    Extradosed Prestressed BridgesSteven L. Stroh, PhD, PE, SE

    Vice President

    Deputy Director of Surface Transportation  – Major Bridges

    URS Corporation, Tampa, FL

  • 8/20/2019 Extra Dosed Bridges

    2/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

     AGENDA

    • The Extradosed Bridge Concept

    • Representative Extradosed Bridges

    • Key Proportioning Parameters and Design

    Considerations

    • Case Study

    • Concluding Remarks• Questions

  • 8/20/2019 Extra Dosed Bridges

    3/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    What is an Extradosed Prestressed Bridge?

    Odawara Port Bridge, Japan (1994)

  • 8/20/2019 Extra Dosed Bridges

    4/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Defining an Extradosed BridgeJacques Mathivat , Journal of FIP, 1988

    “Recent Developments in Prestressed

    Concrete Bridges”

    Tower height is the defining element

    • Cable Stayed 1/5

    • Extradosed 1/15

    Extradosed Prestressing

  • 8/20/2019 Extra Dosed Bridges

    5/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Characteristics of an Extradosed Bridge

    • Shorter tower than cable stayed

    • Shallower girder than a girder bridge, but deeper than a

    cable stayed bridge

    • Flatter cables than a cable stayed bridge, and only over

    a portion of the span.

    • Cables sized to prestress the deck

    • Low fatigue ranges for cables

    • Uniform size range for cables

  • 8/20/2019 Extra Dosed Bridges

    6/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Girder Depth to Span

    1:16 to 1:18 (at support)

    Girder Bridge

  • 8/20/2019 Extra Dosed Bridges

    7/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Girder

    depth:

    5 to 6 ft.

    Tower

    height to

    Span:

    1:4

     V

    H

    Cable-Stayed Bridge

  • 8/20/2019 Extra Dosed Bridges

    8/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Girder Depth

    to Span:

    1:30 to 1:35

    Tower Heightto Span:

    1:10 to 1:15

    ExtradosedPrestressed

    Bridge

  • 8/20/2019 Extra Dosed Bridges

    9/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    More than 60 ExtradosedBridges World-wide

    • More than 30 in Japan• More than 25 countries have at least one

    • Currently 3 in the U.S.

  • 8/20/2019 Extra Dosed Bridges

    10/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Progression of Extradosed Bridge Construction

  • 8/20/2019 Extra Dosed Bridges

    11/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Representative

    Extradosed Prestressed

    Bridges

    11

  • 8/20/2019 Extra Dosed Bridges

    12/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Odawara Port Bridge, Japan (1994))

  • 8/20/2019 Extra Dosed Bridges

    13/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Tsukuhara Bridge, Japan

  • 8/20/2019 Extra Dosed Bridges

    14/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Okuyama Bridge, Japan

  • 8/20/2019 Extra Dosed Bridges

    15/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Miykodogawa Bridge, Japan

  • 8/20/2019 Extra Dosed Bridges

    16/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Kiso and Ibi River Bridges, Japan

  • 8/20/2019 Extra Dosed Bridges

    17/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Rittoh Bridge, Japan

  • 8/20/2019 Extra Dosed Bridges

    18/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Sunnibergbrucke, Switzerland

  • 8/20/2019 Extra Dosed Bridges

    19/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Golden Ears Bridge, Vancouver, BC

  • 8/20/2019 Extra Dosed Bridges

    20/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Introduction

    First U.S. Extradosed Bridge

    Pearl Harbor Memorial Bridge, New Haven CT

  • 8/20/2019 Extra Dosed Bridges

    21/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    I-35 bridges over the Brazos River in Waco, Texas

  • 8/20/2019 Extra Dosed Bridges

    22/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Image Courtesy MnDOT

    St Croix River Bridge, Minnesota - Wisconsin

  • 8/20/2019 Extra Dosed Bridges

    23/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Special Case Bridges (Non-Extradosed)

    Barton Creek Fin-Back Bridge Ganter Bridge, Switzerland

  • 8/20/2019 Extra Dosed Bridges

    24/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Key Proportioning Parameters andDesign Considerations

