+ All Categories
Home > Documents > Engineering Cost Escalations Project Report.pdf

Engineering Cost Escalations Project Report.pdf

Date post: 03-Apr-2018
Category:
Upload: rahul-raghukumar
View: 233 times
Download: 0 times
Share this document with a friend

of 106

Transcript
  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    1/106

    ACKNOWLEDGEMENT

    For the tremendous support and interest I received in carrying out this dissertation

    project, I would to extend my sincere and profound gratitude to all the participants those

    who have actively participated and contributed in the completion of this research project

    and its report which is prepared in partial fulfillment of Executive Masters in Business

    Administration (EMBA)-Operations.

    My particular thanks go to our Dean Dr. Balakrishna Grandhi and Prof. Krishnan

    Navgath for extending their kind support. I would also like to thank Mr. Nihar Kumthekar

    for providing valuable guidance.

    I also take this opportunity to thank my Industry mentor at Dodsal E&C Pte. Ltd., Mr.

    Garry Crighton (Executive Director- Corporate QHSE) who has been my constant

    source of strength. He not only guided me at crucial times but was also was

    instrumental in extracting from me the best possible work.

    Mr. Naresh Rijhwani (Vice President- Engineering) at Dodsal E&C Pte. Ltd. and Mr.

    Jinesh K. Shah (Project Management- Wood group PSN) were also a great source of

    knowledge and information on the research project. I am thankful for their motivation

    and contribution in spite of their busy schedules.

    Last but not least, I also want to thank to my colleagues at Dodsal, classmates at S. P.

    Jain and LinkedIn community members for actively participating in concluding the

    research. I am confident that the outcomes of this research project will be of benefit to

    EPC sector stakeholders with regards to the cost escalation issues for their projects.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    2/106

    EXECUTIVE SUMMARY

    For Project Managers and Project Sponsors, scope creep and the project cost over runs are

    major concerns. The average cost escalation on industrial EPC projects exceeds 12 to 15

    percent from the original estimates. Design deviations (changes, errors, and omissions) are

    accounted for roughly 80 percent of the increased costs. The value stated above is only the tip

    of the iceberg and the real cost escalation sometimes go up to 33 to 50 percent of the estimated

    cost for the project. Earlier identification of design issues (preferably at engineering stage) is

    easier to handle and have lesser impact on project health.

    The research analyzed such cases, referred to various online case studies and gathered expert

    opinion through focused group discussions, personal interviews and online survey, as a part of

    this process.

    As a result, the research could conclude on various aspects of root causes that contribute to the

    cost escalation during the detail engineering stage of the project and interestingly the opinion

    believed that the major cost escalations originate from the estimation stage or proposal stage of

    the project.

    Various factors like short bidding time, Bid selection criteria, Inaccurate FEED (Front End

    engineering Design) are identified as few of major issues and are discussed in detail inside the

    report. Similarly the cost escalation issues arising from during detail design activities like Gold

    plating, lack of proper change management, poor implementation of project management

    practices were identified and discussed.

    Various research methodology tools and techniques and the knowledge areas learnt through

    out EMBA course were used in arriving at a systematic understanding of root causes for cost

    escalation issues.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    3/106

    List of Abbreviations

    CEO Chief Executive Officer

    DCN Design Change Note

    DD Detail Design

    DE Detail Engineering

    E&C Engineering and Construction

    EMBA Executive- Masters of Business Administration

    EPC Engineering, Procurement and Construction

    EPCI Engineering, Procurement, Construction and Installation

    FEED Front End Engineering Design

    FGD Focused Group Discussion

    FIDICFIDIC

    Federation Internationale des Ingenieurs ConseilsInternational Federation of Consulting Engineers

    FPSO floating production, storage and offloading

    FWBS Functional Work Breakdown Structure

    GT Gas Turbine

    HAZOP Hazard And Operability Study

    HR Human Resource

    HSE Health, safety and Environment

    IFC Issued For Construction

    IT Information Technology

    ITT Instruction To Tenderer

    LSTK Lump Sum Turn Key

    MTO Material Take-Off

    P&ID Process and Instrumentation Diagram

    PHO Project Home Office

    PM Project Manager

    PMBOK Project Management Body Of Knowledge

    PMC Project Management Consultant

    PMI Project Management InstitutePMO Project Management Office

    PMT Project Management Team

    PO Purchase Order

    QHSE Quality, Health, Safety and Environment

    QRA Quantitative Research Analysis

    ROM Rough Order of Magnitude

    SIL Safety Integrity Level

    SOW Scope Of Work

    SPJSGM S P Jain School of Global Management

    SPPID Smart Plant P&ID

    SWOT Strength, Weakness, Opportunity and Threats

    TQ Technical Query

    USD United states Dollar

    VAT Value Added Tax

    VDR Vendor Document Review

    WBS Work Breakdown Structure

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    4/106

    TableofContents

    1. INTRODUCTION................................................................................................................................ 3

    2. INDUSTRYBACKGROUND................................................................................................................ 4

    3. INTRODUCTIONTODODSAL............................................................................................................ 8

    4. PROBLEMSTATEMENT..................................................................................................................... 9

    5. RESEARCHOBJECTIVE.................................................................................................................... 12

    6. RESEARCHDESIGN......................................................................................................................... 13

    7. PROJECTSCOPE.............................................................................................................................. 18

    8. FINDINGANDANALYSIS................................................................................................................. 27

    9. RECOMMENDATIONS.................................................................................................................... 36

    10. MANAGERIALIMPLICATIONS

    .........................................................................................................

    45

    11. THEWAYFORWARD...................................................................................................................... 48

    12. CONCLUSION.................................................................................................................................. 51

    13. BIBLIOGRAPHY............................................................................................................................... 52

    List of Appendix

    Appendix 01 InterviewTranscriptwithMr.JineshKShah

    Appendix 02 InterviewTranscriptwithMr.NareshRijhwani

    Appendix 03 TranscriptofFocusedGroupDiscussiononLinkedIn

    Appendix 04 SurveyForm

    Appendix 05 SurveyResults

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    5/106

    2|P a g e

    List of Figures

    Figure 1 - Average Cost escalation/ Deviations ...................................................................................... 9

    Figure 2 - Breakdown of Deviation ........................................................................................................ 10

    Figure 3 - Deviation factor contribution % ............................................................................................. 10

    Figure 4 - Factors Contributing to Design deviations ............................................................................ 11

    Figure 5 - Major Cost Escalation Contributors ...................................................................................... 14

    Figure 6 - Problem Area Graph ............................................................................................................. 28

    Figure 7 - Problem Area Data ............................................................................................................... 28

    Figure 8 - FGD Online Discussion Page on LinkedIn ........................................................................... 29

    Figure 9 - Influential position at bidding stage for Cost Effectiveness ..................................................31

    Figure 11 - Top Influencer in Estimation stage ..................................................................................... 34

    List of Tables

    Table 1- Top 5 Global EPC Contractors ................................................................................................. 4

    Table 2 Top Oil and Gas EPC contractors in Middle East. ..................................................................... 5

    Table 3 - Cost Escalation Factors at bidding stage .............................................................................. 30

    Table 4 - Influential position at bidding stage for Cost Effectiveness ................................................... 31

    Table 5 - Top Factors at the Detail Design stage ................................................................................. 33

    Table 6 - Most Pivotal (Influential) role at Detail Design Stage ............................................................ 34

    Table 7 Top Parameters for improving cost escalation ........................................................................ 35

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    6/106

    3|P a g e

    INTRODUCTION

    The Engineering, Procurement and Construction (EPC) sector plays an important role to

    play in economic and infrastructure development. This industry is working in many

    sectors such as Oil & Gas, Petrochemical, Infrastructure, and Energy etc. From few big

    players to many medium and small companies that work as EPC contractors for major

    projects around the world. EPC project contract value varies from few million to multi-

    billion US dollars.

    For EPC projects, the asset owner or the Client, after successful technical feasibility

    study and commercial viability study, proposes to design, engineer and build a project

    for practical business purposes. The basic design or the Front End Engineering Design

    (FEED) is provided to technically qualified and experienced EPC contractors to propose

    an estimate for the project.

    In this region (GCC) the contracting strategy adopted that of Lump Sum Turn Key

    (LSTK) where the successful bidder are who submitted the lowest price. More Often

    than not the project schedules are tight. The fast track nature of this business results in

    limited time, resources, Information and funds at the bidding stage does not allow a

    Contractor performing due diligence of the tender.

