    Dashboard Software Defects from Mon, 07/06/09 to Sun, 07/12/09 Week 28

    Defects week by type and severity

    Cosmetical Minor Major Critical Total

    assigned 3 14 23 3 43

    resolved 0 7 9 0 16

    closed 9 79 92 16 196

    Total 12 100 124 19 255

    Assigned, resolved and concluded defects cumulated over the last 18 weeks New defects assigned, resolved and concluded last 18 weeks - week on week

    Average resolution / conclusion times in calendar days Average resolution / conclusion times in calendar days last 18 weeks

    Cosmetical Minor Major Critical Total

    10.8 20.9 17.5 8.8 17.9

    6.7 13.9 13.3 6.3 12.7

    17.4 31.7 31.4 15.1 29.6

    Assigned to resolved

    Resolved to closed

    Assigned to closed

    Defect assigned

    fix pending

    Defect assigned,

    fix delivered, not yet retested

    Defect assigned,

    fix delivered and successfully retested

    0

    50

    100

    150

    200

    250

    300

    W 11 W 12 W 13 W 14 W 15 W 16 W 17 W 18 W 19 W 20 W 21 W 22 W 23 W 24 W 25 W 26 W 27 W 28

    Assigned cumulated Resolved cumulated Closed cumulated

    0

    5

    10

    15

    20

    25

    30

    W 11 W 12 W 13 W 14 W 15 W 16 W 17 W 18 W 19 W 20 W 21 W 22 W 23 W 24 W 25 W 26 W 27 W 28

    Assigned Resolved Closed

    0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    Cosmetical Minor Major Critical

    0

    5

    10

    15

    20

    25

    30

    35

    W 11 W 12 W 13 W 14 W 15 W 16 W 17 W 18 W 19 W 20 W 21 W 22 W 23 W 24 W 25 W 26 W 27 W 28

    Assigned to resolved Resolved to closed Assigned to closed

  • 8/13/2019 Export Excel Dashboards to Ppt

    2/21

    Dashboard Software Test Coverage Fri, 10/07/2009 Week 28

    Test cases (TCs) by software modules

    Completion

    rate

    started

    not yet

    f inished finished

    thereof

    passed

    thereof

    failed(finished in % of

    total plan)

    Software Module 1 400 204 209 17 192 170 22 88.5% 48.0% 94.1%

    Software Module 2 300 150 153 9 144 126 18 87.5% 48.0% 96.0%

    Software Module 3 600 300 298 22 276 254 22 92.0% 46.0% 92.0%

    Software Module 4 800 402 417 4 413 364 49 88.1% 51.6% 102.7%

    Software Module 5 400 204 204 15 189 164 25 86.8% 47.3% 92.6%

    Total 2,500 1,260 1,281 67 1,214 1,078 136 88.8% 48.6% 96.3%

    Total actual vs plan over time Passed test cases and success rate threshold

    Actual in % of plan(finished TCs as percentage of planned TCs)

    Success rate in %

    (passed TCs as percentage of finished TCs)

    Goal: 87% or higher success rate

    # TCs

    planned total

    # TCs

    planned for

    end of week

    # TCs executed

    0% 50% 100% 0% 50% 100%

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    W 23 W 24 W 25 W 26 W 27 W 28 W 29 W 30 W 31 W 32 W 33 W 34

    # TCs planned #TCs finished

    169

    377

    550

    710

    893

    1,078

    0

    500

    1,000

    1,500

    2,000

    2,500

    W 23 W 24 W 25 W 26 W 27 W 28 W 29 W 30 W 31 W 32 W 33 W 34

    #TCs passed Success rate threshold

  • 8/13/2019 Export Excel Dashboards to Ppt

    3/21

    Dashboard Software Change Requests Week 28

    Overview actual week Change Request development cumulated

    otal CRs last week New

    this week

    Total CRs this week thereof business thereof IT

    32 1 33 28 584.8% 15.2%

    Change Requests - actual status

    Total 33

    In investigation

    0Approved (in

    implementation) 3

    ncluded (delivered) 21

    Future CRs 4

    Rejected or

    cancelled 5

    Total Change Requests by department Change Request development cumulated by department

