+ All Categories
Home > Documents > Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report ·...

Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report ·...

Date post: 21-Jul-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
28
Expansion of the Repository for Spent Nuclear Fuel A Summary of the Environmental Impact Assessment Report Environmental Impact Assessment 2008
Transcript
Page 1: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

Expansion of the

Repository for Spent

Nuclear Fuel

A Summary of the

Environmental Impact

Assessment Report

Environmental Impact Assessment 2008

Page 2: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact
Page 3: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

3

1 Theprojectanditsjustification

The Finnish Nuclear Energy Act prescribes that nuclear

waste generated in connection with or as a result of use

of nuclear energy in Finland shall be handled, stored

and permanently disposed of in Finland. Teollisuuden

Voima Oyj (hereinafter “TVO”) and Fortum Power and

Heat Oy (“Fortum”) are planning to dispose of spent

nuclear fuel in the repository to be excavated at a depth

of 400–700 metres in the bedrock of Olkiluoto in Fin-

land. The repository is intended to be built in the 2010s,

and final disposal could be started in 2020.

TVO has two boiling water reactors in Olkiluo-

to, Eurajoki, each having a rated electrical output of

860 MW (net). Furthermore, the third plant unit under

construction in Olkiluoto will be a pressurized water

reactor with a rated electrical output of approximately

1,600 MW (net). It is to start commercial operations in

2011. Fortum’s power plant in Loviisa has two pressu-

rised water reactors, both having a rated electrical out-

put of 488 MW (net). Each year, some reactor fuel is

replaced by new fuel. Spent nuclear fuel assemblies are

stored in water pools of plant units and interim storage

facilities. However, interim storage is not intended as a

final solution; the aim is to permanently dispose of fuel

in the Finnish bedrock.

Both owners of Posiva Oy (“Posiva”), TVO and For-

tum, have carried out environmental impact assess-

ment procedures in 2007–2008 concerning the con-

struction of new nuclear power plant units in their plant

areas. On 25 April 2008, TVO submitted an application

to the Government for a decision-in-principle regarding

the construction of a fourth nuclear power plant unit in

Olkiluoto (Olkiluoto 4). Fortum is also in the process of

preparing documents that would allow an application

for a decision-in-principle regarding the third plant unit

in Loviisa (Loviisa 3). If implemented, these would be

the sixth and seventh plant units of Posiva’s owners in

Finland (FIN6 and FIN7).

The environmental impacts of Posiva’s repository

1 The project and its justification

were last assessed comprehensively in connection with

the repository’s EIA procedure in 1999, covering the

disposal of spent nuclear fuel from six plant units cor-

responding to 9,000 tons of uranium.

Posiva started an environmental impact assess-

ment procedure (EIA procedure) concerning the ex-

pansion of the repository in May 2008. The need to

carry out a fresh EIA procedure is due to the Loviisa 3

plant unit (LO3). If required, the expansion of the re-

pository can also be used for the disposal of spent

nuclear fuel from other plant units of Posiva’s own-

ers. By carrying out an EIA procedure that takes into

account the possible seventh nuclear power plant unit,

Posiva is preparing for the eventuality that Fortum

may submit an application for a decision-in-principle

regarding the third plant unit in Loviisa. The seventh

power plant unit is estimated to produce spent nu-

clear fuel amounting to some 3,000 tons of uranium.

By taking into account the plans concerning the con-

struction of new nuclear power plant units for TVO

and Fortum, in addition to the currently operated

units or those under construction, the total volume of

spent nuclear fuel is estimated to increase to approxi-

mately 12,000 tons of uranium.

Posiva is inspecting the expansion of the reposi-

tory for spent nuclear fuel by 3,000 tons of uranium

so that the repository will have capacity for 12,000

uranium-tons of spent nuclear fuel instead of the pre-

viously planned 9,000 tons of uranium. The starting

point of the environmental impacts under inspection is

the final disposal solution that will remain unchanged

regardless of the expansion and is in accordance with

the issued decisions-in-principle and the previous EIA

procedure.

This document presents a summary of the environ-

mental impact assessment report (EIA report). More

detailed information about the project is presented in

the EIA report.

Page 4: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

4

1 The project and its justification

1.1 Previousdecisionsrelatedtotheproject

In 1983, the Government Decision defined the objec-

tives and schedules for the implementation of nuclear

waste management and related research and design

work. This decision required that a disposal site where

final disposal facilities can be built was to be selected

and inspected by the end of 2000. According to the de-

cision, research and design work must proceed so that

it will be possible to start building the repository after

2010 and start final disposal in 2020. The Ministry of

Trade and Industry’s decisions taken in 1991, 1995 and

2003 also refer to these schedules. Research and de-

sign work has advanced according to these intermedi-

ate objectives.

Posiva has carried out an environmental impact

assessment procedure related to the repository for

nuclear waste in 1998–1999. In its statement regard-

ing the assessment report, the Ministry of Trade and

Industry stated that Posiva had inspected the project

and its alternatives in accordance with the statement

issued by the Ministry regarding the EIA programme.

Any changes in the accumulation of the nuclear fuel to

be disposed of were taken into account in the assess-

ment so that its maximum volume corresponded to

9,000 tons of uranium.

In December 2000, the Government made a de-

cision-in-principle based on Posiva’s application, ac-

cording to which the construction of the repository in

Olkiluoto in Eurajoki is in line with the overall good

of society. According to the decision-in-principle, an

amount of spent nuclear fuel corresponding to a maxi-

mum of 4,000 tons of uranium can be processed and

disposed of in the repository. Posiva has concentrat-

ed its research in Olkiluoto through the decision-in-

principle prepared by the Government and ratified by

Parliament.

A decision-in-principle concerning the fifth nucle-

ar power plant unit to be built in Finland, Olkiluoto 3

(OL3), was made in 2002. At the same time, a deci-

sion-in-principle based on Posiva’s previous applica-

tion concerning the construction of the repository for

spent nuclear fuel as an expanded facility was made so

that spent nuclear fuel from OL3 can be disposed of in

the repository. By virtue of the decision-in-principle is-

sued in 2002, final disposal facilities for a maximum of

2,500 uranium-tons of spent nuclear fuel can be built.

On this basis, and together with the Government’s de-

cision-in-principle issued in December 2000, a maxi-

mum of 6,500 uranium-tons of spent nuclear fuel can

be processed and disposed of in the repository in ques-

tion pursuant to the issued decisions-in-principle.

1.2 Environmentalimpactassessmentprocedure

According to the Act on the Environmental Impact

Assessment Procedure (468/1994), projects to be as-

sessed in the environmental impact assessment pro-

cedure are prescribed by the EIA Decree (713/2006).

Facilities intended for the processing, storage and fi-

nal disposal of nuclear waste generated through the

production of nuclear energy fall within the scope of

application of the Act on the Environmental Impact

Assessment Procedure and require an environmental

impact assessment. The Ministry of Employment and

the Economy acts as the statutory coordinating author-

ity in nuclear facility projects.

Posiva’s EIA programme regarding the expansion of

the repository so that the volume of disposable spent

nuclear fuel will be a total of 12,000 tons of uranium

was completed in May 2008. The EIA programme was

presented in various public events and displayed in

summer 2008. The coordinating authority issued its

statement on the EIA programme on 22 August 2008.

The statements and opinions given on the programme

are described in Section 3.1.

The results of the environmental impact assessment

are collected in the environmental impact assessment

Page 5: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

5

1 The project and its justification

report. The EIA report was submitted to the coordinat-

ing authority in autumn 2008 and will be on display for

two months for presenting opinions and statements.