    The competitive environment in EPC sector is pushing EPC Contractors to win project

    bids at cut-throat prices on Lump sum basis. While executing the project, a new team is

    formed to carry out the detail design. There are many discrepancies between the

    estimated and the actual design. As a result, escalation of cost and time are inevitable.

    Cost escalation and scope creep are the top concerns of an EPC Project Manager or a

    Project Sponsor since at the end of the day; he is responsible for maintaining the

    bottom-line to green.

    This research document studies and analyses the factors contributing to such cost

    escalations for the EPC contractor during the detail design phase of the Oil and Gas

    EPC project execution.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    7/106

    4|P a g e

    INDUSTRY BACKGROUND

    Engineering, Procurement and Construction (EPC) sector has grown with consistent

    pace in last 5 to 6 decades. Initially dominated by Contractors from developed countries

    like USA, Europe and Japan, the sector was highly profitable. Technological

    advancement, research & development and methodological advancement in the sector

    reached saturation in late 20th century. In past 20 years, the industry has grown from

    few players to over 150 around the globe. At the same time large projects are sub

    divided in smaller packages & sub-contracts, depending upon the value associated and

    the complexity of the project.

    EPC contracts are mainly in following sectors:

    Infrastructure/Building Construction

    Oil & Gas,

    Power,

    Chemicals & Petrochemicals and

    Specialized Sectors

    Following are Top 5 contractors of the time.

    Table1- Top5GlobalEPCContractors

    RANK FIRM TOTAL 2012

    REVENUE $MIL2013 2012

    1 1 Bechtel 29,436.0

    2 2 Fluor 22,352.83 3 Kiewit 9,600.7

    4 4 Turner Corp 9,084.9

    5 6 PCL Construction 6,841.5

    (https://enr.construction.com, 2013)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    8/106

    5|P a g e

    Over the period there is growing concern on contractors capabilities and project

    management skills. Projects contracting strategies have mostly transited from item rate

    based contracts to LSTK based. By signing a Lump-sum contract, todays contractor is

    deemed to have obtained all necessary information as to risks, contingencies and other

    circumstances which may influence or affect the Works.

    Table2TopOilandGasEPCcontractorsinMiddleEast.

    RANK FIRM TOTAL 2012REVENUE $MIL

    2012

    1 Petrofac 7006.3

    2 Saipem 4245.0

    3 Samsung Engineering 3130.0

    4 Technip 7099.0

    5 Flour 2291.0

    31-50 Dodsal E&C Not Known

    (Oil & Gas Middle East, 2012)

    By signing the Contract, the Contractor accepts total responsibility for having foreseen

    all difficulties and costs of successfully completing the Works; and the contract price

    cannot be adjusted to take account of any unforeseen difficulties or costs.

    As the majority of project risks are transferred to EPC contractors, the contractors risk

    appetite and the financial capacity becomes increasingly significant. The burden of the

    project management has shifted from the owner/developer to the Lump sum EPC

    contractor. Consequently the risk of time and cost overruns are transferred to the EPC

    contractors.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    9/106

    6|P a g e

    The rise of China, India and Korea has stretched the competition even further. The rise

    of unrest in middle-east has further changed the scenario where the localization is

    mandated by the local governments and main works of EPC projects are expected to be

    done by local contractors. Overall, the situation is high risk ownership, low profit

    margins and cut-throat competition. On average if one contractor moves out, five new

    payers enters the market.

    Given this scenario, EPC contractors are bound to find new ways to improve operations

    and re-engineer its processes to ensure that they survive in the market. With increasing

    energy demands, desire for better life, Government investment to push growth model

    and technological advancement in energy exploration will ensure that the sufficient

    number of projects is created in next 10-20 years.

    The major Types of EPC contracts are:

    Fixed price (Lump Sum Turn Key)

    Firm Fixed price (FFP)

    Fixed price Incentive Fee (FPIF)

    Fixed price with Economic price adjustment (FP_EPA) (Project

    Management Institute,Inc., 2008)

    Cost Reimbursable Contracts

    Cost plus Fixed Fees (CPFF)

    Cost plus incentive Fee (CPIF)

    Cost Plus Award Fee (CPAF) (Project Management Institute,Inc., 2008)

    Time and Material Contracts.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    10/106

    7|P a g e

    For the Cost reimbursable type of contracts, the risk is shared between EPC Contractor

    and the owner and the EPC Contractor is more protected for the risk.

    For the Time & Material type contract the majority of the project risk remains with the

    owners. Such contracts are exercised rarely and only when the result of the project is

    unknown.

    Majority of the contracts in the GCC region in Oil and Gas sector are LSTK bases.

    Hence, the research in this project is mainly based on LSTK EPC contracts in Oil and

    Gas sector projects.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    11/106

    8|P a g e

    INTRODUCTION TO DODSAL

    The Dodsal group of companies was founded in Mumbai, India, in 1948 by the Nandlal

    Kilachand family as a trading company in partnership with a British trading company

    (DODWEL) and Mr. Karsa Salem. Since then, Dodsal has transformed from a family

    trading enterprise into a multi-billion dollar Organization.

    Today, Dodsal is a Dubai based diversified multinational conglomerate which operates

    in the areas of Engineering, Procurement and Construction; Trading and Distribution;

    Exploration and Production; Casual Dining Restaurants; and Manufacturing.

    ENGINEERING, PROCUREMENT AND CONSTRUCTION

    Dodsal Engineering and Construction Pte. Limited, the holding company for the

    Dodsals Engineering and Construction business is one of the leading EPC players in

    the Energy, Industrial and Infrastructure sectors and has successfully implementedprojects in over 22 countries in the Middle East, Europe, Africa, the Indian Subcontinent

    and South-East Asia.

    Dodsal E&C Pte. Ltd. also carries out Infrastructure development and management

    projects and has already completed on finance, build, operate and transfer basis,

    pipeline projects in India and North Africa.

    Engineering and Construction is the flagship business of the Dodsal that undertakes

    Engineering, Procurement and Construction projects as well as large scale complex

    Construction only Projects in the Energy, Industrial and Infrastructure sectors in the

    Middle East, Asia, Africa and Europe.

    On its projects, Dodsal deploys full time Project Management task forces comprising of

    project personnel from all disciplines, including Project Management, Engineering,

    Procurement, Construction, Commissioning and Project Support Services.

    Dodsals Engineering and Construction teams have a proven track record of high safety

    standards and the company has achieved Lost Time Injury Frequencies that are

    consistently well below industry averages, receiving several letters of appreciation andsafety awards for their successful and timely project execution. (Dodsal E & C Pte. Ltd.,

    2012)

    You can find more details of company business at company website:

    http:\\www.dodsal.com

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    12/106

    9|P a g e

    PROBLEM STATEMENT

    Highly competitive Oil & Gas EPC market is yet another Red Ocean where the

    contractors bid projects absorbing very high business risk. Oil & Gas Companies, taking

    advantage of the market situation, pass on complete project risks to the EPC contractor

    in the form of Lump-sum Turn Key (LSTK) contracts.

    It is highly essential for the EPC to complete the project within Time, Cost and Quality

    constraints, absorbing all the risks. The cost escalation during the project execution is

    highly detrimental to the financial health of the project. For many contractors, it is a

    matter of survival in the industry.

    In spite of due care in project estimation process, the contractor encounters various

    unforeseen cost escalations during the execution of an EPC project. Engineering phase

    being most critical phase in deciding the desired project output; identifies many issues

    that lead to the cost escalation for overall project.

    The average cost escalation on industrial EPC projects exceeds 12 to 15 percent.

    Figure 1 - Average Cost escalation/ Deviations

    87.60%

    12.40%

    Basiccosts

    Deviations

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    13/106

    Design

    the incr

    (Constr

    The val

    to 33%

    If we s

    chart. (

    eviations

    ased cost

    ction Indu

    e stated a

    o 50% of t

    e the par

    onstructi

    (changes,

    s, while co

    try Institut

    Fi

    bove is on

    e estimat

    to analysi

    n Industry

    Figur

    2.5

    17.00

    rrors, and

    nstruction

    e, 2013).

    ure 2 - Br

    ly the tip o

    d cost of t

    s of the d

    Institute, 2

    3 - Deviati

    %

    0.40%

    4.00%

    omissions

    eviations

    akdown of

    the icebe

    e project.

    viation co

    13)

    on factor c

    9.50%

    79.00%

    accounte

    ccounted

    Deviation

    g and the

    sts the re

    ontribution

    for rough

    for only ab

    real cost e

    ults look

    %

    Design

    Constructi

    Others

    Design

    Construct

    Others

    10|P

    ly 80 perc

    out 20 per

    scalation g

    imilar to b

    n

    ion

    a g e

    nt of

    cent.

    o up

    elow

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    14/106

    The De

    The ab

    (Constr

    All the

    complet

    the pro

    escalati

    manage

    over.