    Fri, 10/07/2009

    0

    1

    2

    3

    4

    56

    7

    8

    9

    10

    02 04 06 08 10 12 14 16 18 20 22 24 26 28

    Weeks

    Department 1 Department 2 Department 3 Department 4 Department 5 IT

    3

    5

    5

    5

    6

    9

    Department 5

    Department 1

    Department 4

    IT

    Department 3

    Department 2

    0

    5

    10

    15

    20

    25

    30

    35

    02 04 06 08 10 12 14 16 18 20 22 24 26 28

    Weeks

  • 8/13/2019 Export Excel Dashboards to Ppt

    4/21

    Data Defects

    Defect ID Severity State Assigned on Resolved on Concluded on

    1 Critical closed 1/28/2009 1/28/2009 1/30/2009

    2 Major closed 1/29/2009 1/30/2009 1/31/2009

    3 Major closed 1/30/2009 2/12/2009 2/14/2009

    4 Minor closed 1/30/2009 2/14/2009 2/17/2009

    5 Major closed 1/30/2009 3/17/2009 4/1/2009

    6 Minor closed 1/31/2009 2/10/2009 2/11/2009

    7 Minor closed 1/31/2009 2/4/2009 3/27/2009

    8 Minor closed 2/3/2009 2/14/2009 7/14/2009

    9 Minor closed 2/6/2009 2/13/2009 2/17/2009

    10 Minor closed 2/7/2009 2/14/2009 3/6/2009

    11 Major closed 2/7/2009 2/28/2009 3/4/2009

    12 Minor closed 2/7/2009 3/5/2009 3/7/2009

    13 Minor closed 2/8/2009 2/13/2009 2/25/2009

    14 Minor closed 2/8/2009 2/28/2009 3/7/200915 Cosmetical closed 2/10/2009 3/13/2009 3/14/2009

    16 Major closed 2/11/2009 2/28/2009 4/1/2009

    17 Minor closed 2/11/2009 2/13/2009 6/13/2009

    18 Minor closed 2/12/2009 2/13/2009 9/15/2009

    19 Major closed 2/12/2009 2/12/2009 7/8/2009

    20 Cosmetical closed 2/13/2009 2/18/2009 2/19/2009

    21 Major closed 2/13/2009 2/28/2009 3/3/2009

    22 Major closed 2/13/2009 2/20/2009 2/25/2009

    23 Major closed 2/13/2009 2/28/2009 3/5/2009

    24 Major closed 2/13/2009 2/14/2009 2/14/2009

    25 Minor closed 2/15/2009 4/7/2009 5/9/2009

    26 Minor closed 2/15/2009 4/7/2009 4/10/200927 Major closed 2/17/2009 3/4/2009 3/7/2009

    28 Minor closed 2/18/2009 2/18/2009 2/19/2009

    29 Minor closed 2/19/2009 4/7/2009 4/12/2009

    30 Minor closed 2/19/2009 4/7/2009 6/30/2009

    31 Major closed 2/19/2009 4/7/2009 4/12/2009

    32 Major closed 2/19/2009 4/18/2009 4/18/2009

    33 Cosmetical closed 2/19/2009 2/20/2009 3/27/2009

    34 Major closed 2/19/2009 3/13/2009 3/20/2009

    35 Minor closed 2/19/2009 3/13/2009 4/17/2009

    36 Major closed 2/20/2009 3/13/2009 3/25/2009

    37 Major closed 2/20/2009 3/13/2009 5/5/2009

    38 Major closed 2/20/2009 4/14/2009 4/14/2009

    39 Major closed 2/21/2009 2/24/2009 2/24/200940 Major closed 2/21/2009 4/3/2009 5/5/2009

    41 Minor closed 2/25/2009 3/13/2009 5/6/2009

    42 Major closed 2/25/2009 4/2/2009 4/16/2009

    43 Minor closed 2/25/2009 3/20/2009 3/27/2009

    44 Major closed 2/26/2009 3/13/2009 4/24/2009

    45 Major closed 2/26/2009 3/18/2009 4/1/2009

    46 Minor closed 2/26/2009 8/17/2009 9/18/2009

    47 Major closed 2/26/2009 2/26/2009 2/26/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    5/21

    48 Major closed 2/27/2009 4/8/2009 5/1/2009

    49 Minor closed 2/27/2009 4/7/2009 4/22/2009

    50 Major closed 2/27/2009 3/24/2009 4/10/2009

    51 Minor closed 2/28/2009 3/7/2009 5/2/2009

    52 Minor closed 2/28/2009 3/13/2009 3/25/2009

    53 Minor closed 3/1/2009 3/13/2009 3/14/2009

    54 Major closed 3/5/2009 4/7/2009 6/13/200955 Minor closed 3/5/2009 3/20/2009 3/21/2009

    56 Major closed 3/5/2009 4/7/2009 6/13/2009

    57 Major closed 3/5/2009 4/7/2009 6/13/2009

    58 Minor closed 3/5/2009 4/7/2009 6/13/2009

    59 Minor closed 3/5/2009 4/7/2009 6/13/2009

    60 Major closed 3/5/2009 3/5/2009 3/5/2009

    61 Major closed 3/5/2009 4/7/2009 4/10/2009

    62 Minor closed 3/5/2009 4/7/2009 4/10/2009

    63 Minor closed 3/6/2009 3/7/2009 3/7/2009

    64 Minor closed 3/6/2009 3/13/2009 3/25/2009

    65 Minor closed 3/6/2009 4/22/2009 4/29/2009

    66 Major closed 3/7/2009 4/3/2009 6/10/200967 Minor closed 3/8/2009 7/10/2009 7/14/2009

    68 Cosmetical closed 3/10/2009 3/13/2009 3/14/2009

    69 Cosmetical closed 3/10/2009 3/13/2009 3/14/2009

    70 Cosmetical closed 3/10/2009 3/13/2009 3/14/2009

    71 Minor closed 3/11/2009 3/21/2009 3/25/2009

    72 Major closed 3/11/2009 4/2/2009 4/15/2009

    73 Major closed 3/11/2009 4/7/2009 4/24/2009

    74 Major closed 3/11/2009 4/7/2009 4/18/2009

    75 Minor closed 3/11/2009 3/18/2009 3/25/2009

    76 Major closed 3/11/2009 4/7/2009 5/1/2009

    77 Major closed 3/12/2009 3/17/2009 4/3/2009

    78 Major closed 3/13/2009 3/25/2009 3/25/2009

    79 Major closed 3/14/2009 4/2/2009 4/9/2009

    80 Minor closed 3/14/2009 7/10/2009 7/18/2009

    81 Minor closed 3/15/2009 3/16/2009 3/23/2009

    82 Minor closed 3/15/2009 3/16/2009 3/23/2009

    83 Major closed 3/15/2009 4/2/2009 4/30/2009

    84 Critical closed 3/15/2009 4/2/2009 4/24/2009

    85 Major closed 3/15/2009 4/22/2009 4/24/2009

    86 Minor closed 3/15/2009 4/8/2009 4/9/2009

    87 Major closed 3/18/2009 3/18/2009 3/18/2009

    88 Minor closed 3/18/2009 4/7/2009 6/13/2009

    89 Major closed 3/20/2009 4/2/2009 5/5/2009

    90 Minor closed 3/20/2009 4/3/2009 4/14/2009

    91 Minor closed 3/21/2009 4/3/2009 4/8/200992 Minor closed 3/24/2009 4/7/2009 6/13/2009

    93 Major closed 3/25/2009 4/2/2009 4/8/2009

    94 Critical closed 3/25/2009 4/2/2009 4/16/2009

    95 Major closed 3/25/2009 4/3/2009 4/4/2009

    96 Minor closed 3/25/2009 4/2/2009 4/3/2009

    97 Minor closed 3/25/2009 4/18/2009 5/5/2009

    98 Major closed 3/27/2009 5/22/2009 5/23/2009

    99 Major closed 3/27/2009 4/2/2009 4/3/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    6/21

    100 Major closed 3/27/2009 4/3/2009 4/17/2009

    101 Minor closed 3/28/2009 4/18/2009 4/22/2009

    102 Major closed 3/28/2009 4/8/2009 5/8/2009

    103 Minor closed 3/31/2009 4/7/2009 4/10/2009

    104 Cosmetical closed 4/1/2009 4/9/2009 4/23/2009

    105 Critical closed 4/3/2009 4/8/2009 4/9/2009

    106 Minor closed 4/5/2009 4/16/2009 4/17/2009107 Major closed 4/5/2009 4/24/2009 4/30/2009

    108 Minor closed 4/8/2009 5/12/2009 5/22/2009

    109 Major closed 4/8/2009 4/18/2009 4/22/2009

    110 Minor closed 4/8/2009 4/18/2009 4/22/2009

    111 Major closed 4/9/2009 7/15/2009 7/22/2009

    112 Minor closed 4/9/2009 4/18/2009 4/23/2009

    113 Minor closed 4/9/2009 4/18/2009 4/23/2009

    114 Minor closed 4/9/2009 4/16/2009 4/17/2009

    115 Minor closed 4/9/2009 5/22/2009 5/22/2009

    116 Major closed 4/10/2009 7/15/2009 8/18/2009

    117 Major closed 4/10/2009 4/10/2009 4/10/2009

    118 Minor closed 4/10/2009 5/15/2009 5/23/2009119 Critical closed 4/11/2009 4/18/2009 4/23/2009

    120 Minor closed 4/11/2009 5/1/2009 5/2/2009

    121 Minor closed 4/14/2009 5/22/2009 6/10/2009

    122 Major closed 4/14/2009 4/15/2009 4/24/2009

    123 Major closed 4/16/2009 4/22/2009 4/24/2009

    124 Major closed 4/16/2009 5/29/2009 5/30/2009

    125 Critical closed 4/16/2009 5/9/2009 5/14/2009

    126 Minor closed 4/16/2009 5/9/2009 5/13/2009

    127 Major closed 4/17/2009 5/1/2009 9/19/2009

    128 Major closed 4/17/2009 5/1/2009 5/7/2009

    129 Minor closed 4/17/2009 7/22/2009 9/19/2009

    130 Major closed 4/17/2009 5/9/2009 5/9/2009

    131 Minor closed 4/17/2009 5/5/2009 5/6/2009

    132 Major closed 4/17/2009 5/1/2009 5/6/2009

    133 Critical closed 4/18/2009 5/22/2009 5/29/2009

    134 Major closed 4/22/2009 5/23/2009 6/2/2009

    135 Major closed 4/22/2009 5/23/2009 6/3/2009

    136 Major closed 4/22/2009 5/11/2009 5/13/2009

    137 Major closed 4/23/2009 5/23/2009 5/23/2009

    138 Major closed 4/23/2009 7/15/2009 7/22/2009