After the public display, the coordinating authority will

compile the opinions and statements issued and pro-

vide its statement on the assessment report. The as-

sessment procedure will be completed once the coordi-

nating authority has issued its statement.

International hearing

The Convention on Environmental Impact Assessment

in a Transboundary Context of the United Nations Eco-

nomic Commission of Europe will be applied to the

project (Espoo Convention 67/1997). The nuclear facili-

ty is included in the convention’s project list. In Finland,

the convention’s coordinating party is the Ministry of

the Environment, which notified the environmental au-

thorities of Sweden, Norway, Estonia, Latvia, Lithuania,

Denmark, Poland and Russia of the commencement

of the EIA procedure concerning the expansion of Po-

siva’s repository and inquired about the willingness of

these countries to take part in the EIA procedure.

The statements and opinions given on the EIA pro-

gramme through international hearing are presented

in Section 3.2. The factors presented in the statements

have been taken into consideration and included in the

assessment report, and in this summary with regard to

the most important impacts.

Figure 1-2 Olkiluoto’s location in Finland.Figure 1-1 The location of Eurajoki and Olkiluoto. Eurajoki is located along highway 8. (Base map © Affecto Finland Oy, Map Centre, licence number L 7630/08.)

Page 6: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

6

1 The project and its justification

1.3 LicencesrequiredfortheprojectundertheNuclearEnergyAct

According to the Finnish Nuclear Energy Act, the con-

struction of a nuclear facility of considerable general

significance requires a decision-in-principle issued by

the Government and ratified by the Parliament to en-

sure that the construction project is in line with the

overall good of society. The expansion of the repository

is regarded as such a significant project that it requires

the EIA procedure and the Government’s decision-in-

principle. The EIA report shall be enclosed with the de-

cision-in-principle application.

The Government will grant the construction and

operating licence if the prerequisites for granting the

licences for a nuclear facility prescribed in the Nuclear

Energy Act (990/1987) are met.

1.4 Locationandlanduseneeds

Posiva’s repository is planned to be built on Olkiluoto

island in the municipality of Eurajoki on the west coast

of Finland. The distance from Olkiluoto to the nearest

town, Rauma, is approximately 13 kilometres (Figure

1-1). The neighbouring country closest to the repository

is Sweden, where the mainland areas closest to the re-

pository are located about 200 kilometres west of the

repository (Figure 1-2).

The repository area for spent nuclear fuel is located

in the middle of the Olkiluoto island (Figure 1-3). The

aboveground construction area of the repository area

(i.e. the area of buildings, roads, storages and fields) is

a total of 20 hectares. The area required by the under-

ground repository section is about 190 hectares for an

amount of 9,000 tons of uranium of disposable fuel.

The expansion of the repository from 9,000 tons of ura-

nium to 12,000 tons of uranium will increase the area

required by final disposal by about 50 hectares.

Figure 1-3 The location of the repository area in Olkiluoto.

Page 7: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

7

2 Project description

2.1 Projectoptions

The main option in the environmental impact assess-

ment is the expansion of the repository so that the total

volume of disposable spent nuclear fuel will be 12,000

tons of uranium. The expansion mainly concerns the

underground repository. The expansion of the reposi-

tory facilities may require construction of new vertical

shafts outside the current plant area for the ventilation

system and as exit routes.

The zero option to be studied is a situation where

Posiva’s repository will not be expanded and a maxi-

mum of 9,000 tons of uranium can be disposed of in

the repository. In the zero option, the spent nuclear fu-

el from six nuclear power plant units can be disposed

of in the Olkiluoto disposal facility. In this case, spent

fuel from the seventh nuclear power plant unit will be

stored in water pools in a spent fuel interim storage un-

til the processing of the fuel or its permanent disposal

is decided upon.

2.2 Technicaldescriptionofthefinaldisposalfacility

Posiva’s disposal solution is based on the KBS-3 so-

lution developed by Svensk Kärnbränslehantering AB

(SKB), which is a company responsible for nuclear

waste management in Sweden. The purpose of the dis-

posal of spent nuclear fuel is to:

package (encapsulate) spent nuclear fuel assem- π

blies in a form suitable for permanent disposal

inside the bedrock

dispose of the packaged spent nuclear fuel as- π

semblies in a permanent manner inside the

bedrock.

The long-term safety concept of the final disposal solu-

tion is based on the multi-barrier principle (i.e. several

release barriers securing each other) so that the defi-

ciency of one barrier will not compromise long-term

safety. Release barriers include a canister, bentonite

2 Projectdescription

Page 8: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

8

2 Project description

barrier, tunnel backfill and intact bedrock around the

disposal facilities. The release of radionuclides is sig-

nificantly slowed by the structure of the spent nuclear

fuel; uranium dissolves very slowly in water in the con-

ditions existing deep inside the bedrock. The multi-bar-

rier principle for final disposal is shown in Figure 2-1.

The final disposal facility consists of two sections:

the aboveground encapsulation plant where π

spent nuclear fuel is received, dried and packed

into final disposal canisters

the repository located deep inside the bedrock π

where the significant section consists of tunnels

and deposition holes where the encapsulated

spent nuclear fuel is disposed of in a permanent

manner.

2.3 Safetyofthefinaldisposalfacility

In addition to decisions-in-principle, Finnish nuclear

waste management is prescribed by the Nuclear Ener-

gy Act and the Nuclear Energy Decree that entered into

force in 1988 defining the obligations of nuclear en-

ergy producers, licence procedures and control rights.

In 1994, the Nuclear Energy Act was amended so that

all nuclear waste generated in connection with nuclear

energy in Finland must be disposed of in Finland. In

addition, the Nuclear Energy Act forbids the import of

nuclear waste to Finland.

The Radiation and Nuclear Safety Authority (STUK)

controls the safety of nuclear waste management, stor-

age and final disposal in Finland. In order to secure ap-

propriate planning for the final disposal of spent nu-

1. DISPOSAL TUNNEL2. COMPACTED BENTONITE3. DISPOSAL CANISTER4. TUNNEL BACKFILL

Figure 2-1 Multi-barrier principle for final disposal. Differ-ent barriers back-up each other.

Page 9: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

9

2 Project description

clear fuel, the authorities have set reporting obligations

for nuclear waste producers. STUK, together with other

expert organisations, inspects all research and techni-

cal plans aimed at safe disposal of nuclear waste and

gives feedback to the implementing party.

The Government issues the general safety regula-

tions concerning nuclear waste management. The safe-

ty regulations relating to the processing and storage of

nuclear waste are included in the Government Decision

on the Safety of Nuclear Power Plants (VNP 395/1991).

There are two Government Decisions on the safety of

final disposal, one of which concerns spent nuclear fuel

(VNP 478/1999) and the other concerns low and inter-

mediate level power plant waste (VNP 398/1991). More

detailed regulations on nuclear waste management can

be found in STUK’s guidelines.

According to the general safety principles for nucle-

ar waste management, there must not be any radiation

endangering health or any other damage to the envi-

ronment or property. This principle extends into the fu-

ture. Final disposal must not cause such future health

or environmental damage that exceeds the currently ac-

cepted maximum level.

Page 10: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

10

3 Statements on the assessment programme

3.1 Nationalhearing

The coordinating authority requested statements on

the assessment programme from 39 authorities, mu-

nicipalities and organisations. Of these, 25 issued their

statements. Furthermore, 21 associations or private

people presented their opinions.