    If the f

    (Biddin

    The re

    escalati

    ign factors

    ve clearly

    ction Indu

    PC contr

    ing project

    curement

    ns are o

    ment tea

    ctors cont

    and Detai

    earch is

    n during e

    4.50%

    are furthe

    igure 4 - F

    hows the i

    try Institut

    ctors in O

    over its b

    and const

    igination f

    is helple

    ributing th

    l design) o

    n honest

    ngineering

    20%

    classified

    actors Con

    mpact of d

    e, 2013)

    il & Gas s

    udget. Th

    ruction st

    om biddin

    s as the ti

    cost esc

    the projec

    effort to l

    stage of t

    as below.

    tributing to

    esign chan

    ctor in sp

    realizatio

    ges of t

    g or engi

    me has p

    lations ar

    , then maj

    ook in to

    e project.

    54.10%

    Design de

    ges on the

    ite of kno

    of the co

    e project

    eering sta

    ssed and

    taken ca

    rity of cos

    various is

    D

    D

    D

    viations

    overall pr

    ing these

    t escalatio

    . Majority

    ge. Howe

    the Engin

    re during t

    risk can b

    sues leadi

    esignchange

    esignerror

    esignomission

    11|P

    ject outco

    facts end

    n comes u

    of these

    er, the pr

    ering pha

    he initial

    e avoided.

    ng to the

    s

    a g e

    e.

    p in

    nder

    cost

    oject

    e is

    tage

    cost

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    15/106

    12|P a g e

    RESEARCH OBJECTIVE

    The objective of this research project is to identify and address the root causes

    contributing to the cost escalation during engineering phase of EPC oil & Gas Project

    execution. The project research shall not only focus on the root causes contributing to

    the cost escalation but also to suggest recommendation to overcome the risk of Cost

    escalation.

    The research will be carried out based on Industry data; Web based case studies,

    captured cost escalation cases (Within and outside Dodsal) and lessons learnt on

    recent EPC projects executed by Dodsal in recent past.

    The main research objectives are:

    To study and identify the factors contributing to cost escalation during project

    Engineering execution phase.

    To study and identify the operational issues in engineering execution process

    for EPC project.

    To conform if the problems are company specific or across the EPC sector.

    To gather information on the best practices adopted across the industry.

    To apply Management knowledge area tools and techniques for identifying

    remedies to the contributing factors.

    To propose the improvements in current process to avoid the risk of cost

    escalation.

    To establish a well-rounded report and conclusion at the end of the study.

    At the end of the research project, a comprehensive project report and Power point

    presentation is prepared based on facts, findings and resultants of the qualitative and

    quantitative research. The project reports not only focus on the root causes contributing

    to the cost escalation but to suggest recommendation to overcome the risk of Cost

    escalation. A brief power point presentation shall be conducted for the stake holders.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    16/106

    13|P a g e

    RESEARCH DESIGN

    The Research Design was combination of both Qualitative and Quantitative

    methodology. The below paragraphs details the type of research data used for the

    project. Both Secondary and Primary data research carried out as part of the project

    work.

    Secondary research data:

    The Secondary research data in terms of Design change notes, Lessons learnt from

    previous projects and web based literature was referred.

    The Design change notes, lessons learnt with cost variation notes are captured and

    stored from various recent projects within the company. Engineering failures and quality

    non- conformance identified in past were reviewed and identified to prepare the

    preliminary basis to start the project.

    Web based research data, competitor data, and research work carried out in past were

    cited for problem definition.

    Primary research data:

    Personnel interviews and web based Focused Group Discussions as primary research

    was conducted for problem definition and inputs to generate the basis for quantitative

    research.

    Qualitative research in the initial stages of the survey, incorporating video calls,

    Focused Group discussions and debates helped broaden our knowledge and

    understanding of the problem providing an exploratory report.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    17/106

    The qu

    establis

    related

    Detaile

    determi

    Below i

    Resear

    The 3 m

    I

    F

    antitative

    ing focus

    to Engine

    percenta

    e the resu

    an illustra

    h Instrum

    ain resear

    terview S

    GD and

    uestionnai

    research i

    d and con

    ering activ

    e and gr

    lts more ef

    tion of our

    Figure 5

    ents

    h instrum

    hedules

    res

    ncluding

    clusive res

    ities were

    phs are

    ectively.

    Quantitativ

    - Major Co

    nts includ

    detailed

    ults. The t

    gathered

    ubmitted

    e Researc

    st Escalati

    d in this re

    question

    rget respo

    by means

    as a part

    results.

    n Contrib

    search:

    aire and

    nses of 20

    of online

    of the re

    tors

    14|P

    survey h

    + respon

    question

    ult in ord

    a g e

    lped

    ents

    aire.

    r to

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    18/106

    15|P a g e

    Since there are various research instruments, a healthy mix of survey was selected for

    great benefit to establish the desired results.

    The steps and procedures was followed systematically and included:

    Content Analysis.

    Evaluation Research on the various triggers of cost Escalation.

    Human Factors and psychology of the Team members.

    Organizational analysis of different competitor industries.

    Extensive Surveys

    Sampling Methodology

    There are various methods that can identify the frame of aspects contributing to the

    cost escalation factors as understood by the stakeholders. However, the 2 methods

    incorporated were:

    Systematic sampling (75%)

    Stratified sampling (25%)

    Systematic sampling conducted by arranging a target population to which we

    reached out to with the set questionnaire. A key study was drawn initially to ensure

    that the target population selected was all of the similar experience levels with

    similar industry sector. This was aimed to produce accurate results.

    Stratified sampling was important to accurately draw a final conclusion. Here we

    gathered a whole target population after which we divided them into individual strata.

    Each Stratum was divided by the years of experience, positions held, Complexity

    and performance on cost escalation sides. This method ignored irrelevant and

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    19/106

    16|P a g e

    incomplete data; targeting achievement of efficient results. It permitted greater

    balancing of statistical power of tests of differences between the different strata and

    sample equal numbers from the varying audience.

    Systematic sampling technique used predominantly throughout the research. The

    participants for personal interview and FGD were selected from the relevant groups

    and organizations, based on their relevance to the subject, willingness to contribute

    and experience level.

    For Quantitative research, the online questionnaire was distributed through e-mail

    and web based survey will be conducted.

    Sample Size

    The sample size for personal interview was 2.

    One person within and one person outside company, within industry.

    100+ responses collected for detailed questionnaire.

    Target Respondent

    The Qualitative research was planned in two parts, that is Personal interview and

    Focused group discussions. Two detailed interviews conducted Mr. Naresh

    Rijhwani from Dodsal and Mr. Jinesh K Shah from the similar EPC industry player.

    The criteria for the selection of the personnel were on the basis of the participants

    experience and his willingness to contribute for the cause. Their experience level

    varies from 20 to 35 years in EPC industry having senior to top management level

    position.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    20/106

    17|P a g e

    Focused group discussion was conducted in EPC consultants group on LinkedIn

    with more than 28000 professional and experts coming from various disciplines,

    whose interests are linked with the project. Please refer appendix-03 for details of

    the FGD opinions. Estimation, HR, HSEQ, Project Planning, Project controls are

    few disciplines to name a few in the list with engineering discipline.

    The representatives are 1-40 years of experience working in EPC sector similar to

    Dodsal.

    For quantitative research, a questionnaire was prepared on

    www.surveymonkey.com and distributed through e-mail and website (LinkedIn)

    connections. Please refer to the appendix-04 for details of the survey form.

    At least 200 respondents working in various EPC contractor companies attended

    the survey, out of which 100+ completed survey result were considered for further

    analysis. Refer appendix-05 for survey results.

    Web assistance ofwww.surveymonkey.com orwww.linkedIn.com helped targeting

    the right audience with higher number of respondents. A larger data collection

    brought a good collection and the target respondents were found to be key stake

    holders of EPC project execution.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    21/106

    18|P a g e

    PROJECT SCOPE

    The EPC project life cycle typically vary from 1 to 3 years and gets executed broadly in

    3 phases as the name suggests- Engineering, Procurement and Construction. The

    Engineering process during the project execution is generally called as Detail

    Engineering Design. The research project will mainly focus on the Engineering part of

    the EPC life cycle.

