive electricity market model can be

done and has different dynamics/costs to CET• Baseload-Mid substitution not Peak• Fixing capital: Adjustment cost depends on speed

of tax introduction– Inefficient capital allocation, merit order switching– Capital decommissioning

Page 31: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Possible further work• Simple international analysis

– based on projected capital/fixed/variable costs– Compare economic costs with CET

• Figure out way of adjusting CET implementation to approximate detailed model

• Intermittent generation

Page 32: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Extra slides

Tony Wiskich2013 conference

Page 33: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 1112 13 1415 16 1718 1920 21 2223 24 2526 27 2829

0

200

400

600

800

1000

1200

GDP Cost: CES slow vs fast tax

fast CES

slow CES

fast tax

slow tax

Page 34: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

200

400

600

800

1000

1200

GDP Cost: CES slow vs fast tax

fast CES

slow CES

fast ELY

slow ELY

fast tax

slow tax


Recommended