    139 Major closed 4/23/2009 5/22/2009 5/31/2009

    140 Cosmetical closed 4/24/2009 7/22/2009 7/30/2009

    141 Minor closed 4/25/2009 5/1/2009 5/1/2009

    142 Minor closed 4/29/2009 4/29/2009 4/29/2009

    143 Minor closed 4/30/2009 7/10/2009 7/10/2009144 Minor closed 4/30/2009 7/3/2009 7/19/2009

    145 Minor closed 4/30/2009 5/23/2009 5/23/2009

    146 Minor closed 4/30/2009 5/12/2009 6/3/2009

    147 Major closed 4/30/2009 5/22/2009 5/28/2009

    148 Major resolved 5/1/2009 5/22/2009 5/30/2009

    149 Major closed 5/1/2009 5/29/2009 6/9/2009

    150 Minor closed 5/1/2009 5/12/2009 6/6/2009

    151 Major closed 5/1/2009 5/22/2009 5/23/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    7/21

    152 Major closed 5/2/2009 5/29/2009 5/30/2009

    153 Major closed 5/2/2009 5/21/2009 5/23/2009

    154 Critical closed 5/2/2009 5/6/2009 5/6/2009

    155 Minor closed 5/2/2009 5/29/2009 6/10/2009

    156 Minor closed 5/3/2009 5/12/2009 5/23/2009

    157 Minor closed 5/3/2009 5/9/2009 5/21/2009

    158 Major closed 5/3/2009 5/29/2009 7/1/2009159 Major closed 5/6/2009 5/22/2009 5/29/2009

    160 Major closed 5/6/2009 5/22/2009 5/23/2009

    161 Major closed 5/6/2009 5/23/2009 5/23/2009

    162 Minor closed 5/6/2009 7/10/2009 7/19/2009

    163 Critical closed 5/6/2009 5/9/2009 5/9/2009

    164 Major closed 5/7/2009 6/4/2009 6/10/2009

    165 Minor closed 5/7/2009 5/22/2009 6/2/2009

    166 Major closed 5/8/2009 5/22/2009 5/29/2009

    167 Minor closed 5/8/2009 7/24/2009 7/25/2009

    168 Major closed 5/8/2009 7/15/2009 7/22/2009

    169 Critical closed 5/9/2009 5/15/2009 5/22/2009

    170 Critical closed 5/9/2009 7/31/2009 8/12/2009171 Cosmetical closed 5/12/2009 5/29/2009 6/3/2009

    172 Major closed 5/13/2009 5/19/2009 5/21/2009

    173 Minor closed 5/14/2009 7/15/2009 10/1/2009

    174 Cosmetical closed 5/15/2009 6/10/2009 6/11/2009

    175 Minor closed 5/16/2009 6/29/2009 7/8/2009

    176 Major closed 5/19/2009 5/28/2009 7/30/2009

    177 Major closed 5/19/2009 5/22/2009 7/11/2009

    178 Critical closed 5/21/2009 7/15/2009 7/25/2009

    179 Minor closed 5/22/2009 6/4/2009 6/4/2009

    180 Minor closed 5/22/2009 7/15/2009 8/18/2009

    181 Critical closed 5/23/2009 5/29/2009 6/2/2009

    182 Critical closed 5/23/2009 5/29/2009 5/30/2009

    183 Minor closed 5/23/2009 5/30/2009 5/30/2009

    184 Minor closed 5/24/2009 9/1/2009 9/30/2009

    185 Critical closed 5/24/2009 5/30/2009 6/3/2009

    186 Critical closed 5/26/2009 5/27/2009 5/28/2009

    187 Major closed 5/26/2009 7/15/2009 7/22/2009

    188 Major closed 5/27/2009 6/4/2009 6/9/2009

    189 Major closed 5/27/2009 7/15/2009 7/22/2009

    190 Minor closed 5/27/2009 6/7/2009 7/8/2009

    191 Critical closed 5/28/2009 7/15/2009 7/23/2009

    192 Major closed 5/28/2009 5/30/2009 6/3/2009

    193 Major closed 5/28/2009 6/4/2009 6/10/2009

    194 Major closed 5/28/2009 6/10/2009 6/10/2009

    195 Minor closed 5/29/2009 10/21/2009 10/21/2009196 Major closed 5/29/2009 6/5/2009 6/6/2009

    197 Major closed 5/30/2009 7/22/2009 7/30/2009

    198 Minor closed 5/30/2009 5/31/2009 6/6/2009

    199 Critical closed 5/31/2009 6/10/2009 7/8/2009

    200 Major closed 6/2/2009 6/10/2009 6/13/2009

    201 Major closed 6/2/2009 6/7/2009 6/9/2009

    202 Major closed 6/2/2009 7/31/2009 9/12/2009

    203 Minor closed 6/3/2009 6/10/2009 6/10/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    8/21

    204 Minor closed 6/3/2009 6/30/2009 7/10/2009

    205 Minor closed 6/3/2009 6/13/2009 6/13/2009

    206 Major closed 6/3/2009 6/4/2009 7/7/2009

    207 Major closed 6/3/2009 7/15/2009 7/28/2009

    208 Minor closed 6/3/2009 6/29/2009 7/1/2009

    209 Minor closed 6/3/2009 6/10/2009 6/11/2009

    210 Minor closed 6/3/2009 6/10/2009 6/11/2009211 Minor closed 6/4/2009 7/15/2009 8/18/2009

    212 Major closed 6/4/2009 6/4/2009 6/11/2009

    213 Major closed 6/4/2009 6/25/2009 7/3/2009

    214 Minor closed 6/4/2009 6/30/2009 6/30/2009

    215 Major closed 6/5/2009 6/10/2009 6/10/2009

    216 Minor closed 6/5/2009 7/22/2009 7/22/2009

    217 Major closed 6/9/2009 6/11/2009 6/11/2009

    218 Major closed 6/9/2009 7/15/2009 7/28/2009

    219 Major closed 6/10/2009 6/25/2009 7/4/2009

    220 Major closed 6/11/2009 6/19/2009 7/4/2009

    221 Major closed 6/11/2009 6/14/2009 7/25/2009

    222 Major closed 6/11/2009 6/25/2009 7/9/2009223 Major closed 6/11/2009 7/10/2009 7/16/2009

    224 Major closed 6/12/2009 7/3/2009 7/24/2009

    225 Minor closed 6/12/2009 7/21/2009 7/28/2009

    226 Major resolved 6/13/2009 7/23/2009 7/29/2009

    227 Major closed 6/18/2009 7/15/2009 7/28/2009

    228 Major closed 6/23/2009 7/3/2009 7/15/2009

    229 Major closed 6/23/2009 7/10/2009 7/16/2009

    230 Minor closed 6/23/2009 7/7/2009 7/8/2009

    231 Major closed 6/24/2009 7/15/2009 7/28/2009

    232 Major closed 6/24/2009 7/15/2009 7/25/2009

    233 Major closed 6/25/2009 7/24/2009 7/25/2009

    234 Minor closed 6/25/2009 7/3/2009 7/5/2009

    235 Major closed 6/25/2009 7/15/2009 7/24/2009

    236 Major closed 6/28/2009 6/29/2009 7/2/2009

    237 Critical closed 6/30/2009 7/3/2009 7/3/2009

    238 Major closed 7/2/2009 7/3/2009 7/18/2009

    239 Major closed 7/2/2009 7/3/2009 7/15/2009

    240 Minor closed 7/2/2009 7/3/2009 7/3/2009

    241 Major closed 7/3/2009 7/22/2009 7/25/2009

    242 Minor closed 7/3/2009 7/21/2009 7/28/2009

    243 Major closed 7/3/2009 7/18/2009 7/21/2009

    244 Major closed 7/4/2009 7/21/2009 8/4/2009

    245 Minor closed 7/4/2009 7/10/2009 7/15/2009

    246 Minor closed 7/7/2009 7/10/2009 7/12/2009

    247 Cosmetical closed 7/7/2009 7/21/2009 8/7/2009248 Major closed 7/7/2009 7/18/2009 7/24/2009

    249 Minor closed 7/7/2009 7/21/2009 8/12/2009

    250 Minor closed 7/7/2009 7/22/2009 7/25/2009

    251 Major closed 7/7/2009 7/18/2009 7/30/2009

    252 Minor closed 7/7/2009 7/21/2009 7/24/2009

    253 Cosmetical closed 7/9/2009 7/24/2009 8/7/2009

    254 Major closed 7/9/2009 7/18/2009 7/25/2009

    255 Major closed 7/10/2009 7/18/2009 7/28/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    9/21

    256 Major closed 7/15/2009 7/31/2009 9/17/2009

    257 Minor closed 7/15/2009 8/7/2009 8/8/2009

    258 Minor closed 7/16/2009 8/15/2009 8/21/2009

    259 Major closed 7/16/2009 8/15/2009 9/3/2009

    260 Major closed 7/21/2009 7/31/2009 7/31/2009

    261 Major closed 7/21/2009 7/28/2009 8/13/2009

    262 Minor closed 7/22/2009 9/2/2009 9/20/2009263 Major closed 7/22/2009 8/7/2009 9/1/2009

    264 Minor closed 7/23/2009 8/5/2009 9/4/2009

    265 Major resolved 7/23/2009 9/2/2009 9/10/2009

    266 Major resolved 7/23/2009 9/2/2009 9/9/2009

    267 Minor closed 7/23/2009 7/29/2009 7/30/2009

    268 Major closed 7/23/2009 7/29/2009 7/31/2009

    269 Cosmetical closed 7/24/2009 8/5/2009 8/8/2009

    270 Minor closed 7/25/2009 8/5/2009 8/12/2009

    271 Minor closed 7/25/2009 9/3/2009 9/11/2009

    272 Minor closed 7/25/2009 8/5/2009 9/11/2009

    273 Major closed 7/29/2009 8/15/2009 8/25/2009

    274 Minor closed 7/29/2009 9/2/2009 9/24/2009275 Minor closed 7/30/2009 7/30/2009 7/30/2009

    276 Major closed 7/30/2009 8/6/2009 9/16/2009

    277 Major closed 8/1/2009 8/21/2009 9/8/2009

    278 Cosmetical closed 8/1/2009 8/7/2009 8/11/2009

    279 Critical closed 8/1/2009 8/6/2009 8/13/2009

    280 Major closed 8/5/2009 9/12/2009 9/29/2009

    281 Major closed 8/5/2009 8/15/2009 8/25/2009

    282 Major closed 8/5/2009 9/1/2009 10/2/2009

    283 Major closed 8/6/2009 10/8/2009 10/17/2009

    284 Major closed 8/8/2009 8/17/2009 8/26/2009

    285 Major closed 8/8/2009 8/11/2009 8/26/2009