    • Span Lengths

    • Side Span Ratios• Multi Span Bridges

    • Tower Height

    • Girder Depth/Haunch• Bridge Width

    •  Aesthetic Opportunities

  • 8/20/2019 Extra Dosed Bridges

    25/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Economical Bridge Types

  • 8/20/2019 Extra Dosed Bridges

    26/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Economical Bridge Types

    200 900Extradosed

  • 8/20/2019 Extra Dosed Bridges

    27/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Side Span/Main Span Ratio

    Girder Bridges

     – Cast on falsework:

    L1/L = 0.8

     – Balanced Cantilever:L1/L = 0.65

    Cable Stayed Bridges

     – Steel

    L1/L = 0.35

     – Concrete

    L1/L = 0.42

    Extradosed Bridges

     – Mean L1/L Ratio = 0.57

     – One Std. Deviation = 0.45 to 0.69

     – Use L1/L = 0.6

  • 8/20/2019 Extra Dosed Bridges

    28/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Backstay Cable

    Consideration of Multi-Span Cable-Stayed Bridges

  • 8/20/2019 Extra Dosed Bridges

    29/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Multi-Span Cable-Stayed Bridges

    • Population of 1200 bridges

    • Number of multi-span CS Bridges = 7

    Rion-Antirion Bridge,

    Greece

    Ting Kau Bridge,Hong Kong

  • 8/20/2019 Extra Dosed Bridges

    30/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Multi-Span Extradosed Bridges

    • Population of 63 bridges

    • Number of multi-span Extradosed Bridges = 19

    Kiso and Ibi River Bridges, Japan

    Fl id

  • 8/20/2019 Extra Dosed Bridges

    31/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Tower Height Expressed as H/L• H = tower height

    • L = Main Span Length

    • For Cable Stayed:

    • H/L ≈1/4 to 1/5

    • For Extradosed:

    • H/L ≈ 1/10

    Fl id

  • 8/20/2019 Extra Dosed Bridges

    32/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Span/Depth Ratios for Extradosed Bridges

    For Girder Bridges:

    • Constant Depth: S/D ≈ 22

    • For Variable Depth:

    • S/D ≈ 17 at pier • S/D ≈ 50 at mid-span

    For Cable Stayed Bridges:

    • Range of depth/span

    ≈ 50-250

    For Extradosed Bridges:

    • S/D ≈ 30 at pier 

    • S/D ≈ 50 at mid-span

    Fl id

  • 8/20/2019 Extra Dosed Bridges

    33/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Typical Proportioning ParametersExtradosed Bridges

    •  Applicable Span Range: 200-900 ft.

    • Side/Main Span Ratio: 0.6

    • Tower Height/Span Ratio: 1:10

    • Span/Girder Depth Ratio:

     – Midspan 1:50

     –  At Tower 1:30•  Applicable to multi-span bridges

    Florida

  • 8/20/2019 Extra Dosed Bridges

    34/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

     Aesthetics – General Structural Arrangement

    Single Cable Plane Twin Cable Plane Three Cable Planes

    Florida

  • 8/20/2019 Extra Dosed Bridges

    35/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

     Aesthetics Stay Cable Arrangement

    Fan Cable Arrangement Harp Cable Arrangement

    Florida

  • 8/20/2019 Extra Dosed Bridges

    36/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

     Aesthetics – Towers Arrangement/Shape

    Florida

  • 8/20/2019 Extra Dosed Bridges

    37/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Case Study

    Pearl Harbor Memorial Bridge, New Haven CT

    Florida

  • 8/20/2019 Extra Dosed Bridges

    38/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Project Overview

    Pearl Harbor Memorial Bridge (PHMB)

    38

    Florida

  • 8/20/2019 Extra Dosed Bridges

    39/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    •Opened - 1958

    •Main Span 387 ft.

