Hydrocarbon Mid & Downstream
EPCC / LSTK Project -
• Is a unique endeavour
• Is designed to achieve a agreed objective/s
• Requires a variety of resources
• Needs to be completed within specified time &
cost
2
Hydrocarbon Mid & Downstream
Project Management -
• An art & science of converting vision into reality
• Application of knowledge, skills, tools & techniques
• Involves stages - Initiating , Planning, Executing,
Controlling and Closing
3
Owner
PROJECT STAKE-HOLDERS
Licensor
PMC
EPCC / LSTK Contractor
Vendors / Subcontractors
Service ProvidersHydrocarbon Mid & Downstream
5
CUSTOMER EXPECTATIONS TODAY:
• Concept to Commissioning
• Facilitate & Suggest
• No hassles & worries of monitoring
• No running around vendors
• No multiple disputes & legal battles
• No sleepless nights
Hydrocarbon Mid & Downstream6
LSTK Concept – Advantages to OWNER
Reduced Organizational Resources
OptimumCompletionTime
ComprehensiveGuarantees
Coordinated Design & Engg.
CommittedCost
SinglePointResponsibility
Minimal Risk
Hydrocarbon Mid & Downstream
7
Hydrocarbon Mid & Downstream
LSTK – A Global Trend
LSTK is a global trend, because of:
• Single point responsibility
• Comprehensive guarantees for performance
• Minimal risk exposure to Owner
• Use of core competency of Contractor
• Coordinated efforts, lesser site modifications
• Better involvement of Owner in Key functions
• Minimum organization resources by Owner
8
Process Licensor
Owner
PMC
Project Management Team
EPCC Contractor
Vendors(1,2,…,n)
ConstructionSub-contractors
(1,2,…,n)
Throughout AllPhases of the
Project
LSTK MODEL
Project Definition Phase EPC Implementation Phase
Hydrocarbon Mid & Downstream9
PMC
EPCC
EPCC
PROJECT PHASES
Technology Selection
Process Package Dev.
Tender Preparation
Detailed Engineering
Procurement
Construction
Commissioning
FEED Package
Performance Run
Owner
PMC
Co
ntr
olled
By
Resp
on
sib
ilit
y
Licensor
Licensor
Hydrocarbon Mid & Downstream
10
PROPOSAL PREPARATION
• Understanding Customer Requirements
• Study of Engg. Specifications / Clarifications from PMC
• Basic System Configuration & Design
• Parametric Comparison & Value Engineering
• Project Cost Estimation
• Study of GCC / SCC
• Assessment of Risks & Deviations
• Learnings from Past Projects
• Technical Proposal Preparation
• Preparation of Execution Plan & Project Schedule Preparation
Hydrocarbon Mid & Downstream12
PROJECT COMPLETION MILESTONES
Typical project with 36 months PAC
36 Months
Zero Date
0 36
Bid Validity
Bid Closing Date
Initial Acceptance
FinalAcceptance
48
Mechanical Completion RFSU
Warranty Period *12 Months
12 Months
120 Days
Commissining PGTRZero Date Initial
AcceptanceFinalAcceptance
Mechanical Completion RFSU
Warranty Period *12 Months
Commg. PGTR
30
Bid
Validity
Zero Date Provisional Acceptance
FinalAcceptance
RFSU
Warranty Period *12 Months
PGTR
Hydrocarbon Mid & Downstream 15
Hydrocarbon Mid & Downstream
Project Task Force
Project Manager
Project EnggManager
Planning Engineer
Project Control Manager
HSE Manager
Res. Constn. Manager
Document Controller
Project Procur. Manager
Dy. Project Mgr E&I
Procurement Team (PPC)
Commissioning
Manager
QA & I Manager
DyPEM
Engg
Team
Support Team:
IT & EALPS:
Contract Manager
Qty Controller
Construction Team(HCP)
Cost Control