The statements considered the programme to be

mainly appropriate and comprehensive. The state-

ments and opinions paid attention to the following:

The definition of the zero option π

The comparability of the options (6,500 tU, π

9,000 tU and 12,000 tU)

The suitability of Olkiluoto as the disposal π

location

The need to describe the repository and disposal π

technology in more detail

The safety and environmental impact of the π

transportation of spent nuclear fuel

Long-term safety π

3 Statementsontheassessmentprogramme

Malfunctions and accidents π

Combined impacts together with other functions π

planned in Olkiluoto

Alternative methods of processing spent nuclear π

fuel

Possibilities of participation during the EIA π

procedure

The extent of the scope for inspecting functional π

and techno-economical impacts and impacts on

people

The implementation schedule of the EIA π

procedure.

The Ministry of Employment and the Economy issued

its statement based on the statements and opinions

requested and presented. In its statement, the Ministry

required the following:

The EIA report must present a comprehensive π

description of the disposal facilities and its en-

Page 11: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

11

3 Statements on the assessment programme

Statementsgivenintheinternationalhearing How the statement has been taken into account in the assessment(referencestosectionsoftheEIAreport)

Sweden

The EIA procedure is to handle the repository approved in the project’s decision-in-principle and present an alternative location if Olkiluoto is not suitable.

The EIA report describes facilities for the disposal of 6,500 tU, 9,000 tU and 12,000 tU of spent nuclear fuel. The repository’s environmental im-pacts are also described in the aforementioned situations.The assessment only applies to the disposal location in Olkiluoto. It was selected as the disposal location among several alternatives on the ba-sis of extensive research work consisting of a number of stages in 1999. In 2000 the Government prepared a decision-in-principle, according to which the construction of the repository in Olkiluoto in Eurajoki is in line with the overall good of society.

The environmental impact assessment is to present the methods by which the transfer of radioactive substances to the Baltic Sea is pre-vented.

The long-term safety concept of the final disposal solution is based on the multi-barrier principle designed to prevent radioactive substances accessing the living nature. Release barriers include a canister, ben-tonite barrier, disposal tunnel filling and intact bedrock around the dis-posal facilities. The multi-barrier principle is described in more detail in Sections 3.3 and 11 of the EIA report.

Table 3-1 The central themes of the statements given on the EIA programme in the international hearing and their application to the environmental impact assessment.

vironmental impact when the volume of dispos-

able fuel is 6,500 tons of uranium, 9,000 tons of

uranium and 12,000 tons of uranium.

The impact assessment must take into account π

the total impact and cumulating impacts that

are caused by other projects in Olkiluoto.

The EIA report must describe how the suitabil- π

ity of the location for the intended purpose is

assessed.

The assessment must pay attention to trans- π

boundary impacts.

The participation arrangements must be justified. π

3.2 Internationalhearing

Sweden, Norway, Germany and Estonia issued their

statements on the EIA programme and notified their

participation in the EIA procedure. Denmark, Lithuania

and Poland responded to the Ministry of the Environ-

ment that they will not take part in the EIA procedure.

The Ministry of the Environment has not received a re-

sponse from Latvia or Russia.

Questions raised in the international hearing in-

cluded the impact of malfunctions and accidents and

long-term safety. With regard to these questions, the

statements paid particular attention to transbound-

ary impacts. The central themes of the statements and

comments presented in the international hearing are

discussed in Table 3-1. The issues presented in the

statements are taken into account and included in the

assessment report, and this summary with regard to

the most significant impacts.

Page 12: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

12

The EIA report is to present the current understanding of long-term safety.

Mechanically strong and corrosion-resistant canisters placed in steady bedrock and surrounded with bentonite clay will most likely contain all radionuclides for the minimum of several millions of years. However, the possibility of individual canisters breaking during this time cannot be completely excluded. In such cases, radioactive substances could be slowly released into the environment. However, only a few canister dam-ages are expected even in violent rock movements. Such cases have been analysed and the released radioactivity would only have a minimal impact on people and other living environments. The current under-standing of long-term safety is presented in greater detail in Section 11 of the EIA report.

The assessment is to cover the entire facility, including transportation and related risks of accidents, as well as the actions used to prevent accidents.

The environmental impact assessment covers environmental impacts caused by the repository’s (Section 3 in the EIA report) normal opera-tions (Section 9), malfunctions (Section 10.4) and accidents (Section 10.6). The measures for preventing any repository accidents are pre-sented in Section 15.2. The assessment covers also the environmental impacts caused by transportation (Section 3.6.3) and related malfunc-tions and accidents (Section 9.1.2). The measures for preventing any transportation accidents are presented in Section 15.5. The radiation impacts caused by repository and transportation accidents fall below the limits set by the authorities.

The assessment is to take into account the preventive and transbound-ary joint actions taken for nuclear facility questions and the communica-tion systems that will be installed for warning measures in the event of a radiation leakage.

Cooperation is carried out with international nuclear organisations (IAEA and OECD/NEA).In the event of any accident, STUK will notify the neighbouring countries of the accident in accordance with international agreements. There is a Convention on the Early Notification of Nuclear Accidents (1017/86, 98/86).

Estonia

The EIA report is to present a detailed assessment of the impact of un-anticipated and accident situations, and the possibilities for preventing them.

The doses caused by postulated malfunctions and accidents will be smaller than the required limit value, even in the immediate vicinity of the incident area (a distance of less than five kilometres). The impacts of malfunction and accident situations are presented in Section 10 of the EIA report. The prevention of malfunctions and accidents and the management of consequences are presented in Section 15.2 of the EIA report.

The EIA report is to describe the methods used to supervise final dis-posal.

The Nuclear Energy Act prescribes the general criteria for the use of nuclear energy and the supervision of operations.The disposal of spent nuclear fuel, including the transportation of spent fuel, comprises operations subject to a licence pursuant to the Nuclear Energy Act. The decision-in-principle, construction licence and operat-ing licence for nuclear facilities are applied for from the Government. Other licences and permits are to be applied for from the Radiation and Nuclear Safety Authority (STUK).Posiva’s obligation is to ensure safe operations of the repository. STUK is responsible for supervising the safe operations of nuclear energy. In addition, STUK’s task is to see to the supervision of safety and emer-gency arrangements, and the safeguards of nuclear materials. With its inspection programme for the construction phase, STUK can verify that the construction of the nuclear facility follows the construc-tion licence, approved plans and authority decisions. With its inspection programme for the operating phase, STUK can ver-ify that the facility is operated and maintained in accordance with the authority regulations, design criteria and the guidelines of the licence holder’s quality management system. STUK also supervises the closing of the disposal facilities. According to the Nuclear Energy Act, the final disposal must in its entirety be imple-mented in such a manner that no monitoring will be required afterwards in order to ensure its safety.

3 Statements on the assessment programme

Page 13: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

13

3 Statements on the assessment programme

Cumulative impacts are to be assessed. The assessment covers the disposal of 12,000 tons of uranium and the resulting impacts. An increased volume of fuel prolongs the operational phase of the repository and postpones the closing phase to a later date. The nature of operations remains similar throughout the operations. In addition to the duration of the repository’s operational and closing phases, the size of the underground repository as well as the length and number of tunnels to be built will change. The area with an impact on groundwater possibly widens, and the amount of rock material in-creases.

Norway

The assessment is to cover the entire volume of spent nuclear fuel. The assessment covers the disposal of 12,000 tons of uranium and the resulting impacts.