    In addition, the estimation process involves limited amount of engineering (Pre-bid

    Engineering) that leads to cost estimation of the project bid shall be covered in the

    project scope. Though, the pre-bid engineering does not form the part of the project

    execution, it defines the cost and schedule base lines for the project. Hence, it has a

    considerable impact on project engineering execution. The research is mainly focusing

    on the operational issues of the proposal stage and detail engineering design and will

    not address the contractual and financial aspects of the project.

    Though the explicit procurement and Construction phase cost escalation are not part of

    the research, the research recommendations shall address the issues originating at

    engineering phase.

    The scope of the study will also cover the Human resource aspects like skill sets,

    competency and soft issues essential for smooth project execution.

    The project mainly focuses on the identification of cost escalation factors and proposes

    possible check points to avoid such occurrence for few cases. The judgment for the

    proposed check point is an expert opinion and shall be applied on case to case basis

    specific to company. EPC sector is widely diversified in terms of geographical regions,

    culture, complexity, and scales and hence the concepts discussed may not be used

    directly- as is - but with tailoring to the operating context.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    22/106

    19|P a g e

    Various cost escalation reports with company were reviewed and analyzed. The

    relevant data are classified information and cannot be displayed in the report. However,

    the leanings out of the cases were captured in the research project.

    EXCLUSIONS

    Any cost escalation arising explicitly related Procurement and Construction issues are

    excluded from the scope of the research. However, any development or triggers

    originating from engineering having major cost impact on the procurement and

    construction activities of the project shall be studied and discussed in detail.

    The research is mainly focusing on the operational issues of the proposal stage and

    detail engineering design and will not address the contractual and financial aspects of

    the project.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    23/106

    20|P a g e

    LITERATURE REVIEW

    The cost escalation in EPC sector is a matter of concern for all project holders. In order

    to understand the EPC industry, we could find and review various online reports.

    Pratap Vijay Padode, Editor-in-Chief, Infrastructure Today and Managing Director,

    ASAPP Media Information Group say that delays in our development projects are

    forcing more developers to go the EPC way. The new emphasis on EPC is also, sadly,

    because investments are looking south. With a double-dip threat in the global economy,

    the worst industrial growth in eight quarters in India and projects down to a trickle, EPC

    is a stable option. (Ernst & Young Pvt. Ltd., 2011)

    A decade ago, the EPC industry comprised a handful of large, complex projects and

    multitude small packages and subcontracts. Today, there is no dearth of high value and

    complex projects being executed by government and private players. The increasing

    size and complexity of projects has, however, led to a growing reliance on contractors

    capabilities and project management skills. (Ernst & Young Pvt. Ltd., 2011)

    Contracts have evolved from item rate packages to lump sum fixed price binding

    contracts. Slowly but steadily, the onus of project management has shifted from the

    owner/developer to the contractor. Gradually, the risk of time and cost overruns has

    been transferred to the contractor, along with the responsibility of designing,

    procurement of materials and construction. Standard clauses and conditions prevailed,

    but the EPC contract model has evolved to reflect the shift in balance of risk between

    the owner/developer and the contractor. (Ernst & Young Pvt. Ltd., 2011)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    24/106

    21|P a g e

    The problem of cost escalation, schedule escalation and scope creep in the fields of

    project management are not new. Various online magazines line Engineering News

    records, World Oil, offshore Engineers etc. shall be referred to identify the horizons the

    problems in Industry. Websites related to EPC companies and market like MEED,

    ZAWYA and PMI were explored to gather the secondary data for the project. Various

    study books like PMBOK by PMI, were be referred to standardize the terminology and

    learning area.

    One recent example studied in the MEED was related to Saudi ARAMCO Wasit

    offshore gas project. The project was awarded to Saipem with specified sulfur content in

    the project specification. However, while executing the project, there was unexpectedly

    high sulfur content. There was a difficult situation for both client and Contractor to

    absorb the risk as the project estimated value was amounting to almost 6 Billion USD.

    (MEED, 2012)

    A recent news article reveals that the South Korean construction stocks have lost

    almost 20 percent of their value, falling to levels last seen four years ago, after huge

    losses at two firms sparked widespread fears of overseas projects going sour. After the

    2008 financial crisis, South Korean builders such as Samsung Engineering Co Ltd and

    GS Engineering & Construction Corp won a raft of foreign orders, particularly in the

    Middle East. (http://au.news.yahoo.com, 2013)

    Some of those contracts have turned into losers as fierce competition has driven down

    prices, and inexperience in new areas has meant extra costs. Lack of understanding of

    business conditions in new markets and risk arising from moving into new products

    resulted in big cost increases in some projects, the firm said in a statement. Across the

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    25/106

    22|P a g e

    sector, the decision to chase foreign orders that have turned out to be unprofitable is

    expected to hurt bottom lines. (http://au.news.yahoo.com, 2013)

    There are various case studies and lesson learnt on the issue are available on web

    based literature. At the same time, Dodsal has got vast experience carrying out projects

    in different sectors, locations and at different timeline.

    The Design change notes, lessons learnt with cost variation notes are captured and

    stored from various recent projects. We have strong database within the company for

    engineering failures and quality non- conformance identified in past. The same will be

    identified and reviewed to prepare the preliminary basis to start the project.

    Contract models play very important roles in EPC sector. For understanding of type of

    contracts the PMBOK Guide was referred. (Project Management Institute,Inc., 2008)

    Additionally the FIDIC guidelines for construction contracts were referred. (Savage,

    2012)

    Various sections of the FIDIC Contract recommendations were studied for

    understanding of EPC contracts:

    Red Book: Conditions of Contract for Construction for Building and

    Engineering Works Designed by the Employer;

    Yellow Book: Conditions of Contract for Plant and Design-Build;

    Silver Book: Conditions of Contract for EPC/Turnkey Projects;

    Green Book: Conditions of Short Form of Contract. (Savage, 2012)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    26/106

    23|P a g e

    Aim is to understand the contractual obligations of the EPC contractor to serve the

    client. Since we are studying the cost escalation, in many cases, I would say in majority

    of cases, there is thin line between the change of scope and the contractual obligation.

    Hence, as an EPC representative, one should clearly identify and discriminate the

    activities which are out of project scope. Also, it is imperative that the cost claims are

    put forward in legitimate formats and with legal arguments. (Savage, 2012)

    When we identify the variations in the scope and not take up the claims in a correct

    manner that the efforts may go in to vein. Hence, various recommendations from FIDIC

    for handling the claims were studied and identified as pa part of the research. However,

    there are no specific recommendations made in the report for the FIDIC literature review

    as it is assumed that the professional project management practice includes the

    contract management skills. (Savage, 2012)

    It is important learning that the effective contracts management as a part of project

    management is essential to ensure that the cost claims are protected. It is important to

    write change orders and claims in clear and unequivocal terms. It is important to avoid t

    hint or insinuate. Effective record keeping can assist EPC contractors to prove their

    entitlements and enable to accurately ascertain their positions in the event that a

    dispute arises. (www.out-law.com, 2011)

    Various reports on the similar lines from the competitors companies will be requested

    and reviewed. Research work related on similar problems carried out by some other

    companies, consultants in different sector, region or industry shall be cited for preparing

    the basis. As the problem related data within company is available in abundance; more

    focus was given to it.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    27/106

    24|P a g e

    Various online articles on the estimation process were searched on websites and

    referred. In the PMI knowledge self Hrishikesh Karekar, PMP mentions that the Cost

    and timeline overruns are typically associated with what are referred to as forecasting

    errors or technical errors, such as imperfect techniques, inadequate data, honest

    mistakes, inherent problems in predicting the future, lack of experience on the parts of

    forecasters, and so forth. (Karekar, 2013)

    These overruns can occur at any point in the project life cycle and for a variety of

    reasons: incomplete requirements, poor design (lack of skills to manufacture the

    design), and inadequate testing. These reasons are valid and the inadequacies caused

    by these reasons can be mitigated by rigorously following many of the standard project

    management methodologies and best practices across organizations and industries.

    (Karekar, 2013)

    Various suggestions are discussed in detail for addressing the gap in estimation

    process. The recommendations were analyzed for its application in current scenario.

    While accessing the existing scenario in EPC markets, various online magazines were

    reviewed and the Project Vendor was one of them. There were interesting articles in the

    magazine and one Enhancing the EPC Efficiency was very interesting.

