NSF Engineering Research Center for Recongurable Manufacturing Systems University of Michigan College of Engineering 1 The University of Michigan, Ann Arbor Engineering Research Center for Recongurable Manufacturing Systems Virtual Fusion: The Complete Integration of Simulated and Actual William Harrison, Graduate Student James Moyne, Associate Research Scientist Dawn Tilbury, Professor January 14, 2008
Transcript
Page 1: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

1

The University of Michigan, Ann Arbor

Engineering Research Center for

Reconfigurable Manufacturing Systems

Virtual Fusion: The Complete Integration of Simulated andActual

William Harrison, Graduate StudentJames Moyne, Associate Research Scientist

Dawn Tilbury, Professor

January 14, 2008

Page 2: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

2

Demonstration

• Run the Reconfigurable Factory Testbed with nosimulated parts

• Replace an entire cell

• Add a cell to the existing infrastructure

• Monitoring

Page 3: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

3

Inefficient Robot Throughput Low

Cell and Component Swapping in the RFT

Part

Motoman DA20

• 20kg payload/arm

• 13 dof

• “Jigless” operation

Page 4: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

4

DEMO: Robot Swapping in the RFT

System Level Controller

CNC

CNC robot

Cell 2

Controller

Conveyor

Conveyor

Controller

CNC

CNCrobot

Cell 1

Controller

Supply Cellcontroller

Gantry

Page 5: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

5

Supply Cell : Adding a New Cell

• Replace existing manualpart loading station withnew automated system– Example: Overhead gantry

setup

– Simulating the hardwareand the PLC software

Page 6: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

6

Conveyor

CNC

CNC

CNC

CNC CNC

CNC

Hybrid Process Simulation: Normal Process

CNC

Conveyor

CNC

CNC

Hybrid Process Simulation: Hardwired SimulationHybrid Process Simulation: Hybrid ModeHybrid Process Simulation Extension: Monitoring

CNC

Page 7: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

7

Cyber-Physical System Integration

• Large amounts ofavailable datanecessitates state of theart interface– Desktop

– 3D Geowall

• Wide Scale Monitoring– In Plant (game engine)

– World Wide (2nd Life)

Page 8: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

8

END

Page 9: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

9

Presentation Outline

• Problem

• Task and Purpose

• Virtual Fusion and Hybrid Process Simulation• Objectives, Deliverables, and Benefits• Application of Hybrid Process Simulation Methodology• Simulation and Modeling• Reality Science• Future Plans• Demo

Page 10: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

10

Problem: Cost (Ramp Up Time and Change OverTime can always be better)

• Simulation models are sometimes inaccurate

• Expensive to develop

• Centralized in one program and one simulationcompany

• Simulation models go unused after planning

Page 11: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

11

Task and Purpose

• Task: Reduce Cost by decreasing ramp up andchange over time

– Finding better ways to integrate simulation into thedevelopment process and throughout the product lifecycle

• Purpose of Presentation

– Show the technical developments on the ReconfigurableFactory Testbed

– Briefly introduce intellectual contributions thus far

Page 12: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering # 12

Virtual Fusion: The Complete Integration of Simulated and Actual-Ongoing (Fall 06) ; Core Project; 1 Student; GM Partner

• Objectives

– Develop HILS methodology

for logic control verification

and validation

– Pre-launch validation,

online monitoring and

operator training

• Key Deliverables

– HILS tools and logic validation survey (CASE 2007)

– HILS implementation on ERC-RFT

– Methodology on use of HILS for logic validation

– Solution for HILS use in monitoring and operator training

• Benefits to Industry– Understand state-of-the-art of HILS in auto manufacturing

– Reduce launch time and downtime due to unanticipated behavior

– Provide platform for testing difficult-to-simulate components

Page 13: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

13

Inefficient Robot Throughput Low

June 2008 Demo: Cell Swapping in the RFT

Part

Motoman DA20

• 20kg payload/arm

• 13 dof

• “Jigless” operation

Page 14: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

# 14

Supply Cell : Adding a New Cell

• Replace existing manualpart loading station withnew automated system– Example: Overhead gantry

setup

– Simulating the hardwareand the PLC software

• Current status: VirtualCell is completed andintegration is beingtested

Page 15: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

# 15

Fanuc Roboguide Integration

• Leverage Fanuc’s existing

simulation software for

system validation

• Roboguide: Fanuc’s robot

simulation software

– Same interface as real robot

– Execute actual program and

confirm motion path and logic

– Highly accurate simulation of

movement and application

commands

Page 16: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

# 16

• Virtual world reflects

real time “ground truth”

of the plant floor

• Improved information

visualization leads to

better understanding of

system operation, rapid

fault diagnosis and

reduced downtime

Monitoring System Real Time Data

Page 17: Engineering Research Center for gurable Manufacturing ...€¦ · operator training • Key Deliverables ... Fanuc Roboguide Integration • Leverage Fanuc’s existing simulation

NSF Engineering Research Center for Reconfigurable Manufacturing SystemsUniversity of Michigan College of Engineering

# 17

Milestones and Future Plans

June 2008

Nov 2009

Dec

2008

May 2009

• Motoman Cell Level Swap

• Robot Emulator Validation

• Supply Cell Addition

• Fanuc Low-Level Simulation Integration

• Methodology for Validation by Swapping

• Methodology for Evaluating System Fidelity

• Monitoring System Implementation on RFT

February 2007