The impacts of accidents and irregular situations on Norway are to be assessed.

The impacts of malfunctions and accidents during the operating stage are presented in Chapter 10 of the EIA report. The doses caused by pos-tulated malfunction and accident situations will be below the limit value set by the requirements, even close to the incident (a distance of less than five kilometres). Long-term safety is assessed in Section 11 of the EIA report. Even the maximum dose rates will be rather small in the vicinity of the repository. In practice, no radiation doses would be targeted at Norway because the distance between Olkiluoto and Norway is about 500 kilometres.

Germany

The period covered by long-term safety is to be identified. The inspection period for long-term safety extends to hundreds of thou-sands, even millions, of years.

Has a scenario been prepared for the assessment, inspecting the breach of a copper canister caused by geological movement as a result of an ice age, which would release radioactive emissions from the repository?

The assessment has utilised the safety assessments prepared for the disposal concepts KBS-3V and KBS-3H (a preliminary Swedish safety assessment for the vertical disposal solution SR-Can (www.skb.se, SKB TR-06-09) and a preliminary safety assessment for the horizontal dis-posal solution (www.posiva.fi, Posiva 2007-06)). The assessments in-clude scenarios where the copper canister breaches as a consequence of geological movement.

Long-term impacts on the atmosphere and water system are to be iden-tified in the event of an accident, such as when an aircraft collides with the encapsulation plant or in the aforementioned event where a copper canister breaks due to geological movement.

Long-term impacts on the atmosphere and water system are presented in Section 11 of the EIA report. The encapsulation plant is structurally designed against postulated ex-ternal incidents (including a collision with a small plane). When assess-ing the significance of external threats, it should be taken into account that only small fuel volumes are processed in the encapsulation plant at any one time. During the process, fuel will be processed in facilities lo-cated below the ground surface for most of the time, when the structure of the plant provides the best protection against external threats. Fuel waiting for encapsulation will be stored into a fuel transportation con-tainer in the encapsulation plant. The container is designed against any accidents taking place during transportation. Furthermore, the encapsu-lation plant is a rather small building, which reduces the probability of aircraft collision with the building.The probability and consequences of a major earthquake damaging the final repository are presented in Section 11.6. Only a little canister dam-age can occur, even in violent rock movements. Releases of radioactive isotopes caused by such damage would only have a minimal effect on people and other living environments.

Page 14: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

14

4 The project’s impacts

4 Theproject’simpacts

When inspecting the environmental impact of the ex-

pansion of Posiva’s repository, the reference point is

a situation where the repository is built for the entire

fuel volume of 9,000 tons of uranium. The status of

the environment was inspected during the previous

EIA procedure, as well as the environmental impact

caused by the disposal of a maximum of 9,000 tons

of uranium. When assessing the environmental impact

of the expansion of the repository, the EIA report pre-

pared in 1999 has been taken into account, as well as

the updated report on the repository’s environmental

impacts prepared in spring 2008 and the research and

monitoring results obtained after the completion of the

reports. The expansion required by the final disposal

will be started in the 2070s at the earliest.

In practice, there are some uncertainties related

to the description of the environmental conditions in

2070. For this reason, this document describes the

current status in Olkiluoto and the possible changes

caused by the activities connected to final disposal.

The EIA report has described and assessed the fol-

lowing impacts taking place during the construction

and operations of the repository:

Impact of transportation and traffic π

Impact on land use, cultural heritage, landscape, π

buildings and structures

Impact on the soil, bedrock and groundwater π

Impact on the air and air quality π

Impact on water systems π

Impact of waste and by-products π

Impact of noise and vibration π

Impact on flora and fauna and protected areas π

Impact on the utilisation of natural resources π

Impact on people, including health impact, and π

attitudes towards the disposal of spent nuclear

fuel

Impact on social structure, regional economy π

and the image of the municipality of Eurajoki.

In addition, the following issues have been addressed:

Impact of malfunction and accident situations π

Long-term safety π

Impact of non-implementation of the project π

Comparison of the options (6,500 tU, 9,000 tU π

and 12,000 tU).

This document comprises a summary of the impacts

considered to be the most important.

4.1 Impactoftransportationandtraffic

Traffic to and from Posiva’s repository comprises a

small part of all traffic on Olkiluoto Island (approxi-

mately 5 percent of the total traffic volume); thus, it will

not have a major impact on the traffic volume and re-

sulting impacts. The expansion of the disposal facilities

will not have any impact on the daily traffic volume.

In addition to the Olkiluoto nuclear power plant,

spent nuclear fuel will be transported to the repository

from the Loviisa nuclear power plant. The transporta-

tion of fuel from Loviisa to Olkiluoto is planned to be

performed as road transportation, but railroad and sea

transportation and a combination of these have been

examined as optional transportation methods. Figure

4-1 presents the alternative routes for road, rail and

sea transportation inspected for the transportation of

spent nuclear fuel. A transportation risk analysis has

been carried out for each transportation option, iden-

tifying the health risks caused by transportation from

the Loviisa nuclear power plant to the repository in

Olkiluoto.

The amount of fuel transportation depends on the

volume and type of fuel, burn-up, cooling time and the

size of the transport container. At most, there will be

ten transports per year. For transportation, the expan-

sion of the repository means that the operations will

continue as before but transportation will continue for

a longer period. Due to the small transport volume,

Page 15: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

15

Figure 4-1 Alternative routes for road, rail and sea transportation from Loviisa to Olkiluoto inspected for the transporta-tion of spent nuclear fuel.

4 The project’s impacts

the environmental impacts due to exhaust gas emis-

sions in case of all the transport alternatives will be

insignificant.

The risk of serious cancer cases caused by radia-

tion from normal transportation is fewer than 0.00007

cases/year along the inspected routes, and the cancer

risk as a consequence of accidents is even lower. This

means that transportation is not expected to cause

a single death due to cancer. The health risk caused

by radiation related to the transportation of spent nu-

clear fuel is smaller than that caused by regular traffic

accidents.

4.2 Impactonlanduse

The normal operations or anticipated malfunctions or

accidents of the underground facilities will not pose any

land use limitations. The area for the underground dis-

posal facilities is indicated through normative outlines

in the Olkiluoto component master plan approved by

the Eurajoki municipal council on 19 May 2008. Two

complaints have been filed for the approval decision

and they are currently being handled.

The component master plan includes reservations

for areas required for aboveground final disposal func-

tions. The regulations concerning the energy mainte-

nance area (EN area) include the statement to the ef-

fect that nuclear waste facilities related to final disposal

of low and intermediate level as well as high-level nu-

clear waste may be built on the area according to the

construction licence granted under the Nuclear Ener-

gy Act. These include access buildings and structures

providing access to underground repository facilities

as well as encapsulation facilities and related auxiliary

facilities.

The component master plan proposes a safety zone

for the underground disposal functions. The zone will

be subject to a notification obligation aimed at land use.

When excavating and drilling the bedrock, it should be

noted that the area comprises a safety zone for the re-

pository. The party responsible for the final disposal

opera tions must be consulted before excavation and

drilling of the bedrock is commenced.

When granting the closing permit for the repository,

land use restrictions can also be set that can apply to

boring or excavation operations in the area.

4.3 Impactsonthesoil,bedrockandgroundwater

Figure 4-2 presents a basic image of the disposal facili-

ties following the current assessments for the disposal

of 9,000 and 12,000 tons of uranium in Olkiluoto. The

area required by the underground repository for 6,500

tons of uranium of fuel to be disposed of is about

Sea route

Railroad route

Road route

Alternative road route

100 km

Page 16: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

16

4 The project’s impacts

150 hectares. When the disposable volume is 9,000

tons of uranium, the area will be about 190 hectares.