Dy. Project MgrPiping & Packages
Executive Sponsor
18
EXECUTION STRATEGY
• Establishing work centres
• Strict adherence to specifications, codes/standards, local
bye-laws and regulations
• Early ordering of LLEs
• Global sourcing
• Construction driven Engineering & Procurement
• Adherence to Highest HSE and Quality Standards
• Close interaction with Owner/PMC to resolve issues
• Effective Interface with other agencies / contractors
• On-time delivery of a safe and trouble free plant
Hydrocarbon Mid & Downstream19
Hydrocarbon Mid & Downstream
Strategic HSE Objectives
Organisational Culture
Legislation and Standards
Systems & Procedures
Occupational Injury or Illness
Performance Data & Analysis
Risks to People & Environment
Training & Motivation
Contractors Engagement
21
PLANNING & MONITORING
• Project Network (L3 & L4 levels)
• Monitoring of Intermediate Milestones
• Engineering
• Procurement
• Construction
• Pre-commissioning and Commissioning
• Detailed schedule for
• Critical Manufacturing
• Packages
• Heavy erection
• Systems/Sub-systems for PC/Commissioning
• Recovery Plans
Hydrocarbon Mid & Downstream26
Micro Planning on Primavera
PROJECT PLANNING
15-Nov-0215-Dec-0215-Jan-0315-Feb-0315-Mar-0315-Apr-0315-May-0315-Jun-0315-Jul-0315-Aug-0315-Sep-0315-Oct-0315-Nov-0315-Dec-0315-Jan-0415-Feb-0415-Mar-0415-Apr-0415
Month Act 0.00 0.17 0.72 1.59 2.60 4.28 3.55 4.47 3.48 2.99 3.43 6.17
Cum Orig Sch. 0.00 0.02 1.39 3.78 7.18 11.25 16.19 21.79 27.49 33.37 39.60 46.01 52.59 59.99 67.47 74.60 81.64 87.90
Cum Org Est Fronts 0.63 2.36 4.48 8.52 14.60 21.57 28.05 36.09 43.46 53.52 59.74 67.49 74.61 81.69 87.92 93.32 96.91 98.50
Cum Targets 20.33 25.01 30.29 37.47 40.48 48.20 55.82 63.28 70.73 77.89
Cum Projected Fronts 30.09 36.71 43.54 48.30 54.20 62.87 70.71
Cum Actual Fronts 0.00 0.44 4.85 7.46 13.32 14.44 19.66 22.61 30.09 35.37 37.23 44.60
Cum. Act. 0.00 0.17 0.89 2.48 5.08 9.37 12.92 17.38 20.87 23.86 27.29 33.46
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
110.00
MonthMonth Act Cum Orig Sch.
``
Cum Target
Cum Orig Fronts
Cum Actuals
Hydrocarbon Mid & Downstream28
DETAILED ENGINEERING
• Design Basis Report
• Time Schedule for Detailed Engineering
• Early Release of Specifications for procurement of LLEs
• Perform Design/HSE Reviews (HAZOP / 3D Model)
• Conduct Engineering Studies (HAZID / SIL / SAFOP)
• Generation of Accurate & Matching Bill of Material
• Release of Construction Drawings (AFC), as scheduled
• Co-ordination with Owner and PMC for Reviews / Approvals
• System Integration
• Field Engineering & Commissioning Support
• As-built Documentation
Hydrocarbon Mid & Downstream29
Hydrocarbon Mid & Downstream
Value Engineering
Identify and prioritize area where value engineering possible
Work shop with all task force members to decide timeline, implementation feasibility & expected benefits for VE ideas
Track implementation of the VE ideas and measure actual VE benefits
Disciplines/Task Force Members are encouraged to come up with VE ideas, in addition to the databases
Identification and prioritization of opportunities where quantity / specification could be optimized leveraging engineering competencies without compromising the basic technical requirement
Work shop is conducted at 2 phasesDuring the Proposal Stage.