    286 Minor closed 8/8/2009 9/8/2009 10/2/2009

    287 Critical closed 8/11/2009 8/13/2009 9/3/2009

    288 Minor closed 8/12/2009 8/18/2009 9/8/2009

    289 Major closed 8/14/2009 9/30/2009 10/2/2009

    290 Major closed 8/15/2009 8/19/2009 8/26/2009

    291 Critical closed 8/15/2009 8/16/2009 8/18/2009

    292 Major closed 8/18/2009 10/7/2009 10/9/2009

    293 Major closed 8/18/2009 10/8/2009 10/17/2009

    294 Major closed 8/18/2009 9/5/2009 9/22/2009

    295 Major closed 8/19/2009 9/26/2009 9/29/2009

    296 Minor closed 8/19/2009 9/6/2009 9/22/2009

    297 Minor closed 8/21/2009 9/2/2009 9/10/2009

    298 Major closed 8/22/2009 10/14/2009 10/21/2009

    299 Major closed 8/22/2009 9/6/2009 9/23/2009300 Major closed 8/26/2009 8/27/2009 8/27/2009

    301 Minor closed 8/26/2009 8/28/2009 9/4/2009

    302 Minor closed 8/26/2009 9/11/2009 10/1/2009

    303 Major closed 8/26/2009 9/1/2009 9/4/2009

    304 Major assigned 8/26/2009 9/3/2009 9/9/2009

    305 Cosmetical resolved 8/29/2009 10/14/2009 10/21/2009

    306 Major closed 8/29/2009 9/5/2009 10/2/2009

    307 Major closed 9/1/2009 10/14/2009 10/21/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    10/21

    308 Minor closed 9/3/2009 10/14/2009 10/20/2009

    309 Cosmetical assigned 9/3/2009 9/15/2009 9/21/2009

    310 Minor closed 9/5/2009 9/26/2009 9/27/2009

    311 Major closed 9/5/2009 9/18/2009 9/23/2009

    312 Minor assigned 9/6/2009 9/14/2009 9/23/2009

    313 Minor closed 9/8/2009 9/11/2009 9/23/2009

    314 Minor closed 9/8/2009 9/11/2009 9/11/2009315 Minor closed 9/8/2009 9/18/2009 9/24/2009

    316 Major resolved 9/8/2009 10/14/2009 10/21/2009

    317 Major closed 9/9/2009 9/22/2009 9/30/2009

    318 Cosmetical closed 9/9/2009 9/16/2009 9/26/2009

    319 Major closed 9/10/2009 9/18/2009 9/19/2009

    320 Major closed 9/10/2009 9/18/2009 9/19/2009

    321 Minor closed 9/10/2009 9/23/2009 9/24/2009

    322 Major closed 9/10/2009 9/23/2009 10/2/2009

    323 Major closed 9/11/2009 9/20/2009 9/29/2009

    324 Minor closed 9/11/2009 9/18/2009 9/24/2009

    325 Minor closed 9/11/2009 9/20/2009 10/3/2009

    326 Minor closed 9/11/2009 9/11/2009 10/1/2009327 Minor closed 9/11/2009 9/18/2009 9/29/2009

    328 Major closed 9/12/2009 9/23/2009 10/1/2009

    329 Major closed 9/13/2009 9/21/2009 10/1/2009

    330 Major assigned 9/13/2009 9/23/2009 9/30/2009

    331 Cosmetical closed 9/13/2009 9/22/2009 9/26/2009

    332 Cosmetical closed 9/15/2009 9/25/2009 9/29/2009

    333 Minor closed 9/16/2009 9/30/2009 10/3/2009

    334 Major closed 9/16/2009 9/26/2009 9/30/2009

    335 Minor closed 9/16/2009 9/23/2009 9/25/2009

    336 Minor resolved 9/16/2009 10/14/2009 10/23/2009

    337 Major resolved 9/16/2009 10/14/2009 10/20/2009

    338 Major closed 9/17/2009 9/26/2009 9/30/2009

    339 Major closed 9/17/2009 9/23/2009 9/23/2009

    340 Major closed 9/18/2009 10/14/2009 10/17/2009

    341 Minor closed 9/18/2009 9/25/2009 9/26/2009

    342 Minor assigned 9/19/2009 9/29/2009 10/5/2009

    343 Minor closed 9/19/2009 9/26/2009 10/2/2009

    344 Major resolved 9/19/2009 10/14/2009 10/23/2009

    345 Minor resolved 9/19/2009 10/14/2009 10/19/2009

    346 Major closed 9/20/2009 9/26/2009 9/27/2009

    347 Minor closed 9/22/2009 9/25/2009 10/3/2009

    348 Minor closed 9/23/2009 9/26/2009 9/30/2009

    349 Minor closed 9/24/2009 9/24/2009 9/24/2009

    350 Major closed 9/25/2009 9/30/2009 10/3/2009

    351 Cosmetical closed 9/25/2009 9/26/2009 9/29/2009352 Major resolved 9/25/2009 10/14/2009 10/22/2009

    353 Major resolved 9/25/2009 10/14/2009 10/19/2009

    354 Minor closed 9/26/2009 10/15/2009 10/20/2009

    355 Major resolved 9/26/2009 10/14/2009 10/19/2009

    356 Major closed 9/29/2009 10/14/2009 10/28/2009

    357 Major closed 9/30/2009 10/14/2009 10/17/2009

    358 Minor resolved 9/30/2009 10/14/2009 10/20/2009

    359 Minor closed 10/1/2009 10/14/2009 10/17/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    11/21

    360 Cosmetical closed 10/2/2009 10/21/2009 10/22/2009

    361 Major resolved 10/2/2009 10/23/2009 10/29/2009

    362 Major resolved 10/2/2009 10/23/2009 10/29/2009

    363 Minor resolved 10/2/2009 10/17/2009 10/27/2009

    364 Minor resolved 10/2/2009 10/15/2009 10/22/2009

    365 Major closed 10/2/2009 10/4/2009 10/9/2009

    366 Minor resolved 10/3/2009 10/14/2009 10/24/2009367 Minor resolved 10/3/2009 10/14/2009 10/21/2009

    368 Minor resolved 10/3/2009 10/3/2009 10/11/2009

    369 Cosmetical assigned 10/6/2009 10/15/2009 10/20/2009

    370 Major closed 10/8/2009 10/20/2009 11/3/2009

    371 Major resolved 10/8/2009 10/20/2009 10/25/2009

    372 Minor resolved 10/9/2009 10/24/2009 11/1/2009

    373 Minor resolved 10/9/2009 10/20/2009 10/30/2009

    374 Major closed 10/9/2009 10/21/2009 10/22/2009

    375 Cosmetical resolved 10/13/2009 10/24/2009 11/1/2009

    376 Minor resolved 10/13/2009 10/23/2009 10/29/2009

    377 Minor closed 10/15/2009 10/21/2009 10/22/2009

    378 Major assigned 10/16/2009 10/23/2009 10/28/2009379 Major assigned 10/16/2009 10/24/2009 11/2/2009

    380 Minor closed 10/20/2009 10/23/2009 10/30/2009

    381 Cosmetical assigned 10/20/2009 10/29/2009 11/8/2009

    382 Major assigned 10/21/2009 11/1/2009 11/8/2009

    383 Minor assigned 10/21/2009 11/1/2009 11/10/2009

    384 Major closed 10/21/2009 10/22/2009 10/28/2009

    385 Major assigned 10/22/2009 11/2/2009 11/8/2009

    386 Minor assigned 10/23/2009 10/30/2009 11/4/2009

    387 Minor assigned 10/23/2009 10/30/2009 11/9/2009

    388 Major assigned 10/24/2009 10/31/2009 11/10/2009

    389 Major assigned 10/24/2009 9/2/2009 9/9/2009

    390 Major resolved 10/27/2009 11/3/2009 11/13/2009

    391 Major assigned 10/27/2009 11/8/2009 11/13/2009

    392 Major assigned 10/28/2009 11/9/2009 11/17/2009

    393 Minor assigned 10/28/2009 11/8/2009 11/18/2009

    394 Minor resolved 10/28/2009 10/28/2009 11/4/2009

    395 Minor assigned 10/28/2009 11/7/2009 11/16/2009

    396 Major closed 10/28/2009 10/30/2009 10/30/2009

    397 Major assigned 10/28/2009 11/7/2009 11/13/2009

    398 Major assigned 10/28/2009 11/7/2009 11/13/2009

    399 Major assigned 10/30/2009 10/16/2009 10/24/2009

    400 Minor assigned 10/30/2009 11/10/2009 11/17/2009

    401 Minor assigned 10/30/2009 11/9/2009 11/18/2009

    402 Minor assigned 11/3/2009 11/13/2009 11/22/2009

    403 Major assigned 11/3/2009 11/15/2009 11/25/2009404 Minor assigned 11/3/2009 11/14/2009 11/23/2009

    405 Major assigned 11/3/2009 11/13/2009 11/20/2009

    406 Critical assigned 11/3/2009 11/14/2009 11/22/2009

    407 Minor assigned 11/3/2009 11/12/2009 11/21/2009

    408 Minor assigned 11/3/2009 11/10/2009 11/15/2009

    409 Minor assigned 11/3/2009 11/11/2009 11/18/2009

    410 Minor assigned 11/3/2009 11/10/2009 11/17/2009

    411 Minor assigned 11/3/2009 11/15/2009 11/21/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    12/21

    412 Minor assigned 11/3/2009 11/11/2009 11/17/2009

    413 Major assigned 11/3/2009 11/13/2009 11/21/2009

    414 Minor assigned 11/4/2009 11/16/2009 11/26/2009

    415 Major assigned 11/4/2009 11/12/2009 11/21/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    13/21

  • 8/13/2019 Export Excel Dashboards to Ppt

    14/21

    Data Test

    Planned test cases by module

    Software Module 1 400

    Software Module 2 300

    Software Module 3 600

    Software Module 4 800

    Software Module 5 400

    Test threshold success rate 87% goal of successfully conducted test cases in % of all test casesThreshold completion rate 95% highlight if actual completion rate is lower than this threshold