The expansion of the repository from 9,000 to 12,000

tons of uranium will increase the area required by final

disposal by about 50 hectares, The expansion of the un-

derground repository can be seen above ground as new

shaft buildings of about 20 m2. Other aboveground

buildings will already be built before starting the expan-

sion stage for final disposal operations.

The increase in the volume of disposable fuel

from 9,000 to 12,000 tons of uranium will increase

the amount of rock waste by 410,000 m3, increasing

the total volume of rock waste from approximate-

ly 1,670,000 m3 to 2,080,000 m3. If the fuel volume

is 6,500 tU, the amount of rock waste will be about

1,450,000 m3. Approximately 20,000 m3 of quarried

materials will be generated annually. Some of the rock

waste will be used as filling material in the repository

and the excessive rock waste can be used for other pur-

poses, e.g. it can be sold as such or crushed into filler

or building material.

The decay heat of spent nuclear fuel will expand the

bedrock and elevate the ground surface in the middle

of the repository by a maximum of 7 cm in more than a

thousand years from the final disposal.

When excavating the tunnels to open rock facili-

ties will leak groundwater that will be pumped to the

ground surface. This will lower the level of groundwa-

ter around the tunnel system. The amount of leaked

water and the scope of the impacts will be reduced as

the construction works progress by sealing the bedrock

around the tunnel.

The volume of groundwater flowing into the expan-

sion of the repository area and the impact of the expan-

Figure 4-2 A basic image of the location principles of the disposal facilities in the Olkiluoto bedrock. Disposal facilities for the current plant units and the plant unit under construction are shown in green (6,500 tU). The underground expan-sion for a fuel volume of 9,000 tU is shown in blue and the expansion for a fuel volume of 12,000 tU in violet. The image presents the known bedrock fragmentation structures according to current research data that regulate the locations and their safety zones.

Page 17: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

17

4 The project’s impacts

sion on the level of groundwater has been assessed us-

ing numerical flow modelling. The flow model has been

updated to correspond to the observed and measured

data compiled by the end of 2007.

According to the numerical model, the construction

of the expansion will increase the volume of water flow-

ing into the entire tunnel system by approximately 20

percent when both the ONKALO facility and the entire

repository are assumed to be open at the same time. In

practice, the tunnel system will be built in stages and

only a part of the tunnel system is open at the same time,

which will reduce true impact from the estimates.

An increase in leakage water will lower the level of

groundwater by an average of 2–4 metres in the exam-

ined area depending on the success of the sealing proc-

ess. The drawdown will be higher locally in parts where

rock with better conductivity than the average is locat-

ed close to the surface.

The chemical composition and gas composition of

deep groundwater is still close to the so-called basic

status that prevailed in Olkiluoto island before the con-

struction of ONKALO started; no major changes have

occurred. However, the hydrogeochemical monitoring

period is still short and the hydrogeochemical changes

caused by the construction of ONKALO may only be-

come visible after several years.

Changes in the groundwater samples taken in

ONKALO have been small.

4.4 Noiseandvibrationimpacts

Excavation work, blasting, rock waste handling, crush-

ing and the use of vehicles and machinery will cause

noise and vibration. These operations will be performed

so that they will not cause any significant impacts on

the environment.

The repository for spent nuclear fuel will be con-

structed as required when spent nuclear fuel is dis-

posed of. The noise generated by the excavation of the

disposal facilities will not extend outside the plant area.

At the construction stage, the crushing of quarried

materials will cause noise during the day. The impact

will not be significant because of the short duration of

the operations and the small size of the affected area.

Crushing of quarried materials will end when all the fu-

el to be placed in the Olkiluoto bedrock has been dis-

posed of.

In practice, the volume of disposable fuel will not

have an impact on the noise zones: if the amount of

fuel to be disposed of increases, the repository will

simply remain in operation longer. The excavation and

boring of any new shafts required may generate noise.

However, the impact will be minor because of the raise

boring technique and the short duration of operations.

Page 18: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

18

4 The project’s impacts

4.5 Impactonflora,faunaandobjectsofprotection

The impacts of the project on flora and fauna are prima-

rily related to the land areas required for buildings and

structures, as well as the construction work. There will

be no significant impact during the operations of the

repository and after its closing.

Most plants take water from soil water above the

bedrock. Thus, the lowering of the groundwater table

level due to the underground facility will not influence

the plants. A significant decrease in the water table lev-

el is not expected in the soil layers.

As a result of the Natura assessment carried out

in the Liiklankari conservation area, it was stated that

the projects enabled in Olkiluoto through the master

plan (including the repository) will not have a signifi-

cant impact on the values, because of which the Liik-

lankari area is included in the Natura 2000 conserva-

tion programme.

4.6 Impactonhumanhealth

Health impact during normal operations

The emissions of radioactive materials from the final

disposal facility during the encapsulation process are

insignificant under normal conditions. The volumes of

radioactive substances handled at any one time at the

encapsulation plant will be small compared to the cor-

responding volumes at nuclear power plants.

The dose for a person belonging to the population

caused by normal one-year emissions over a period of

50 years will very probably be less than 0.01 mSv in the

immediate vicinity of the plant area. The dose will be

at least one order of magnitude smaller at a distance

of five kilometres than in the repository’s immediate

vicinity. The dose farther away will be even smaller. The

doses caused by the normal emissions are thus insig-

nificant when compared to natural radiation (approxi-

mately 3 mSv / year), for example.

As the volume of spent nuclear fuel to be disposed

of increases, so the operating stage of the repository

will also be extended. The increase in the volume of

fuel to be disposed of or the extension of the operating

stage will not have any relevant impact on the radiation

doses that a member of the general public will receive

as a result of the normal operation of the plant. But the

total dose received by the general public as a result of

the operation of the plant will roughly increase in direct

proportion to the increase in fuel volume. Hence the in-

creased amount of fuel will not increase the health risks

due to the normal operation of the plant on the individ-

ual level. As for the health risks to the entire population,

these are increased in approximately direct proportion

to the increase in the quantity of fuel.

Impact of malfunction and accident situations

An anticipated operational malfunction refers to a safe-

ty-related incident which is estimated to occur less fre-

quently than once a year but have a significant probabil-

ity to occur at least once during the operational period

of the facility. A postulated accident is an event that is

used as a design criterion for the safety functions of the

repository and that has a low probability to occur dur-

ing the operational period of the facility.

The radiation doses caused by emissions from mal-

function and accident situations have been assessed

using a computer model. The dose caused by a single

malfunction for a person belonging to the general pub-

lic over a period of 50 years will in all probability be less

than 0.001 mSv. Doses caused by malfunctions will

thus remain substantially smaller than the required an-

nual limit of 0.1 mSv a year.

The structures of the repository will be implemented

so that accidents related to fuel at the processing stage

that lead to significant damage to the fuel will not cause

any immediate danger to the health of the personnel or

the residents in the surrounding areas.

With high probability, the dose for any individual of

the population caused by a postulated accident will be

less than 0.5 mSv during the first year and less than

0.8 mSv within 50 years. Doses caused by postulated

accidents remain thus smaller than the required an-

nual limit (1 mSv). The highest dose will occur in the

immediate vicinity of the facility, assuming there is

permanent habitation and agriculture with their own

products as a main source of food. The main dose is

accumulated from radionuclides settled on the ground,

with intake through the food chain as in the case of op-

erational transients. The dose will be clearly smaller at

a distance of five kilometres from the plant, and even

smaller farther away.