At the start of Project Execution
34
Integrated Engineering Through 3D Modeling
PDS 3D MODEL
ELECTRICAL MODELING
PROCESS2D
ENVIRONMENT
EQUIPMENTMODELING
INSTRUMENT MODELING
CIVIL AND STRUCTURAL MODELING
PIPING MODELING
FIRE FIGHTINGMODELING
Hydrocarbon Mid & Downstream 35
Supply Chain Management
• Ordering as per Engineering Specifications
• Matching Deliveries as per Project Schedule
• Ordering as per schedule & within budget
• Expediting through network / agencies
• Addressing Quality Requirements
• Inspection Co-ordination
• Supplier Relations
• Timely Deliveries at Site
• Vendor support during pre-commg and commg
• Spares Management
Hydrocarbon Mid & Downstream40
Global Sourcing
• Sourcing of materials, Equipment and services from qualified &
approved vendors
• Evaluation of vendors based on
Past Experience
Price Competitiveness Quality Delivery Reliability After-Sales-Service
• Indigenous/Global sourcing
• Through State-of-the-Art SAP system
41Hydrocarbon Mid & Downstream
Hydrocarbon Mid & Downstream
Global Sourcing for ongoing Job
INDIA – 64%Packages, Static, Piping,
Rotary, Structural,
Instruments, Electrical
USA – 5%Static, Packages,
Instruments, Piping
Others – 1.2%
South Korea – 9%Static, Packages, Piping
EUROPE – 6.6%(France, Germany, Italy,
Spain, UK, Belgium,
Netherlands, Sweden)
Piping, Static, Instruments,
Electrical, Rotary, Packages
Japan – 14%Rotary
Malaysia– 0.1 %Static
Singapore – 0.1%Instruments
42
Ordering Cycle
Issue of
MR
Approval
of MR
Issue
of
TBE
Approval
of TBE
Enquiry
Floating
Offers
Receipt
Technical
Query
Issue Award
Recomendation
Approval of
Award
Recomendation
Issue of P.O
Issue of PR
43
Hydrocarbon Mid & Downstream
Logistics Management
Preparation of Project Specific Logistic Plan comprising the following:
• Route survey report
• Port of import in country of project.
• Recommended mode of Transport for Materials & Equipment
• Shipment Execution & Monitoring
• Receipt date at site based on the committed dispatch date.
• Selection of Freight Forwarder based on Geographic Location
• Schedule for contract award for LSP / Freight Forwarders
• Progress reporting Freight Forwarder
• Format for overall Progress Report and frequency of updation
L&T has a dedicated Logistics Management Centre & a team of Logistics Specialists
44
CONSTRUCTION
• Establish Site Infrastructure at early stage
• Construction Management
• Progress Monitoring & Control
• Generation of sequential & parallel work-fronts
• Full utilization of SAP, e-Alps, easy-TRACK, MOSS, Spool-gen & Punch-Mon systems
• Resource mobilization & Effective Utilisation
• Parallel working
• Strict HSE Compliance
• Adherence to Quality Standards
• Compliance with Statutory Regulations
Hydrocarbon Mid & Downstream45
Hydrocarbon Mid & Downstream
Site Infrastructure
• The mobilization phase involves meticulous planning and
establishment of infrastructure to handle the quantum of work
and the challenges. The following is generally planned:
o Project Office with VC facility and hot linked to design and PMT office.
o Site establishments like Consumable Store, Piping storage yard, Labour-
colony with all amenities and hygiene facilities etc.
o Rebar service center, Batching Plants, Carpentry Work shop and P&M
Work shop
o Worker Canteen and Workers Rest Shed at site.
46
Hydrocarbon Mid & Downstream
CONSTRUCTION EXECUTION
• Early start-up of Soil Investigation
• Participation in constructability study
• Focus on completion of UG works very early
• Prefabrication of Critical Piping away from site
• Continuous monitoring of 100% matching front
• Aligning pre-fabrication of piping with erection fronts
• Hanging platform beneath Pipe-racks for ease of AG
piping erection / other E&I works
• Strict monitoring of RT works to avoid any pile up
• Define hydro-test loops & Process systems in advance
47
Hydrocarbon Mid & Downstream
COMMISSIONING
• Pre-commissioning with objective of “first time right” start-up
• Established work practices
• High emphasis on HSE during pre-commg and commg
• Thorough audit of construction prior to pre-commissioning
• Pre Start-up safety audits
• Inputs to models review, HAZOP studies, P&IDs review, SIL studies etc.
• Accessibility, Operability, Maintainability studies during model reviews
• On time support from vendors
• Leverage from database of learnings from previous projects
• Team of highly experienced Managers, Engineers & Operators
• Project specific training for Engineers
• Provide training to Client’s O&M teams
• Seamless alignment with Client’s O&M teams during commissioning
49
Hydrocarbon Mid & Downstream
KEY SUCCESS FACTORS
• Customer Delight : On time Completion
• Right person at right place in right time
• Prompt Decision-making
• Optimum Engineering Solutions
• Continuous tracking and monitoring
• Timely Deliveries
• Adherence to Highest Quality Standards
• Implement best HSE Practices for accident Free
Execution
• Risk Management
• IT enablers50
Smooth Execution of a Project requires complete commitment of
OWNER PMC
EPCCLICENSOR
Hydrocarbon Mid & Downstream51