    Mr. P. P. Gupta, Managing Director- Techno Electric & Engineering Co. Ltd says that

    challenges are inevitable in current EPC market scenario, but the approach to the

    management of such problems will be the key to the continuous success. (Project

    Vendor, 2010)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    28/106

    25|P a g e

    Mr. Gupta further explains that the qualification criteria for project award are being

    limited to competitive pricing, the new inexperienced players winning the project at

    reduced Pricing escalates the project risk to the significant high. (Project Vendor, 2010)

    According to Mr. Susnato Sen, Project Head (Infrastructure), Tata strategic

    management group say that the major challenges to the EPC sector are:

    1) Shortage of skilled manpower

    2) Low Focus on Engineering as compared to procurement and Construction

    3) In efficient sourcing

    4) Lack of advanced Project management practice

    5) Risk management practices are not yet developed

    6) Burdened with less expected revenues and higher debt. (Project Vendor, 2010)

    The article discusses various factors that can affect the positive outcomes of the project

    or the prevailing threats to the projects success. The major one identified and

    discussed is Cost escalation. (Project Vendor, 2010)

    The article describes delay in starts and completion of the project, ambiguity in design,

    wrong methodology, lack of coordination, frequent changes and socio-economic factors

    as major influencers to the cost escalation of the project. Bad project management is

    identified as major factor for cost escalation by experts in the article. (Project Vendor,

    2010)

    The article also suggests the professional project management approach such as

    process design flow, material management, and risk assessment can significantly

    address the major cost escalation issue of the EPC project. (Project Vendor, 2010)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    29/106

    26|P a g e

    To eliminate challenges in EPC project execution, Mr. Susnato Sen expresses that that

    best-in-class project management tools and techniques need to be adopted. He also

    emphasizes on necessity to develop an in-house team of experienced professional

    project management personnel and developing more understanding of expert

    engineering design, particularly for complex technology EPC projects. One of the

    important suggestions by Mr. Sen in this context is to set up internal project

    management and Engineering Management teams and factor in required time along

    with a need to create a risk assessment /management team for large EPC projects.

    (Project Vendor, 2010)

    It was important to indicate the quantitative figures and facts that can demonstrate the

    negative impact on the project. Various online data and previous research projects were

    reviewed to judge the quantitative aspects. It is important to note that no clear band can

    be defined for cost escalations and experiences have taught us that the cost escalations

    can go up to 50% of the original cost depending upon the nature of the project and EPC

    execution capabilities. (The Construction Industry Institute)

    The Power Engineering magazine was reviewed for various types of contracts for the

    understanding of the risk distribution between the owner and the EPC contractor. The

    article describes the various approaches in EPC contract award and its estimation

    processes. The article clearly says that the lump sum turnkey EPC with Firm Fixed

    Price could be the most costly contracting approach and the majority of the risk lies with

    the EPC contractor. (Power Engineering)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    30/106

    27|P a g e

    FINDING AND ANALYSIS

    The design change notes and the cost variations reports are major issues that spoil the

    day. Cost overruns are difficult to justify and when we analyze them, we understand that

    the time has already passed to correct or reverse those mistakes. They mostly come as

    result of some actions taken or not taken in to the project engineering stage. On the

    same lines, I decided to go ahead with my dissertation project and determined to

    capture those cost escalations during the detail design stage of the EPC project.

    The research started with the understanding that the majority of the cost escalation

    came from the detail engineering stage. As we started analyzing the past project data,

    industry cases and discussing in the expert forum we came to learn an important

    opinion about root causes of cost escalation issues, which was different than the basic

    understanding. When analyzed in detail, the cost escalation issues for its root causes,

    an important learning came out and that says, for many cases the roots of the cost

    escalation lies with the estimation or the bidding stage of the project.

    The project scope was extended for the bidding stage analysis as the cost escalations

    arising at detail design stage cannot be seen in isolation. It was evident in personal

    interviews and the Focused group discussions that the majority of industry expert

    believe that major cost escalations come from the bidding stage. The complete research

    work then was divided in to two areas,

    1. Cost escalations originating from bidding stage.

    2. Cost escalations origination from Detail design stage.

    Result of the online survey reinforced our understanding that the majority of cost

    escalations come from bidding stage.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    31/106

    When a

    Accordi

    Please

    originat

    (Procur

    Majority

    The ch

    Focuse

    the exp

    Professi

    details

    sked-

    g to you

    see any

    s...

    ment and

    of the res

    llenge wa

    group di

    erts all ov

    onals grou

    f the discu

    hich area

    ost escal

    constructio

    ondents v

    s to identi

    cussion o

    r the EP

    p with mo

    ssions are

    ontributes

    tion from

    n are not i

    igure 6 - P

    Figure 7 -

    ted the Bi

    fy the cos

    LinkedIn

    sector.

    e than 28

    available i

    the most f

    its root

    cluded as

    roblem Are

    roblem Ar

    ding stag

    t escalatio

    website re

    he surve

    00 memb

    Appendix

    r EPC pro

    ause poi

    part of the

    a Graph

    ea Data

    as more r

    n factors

    ceived a t

    was laun

    rs associ

    - 03.

    ect cost e

    t of view

    survey)

    esponsible

    nd its ro

    emendous

    ched in E

    ted with E

    28|P

    calation?

    from whe

    .

    t causes.

    response

    C Consul

    PC sector.

    a g e

    re it

    Our

    from

    ants

    The

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    32/106

    The key

    listed b

    factors id

    low:

    1. Sele

    2. Short

    3. Inacc

    4. Insuf

    5. Skills

    6. Biddi

    7. Abse

    8. In ad

    9. Insuf

    10. Impr

    11. Impr

    12. Over

    13. Too

    14. Ignor

    Figure 8 -

    ntified for t

    tion of bid

    bidding ti

    urate FEE

    icient revi

    of Estimat

    ng complet

    nce of less

    equate Ris

    icient conti

    per bid co

    per FEED

    ptimistic f

    any appli

    ing and po

    GD Online

    he cost es

    without ev

    e

    w of ITT d

    ion Team

    ely new se

    ons learnt

    k analysis

    ngency re

    rdination/

    verificatio

    asibility

    able stand

    r assumin

    Discussio

    alation in

    luating its

    cuments

    ctor

    rom previ

    erve

    anageme

    ards

    g of non-m

    Page on L

    idding sta

    SWOT

    us project

    nt

    aterial cost

    inkedIn

    ge of EPC

    s.

    29|P

    project are

    a g e

    as

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    33/106

    30|P a g e

    As a result of the online survey,

    Inaccurate FEED,

    Skills of Estimation Team and

    Improper FEED verification

    are identified as top 3 factors.

    Table 3 - Cost Escalation Factors at bidding stage

    Inaccurate FEED3.86

    Skills of Estimation Team3.84

    Improper FEED verification3.72

    Insufficient review of ITT documents3.64

    Selection of bid without evaluating its SWOT3.63

    Bidding completely new sector3.62

    In adequate Risk analysis

    3.59

    Short bidding time3.57

    Overoptimistic Feasibility Study3.56

    Absence of lessons learnt from previous projects3.55

    Ignoring and poor assuming of non-material costs3.54

    Improper bid coordination/management

    3.40

    Insufficient contingency reserve3.31

    Too many applicable standards3.03

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    34/106

    The low

    I

    I

    When a

    manage

    The res

    F

    T

    Answer

    Estimation

    Engineerin

    Estimation

    Engineerin

    Business

    Contracts

    est contrib

    proper bi

    sufficient

    oo many a

    sked- Whi

    ment (avoi

    lts were

    igu re 9 - In

    able 4 - Infl

    hoices

    /proposal man

    g Discipline L

    leads

    g manager

    evelop Mana

    anager

    tors are id

    coordinat

    ontingenc

    pplicable s

    h role do

    d cost esc

    luential po

    uential pos

    ager

    ads

    er

    entified ar

    ion/manag

    reserve a

    andards

    you think i

    lation) at t

    sition at bi

    ition at bid

    :

    ment

    nd

    s the mos

    e estimati

    ding stag

    ding stage

    pivotal (I

    on stage?

    for Cost E

    for Cost Ef

    fluential) i

    ffectivenes

    fectivenes

    Res

    3

    1

    1

    1

    7

    4

    31|P

    n effective

    s

    ponses

    .02%

    .70%

    .07%

    .82%

    .32%

    .07%

    a g e

    cost

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    35/106

    32|P a g e

    Majority of the opinion said that the Estimation/Proposal Manager has the highest

    influence over the cost escalation and the contracts manager has the lowest.