Radioactive substances released in accident con-

ditions and the radiation caused by these substances

could be detected in the environment through meas-

urements. The extent and shape of the impact area will

Page 19: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

19

4 The project’s impacts

depend on the quantity of release and the prevailing

weather conditions. Detection would be made difficult

by the existence of natural radioactive substances and

artificial radioactive substances originating from other

sources. The affected zone of a postulated accident

would, in the spreading direction, extend to a distance

of about five kilometres, whereas the annual dose of

0.1 mSv is considered to be the limit value (an average

of 3 mSv/year for natural radiation).

As the volume of spent nuclear fuel to be disposed

of increases, so the operating stage of the repository

will also be extended. The increase in the volume of

fuel to be disposed of or the extension of the operating

stage will not have any relevant effect on the radiation

doses that a member of the general public will receive

as a result of expected malfunctions or postulated ac-

cidents. But the probability that a malfunction or acci-

dent will occur during the whole operating stage of the

plant will roughly increase in direct proportion to the

increase in fuel volume. Hence the increased volume

of fuel will not increase the health risks caused by mal-

functions or accidents at the individual level. Health

risks to the entire population will be increased in direct

proportion to the increase in the quantity of fuel.

The above ground encapsulation plant will be struc-

turally designed for any anticipated external incidents,

such as a collision with a light aircraft, earthquakes and

flooding.

4.7 Long-termsafety

The long-term safety of the final disposal of the spent

nuclear fuel is indicated using a safety case. The safety

case consists of a group of separate reports that present

the starting points of safety assessment, the models

and initial data used, the assessment methods, the as-

sessment results and related uncertainties and conclu-

sions of the safety inspections and their reliability.

The long-term analyses included in the safety case

identify radiation doses up to thousands of years re-

lated to probable development paths and improbable

incidents that reduce long-term safety. The emission

rates of radioactive substances released to the living

environment relating to these incidents and develop-

ment paths are assessed over a longer period.

The safety analyses present conservative estimates

of the radiation doses and release rates of radionu-

clides. The purpose of the analyses is to study the con-

sequences for people or the environment if one or sev-

eral emission barriers failed and radioactive substances

were released from the repository into the environment.

The safety analyses also deal with the uncertainties as-

sociated with the assessment of the behaviour of the

disposal system, various events and processes. When

assessing risks, the probability of the events will be tak-

en into account.

The mechanically-strong and corrosion-resistant

canisters that will be located in the steady bedrock and

surrounded with bentonite clay will most likely hold all

radioactive substances inside for at least several mil-

lion years. However, the possibility of individual can-

isters breaking during this time cannot be completely

excluded. In such cases, radioactive substances could

be slowly released into the environment. Canister leak-

age could result from the emplacement of an originally

damaged canister in the repository, the breakage of a

few canisters placed in poor locations in earthquakes

that may take place as the ice originating from the ice Figure 4-4 Earthquakes in Finland from 1965 to 2006 (Uni-versity of Helsinki 2007).

EarthquakesinFinlandfrom1965to2006

magnitudes

Page 20: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

20

4 The project’s impacts

age withdraws, the erosion of the bentonite clay around

the canister caused by melting waters and the consecu-

tive corrosion of the canister.

However, only a few cases of canister breach are ex-

pected. Releases of radioactive isotopes caused by such

damage would only have a minimal impact on people

and the living environment. Safety assessments have

also considered the uncertainties affecting the release

and transport of radioactive substances. Clarification

of safety relevant issues continues to reduce uncertain-

ties. The feasibility and adequate quality of technical

solutions will be proven through testing. The full-scale

safety case to be submitted in 2012, supporting the fi-

nal repository construction licence, will be based on

these tests.

4.8 Attitudestowardsthefinaldisposalofspentnuclearfuel

The attitudes of Finnish people towards nuclear waste

have been studied as part of the annual Finnish Energy

Attitudes monitoring survey. Nuclear waste has been

previously stated to arouse clear suspicions. In a sur-

vey conducted in 2007, one-third of all respondents

(32 percent) considered the final disposal of nuclear

waste inside the bedrock to be safe in Finland. There

were more of those who had their doubts, almost half

(46 percent) of the population. Reserved attitudes are

explained by the impression of two-thirds (68 percent),

according to whom nuclear waste comprises a continu-

ous threat to the lives of future generations. Only one

respondent in seven disagreed (15 percent). The atti-

tudes have not become more neutral during the entire

research period of 25 years.

As previously, the attitudes toward nuclear waste

in municipalities containing a power plant were more

positive than the average in the country. Trust in the

safety of final disposal was stronger in such municipali-

ties. The difference between power plant municipalities

and the nation’s average has, however, reduced in the

recent years.

The survey conducted in the winter of 2007–2008

examined the Eurajoki residents’ trust in the safe dis-

posal of spent nuclear fuel. A query was mailed to 400

randomly-selected Eurajoki residents. Furthermore,

the ideas of 18 Eurajoki residents were identified us-

ing theme interviews. On the basis of the results of the

query, approximately 40 percent of the responding resi-

dents had a positive attitude towards the final disposal

of spent nuclear fuel and 12 percent a neutral attitude.

The location of the repository in the home municipality

was regarded as alarming by about 45 percent of resi-

dents. Based on the interviews, the most major con-

cern connected with final disposal was the import of

spent nuclear fuel from abroad to Finland and to Eura-

joki for disposal.

The opinions, attitudes and concerns of Eurajoki resi-

Page 21: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

21

4 The project’s impacts

dents concerning final disposal were also studied using

theme interviews in July 2008. A total of 21 people were

interviewed personally and they were divided into two

groups: those living in Olkiluoto and its immediate sur-

roundings and a group of young Eurajoki residents, half

of whom were 18–19-year-old upper secondary school

students and half under 30-year-old parents of small chil-

dren. The selection of young people as the target group

was based on a comment presented at a public event in

2008, according to which the municipality’s young peo-

ple should be taken into account in the environmental

impact assessment procedure. The second target group

selected included those residents in the surrounding re-

gion that are mostly affected by the project.

The interviewees did not consider the impacts of the

expansion of the repository to be significant compared

to the situation that the repository will be, nonetheless,

built in the municipality. The majority of the interview-

ees had neutral or rather positive attitudes towards

the repository. Bedrock disposal was deemed the best

alternative among the potential final disposal alterna-

tives. Safety risks were, however, identified, mostly in

the long term. None of the interviewees had actual

fears relating to final disposal, even though there were

some concerns, such as the risks related to the trans-

portation of nuclear waste. An impact deemed positive

for the municipality included the repository’s impacts

on employment and tax income. None of the interview-

ees felt that the concerns related to final disposal would

cast a shadow over their lives or cause stress. Only one

of the interviewees believed that final disposal could

cause danger to personal safety.

However, the expansion of the repository compared

to the fact that a smaller plant will be built in any case

was a neutral or positive factor regarding safety accord-

ing to nearly all interviewees. The expansion mainly

aroused concern because many believed it to include

plans to import nuclear waste from abroad.