    Week Date Software Module #TCs

    completed

    #TCs not

    completed #TCs passed #TCs failed

    W 23 Fri, 05/06/2009 Software Module 1 29 1 25 4

    W 23 Fri, 05/06/2009 Software Module 2 21 1 19 2

    W 23 Fri, 05/06/2009 Software Module 3 49 1 46 3

    W 23 Fri, 05/06/2009 Software Module 4 55 2 49 6

    W 23 Fri, 05/06/2009 Software Module 5 37 2 30 7

    W 24 Fri, 12/06/2009 Software Module 1 67 5 60 7

    W 24 Fri, 12/06/2009 Software Module 2 51 2 46 5

    W 24 Fri, 12/06/2009 Software Module 3 97 9 92 5

    W 24 Fri, 12/06/2009 Software Module 4 132 7 120 12

    W 24 Fri, 12/06/2009 Software Module 5 68 1 59 9W 25 Fri, 19/06/2009 Software Module 1 102 0 93 9

    W 25 Fri, 19/06/2009 Software Module 2 71 4 62 9

    W 25 Fri, 19/06/2009 Software Module 3 143 13 129 14

    W 25 Fri, 19/06/2009 Software Module 4 210 11 180 30

    W 25 Fri, 19/06/2009 Software Module 5 98 0 86 12

    W 26 Fri, 26/06/2009 Software Module 1 131 12 117 14

    W 26 Fri, 26/06/2009 Software Module 2 92 6 80 12

    W 26 Fri, 26/06/2009 Software Module 3 189 0 173 16

    W 26 Fri, 26/06/2009 Software Module 4 271 24 236 35

    W 26 Fri, 26/06/2009 Software Module 5 125 4 104 21

    W 27 Fri, 03/07/2009 Software Module 1 158 3 139 19

    W 27 Fri, 03/07/2009 Software Module 2 116 0 102 14

    W 27 Fri, 03/07/2009 Software Module 3 229 0 212 17

    W 27 Fri, 03/07/2009 Software Module 4 342 24 307 35

    W 27 Fri, 03/07/2009 Software Module 5 156 8 133 23W 28 Fri, 10/07/2009 Software Module 1 192 17 170 22

    W 28 Fri, 10/07/2009 Software Module 2 144 9 126 18

    W 28 Fri, 10/07/2009 Software Module 3 276 22 254 22

    W 28 Fri, 10/07/2009 Software Module 4 413 4 364 49

    W 28 Fri, 10/07/2009 Software Module 5 189 15 164 25

    W 29 Fri, 17/07/2009 Software Module 1 223 9 199 24

    W 29 Fri, 17/07/2009 Software Module 2 172 2 151 21

    W 29 Fri, 17/07/2009 Software Module 3 321 13 296 25

    W 29 Fri, 17/07/2009 Software Module 4 473 0 421 52

    W 29 Fri, 17/07/2009 Software Module 5 223 22 192 31

    W 30 Fri, 24/07/2009 Software Module 1 259 26 226 33

    W 30 Fri, 24/07/2009 Software Module 2 195 0 172 23

    W 30 Fri, 24/07/2009 Software Module 3 378 30 347 31

    W 30 Fri, 24/07/2009 Software Module 4 548 22 476 72

    W 30 Fri, 24/07/2009 Software Module 5 252 0 215 37W 31 Fri, 31/07/2009 Software Module 1 287 6 252 35

    W 31 Fri, 31/07/2009 Software Module 2 216 13 190 26

    W 31 Fri, 31/07/2009 Software Module 3 427 38 394 33

    W 31 Fri, 31/07/2009 Software Module 4 601 36 526 75

    W 31 Fri, 31/07/2009 Software Module 5 280 3 238 42

    W 32 Fri, 07/08/2009 Software Module 1 324 10 286 38

    W 32 Fri, 07/08/2009 Software Module 2 239 24 210 29

    W 32 Fri, 07/08/2009 Software Module 3 469 23 434 35

    W 32 Fri, 07/08/2009 Software Module 4 656 7 577 79

    W 32 Fri, 07/08/2009 Software Module 5 314 31 265 49

    W 33 Fri, 14/08/2009 Software Module 1 363 25 323 40

    W 33 Fri, 14/08/2009 Software Module 2 268 11 238 30

    W 33 Fri, 14/08/2009 Software Module 3 517 31 478 39

    W 33 Fri, 14/08/2009 Software Module 4 725 36 630 95

    W 33 Fri, 14/08/2009 Software Module 5 343 24 289 54

    W 34 Fri, 21/08/2009 Software Module 1 400 0 356 44

    W 34 Fri, 21/08/2009 Software Module 2 294 0 263 31

    W 34 Fri, 21/08/2009 Software Module 3 600 0 557 43

    W 34 Fri, 21/08/2009 Software Module 4 798 0 694 104

    W 34 Fri, 21/08/2009 Software Module 5 400 0 338 62

    #TCs cumulated

  • 8/13/2019 Export Excel Dashboards to Ppt

    15/21

    Data Change Requests

    CR # Change Request Department New (entered) Approved (in

    implementation)

    Included

    (delivered)

    Future CRs Rejected or

    cancelled

    1 Change Request 001 Department 5 Thu, 05/02/2009 Mon, 09/02/2009 Thu, 05/03/2009

    2 Change Request 002 Department 1 Fri, 13/02/2009 Wed, 18/02/2009 Fri, 06/03/2009

    3 Change Request 003 Department 1 Thu, 19/02/2009 Mon, 23/03/2009 Fri, 10/04/2009

    4 Change Request 004 Department 2 Mon, 02/03/2009 Thu, 05/03/2009 Mon, 16/03/2009

    5 Change Request 005 Department 1 Fri, 06/03/2009 Wed, 11/03/20096 Change Request 006 IT Mon, 16/03/2009 Fri, 20/03/2009 Wed, 08/04/2009

    7 Change Request 007 IT Tue, 17/03/2009 Fri, 20/03/2009 Mon, 06/04/2009

    8 Change Request 008 IT Wed, 25/03/2009 Mon, 30/03/2009

    9 Change Request 009 Department 3 Tue, 31/03/2009 Thu, 02/04/2009 Mon, 13/04/2009

    10 Change Request 010 Department 2 Wed, 08/04/2009 Mon, 13/04/2009 Tue, 28/04/2009

    11 Change Request 011 Department 2 Thu, 16/04/2009 Fri, 17/04/2009 Mon, 27/04/2009

    12 Change Request 012 Department 5 Fri, 17/04/2009 Tue, 21/04/2009 Fri, 08/05/2009

    13 Change Request 013 Department 1 Thu, 16/04/2009 Mon, 20/04/2009 Thu, 14/05/2009

    14 Change Request 014 Department 2 Mon, 20/04/2009 Wed, 22/04/2009

    15 Change Request 015 Department 2 Fri, 24/04/2009 Mon, 27/04/2009 Tue, 12/05/2009

    16 Change Request 016 Department 4 Fri, 01/05/2009 Wed, 06/05/2009

    17 Change Request 017 Department 3 Fri, 01/05/2009 Tue, 05/05/2009 Thu, 21/05/2009

    18 Change Request 018 Department 4 Mon, 04/05/2009 Thu, 07/05/2009 Mon, 25/05/2009

    19 Change Request 019 Department 1 Tue, 05/05/2009 Thu, 07/05/2009 Fri, 15/05/2009

    20 Change Request 020 Department 3 Tue, 05/05/2009 Fri, 08/05/2009 Tue, 19/05/2009

    21 Change Request 021 Department 4 Mon, 18/05/2009 Mon, 25/05/2009 Tue, 09/06/200922 Change Request 022 Department 4 Wed, 20/05/2009 Mon, 25/05/2009