    The key factors identified for the cost escalation during detail design stage of EPC

    project are as listed below:

    1. Improper change management

    2. Poor Risk Management

    3. Different team for estimation and detail design

    4. Poor coordination between Lead engineers

    5. Poor Coordination with Client/PMC

    6. Realizing of unstated requirement in Bid

    7. Improper multidisciplinary/internal review of documents

    8. Engineers biased to high tech products

    9. Over specifying (Gold plating)

    10. Incapable project manager

    11. Interference of client Operation/production team

    12. Scope creep due to detail studies (Hazop/QRA etc.)

    13. Client/PMC with highly wishful thinking

    14. Client/PMC delaying disputes, decisions and reviews

    15. Technically weak Client PMC team

    16. Engineering subcontractor delays

    17. Cost Insensitive Engineering Subcontractor

    18. Manpower shortages

    19. Frequent changes in Engineering team

    20. Inexperienced engineering team

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    36/106

    33|P a g e

    As a result of the survey the top five factors identified are:

    Inexperienced Engineering team

    Incapable project manager

    Improper change management

    Client/PMC delaying disputes, decisions and reviews

    Frequent changes in Engineering team

    Table 5 - Top Factors at the Detail Design stage

    Inexperienced engineering team3.94

    Incapable project manager3.90

    Improper change management3.79

    Client/PMC delaying disputes, decisions and reviews3.79

    Poor Coordination with Client/PMC3.69

    Frequent changes in Engineering team3.69

    Cost Insensitive Engineering Subcontractor3.62

    Improper multidisciplinary/internal review of documents3.60

    Engineering subcontractor delays3.57

    Scope creep due to detail studies (HAZOP/QRA etc.) 3.55

    Poor Risk Management3.54

    Realizing of unstated requirement in Bid3.54

    Client/PMC with highly wishful thinking3.51

    Poor coordination between Lead engineers3.46

    Over specifying (Gold plating)3.46

    Interference of client Operation/production team3.41

    Manpower shortages3.39

    Technically weak Client PMC team3.31

    Different team for estimation and detail design3.28

    Engineers biased to high tech products3.09

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    37/106

    The low

    Wheman

    The

    Table 6

    Engineeri

    Project M

    Engineeri

    Project C

    PMC

    Risk man

    est 3 influe

    echnically

    ifferent te

    ngineers b

    n asked-agement (

    results are

    Most Pivo

    ng manager

    anager

    ng discipline

    ntrols mana

    ager

    ncers are:

    weak Clien

    m for esti

    iased to hi

    hich rolevoid cost

    tal (Influent

    Leads

    ger

    Figure 1

    t PMC tea

    ation and

    h tech pro

    o you thinscalation)

    ial) role at

    0 - Top Infl

    detail desi

    ducts

    is the moat the Det

    Detail Desi

    uencer in E

    n

    st pivotal (Iil Design s

    gn Stage

    stimation

    nfluential)tage?

    32.50

    27.50

    23.33

    10.83

    3.33

    2.50

    tage

    34|P

    in effective

    %

    %

    %

    %

    a g e

    cost

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    38/106

    35|P a g e

    The majority believed that the Engineering Manager, Project Manager and Discipline

    Leads are the key influencers to the cost escalations.

    The research is intended for the resolution to the problem; hence it is import to judge

    that what are the influential factors that contribute to effective cost management of

    the project?

    When asked- Please rate below parameter on the scale of 1-5 that can

    improve/avoid cost escalation. (1 lowest, 5 highest)

    Table 7 Top Parameters for improv ing cost escalation

    Strict project design change management system3.98

    Implementation of proper Project management practices. 3.81

    Careful Selection of Bid after proper evaluation.3.76

    Implementation of proper Risk management practices.3.71

    Cost/Budget awareness programs.3.71

    Focus on motivated Team to execute the Jobs.3.71

    Emphasis on learning from past projects.3.68

    Emphasis of capturing and review of lessons learnt. 3.63

    Continuous focus on Learning and Growth.3.46

    Implementation of Award and Recognition program3.22

    The top 3 factors were

    Strict project design change management system

    Implementation of proper Project management practices.

    Careful Selection of Bid after proper evaluation.

    The least important factors were:

    Continuous focus on Learning and Growth.

    Implementation of Award and Recognition program

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    39/106

    The re

    project.

    The nor

    Strengt

    Careful

    selectio

    bid in t

    experie

    reputati

    propose

    decisio

    The tim

    date ext

    be det

    Compa

    ort recom

    mal EPC p

    hen the Bi

    bid selecti

    of projec

    rms of E

    ce in sect

    n shall b

    d PMC c

    .

    allowed t

    ension is q

    rmined b

    y.

    Phase

    Ph

    ends foll

    roject phas

    d selectio

    on can le

    t for biddin

    C Contra

    r, comple

    e evaluate

    nsultant b

    o bid is ver

    uite comm

    sed on

    1Tender

    se2Esim

    Phase3

    Phase

    Ph

    RECOM

    wing mai

    es are as il

    process

    d to avoi

    g shall be

    tors expe

    ity and sc

    d. Contra

    y the Co

    y importan

    on in EPC

    tatistical

    Reviewa

    ationpro

    etailDes

    4Procur

    ase5Co

    MENDA

    action pl

    lustrated b

    at phase -

    ance of l

    selected b

    rtise in pr

    le of the p

    tors past

    pany sha

    t factor. It i

    sector. He

    methods

    ndappro

    cess

    gnonaw

    mentse

    struction

    IONS

    ans for th

    elow for e

    1

    ss of tim

    ased on p

    cess tech

    oject. The

    experienc

    ll be eval

    s well kno

    ce, an est

    nd previ

    al

    ard

    vices

    services

    Estimati

    sy underst

    and effo

    roper asse

    nology, G

    nature of t

    e in hand

    ated prior

    n that the

    imate of bi

    us experi

    36|P

    n stage o

    anding.

    ts. The c

    ssment of

    ographic

    e client a

    ling the c

    to Go/No

    bid submi

    ding time

    ence with

    a g e

    the

    reful

    EPC

    rea,

    d its

    lient,

    GO

    sion

    shall

    the

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    40/106

    37|P a g e

    Preliminary review of the FEED content shall be carried out by the select team of

    expertise from Contracts, estimation and Engineering for its completeness.

    Comprehensive SWOT analysis needs to be done and shall form the basis of Go/ No

    Go for the project.

    Implementation of Risk Management Process at phase - 2 to 5

    Proper Risk management practices shall be implemented in both bidding and detail

    design phase of the project. In fact the process shall be extended for the entire project

    life cycle. Qualitative and quantitative risk identification tools and techniques may be

    included as per the nature of the project. All risks, may it be smallest and have lowest

    impact shall be captured and evaluated for its avoidance, transfer, acceptance and

    mitigation. A comprehensive risk register shall be a must requirement.

    A proper Risk data quality assessment, risk categorization, risk urgency assessment

    and continuous update of risk register shall be implemented. Identified risks and its

    triggers shall be well documented. The ownership of the risk shall be distributed to

    project personnel for continuous monitoring and update of the risk register.

    Professional Project management approach for not only execution but to Bid

    stage at phase - 2 to 5

    There is no doubt that companies implementing professional project management

    during project execution achieve higher rate of success. However, the bid estimation

    stage is executed in traditional way. The bid estimation shall be considered as a project

    itself. A complete project management practice shall be applied in carrying out the

    project Bid. All five process groups and various processes as documented and guided

    by PMBOK shall be considered with appropriate selection and tailoring of the project

    management processes.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    41/106

    38|P a g e

    Each phase of the estimation process and lessons learnt, assumptions shall be

    captured and documented so that it can be passed on to the execution team for post bid

    works. Clear-cut project baselines in terms of schedule, cost and quality shall be

    defined and issued for execution.

    Implementation of scope identification and scope definition with help of detailed FWBS

    (Functional Work Breakdown Structure) shall be practiced and the bottom-up estimation

    shall be used. Apart from above methods, tools like analogous estimation, parametric

    estimation and reserve analysis shall be used to achieve correct rough order of

    magnitude. It is important to remember that the estimation being short-time process

    may not allow the estimation to be accurate to the extent of +/- 10%. Hence the reserve

    analysis and cost of quality like tools shall be employed as required.