4.9 Impactonsocialstructure,regionaleconomyandtheimageofthemunicipalityofEurajoki

According to the report entitled “The impacts of final

disposal of spent nuclear fuel on regional, social and

municipal economy”, prepared in 2007, the decision

on the location of the repository, Posiva’s relocation to

Eurajoki, the renovation of the Vuojoki Mansion, the re-

newed operations, the start of the repository’s research

stage and the construction of ONKALO have had a pos-

itive impact on the development of regional, social and

municipal economy in Eurajoki and the entire region in

the early 2000s.

The project’s impact on employment is expected

to be approximately 550 man-years per year at most.

During the operational stage, the immediate annual

employment impact has been estimated to be about

130 man-years. The employment impacts of the reposi-

tory are major for the entire region, approximately 220

man-years/year at most. The employment effect on the

Page 22: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

22

4 The project’s impacts

municipality of Eurajoki and the region will have a sig-

nificant positive impact on employment in the munici-

pality and region.

The construction and operations of the reposi-

tory will have an impact on the municipal economy of

Eurajoki. Real estate tax paid by the plant will slowly

strengthen the municipality’s income tax base as the

real estate tax increases until 2020 at least. This will

enable a strong annual balance and exceptional possi-

bilities for the municipality compared to other munici-

palities, resulting in an increase in the attractiveness of

the municipality for potential house-movers compared

to the rest of the region.

People in the region’s municipalities are satisfied

with the project’s positive impacts on regional econ-

omy. An impact deemed especially positive impact is

the fact that the construction and operation of the fa-

cility will take place over a long period of time, and the

impacts can be reasonably well anticipated and will oc-

cur during a long period of time. The potential nega-

tive external impacts connected with the repository in

advance have not been realised. Based on available in-

formation, the repository project has not caused any

harm to the residents, and the visibility and image of

the municipality of Eurajoki have improved.

4.10Impactofnon-implementationoftheproject

The project’s zero option means that the expansion will

not be implemented. The state of the environment and

the impact of environmental load correspond to the

situation in which the amount of uranium disposed of

in the repository is 9,000 uranium-tons of spent nu-

clear fuel. In the zero option, operations in the reposi-

tory would be finished earlier than in the main option,

i.e. after the disposal of 9,000 tons of uranium. In this

case, spent nuclear fuel from the seventh nuclear pow-

er plant unit will be stored in water pools in an interim

storage for spent fuel at the nuclear power plant until

the processing of the fuel or its permanent disposal is

decided upon.

A precondition for the safety of the interim stor-

age is that the storage and fuel are actively managed.

Should this management end for one reason or another,

the storages would cause a considerable threat to the

environment. In the long run, the safety of the interim

storage depends on human actions, which means that

future generations must commit to using resources un-

der the management of the waste storages. According

to current thinking, the disposal of spent nuclear fuel in

a repository is less risky than storing spent nuclear fuel

in an interim storage.

Non-implementation of the project means that the

environmental impacts caused by the expansion of the

repository assessed in this report will not be realised.

The condition of the environment and the impact of en-

vironmental load correspond to the situation in which

the amount of uranium disposed of in the repository is

9,000 tons of uranium of spent nuclear fuel.

4.11 Comparingalternatives

An increased volume of fuel prolongs the operation-

al phase of the repository and postpones the closing

phase. The nature of operations remains similar. In ad-

dition to the duration of the disposal facility’s opera-

tional and closing phases, the size of the underground

repository, as well as the length and number of tunnels

to be built, will change. The expansion of the final dis-

posal operations will increase the size of the area where

the operations may have an impact on groundwater.

Furthermore, the volume of rock waste generated will

increase.

The increase in the volume of fuel does not have a

significant impact on the safety of the repository. Ac-

cording to safety assessments, the most probable situ-

ation is that radioactive substances will not be released

from canisters in millions of years.

The environmental impact of the repository in the

event where 6,500, 9,000 and 12,000 uranium-tons of

spent nuclear fuel would be disposed of in the reposi-

tory is shown in Table 4-1.

Interim storage of spent nuclear fuel is not a pos-

sible alternative for final disposal because the environ-

mental protection objectives and legislation require the

disposal of spent nuclear fuel in a permanent manner

in Finland. In practice, the implementation of the zero

option would mean that the decision on permanent

disposal will be postponed into the future.

After comparing the zero option and the project op-

tion, the final conclusion is that

storing in water pools transfers the obligation π

to continuously maintain the storage to future

generations

storing in water pools does not offer protection π

for long-term risks caused by social situations.

Page 23: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

23

4 The project’s impacts

6,500tU 9,500tU 12,000tU

Impact of transportation and traffic The traffic volume towards the repository will be low and will not have a major impact on the traffic volumes and traffic impacts. For transport, the expansion of the repository means that the operation will continue as before but there will be transportation for a longer pe-riod of time. The expansion will not have any impact on the daily traffic volume.

Impact on land use, landscape and buildings An area for the underground repository required by final disposal has been defined in the component master plan. The extent of the area is determined on the basis of the occurrence of the bedrock type most favourable for final disposal at the final disposal level.The expansion of the repository may require construction of new vertical shafts outside the current plant area for the ventilation system and as exit routes. A building of approximately 20 m2 would be built at a verti-cal shaft, and the building would be separated from the rest of the area with a fence. Other aboveground buildings will already be built before starting the expansion stage for final disposal operations.

Impact on the soil and bedrock Underground quarrying for the disposal facilities will continue for the entire operating period of the repository. An increased amount of quar-ried material will enlarge the pile of rock waste and, thus, further expand the repository area. If the quarried material is sold as construction mate-rial elsewhere, the repository area will not expand.

• Size of the underground repository area 150 ha 190 ha 240 ha

• Total length of underground tunnels 64,000 m 82,000 m 104,000 m

• Volume of quarried materials generated 1,450,000 m3 1,670,000 m3 2,080,000 m3

• Impact of heat generation on the bedrock The total heat production of the final repository is roughly in direct pro-portion to the number of waste canisters in the repository. The tem-perature in the area immediately around the canisters is not assumed to be especially responsive to the total number of canisters stored in the repository because the canisters will in any case be placed separate from each other in order to avoid excessively high temperatures. The ground surface will rise by a maximum of 7 cm in more than thou-sand years.

Impact on groundwater

• Changes in the amount of water leaking into the tunnel system The volume of water flowing into the expansion will be 0.11–0.14 l/min for each 100 m of open tunnel section. When assumed that the entire tunnel capacity to be excavated is open at the same time, assumption which overestimates the impact concerning the volume of total leakage water will increase by 25–30 l/min from the option of 9,000 tons of uranium to the option of 12,000 tons of uranium.

• Changes in the decrease in the groundwater level The most significant change in the level of groundwater will be caused by the construction of the ONKALO facility. The expansion of the reposi-tory will have a more minor impact on the level of groundwater because the bedrock capacity open at any one time will be relatively stable. If the entire tunnel capacity to be excavated is open at the same time (an assumption overestimating the impact), there will be a decrease of 2–4 metres in the level of groundwater when transferring from the option of 9,000 tons of uranium to 12,000 tons of uranium.

Impact on air quality The traffic caused by the expansion will not have any major impact on the air quality.

Impact on waters The expansion will not have any impact on water consumption or the amount of wastewater at a daily level. The facility will simply be used for a longer time if more fuel is to be disposed of.

Noise impact The crushing of rock waste will cause noise in the daytime. Crushing will end when all spent nuclear fuel has been disposed of. The expansion of the repository will practically have a nonexistent impact on the noise zones. If the amount of fuel to be disposed of increases, the repository will simply remain in operation longer. Some noise may be caused by the excavation and drilling if any new shafts required. The impact will be short-term because the raise boring method will be used, and the excavation and drilling will not take a long period.

