EXCAVATION AND BASE PREPARATION
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
BASE SLAB REBAR AND CONCRETE
EXCAVATION AND BASE PREPARATION
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONROOF ERECTION
2- TOWER CRANES OUTSIDE2-PLACER BOOM WITH CONC. PUMP & POURER
LNG TANKErection Sequence
5M X 5M OPENING IN CONCRETE WALL
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONROOF ERECTION
BASE VAPOUR BARRIER INSTALLATIONINSIDE CRANES TAKEN OUT
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONROOF ERECTION
BASE VAPOUR BARRIER INSTALLATION
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONROOF ERECTION
SUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY M M ahuja
WALL CONSTRUCTIONROOF ERECTION
SUSPENDED DECK ERECTION ON STAGING
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONCOMPRESSION PLATE INSTALLATION
ROOF ERECTIONSUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONCOMPRESSION PLATE INSTALLATION
ROOF ERECTIONSUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
WALL CONSTRUCTIONCOMPRESSION PLATE INSTALLATION
ROOF ERECTIONSUSPENDED DECK ERECTION
LNG TANKErection Sequence
INSTALL AIRLIFT EQUIPMENTCOMPLETE AIR LIFT PREPARATION
KING POST REMOVEDACCESS OPENING CLOSED
LNG TANKErection SequenceDEVELOPED BY M M Ahuja
COMMENCE AIR LIFT
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
AIR LIFT
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
AIR LIFT COMPLETEDWELD ROOF TO
COMPRESSION PLATE
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM,
CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS
ERECT ROOF WALKWAYSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM,
CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS
ERECT ROOF WALKWAYSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM,
CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS
ERECT ROOF WALKWAYSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
ERECT INNER TANK AND WALL VAPOUR BARRIERINSTALL ROOF FITTINGS AND TANK INTERNALS
ERECT ROOF PLATFORMSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
ERECT INNER TANK SHELL AND VAPOUR BARRIERCOMPLETE BOTTOM INSULATION, SECONDARY BOTTOM AND
INNER TANK BOTTOMINSTALL ROOF FITTINGS AND TANK INTERNALS
ERECT ROOF PLATFORMSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
ERECT INNER TANK AND VAPOUR BARRIERINSTALL ROOF FITTINGS AND TANK INTERNALS
ERECT ROOF PLATFORMSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
INSTALL FOAM GLASS TO WALLS AND 36% NICKELINSTALL ROOF FITTINGS AND TANK INTERNALS
POST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY M M ahuja
COMMENCE HYDROTESTINSTALL ELECTRICSINSTALL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
COMMENCE HYDROTESTINSTALL ELECTRICSINSTALL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
PERFORM HYDROTESTINSTALL ELECTRICSINSTALL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
PUMP OUT WATER AND CLEAN DOWN INNER TANKINSTAL ELECTRICSINSTAL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
INSULATE INNER TANK SHELLINSULATE SUSPENDED DECK
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
INSULATE INNER TANK SHELLINSULATE SUSPENDED DECK
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
FILL INTERSPACE WITH PERLITE
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja
COMMISSION TANK
LNG TANKErection Sequence
DEVELOPED BY M M Ahuja