    23 Change Request 023 IT Thu, 21/05/2009 Tue, 26/05/2009 Tue, 02/06/2009

    24 Change Request 024 Department 5 Fri, 29/05/2009 Wed, 03/06/2009 Tue, 16/06/2009

    25 Change Request 025 Department 2 Fri, 05/06/2009 Wed, 10/06/2009

    26 Change Request 026 Department 4 Thu, 11/06/2009 Mon, 15/06/2009 Thu, 09/07/2009

    27 Change Request 027 Department 3 Thu, 18/06/2009 Mon, 22/06/2009

    28 Change Request 028 Department 2 Thu, 18/06/2009 Mon, 22/06/2009 Mon, 13/07/2009

    29 Change Request 029 IT Mon, 22/06/2009 Thu, 25/06/2009 Wed, 08/07/2009

    30 Change Request 030 Department 3 Fri, 26/06/2009 Wed, 01/07/2009

    31 Change Request 031 Department 3 Fri, 26/06/2009 Mon, 29/06/2009

    32 Change Request 032 Department 2 Thu, 02/07/2009 Mon, 06/07/2009 Tue, 28/07/2009

    33 Change Request 033 Department 2 Tue, 07/07/2009 Fri, 10/07/2009 Wed, 22/07/2009

    34 Change Request 034 Department 2 Wed, 15/07/2009 Mon, 20/07/2009 Wed, 29/07/2009

    35 Change Request 035 IT Fri, 24/07/2009 Mon, 27/07/2009

    36 Change Request 036 Department 1 Fri, 24/07/2009 Tue, 28/07/2009 Wed, 12/08/200937 Change Request 037 Department 1 Tue, 28/07/2009 Fri, 31/07/2009 Mon, 17/08/2009

    38 Change Request 038 Department 2 Wed, 29/07/2009 Mon, 03/08/2009 Thu, 20/08/2009

    39 Change Request 039 Department 1 Fri, 14/08/2009 Wed, 19/08/2009

    40 Change Request 040 Department 1 Mon, 24/08/2009 Thu, 27/08/2009

    41 Change Request 041 Department 3 Tue, 01/09/2009 Fri, 04/09/2009

    42 Change Request 042 Department 1 Thu, 03/09/2009 Fri, 04/09/2009

    43 Change Request 043 Department 4 Wed, 09/09/2009 Mon, 14/09/2009

    44 Change Request 044 Department 1 Fri, 11/09/2009 Mon, 14/09/2009

    45 Change Request 045 Department 3 Mon, 21/09/2009 Thu, 24/09/2009

    46 Change Request 046 Department 4 Tue, 22/09/2009 Mon, 28/09/2009

    47 Change Request 047 Department 1 Thu, 24/09/2009 Tue, 29/09/2009

    48 Change Request 048 Department 1 Thu, 24/09/2009 Tue, 29/09/2009

    49 Change Request 049 Department 2 Fri, 25/09/2009 Mon, 28/09/2009

    50 Change Request 050 Department 1 Wed, 30/09/2009 Fri, 02/10/2009

    Dates of change request status

  • 8/13/2019 Export Excel Dashboards to Ppt

    16/21

    Defects - Control

    Cosmetical Minor Major Critical Total

    assigned 3 14 23 3 43

    resolved 0 7 9 0 16

    closed 9 79 92 16 196

    Total 12 100 124 19 255

    Week Start End Assigned Resolved Closed Assignedcumulated

    Resolvedcumulated

    Closedcumulated

    Assigned toresolved

    Resolved toclosed

    Assigned toclosed

    Assigned toresolved

    Resolved toclosed

    Assc

    W 11 Mon, 09/03/2009 Sun, 15/03/2009 19 13 5 86 43 27 9.74 3.00 11.85 9.74 3.00

    W 12 Mon, 16/03/2009 Sun, 22/03/2009 5 10 3 91 53 30 10.32 2.97 12.17 10.32 2.97

    W 13 Mon, 23/03/2009 Sun, 29/03/2009 11 2 11 102 55 41 10.62 5.93 15.10 10.62 5.93

    W 14 Mon, 30/03/2009 Sun, 05/04/2009 5 16 7 107 71 48 11.99 6.75 16.90 11.99 6.75

    W 15 Mon, 06/04/2009 Sun, 12/04/2009 13 25 13 120 96 61 16.40 6.28 19.38 16.40 6.28

    W 16 Mon, 13/04/2009 Sun, 19/04/2009 13 12 11 133 108 72 16.61 6.90 21.68 16.61 6.90

    W 17 Mon, 20/04/2009 Sun, 26/04/2009 8 4 14 141 112 86 17.00 7.52 22.43 17.00 7.52

    W 18 Mon, 27/04/2009 Sun, 03/05/2009 17 6 9 158 118 95 16.71 8.34 23.77 16.71 8.34

    W 19 Mon, 04/05/2009 Sun, 10/05/2009 12 7 13 170 125 108 16.57 9.77 25.68 16.57 9.77

    W 20 Mon, 11/05/2009 Sun, 17/05/2009 5 7 3 175 132 111 16.64 9.60 25.67 16.64 9.60

    W 21 Mon, 18/05/2009 Sun, 24/05/2009 10 20 14 185 152 125 17.64 8.97 25.80 17.64 8.97

    W 22 Mon, 25/05/2009 Sun, 31/05/2009 14 14 11 199 166 136 17.40 8.60 25.68 17.40 8.60

    W 23 Mon, 01/06/2009 Sun, 07/06/2009 17 9 12 216 175 148 16.96 8.59 25.32 16.96 8.59

    W 24 Mon, 08/06/2009 Sun, 14/06/2009 10 11 26 226 186 174 16.48 11.51 28.35 16.48 11.51

    W 25 Mon, 15/06/2009 Sun, 21/06/2009 1 1 0 227 187 174 16.44 11.51 28.35 16.44 11.51

    W 26 Mon, 22/06/2009 Sun, 28/06/2009 9 3 0 236 190 174 16.44 11.51 28.35 16.44 11.51

    W 27 Mon, 29/06/2009 Sun, 05/07/2009 9 13 11 245 203 185 16.54 11.67 28.49 16.54 11.67

    W 28 Mon, 06/07/2009 Sun, 12/07/2009 10 9 11 255 212 196 17.94 12.67 29.56 17.94 12.67