Table 4-1 Environmental impact of the repository when 6,500 tU, 9,000 tU or 12,000 tU of spent fuel would be disposed of in the repository.

Page 24: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

24

4 The project’s impacts

6,500tU 9,500tU 12,000tU

Impact on flora, fauna and areas of conservation According to the Natura assessment, the repository will not have a sig-nificant impact on the values which have contributed to the fact that the Liiklankari area has been included in the Natura 2000 conservation programme.

Impact on human health An increase in the amount of fuel to be disposed of or in the length of the operating period will not have a major impact on the radiation doses that an individual member of the public receives as a consequence of normal operations of the plant, anticipated operational malfunctions or postulated accidents. However, the total dose received by the public as a consequence of the repository’s operations, as well as the probability of an operational malfunction or an accident occurring during the entire operational life are all increased in direct proportion to the increase in the volume of fuel. An increase in the volume of fuel will not, therefore, cause an increase in the health risks at an individual level. Health risks to the entire population will be increased in direct proportion to the increase in the volume of fuel.

Attitudes towards final disposal According to the theme interviews conducted in 2008, the interviewees did not consider the expansion of the repository to have any significant impact. Nearly all of the interviewees had neutral or approving attitudes towards the expansion of the repository from 9,000 tons of uranium to 12,000 tons of uranium. The idea was based on the situation that the repository will, nevertheless, be built in the municipality. There were several arguments in favour of the expansion. The expansion mainly aroused concern because many believed it to include plans to import nuclear waste from abroad.

Long-term safety The probability of a single faulty canister passing the inspections and being disposed of is considered to be independent of the number of canisters. Similarly, the probability that a bedrock fracture intersects with a final dep-osition hole, enabling rock movement from an earthquake that results in damage to a canister, is considered to be independent of the number of waste canisters. The number of any damaging canisters in the reposi-tory and the resulting volume of radioactive substances released in the bedrock, the total volume of radioactive substances reaching the ground surface and radiation impact on people and the other living environment will roughly be in proportion to the total volume of disposable fuel.Radioactive substances released from the repository for spent nuclear fuel in the long term will not have any significant impact on people and the other living environment. This applies to all of the fuel volumes in-spected in the table.

Page 25: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

25

5 Information about conceivable environmental impacts across the Finnish border

The expansion of the repository so that the total vol-

ume of disposable spent nuclear fuel will be 12,000

tons of uranium has not been identified to have any

transboundary environmental impacts. The only opera-

tions or actions that can have an impact on other coun-

tries are related to the radionuclide emissions in final

disposal. The doses caused by postulated malfunc-

tions and accidents will be smaller than the required

limit value, even in the immediate vicinity of the reposi-

tory area. The doses in neighbouring countries would

be smaller by several orders of magnitude because the

distance from Olkiluoto to mainland Sweden is more

than 200 kilometres.

STUK, which is the authority that supervises the

safety of nuclear facilities in Finland, stated in its state-

ment on the decision-in-principle in 2001 that the op-

erations of the repository do not include any significant

safety risks and that the plant’s preliminary designs are

appropriate and sufficient. STUK also stated that the

transportation of nuclear fuel or the disposal operations

do not involve the danger of a large accident that could

contaminate the environment

5 InformationaboutconceivableenvironmentalimpactsacrosstheFinnishborder

Page 26: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

26

6 Monitoring environmental impact 7 Schedule

Load and impact monitoring will be performed during

the operations of the repository.

Monitoring of radiation impacts is based on the

measuring of radioactive releases and concentrations

and radiation dose rates. Concentrations and dose

rates are also assessed by means of calculation, using

information such as release and weather information

as it is assumed that, due to the small amounts, radio-

active substances cannot be detected in the environ-

ment. The expected radiation impact will be so small

that special monitoring of the population’s health is

not considered to be necessary: eventual health haz-

ards could not be detected among normal morbidity

rates. As necessary, it is possible to compare the health

of people living in the area with people from a more

remote area with the help of, for example, the National

Public Health Institute’s information.

At the final disposal stage, the releases of radioactive

substances to the environment are monitored. Typical

measuring points include ventilation air and wastewa-

ter discharge routes. Measurements of concentrations

and dose rates already started will be continued.

In order to monitor the environmental impact, a

programme will be prepared, including the following

targets:

Radiation impact on the environment π

The concentration of natural radon gas in rock π

facilities

The level of groundwater in the area around the π

rock facilities

Vegetation distribution in areas affected by π

groundwater

Vibration levels in buildings in the vicinity during π

6Monitoringenvironmentalimpact

7 Schedule

overburden excavations

The image of the Eurajoki municipality π

The occurrence of radiation fears π

Socioeconomic impact. π

Other monitoring obligations may be imposed on, for

example, noise and dust in connection with later licens-

ing processes.

Monitoring measurements carried out by Posiva

will be finished once the plant is closed in a manner ap-

proved by STUK. In the closing phase, Posiva will draw

up a proposal for a monitoring programme for the time

following the closing, and pays the state a lump-sum

settlement. This money will be used by the authorities

for the monitoring and control they deem necessary.

However, final disposal must be implemented so that it

is safe without any later monitoring.

The objective of monitoring following the closing

stage is to identify how the bedrock qualities can be re-

covered to the status preceding the construction stage.

Monitoring of bedrock conditions has been examined

in several international projects.

Monitoring following the closing stage could in-

clude the measurement of radioactivity on ground sur-

face and in deep bore-holes. The holes could also be

used to monitor groundwater levels, currents, chemis-

try, temperature etc. On the ground, geophysical meas-

urements could be used to monitor micro-earthquakes.

Compromising the untouchability of the nuclear mate-

rial with illegal activity would involve operations that

would be visible above ground. The actions would

be detected and internationally monitored from, for

example , satellites.

The project’s EIA procedure is to be concluded early

in 2009. The final disposal of spent nuclear fuel is to

start in 2020. The disposal of spent nuclear fuel from

the new nuclear power plant units (FIN6 and FIN7) will

start in the 2070s at the earliest.

Page 27: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

27

ContactinformationOrganisationresponsiblefortheproject:PosivaOyPostaladdress:Olkiluoto,FI-27160EurajokiTelephone:+3582837231Contactperson:MarkkuFribergE-mail:[email protected]

Coordinatingauthority:MinistryofEmploymentandtheEconomyPostaladdress:P.O.Box32,FI-00023ValtioneuvostoTelephone:+35810606000Contactperson:JaanaAvolahtiE-mail:[email protected]

Internationalhearing:MinistryoftheEnvironmentPostaladdress:P.O.Box35,FI-00023ValtioneuvostoTelephone:+35820490100Contactperson:NunuPesuE-mail:[email protected]

Furtherinformationontheprojectwillalsobepro-videdby:EIAconsultant:PöyryEnergyOyPostaladdress:P.O.Box93,FI-02151EspooTelephone:+358103311Contactpeople:TiinaKähöandJaakkoSavolahtiE-mail:[email protected];[email protected]

Page 28: Expansion of the Repository for Spent Environmental Impact Nuclear Fuel Assessment Report · 2008-12-12 · A Summary of the Environmental Impact Assessment Report Environmental Impact

Posiva OyOlkiluoto, 27160 EURAJOKI, FINLAND

Tel. +358 2 8372 31Fax +358 2 8372 3709

www.posiva.fi

Eura

Pri

nt O

y 1

0/2

00

8 1

00

0


Recommended