    Use of software based estimation shall be considered to avoid manual errors.

    Many organizations have different teams for estimation and execution processes. These

    results in loss of information and knowledge gathered during the bidding process. Key

    personnel for bidding team shall form the part of EPC execution and shall be made

    responsible for capturing cost at early stage.

    The company shall look in to the possibility to reduce the number of design changes by:

    1. Comprehensive project scope definition.

    2. Interdisciplinary reviews with affected stake holders and

    3. Implementing processes to limit scope modifications. (Construction Industry

    Institute, 2013)

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    42/106

    39|P a g e

    The rotation of few members of bidding team and EPC execution team has been found

    to be a useful concept. By doing this as the knowledge of execution problems can be

    well covered in both bidding and execution stage.

    Development of Skil led Estimation team at phase - 1 & 2

    Estimation being short time period process needs higher level of experience. A team of

    experienced engineers mainly from detail engineering background shall be made lead

    for engineering team.

    Concepts of value engineering and innovative approach are must for acquiring the

    competitive advantage over other bidders. An alternate bid with improved functionality

    and reduced cost can outperform the competitors. Careful material selection, optimized

    quantities, proper FEED endorsement, innovative construction methodology, optimized

    man power deployment plan, effective scheduling techniques along with

    detailed/improvised technical documentation at bid stage can reduce the cost escalation

    risk for the EPC contractor.

    Learning and development are important factors for skill development. Vendor

    presentations, Technical seminars, new products, innovative hardware and construction

    technology are important factors that can bring competitive edge in bidding process.

    The report recommends following main action plans for the Detail design stage of the

    project.

    Implementation of Strict Change management system at phase - 3

    While execution stage, most of the documents are developed based on the given FEED

    documentation. Clear baselines in terms of scope, cost and schedule are inputs to the

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    43/106

    40|P a g e

    execution process. While developing the detail design it is important that any change is

    identified and captured at the first/generation stage. All updates, changes, upgrades,

    improvements, detail design, addition, reduction in whatever name it comes shall be

    compared and identified as change and shall be registered in the change register.

    Any change shall be evaluated for its necessity and impact on the project output. If the

    change is agreed to be necessary or unavoidable, shall be routed through its implication

    review. The ROM shall be made and determined if the change comes from the client or

    as a result of detail design.

    Only execute the change that is agreed and approved by project Change management

    committee.

    In the below section, the research process have tried to explain the proposed Change

    management process that can be implemented in order to manage the project changes

    effectively. The basis of the design is based on expert judgment and experience gained

    in past.

    Step-1

    The change management process starts with the identification of change/deviation

    event. This is broadly called as initiate change. The variation or the deviation shall be as

    compared to baselines (Cost/scope and schedule)

    Responsibility: Any project team member.

    Time frame: 1 to 2 days

    Output: Intimation to Project controls department.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    44/106

    41|P a g e

    Step-2

    Register the change description in to project change register/log or IT enabled Change

    management system. Minimum assignments are change number and its Type.

    The Change types can be classified as following:

    Client initiated (scope/schedule and reimbursable cost escalation)

    EPC in-house (value Engineering/ detail Development/ deviation/ baseline shift)

    Output: intimation to Change control Board with change intimation form.

    Step-3

    The change control board shall take the decision on whether to proceed with the

    deviation. It is important while analyzing such trends/changes that the project cost,

    scope and cost baselines shall be evaluated for impact of changes.

    If the decision is made in favor of the change, then the Rough order of magnitude

    ROM estimate shall be prepared and all impact report shall be prepared. The

    proposed changes shall be conveyed to the stakeholders including the client as

    appropriate. Proceed to step-4.

    If the change management board thinks that the change shall not be processed,

    it will advise the project team to develop the mitigation plan. The Change register

    shall be updated for the outcome and the concerned team members shall be

    informed for rejection.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    45/106

    42|P a g e

    Step-4

    If the change is Client dependent or initiated by client requirement, then the change

    approval shall be taken-up with client for approval for its impact on cost, schedule and

    scope baselines. If not, then proceed as in-house change.

    Detailed estimate on Cost, schedule and scope shall be prepared by project

    controls with the help of project management team. The help of Engineering,

    procurement, construction and estimation team may also be taken for arriving on

    definitive estimate. The impact on the project based on definitive estimate shall

    be evaluated for the feasibility and viability. If satisfactory, the Completed

    definitive estimate irrespective of client originated or in-house changes shall be

    submitted to client for final approval.

    Step-5

    The estimate, discussions and negotiations with Client and the project management

    shall continue and shall be iterative until the agreement for approval or rejection is

    reached.

    If not agreed by client, appropriate mitigation plan shall be prepared by the

    project team. The change register shall be updated for the outcome. Concerned

    team members shall be informed.

    If agreed by the client, and if the change is client initiated, official change order

    shall be signed. The change register shall be updated for the outcome. Project

    team shall be informed to execute the approved changes.

    Only agreed change order shall be processed for execution. Reconcile the Cost,

    scope and schedule baselines with execution plans.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    46/106

    43|P a g e

    The potential Change Notice Form being first important step in the process, following

    important fields shall be included in the form as minimum.

    1. Project Change order number

    2. Client name

    3. Project name

    4. Location

    5. Project ID

    6. Date initiated

    7. Discipline engineer

    8. Discipline Lead

    9. Description of potential change notice

    10. Possible Cost impact on Project (Yes/No)

    11. Possible Scope impact on Project (Yes/No)

    12. Possible Schedule Impact on Project. (Yes/No)

    13. Requesting person

    14. Reason for change

    15. Other disciplines affected

    16. Impact if the change is not implemented.

    17. Source (Client change/ in-house change)

    18. Approval (prepare ROM/ reject)

    19. Comment note

    20. Approval authority

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    47/106

    44|P a g e

    Human recourse plan for all Phases of project life cycle.

    Companies relying on qualified personnel are more insulated from the risks.

    Qualified and certified executives with right experience implementing the project can

    drastically change the project outcomes. Researchers have found that the certified

    project managers, Estimation managers and Engineering Managers are vital influencers

    in avoiding the cost escalations

    The process starts with the comprehensive human resource plancareful selection of

    Qualified, certified and well experienced personnel is a first step in process

    A comprehensive performance review and reward system needs to be developed in

    order to retain the key people for the success of the project. There should be incentive

    for Lead engineers to stay with company for specified period as the lead engineers

    leaving in-between the project can significantly hamper the process.

    Skill development for engineers and technocrats can be an important tool that can uplift

    the talent pool for the company. Regular technical trainings and technical participations

    can bring positive results.

    Companies build on its expertise bay carrying the experiences and lessons learnt from

    one project to the next. The right mix of young graduates and long-term employees play

    major role in the process improvements and provide backbone for innovation in order to

    achieve the strategic advantage over the competitors.

    A comprehensive learning management concepts including, process mapping, goal

    setting, balance score cards, 360 degree appraisal process, Team building and internal

    customer satisfaction shall be inducted in to the system to achieve higher satisfaction

    and morale of the team.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    48/106

    45|P a g e

    MANAGERIAL IMPLICATIONS

    The research identifies various factors contributing to the cost escalation in bidding

    stage and the detail design stage of an EPC project. The key influencers identified in

    the process of cost optimizing are Estimation Manager, Project Manager and

    Engineering Manager.

    The first step in the direction will be to form a task force to for identification and

    application of researched data in to present organizational context. The task force

    members shall be selected on the bases of Qualification, certification and expertise in

    the EPC sector. Discipline engineers shall be involved. If required the external

    consultant shall be appointed.

    As a result, the company wide message can be given on emphasis on the cost

    awareness. Management can achieve its goal only with help of the employees and the

    team for the project. Concept of PMO is very important in this context. For consistency

    across the projects and achieving long terms objectives the PMO can provide trained

    project managers, processes and procedures. It can also help providing cultural

    backbone for professional EPC project management.

    The additional man hour costs for the above activities shall be tracked and mapped as

    cost of Quality and cost of prevention. It is important to remember that above

    recommendation increases the overhead expenses of the company. The cost of

    prevention shall be much lower than the cost of defect repair.

    The second step is to collect the organizational process maps. Identification of list of

    important process maps shall be developed and compared with the existing processes.

    If required the new process maps shall be drafted.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    49/106

    46|P a g e

    It shall be ensured that all critical activities are cover by one or multiple process maps.