    Cosmetical Minor Major Critical Total

    Assigned to resolved 10.78 20.87 17.54 8.75 17.94

    Resolved to closed 6.67 13.92 13.28 6.31 12.67

    Assigned to closed 17.44 31.72 31.40 15.06 29.56

    Week ISO 8601 Start End

    W 02 Mon, 05/01/2009 Sun, 11/01/2009

    W 03 Mon, 12/01/2009 Sun, 18/01/2009

    W 04 Mon, 19/01/2009 Sun, 25/01/2009

    W 05 Mon, 26/01/2009 Sun, 01/02/2009

    W 06 Mon, 02/02/2009 Sun, 08/02/2009

    W 07 Mon, 09/02/2009 Sun, 15/02/2009

    W 08 Mon, 16/02/2009 Sun, 22/02/2009

    W 09 Mon, 23/02/2009 Sun, 01/03/2009

    W 10 Mon, 02/03/2009 Sun, 08/03/2009

    W 11 Mon, 09/03/2009 Sun, 15/03/2009

    W 12 Mon, 16/03/2009 Sun, 22/03/2009

    W 13 Mon, 23/03/2009 Sun, 29/03/2009

    W 14 Mon, 30/03/2009 Sun, 05/04/2009

    W 15 Mon, 06/04/2009 Sun, 12/04/2009

    W 16 Mon, 13/04/2009 Sun, 19/04/2009

    W 17 Mon, 20/04/2009 Sun, 26/04/2009

    W 18 Mon, 27/04/2009 Sun, 03/05/2009

    W 19 Mon, 04/05/2009 Sun, 10/05/2009

    W 20 Mon, 11/05/2009 Sun, 17/05/2009

    W 21 Mon, 18/05/2009 Sun, 24/05/2009W 22 Mon, 25/05/2009 Sun, 31/05/2009

    W 23 Mon, 01/06/2009 Sun, 07/06/2009

    W 24 Mon, 08/06/2009 Sun, 14/06/2009

    W 25 Mon, 15/06/2009 Sun, 21/06/2009

    W 26 Mon, 22/06/2009 Sun, 28/06/2009

    W 27 Mon, 29/06/2009 Sun, 05/07/2009

    W 28 Mon, 06/07/2009 Sun, 12/07/2009

    W 29 Mon, 13/07/2009 Sun, 19/07/2009

    W 30 Mon, 20/07/2009 Sun, 26/07/2009

    W 31 Mon, 27/07/2009 Sun, 02/08/2009

    W 32 Mon, 03/08/2009 Sun, 09/08/2009

    W 33 Mon, 10/08/2009 Sun, 16/08/2009

    W 34 Mon, 17/08/2009 Sun, 23/08/2009

    W 35 Mon, 24/08/2009 Sun, 30/08/2009

    W 36 Mon, 31/08/2009 Sun, 06/09/2009W 37 Mon, 07/09/2009 Sun, 13/09/2009

    W 38 Mon, 14/09/2009 Sun, 20/09/2009

    W 39 Mon, 21/09/2009 Sun, 27/09/2009

    W 40 Mon, 28/09/2009 Sun, 04/10/2009

    W 41 Mon, 05/10/2009 Sun, 11/10/2009

    W 42 Mon, 12/10/2009 Sun, 18/10/2009

    W 43 Mon, 19/10/2009 Sun, 25/10/2009

  • 8/13/2019 Export Excel Dashboards to Ppt

    17/21

    W 44 Mon, 26/10/2009 Sun, 01/11/2009

    W 45 Mon, 02/11/2009 Sun, 08/11/2009

    W 46 Mon, 09/11/2009 Sun, 15/11/2009

    W 47 Mon, 16/11/2009 Sun, 22/11/2009

    W 48 Mon, 23/11/2009 Sun, 29/11/2009

    W 49 Mon, 30/11/2009 Sun, 06/12/2009

    W 50 Mon, 07/12/2009 Sun, 13/12/2009

    W 51 Mon, 14/12/2009 Sun, 20/12/2009

    W 52 Mon, 21/12/2009 Sun, 27/12/2009

    W 53 Mon, 28/12/2009 Sun, 03/01/2010

  • 8/13/2019 Export Excel Dashboards to Ppt

    18/21

    Test - Control

    Calculations / Consolidation

    Software Module 1

    Day Week # TCs planned

    total

    # TCs planned

    actual #TCs finished

    #TCs not

    completed #TCs passed #TCs failed Success rate

    Completion

    rate

    Actual in % of

    plan

    05/06/09 W 23 400 34 29 1 25 4 86% 7% 85%12/06/09 W 24 400 68 67 5 60 7 90% 17% 99%

    19/06/09 W 25 400 102 102 0 93 9 91% 26% 100%

    26/06/09 W 26 400 136 131 12 117 14 89% 33% 96%

    03/07/09 W 27 400 170 158 3 139 19 88% 40% 93%

    10/07/09 W 28 400 204 192 17 170 22 89% 48% 94%

    17/07/09 W 29 400 238 223 9 199 24 89% 56% 94%

    24/07/09 W 30 400 272 259 26 226 33 87% 65% 95%

    31/07/09 W 31 400 306 287 6 252 35 88% 72% 94%

    07/08/09 W 32 400 340 324 10 286 38 88% 81% 95%

    14/08/09 W 33 400 374 363 25 323 40 89% 91% 97%

    21/08/09 W 34 400 400 400 0 356 44 89% 100% 100%

    Software Module 2

    Day Week # TCs planned

    total

    # TCs planned

    actual #TCs finished

    #TCs not

    completed #TCs passed #TCs failed Success rate

    Completion

    rate

    Actual in % of

    plan

    05/06/09 W 23 300 25 21 1 19 2 90% 7% 84%

    12/06/09 W 24 300 50 51 2 46 5 90% 17% 102%

    19/06/09 W 25 300 75 71 4 62 9 87% 24% 95%

    26/06/09 W 26 300 100 92 6 80 12 87% 31% 92%

    03/07/09 W 27 300 125 116 0 102 14 88% 39% 93%

    10/07/09 W 28 300 150 144 9 126 18 88% 48% 96%

    17/07/09 W 29 300 175 172 2 151 21 88% 57% 98%

    24/07/09 W 30 300 200 195 0 172 23 88% 65% 98%

    31/07/09 W 31 300 225 216 13 190 26 88% 72% 96%

    07/08/09 W 32 300 250 239 24 210 29 88% 80% 96%

    14/08/09 W 33 300 275 268 11 238 30 89% 89% 97%

    21/08/09 W 34 300 300 294 0 263 31 89% 98% 98%

    Software Module 3

    Day Week # TCs planned

    total

    # TCs planned

    actual #TCs finished

    #TCs not

    completed #TCs passed #TCs failed Success rate

    Completion

    rate

    Actual in % of

    plan

    05/06/09 W 23 600 50 49 1 46 3 94% 8% 98%

    12/06/09 W 24 600 100 97 9 92 5 95% 16% 97%

    19/06/09 W 25 600 150 143 13 129 14 90% 24% 95%

    26/06/09 W 26 600 200 189 0 173 16 92% 32% 95%

    03/07/09 W 27 600 250 229 0 212 17 93% 38% 92%

    10/07/09 W 28 600 300 276 22 254 22 92% 46% 92%

    17/07/09 W 29 600 350 321 13 296 25 92% 54% 92%

    24/07/09 W 30 600 400 378 30 347 31 92% 63% 95%

    31/07/09 W 31 600 450 427 38 394 33 92% 71% 95%

    07/08/09 W 32 600 500 469 23 434 35 93% 78% 94%

    14/08/09 W 33 600 550 517 31 478 39 92% 86% 94%

    21/08/09 W 34 600 600 600 0 557 43 93% 100% 100%

    Software Module 4

    Day Week # TCs planned

    total

    # TCs planned

    actual #TCs finished

    #TCs not

    completed #TCs passed #TCs failed Success rate

    Completion

    rate

    Actual in % of

    plan

    05/06/09 W 23 800 67 55 2 49 6 89% 7% 82%

    12/06/09 W 24 800 134 132 7 120 12 91% 17% 99%

    19/06/09 W 25 800 201 210 11 180 30 86% 26% 104%

    26/06/09 W 26 800 268 271 24 236 35 87% 34% 101%

    03/07/09 W 27 800 335 342 24 307 35 90% 43% 102%

    10/07/09 W 28 800 402 413 4 364 49 88% 52% 103%

    17/07/09 W 29 800 469 473 0 421 52 89% 59% 101%

    24/07/09 W 30 800 536 548 22 476 72 87% 69% 102%

    31/07/09 W 31 800 603 601 36 526 75 88% 75% 100%

    07/08/09 W 32 800 670 656 7 577 79 88% 82% 98%

    14/08/09 W 33 800 737 725 36 630 95 87% 91% 98%21/08/09 W 34 800 800 798 0 694 104 87% 100% 100%

    Software Module 5

    Day Week # TCs planned

    total

    # TCs planned

    actual #TCs finished

    #TCs not

    completed #TCs passed #TCs failed Success rate

    Completion

    rate

    Actual in % of

    plan

    05/06/09 W 23 400 34 37 2 30 7 81% 9% 109%

    12/06/09 W 24 400 68 68 1 59 9 87% 17% 100%

    19/06/09 W 25 400 102 98 0 86 12 88% 25% 96%

    26/06/09 W 26 400 136 125 4 104 21 83% 31% 92%

    03/07/09 W 27 400 170 156 8 133 23 85% 39% 92%

    10/07/09 W 28 400 204 189 15 164 25 87% 47% 93%

    17/07/09 W 29 400 238 223 22 192 31 86% 56% 94%

    24/07/09 W 30 400 272 252 0 215 37 85% 63% 93%

    31/07/09 W 31 400 306 280 3 238 42 85% 70% 92%

  • 8/13/2019 Export Excel Dashboards to Ppt

    19/21

