+ All Categories
Home > Documents > Environental Restoration at the Grand Calumet East Branch

Environental Restoration at the Grand Calumet East Branch

Date post: 01-Jun-2018
Category:
Upload: sweet-water
View: 216 times
Download: 0 times
Share this document with a friend

of 33

Transcript
  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    1/33

    Welcome

    Environmental 

    Restoration 

    at 

    the 

    Grand Calumet

     

    River’s 

    East 

    Branch

    Eric 

    Hritsuk, 

    PENatural Resource Technology, Inc.

    Clean Rivers, Clean Lake Conference

    Milwaukee, Wisconsin

    April 

    30, 

    2015

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    2/33

    Great 

    Lakes 

    Legacy 

    Act 

    (GLLA) 

    of  

    2002

    •   Accelerate the pace of  sediment remediation 

    at Areas

     of 

     Concern

     (AOCs)

     •   2008 Reauthorization includes habitat restoration

    •   Use partnerships as an innovative approach 

    to conducting

     sediment

     remediation

    •   Delist AOCs by removing beneficial use impairment (BUI)

      At 

    least 

    35% 

    of  

    project 

    costs 

    from 

    non‐

    federal sponsor

    •   USEPA provides up to 65%

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    3/33

    Approaches for Generating Non‐

    Federal Cost

     Share

    •   Linking waterfront land revitalization and 

    sediment 

    cleanup 

    efforts•   Combining brownfield revitalization and 

    contaminated sediment remediation

    •   Establishing public‐private partnerships

    •   Establishing a non

    ‐federal

     coalition

    •   State bond programs

    •   In‐kind services

    •   Settlement agreements

    •   Clean Water state revolving funds

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    4/33

    GLLA 

    Goals

    Remediation  Restoration  Revitalization

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    5/33

    Environmental Benefits 

    of  GLLA

      Higher 

    quality 

    habitat 

    for 

    fish 

    and 

    wildlife

    •   Better water quality

    •   Improved fishery

    •   Improved benthic habitat

    •   Reduce contaminant levels to biota

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    6/33

    Economic Benefits

     of 

     GLLA

    •   Cleaner and deeper urban waterway

      Restoration and

     remediation

    •   Increases property values 

    •   Increases recreation 

      Increases tourism

    •   Increases fishing

    •   Increases shipping

    •  Projected

     $50

     billion

     in

     restored

     benefits

     to

     the Great Lakes region (Brookings Institute, 2007)

    6

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    7/33

    Completed or ongoing 

    projects

    Great Lakes Legacy Act Projects

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    8/33

    GLLA To

     Date

    •   21 Clean‐Ups Complete or Agreements Signed

    •   ~3,000,000 cubic

     yards

     (CY)

    •   Total cost: $565 Million 

    •   Leveraged $227

     Million

     non

    ‐federal match

    •   10 years of  successful implementation under GLLA

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    9/33

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    10/33

    Project Background

    •   90% of  flow originates as municipal and industrial effluent, cooling and process water, and storm water 

    overflows 

    •   Legacy pollutants in sediments and surface water

    •   All 14 BUIs included in 1991 remedial action plan

    •   $2.1 million settlement with Hammond Sanitary 

    District in

     1999

    •   $56 million settlement with 9 responsible parties in 2001

    •   US Steel completed dredging of  800,000 cy in upper 5‐mile

     portion

     of 

     East

     Branch

     in

     2007

     and

     performed

     

    additional in‐stream restoration in 2010

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    11/33

    Project Map

      – Reaches

     4A/4B

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    12/33

    Partners and

     Stakeholders

    •   USEPA Great Lakes National Project Office 

    •   Indiana Department of  Environmental Management

    •   Indiana Department of  Natural Resources

    •   U.S. Army Corps of  Engineers

    •   U.S. Fish and Wildlife Service

    •   Shirley Heinze Land Trust

      The Nature

     Conservancy

    •   Save the Dunes Conservation Fund

    •   E.I. du Pont de Nemours and Company

    •   Resco Products Company

    •   SulTRAC (Engineer

     of 

     Record)

    •   Great Lakes Sediment Remediation•   JFBrennan, Environmental Restoration, NRT

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    13/33

    Project Goals

     and

     Objectives

    •   Remove contaminant mass in sediment

      Reduce 

    risks 

    to 

    aquatic 

    life 

    and 

    human 

    health

    •   Reduce contaminant transport to Indiana Harbor and Lake Michigan

    •   Improve water quality in East Branch Grand Calumet River and Grand Calumet River AOC