    Each cost escalation factor identified in the research shall be applied to the existing

    process/processes. Separate checklist based on the for Estimation, Project

    management and Engineering management shall be prepared.

    Cost awareness, tight project control and effective project management are more of

    organizational culture and team work than the demonstration of individual skills. In the

    process, it is important that decisions are taken in favor of companys stated interest of

    effective EPC project execution efficiency based on procedures and not individual

    capacity. The project management team needs continuous guidance from the

    organizational process assets and even the lowest hierarchy of the project team is able

    to take appropriate decisions based on the company guidelines, without waiting for

    higher-ups.

    As recommended, the strict project change control system shall be implemented so that

    only the approved changes are implemented, Concerns are addressed, unnecessary

    work and consequent rework can be avoided. The most important achievement of the

    process is no surprise. All potential deviations and changes are identified at the initial

    stage and not when the consequences are out of control. This will also avoid burden of

    cost overrunning and budget constraints on project management team, increasing

    morale.

    The focus shall be

    1. To identify any change at the earliest stage of the project.

    2. Identified change shall be immediately reported to Change management system.

    3. Thorough review and approval of Change.

    4. Execution of approved changes only.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    50/106

    47|P a g e

    It is assumed that the Risk management activities are carried out by the Project

    Manager and Estimation Manager. If this is not the case, Risk manager shall be actively

    involved in the project.

    Specially, at the estimation stage, risk register shall be initiated with the inputs from all

    concerned disciplines. Careful consolidation of risk register is important. Once the risks

    are identified, logged and consolidated, adequate contingency reserves shall be

    proposed in addition to project costs. The same risk register shall be handed over to the

    project risk manager for tracking and further updating. The advantage is that the project

    manager is aware in advance for envisaged and considered project risks and its

    triggers. A very common scenario in the project execution time that the risk has realized

    and there is no plan or contingency reserve provision for it can be avoided.

    The Human resource management needs to be involved for devising the mechanism to

    recruit, train and retain the project staff. The average cost salary of certified Project

    manager or Risk Manger will be 10-15% more. The retaining costs of the qualified

    people are also higher. However the value buy-in is in multifold.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    51/106

    48|P a g e

    THE WAY FORWARD

    From the analysis of secondary and primary research results I am able to identify and

    analyze the list the cost escalation factors in EPC sector and especially for EPC

    contractors.

    The most important factors and influential parameters are identified in the research. A

    proposed way of resolving the one of the major factors- Change management plan is

    illustrated in the project report. The first thing that needs to be looked in is the existing

    Change management process. The process needs to be reviewed for fulfillment of its

    intended purpose. If required, needs to be updated or revised to the desired level. The

    work shall be accomplished within 2 weeks time. Once approved by management, the

    Change management process shall be mandated to all existing projects. A special

    introduction of Change management plan through trainings, seminars and focused

    Group shall be discussed among the project teams. Within 2 month the process shall be

    operational. A careful monitoring shall be carried out specially for initiating the change

    requests.

    Parallel to above, based on the organizations present situation, the process maps

    related to Estimation and Engineering processes needs to be revisited and the

    adequate check points needs to be ensured in the process. This process takes around

    4 to 8 weeks time or 4-8 months based on preparedness and maturity of the

    organization for its process assets. If required separate checklists shall be prepared and

    implemented across the projects. Since the estimation process is shorter in time as

    compared to Detail design, a special care shall be taken in designing the checkpoints

    ensuring that the check points do not make the process sluggish.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    52/106

    49|P a g e

    Organizations which does not have formal process maps for those activities, may start

    developing the check list as a quick tool to ensure that the cost escalation factors are

    not ignored and in fact captured at the initial stage. Companies can look for IT based

    solutions to reduce the human errors.

    Strict implementation of professional project Management and Risk management

    practices shall be emphasized. The recruitment process shall be updated for more

    focus on right mix of Qualification and experience while selecting the project team.

    A comprehensive skill development and rewards/recognition system to be initiated to

    retain the talent pool of the organization.

    The recommendations need strong management support for implementation.

    The research work was primarily carried out for the Estimation/ bidding stage and detail

    design stage of the EPC project. The EPC sector has two more major phases that

    consumes majority of project budget. Though the activities carried out in procurement

    and construction is based on specifications, drawings and guidelines generated from

    the engineering stage, it has its own area where there is risk of the cost escalation. This

    research being time bound and for academic purpose, limited its scope to Bidding and

    Engineering stage only. Management may take the further decision to promote carrying

    out further research in the area of procurement and Construction of the projects.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    53/106

    50|P a g e

    The time line for implementation of the Implementation process is advised as below.

    Activi tyResponsible

    Function

    Key responsible

    personDuration

    Review and update of existingChange management system

    PMO Head PMO

    2 weeks

    Implementation of Change

    management system

    Project

    ManagementProject Manager

    1 month

    Process mapping for Estimation

    and Engineering processes

    Engineering /

    Estimation

    Discipline

    Manager

    1 to 8 Months

    Implementation of engineering

    checklistsEngineering

    Engineering

    Manager

    3 months to 1

    Year.

    Development of Skill

    development programHuman Resources

    HR Manager/

    Discipline

    Manager

    3 moths

    Development for reward and

    recognition systemHuman Resources HR Manager 3-4 months

    Preparation and implementation

    of Training calendarHuman Resources

    HR Manager /

    Discipline

    Manager

    6 Months

    Start further research on

    Procurement and construction

    phase for identifying the cost

    escalation issues

    Management CEO 1 Year.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    54/106

    51|P a g e

    CONCLUSION

    The cost escalation issues can be effectively handled by EPC organizations at the early

    stage of the EPC projects, mainly during the estimation and detail engineering stage by

    implementing Professional Risk Management and Project Management practices. Early

    identification and definition of cost triggers can be punched in project risk register and

    actively monitored by the project management team during the project life cycle.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    55/106

    52|P a g e

    Bibliography

    Besterfield, D. H., Besterfield, C., Besterfield, M., Besterfield, G., Urdhwareshe, H., &Urdhwareshe, R. (2011). Total Quality Management (3rd ed.). India: PearsonEducation.

    Chandra, P. (2009). Projects (7th ed.). Tata McGraw-Hill.

    Construction Industry Institute. (2013, Jan 1). Retrieved from Construction-Institute:https://www.construction-institute.org

    Dodsal E & C Pte. Ltd. (2012). Risk Management. Procedure, Dodsal E & C Pte. Ltd.,HSEQ.

    Dodsal E&C Pte. Ltd. (2013, February 2). Engineering, Procurement & Construction-The Dodsal Group. Retrieved December 2013, from The Dodsal Group Website:http://www.dodsal.com/enc/

    Ernst & Young Pvt. Ltd. (2011). Engineering, Procurement and Construction (EPC)-Drivig Growth Efficiency. ASAPP Media Information Group.

    Galway, L. (2004). Quantitative Risk Analysis for Project Management-A CriticalReview. RAND Internal Research and Development (IR&D) project, RAND Corporation.

    http://au.news.yahoo.com. (2013). south korean builders brace for losses as overseasprojects go sour. Australia. Retrieved 2013, from http://au.news.yahoo.com/latest/a/-/latest/16831607/south-korean-builders-brace-for-losses-as-overseas-projects-go-sour/

    https://enr.construction.com. (2013). The Top 400 Contractors. Engineering News

    Record.

    IBM Business Continuity and Resiliency Services. (2009, January). Business resilience:The best defense is a good offense. 6.

    Karekar, H. P. (2013, February 25). Reducing the Estimation Gap. Knowledge Shelf-PMI .

    MEED. (2012). Wasit delay a new challenge.

    MEED: Middle East news, data and analysis. (2012, November 15). Retrieved fromMEED: http://www.meed.com

    Middle East Business,Financial and Investment News. (2012, Jan 25). Retrieved fromZawya: http://www.zawya.com/

    Moore, M. (2008, March 19). Seattle Contractors Struggle To Cope With CostEscalation that Adds Risk. Retrieved Jan 12, 2013, from http://enr.construction.com/:http://enr.construction.com/features/bizLabor/archives/080319e.asp

    Mulcahy, R. P. (2009). PMP Exam Prep (Sixth ed.). USA: RMC publications, Inc.

  • 7/28/2019 Engineering Cost Escalations Project Report.pdf

    56/106

    53|P a g e

    Oil & Gas Middle East. (2012). Top EPC Contractors.

    Power Engineering. (n.d.). www.power-eng.com/artproject contracting strategiesevaluating cost risks and staffing req


Recommended