    07/08/09 W 32 400 340 314 31 265 49 84% 79% 92%

    14/08/09 W 33 400 374 343 24 289 54 84% 86% 92%

    21/08/09 W 34 400 400 400 0 338 62 85% 100% 100%

    Total

    Day Week # TCs planned

    total

    # TCs planned

    actual #TCs finished

    #TCs not

    completed #TCs passed #TCs failed Success rate

    Completion

    rate

    Actual in % of

    plan

    05/06/09 W 23 2,500 210 191 7 169 22 88% 8% 91%

    12/06/09 W 24 2,500 420 415 24 377 38 91% 17% 99%

    19/06/09 W 25 2,500 630 624 28 550 74 88% 25% 99%

    26/06/09 W 26 2,500 840 808 46 710 98 88% 32% 96%03/07/09 W 27 2,500 1,050 1,001 35 893 108 89% 40% 95%

    10/07/09 W 28 2,500 1,260 1,214 67 1,078 136 89% 49% 96%

    17/07/09 W 29 2,500 1,470 1,412 46 1,259 153 89% 56% 96%

    24/07/09 W 30 2,500 1,680 1,632 78 1,436 196 88% 65% 97%

    31/07/09 W 31 2,500 1,890 1,811 96 1,600 211 88% 72% 96%

    07/08/09 W 32 2,500 2,100 2,002 95 1,772 230 89% 80% 95%

    14/08/09 W 33 2,500 2,310 2,216 127 1,958 258 88% 89% 96%

    21/08/09 W 34 2,500 2,500 2,492 0 2,208 284 89% 100% 100%

    Dashboard Table

    Success rate

    in %

    Completion

    rate

    Actual in % of

    plan

    started

    not yet

    finished finished

    thereof

    passed

    thereof

    failedSoftware Module 1 400 204 209 17 192 170 22 88.5% 48.0% 94.1%

    Software Module 2 300 150 153 9 144 126 18 87.5% 48.0% 96.0%

    Software Module 3 600 300 298 22 276 254 22 92.0% 46.0% 92.0%

    Software Module 4 800 402 417 4 413 364 49 88.1% 51.6% 102.7%

    Software Module 5 400 204 204 15 189 164 25 86.8% 47.3% 92.6%

    Total 2,500 1,260 1,281 67 1,214 1,078 136 88.8% 48.6% 96.3%

    Bar Chart Success Rate

    Bar Value Bar Dummy Target X Scale Dummy Y

    Software Module 1 89% 87% 100% 0%

    Software Module 2 88% 87% 100% 0%

    Software Module 3 92% 87% 100% 0%

    Software Module 4 88% 87% 100% 0%

    Software Module 5 87% 87% 100% 0%

    Total 89% 100% 87% 100% 100%

    Bar Chart Completion Rate

    Bar Value Bar Dummy Target X Scale Dummy Y

    Software Module 1 94% 100% 103% 0%

    Software Module 2 96% 100% 103% 0%

    Software Module 3 92% 100% 103% 0%

    Software Module 4 103% 100% 103% 0%

    Software Module 5 93% 100% 103% 0%

    Total 96% 103% 100% 103% 100%

    Column Chart Actual vs Plan

    Week # TCs planned #TCs finished Scale Dummy

    W 23 210 191

    W 24 420 415

    W 25 630 624

    W 26 840 808

    W 27 1,050 1,001

    W 28 1,260 1,214

    W 29 0 0

    W 30 0 0

    W 31 0 0

    W 32 0 0

    W 33 0 0

    W 34 0 0 1,260

    Column Chart Success Rate

    Week #TCs passed Threshold X Success rate

    threshold Scale Dummy

    W 23 169 1 183

    W 24 377 2 365

    W 25 550 3 548

    W 26 710 4 731

    W 27 893 5 914

    W 28 1,078 6 1,096

    W 29 0 7 1,279

    W 30 0 8 1,462

    W 31 0 9 1,644

    W 32 0 10 1,827

    # TCs planned

    total

    # TCs planned

    actual

    # TCs executed

  • 8/13/2019 Export Excel Dashboards to Ppt

    20/21

    W 33 0 11 2,010

    W 34 0 12 2,175 2,175

  • 8/13/2019 Export Excel Dashboards to Ppt

    21/21

    Change Requests - Control

    Calculations / Consolidation

    CRs by status CRs by departments (cumulated)

    Friday of week WeekTotal cumulated In investigation Approved (in

    implementation)

    cumulated

    Included

    (delivered)

    cumulated

    Future CRs Rejected or

    cancelled Department 1 Department 2 Department 3 Department 4 Department 5 IT

    Fri, 09/01/09 W 02 0 0 0 0 0 0 0 0 0 0 0

    Fri, 16/01/09 W 03 0 0 0 0 0 0 0 0 0 0 0

    Fri, 23/01/09 W 04 0 0 0 0 0 0 0 0 0 0 0

    Fri, 30/01/09 W 05 0 0 0 0 0 0 0 0 0 0 0

    Fri, 06/02/09 W 06 1 1 0 0 0 0 0 0 0 0 1

    Fri, 13/02/09 W 07 2 1 1 0 0 0 1 0 0 0 1

    Fri, 20/02/09 W 08 3 1 2 0 0 0 2 0 0 0 1

    Fri, 27/02/09 W 09 3 1 2 0 0 0 2 0 0 0 1

    Fri, 06/03/09 W 10 5 2 3 2 0 0 3 1 0 0 1

    Fri, 13/03/09 W 11 5 1 3 2 1 0 3 1 0 0 1

    Fri, 20/03/09 W 12 7 1 5 3 1 0 3 1 0 0 1

    Fri, 27/03/09 W 13 8 1 6 3 1 0 3 1 0 0 1

    Fri, 03/04/09 W 14 9 0 7 3 2 0 3 1 1 0 1

    Fri, 10/04/09 W 15 10 1 7 6 2 0 3 2 1 0 1 Fri, 17/04/09 W 16 13 2 9 7 2 0 4 3 1 0 2

    Fri, 24/04/09 W 17 15 1 11 7 2 1 4 5 1 0 2

    Fri, 01/05/09 W 18 17 2 12 9 2 1 4 5 2 1 2

    Fri, 08/05/09 W 19 20 0 16 10 2 2 5 5 3 2 2

    Fri, 15/05/09 W 20 20 0 16 13 2 2 5 5 3 2 2

    Fri, 22/05/09 W 21 23 3 16 15 2 2 5 5 3 4 2

    Fri, 29/05/09 W 22 24 1 18 16 3 2 5 5 3 4 3

    Fri, 05/06/09 W 23 25 1 19 17 3 2 5 6 3 4 3

    Fri, 12/06/09 W 24 26 1 19 18 3 3 5 6 3 5 3

    Fri, 19/06/09 W 25 28 2 20 19 3 3 5 7 4 5 3

    Fri, 26/06/09 W 26 31 2 22 19 4 3 5 7 6 5 3

    Fri, 03/07/09 W 27 32 1 22 19 4 5 5 8 6 5 3

    Fri, 10/07/09 W 28 33 0 24 21 4 5 5 9 6 5 3

    Fri, 17/07/09 W 29 34 1 24 22 4 5 5 10 6 5 3

    Fri, 24/07/09 W 30 36 2 25 23 4 5 6 10 6 5 3

    Fri, 31/07/09 W 31 38 1 27 25 5 5 7 11 6 5 3 Fri, 07/08/09 W 32 38 0 28 25 5 5 7 11 6 5 3

    Fri, 14/08/09 W 33 39 1 28 26 5 5 8 11 6 5 3

    Fri, 21/08/09 W 34 39 0 28 28 5 6 8 11 6 5 3

    Fri, 28/08/09 W 35 40 0 29 28 5 6 9 11 6 5 3

    Fri, 04/09/09 W 36 42 0 30 28 5 7 10 11 7 5 3

    Fri, 11/09/09 W 37 44 2 30 28 5 7 11 11 7 6 3

    Fri, 18/09/09 W 38 44 0 30 28 5 9 11 11 7 6 3

    Fri, 25/09/09 W 39 49 4 31 28 5 9 13 12 8 7 3

    Fri, 02/10/09 W 40 50 0 34 28 5 11 14 12 8 7 3

    Fri, 09/10/09 W 41 50 0 34 28 5 11 14 12 8 7 3

    Fri, 16/10/09 W 42 50 0 34 28 5 11 14 12 8 7 3

    Fri, 23/10/09 W 43 50 0 34 28 5 11 14 12 8 7 3

    Fri, 30/10/09 W 44 50 0 34 28 5 11 14 12 8 7 3

    Fri, 06/11/09 W 45 50 0 34 28 5 11 14 12 8 7 3

    Fri, 13/11/09 W 46 50 0 34 28 5 11 14 12 8 7 3 Fri, 20/11/09 W 47 50 0 34 28 5 11 14 12 8 7 3

    Fri, 27/11/09 W 48 50 0 34 28 5 11 14 12 8 7 3

    Fri, 04/12/09 W 49 50 0 34 28 5 11 14 12 8 7 3

    Fri, 11/12/09 W 50 50 0 34 28 5 11 14 12 8 7 3

    Fri, 18/12/09 W 51 50 0 34 28 5 11 14 12 8 7 3

    Fri, 25/12/09 W 52 50 0 34 28 5 11 14 12 8 7 3

    Fri, 01/01/10 W 53 50 0 34 28 5 11 14 12 8 7 3

    Overview KPI

    Total CRs last week 32

    New this week 1

    Total CRs this week 33

    thereof business 28 84.8%

    thereof IT 5 15.2%

    Waterfall Chart

    Total In investigation Approved (in

    implementation)

    Included

    (delivered)

    Future CRs Rejected or

    cancelledActuals 33 0 3 21 4 5

    Invisible 0 0 0 3 24 28

    Sorted Bar Chart

    Department CRs No. Dummy Value Position Departments

    sorted Value

    Department 1 5 1 5 5 Department 5 3

    Department 2 9 2 9 1 Department 1 5

    Department 3 6 3 6 4 Department 4 5

    Department 4 5 4 5 6 IT 5

    Department 5 3 5 3 3 Department 3 6

    IT 5 6 5 2 Department 2 9


Recommended