    •   Advance the AOC toward delisting thru removal

     of 

     beneficial

     use

     impairments

    •   Improve biota, fish, and wildlife habitat

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    14/33

    Major Project

     Components

    1. Remove abandoned railroad bridge

    2. Construct temporary upland support areas

    3. Excavate sedimentation basin to protect remedy from upstream contaminants

    4. Partially dredge contaminated river sediments

    5. Excavate adjacent wetlands to remove phragmites and place

     sand

     backfill

     with

     ponds

    6. Dewater sediments and treat water

    7. Offsite transportation and disposal of  dredged materials

    8. Place 

    amended 

    cap 

    over 

    remaining 

    sediments9. Restoration including planting native species

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    15/33

    Railroad Bridge

     Removal

    •   Testing and removal of  abandoned gas pipeline

    •  Removal

     of 

     ties

     and

     walkways

    •   Tested for lead based paints

    •   Disassembly of  girder sections

    •   Removal of  timber piling 

    •   Debris removal

     and

     load

     out

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    16/33

    Upland Support

     Area

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    17/33

    Installation of 

     Sediment

     Basin

      Created to provide sediment trap for upstream contaminated sediments

    •   Dredged 28,000 cy 

      4,400 ft2 sheet pile wall driven across downstream end 

    •   Raises water elevation 1 foot above normal

    •   Functions as

     a weir,

     trapping

     sediment

     behind

     it

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    18/33

    Hydraulic Dredging

    •   40,000 CY river; 82,000 CY 

    wetland

    •   Two 8” dredges with pipeline 

    and booster pumps

    •   Cutter shears for phragmites

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    19/33

    Hydraulic Dredging(continued)

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    20/33

    Water Quality Monitoring During 

    Dredging•   Real time turbidity monitoring

    •   Measure and control downstream transport of  contaminated

     sediment

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    21/33

    Geotextile Tubes

     and

     Water

     Treatment

    •   60 tubes stacked in 

    three layers 

    •   Sized to treat up to 5 

    million gallons per day

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    22/33

    Load Out

     Operations

    •   Dredged sediment and used geotextile tubes 

      Approximately 127,000

     tons

    •   Each truck bed was lined 

    •   Truck scale and tire wash

      All 

    sediment 

    was 

    trucked 

    to 

    the 

    Newton County Landfill, Indiana

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    23/33

    Marsh Excavation

    •   203,000 CY of  material excavated 

    mechanically•   Amphibious equipment

    •   Split into east and west marsh

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    24/33

    Marsh Excavation

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    25/33

    Sand Backfill

    •   Broadcast Capping System 

    (BCS)™

    •   Evenly and gently 

    distributes sand while 

    minimizing intermixing 

    with underlying

     sediments

    •   Wetlands A  – F, sediment 

    basin

    •   100,000 ton

    •   Seidner Marsh

    •   199,000 tons

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    26/33

    Reactive Cap Design

    AquaGate™ (adsorptive)Treatment

    Layer 

    Water Column

    Residual Contamination

    Armoring Layer 

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    27/33

    Sediment Capping•   River segments

    •   16,000 cy of  absorptive cap

    •   40,000 ton

     of 

     armored

     cap

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    28/33

    Ecological Significance

    •   Numerous environmental 

    stakeholders

    •   Globally rare dune and swale 

    complex

    •   Rare Species

    •   Wild Lupine

    •   Harebell

    •   Fringed Gentian

    •   White Indigo

    •   Blazing Star

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    29/33

    Invasive Species

     Control

    •   Eradication of  invasive vegetation 

    (phragmites, cattails)

    •   Herbicide application

    •   Prescribed burning (planned)

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    30/33

    Revegetation•   Genotype Restrictions (Northwest Morianal 

    Division of  Indiana)

    •   Native Seed: 73.90 acres (1,200 lbs.)

    •   Native Plugs: 121,245

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    31/33

    Maintenance and

     Monitoring

    •   Performance Standards•   Coverage (Native and Invasive)

    •   Representation

    •   Survival

      12 months

     from

     EPA

     preliminary acceptance (2016)

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    32/33

    Metrics•   Project length: 1.8 miles

    •   River depth•   Pre‐dredge ~0‐10’

    •   Post‐dredge > 6’

    •   River sediment and wetland dredging volume: ~140,000 cy

    •   Marsh excavation volume: ~203,000 cy

    •   Sediment cap profile: 9” armor over 6” isolation with AquaGate+ORGANOCLAY™

    •   Water treatment:

     3,500

     GPM

     during

     hydraulic

     dredging

    •   Dewatering: ~60 geotextiles tubes stacked 3‐high

    •   Wetlands and marsh invasive species control (47 acres) and restoration (74 acres)

      Project 

    duration: 

    ~3 

    years 

    plus 

    12 

    months 

    revegetation 

    maintenance 

    •   Project budget: ~$80 million

  • 8/9/2019 Environental Restoration at the Grand Calumet East Branch

    33/33


Recommended