    •Longest Plate Girder Spanin Western Hemisphere

    Existing PHMB

    39

    Florida

  • 8/20/2019 Extra Dosed Bridges

    40/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    40

    •Designed for 40,000 VPD

    •Currently over 140,000 VPD

    •Functionally and Structurally Deficient

    Existing PHMB

    Florida

  • 8/20/2019 Extra Dosed Bridges

    41/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    Replacement Bridge

    41

    •Increase from 6 lanes to 10 lanes

    •Improved Safety

    •Improved Navigation

    Florida

  • 8/20/2019 Extra Dosed Bridges

    42/82

    F D O T D E S I G N T R A I N I N G E X P O

    Florida

    Department of

    Transportation

    42

    Why an Extradosed Bridge for the PHMB?• Longer Span Desired for Navigation

    • Tower Height Restricted by Tweed Airport

    • Girder Depth and Profile Controlled by Adjacent Interchange

    • Economical Bridge Desired

    • Bridge Worthy of Pearl Harbor Memorial Bridge Designation wasDesired

    Florida

  • 8/20/2019 Extra Dosed Bridges

    43/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    43

    Side Span / Main Span Ratio

    248.5’/515.0’/248.5’ = 0.48 Ratio

    Recommended Ratio = 0.6Typical Range = 0.45 – 0.69

    Resulting Uplift = 570 kips (5% of the max. reaction)

    Counterweight Provided

    Florida

  • 8/20/2019 Extra Dosed Bridges

    44/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    Bridge Deck WidthGirder Cross Section

    Overall Roadway Width Varies 190-215 feet

    Florida

  • 8/20/2019 Extra Dosed Bridges

    45/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    Deck Depth / Haunch Arrangement

    Recommended Span/Depth

    •  At Tower = 25-35

    •  At midspan 50

    Provided Span/Depth• At Tower =31.4 (16.4’ depth)

    •  At midspan = 45

    • (11.5’ depth)

    Florida

  • 8/20/2019 Extra Dosed Bridges

    46/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    46

    Superstructure Cross-Section

    Florida

  • 8/20/2019 Extra Dosed Bridges

    47/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    47

    Transverse Post-Tensioning

    Florida

  • 8/20/2019 Extra Dosed Bridges

    48/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    Tower Height

    • Suggested L/H = 10

    • Selected 60 ft. tower

    height

    • L/H = 8.6

    Wide Heavy Deck

    Limit Fatigue

    Demand on Stays

    Pearl HarborMemorialBridge

    Florida

  • 8/20/2019 Extra Dosed Bridges

    49/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    49

    Tower Elevation

    Florida

    f

  • 8/20/2019 Extra Dosed Bridges

    50/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    50

     Anchor Pier Elevation

    Florida

    D t t f

  • 8/20/2019 Extra Dosed Bridges

    51/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    • 0.6” (15mm) Grade 270 Strand

    • Greased and Individually Sheathed

    • Co-extruded PE pipe

    • Jacked Strand-by-Strand at tower 

    • Stay Design Stresses

    - 0.55 f’s for AASHTO Group I

    - 0.60 f’s other Load Groups

    - 0.60 f’s construction or stay replacement

    Stay Cable Design Criteria

    51

    Florida

    D t t f

  • 8/20/2019 Extra Dosed Bridges

    52/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    52

    Erection

    Florida

    D t t f

  • 8/20/2019 Extra Dosed Bridges

    53/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    Form Traveler Construction

    53

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    54/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    54

    Main Span Construction Sequence

    54

    • Stage 1 - Construction of Substructures and Pier Tables

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    55/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    55

    Main Span Construction Sequence

    55

    • Stage 2 - Assembly of Traveling Forms

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    56/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    56

    Main Span Construction Sequence

    56

    • Stage 3 - Balanced Cantilever Construction and Cable Installation

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    57/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    57

    Main Span Construction Sequence

    57

    • Stage 4 - Continuation - Cantilever Construction

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    58/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    58

    Main Span Construction Sequence

    58

    • Stage 5 - Closure at Side Span

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    59/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    59

    Main Span Construction Sequence

    59

    • Stage 6 - Closure at Main Span

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    60/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    60

    Main Span Construction Sequence

    60

    • Stage 7 - Finishing Works

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    61/82

    F D O T D E S I G N T R A I N I N G E X P O

    Department of

    Transportation

    Aesthetics

    61

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    62/82

    F D O T D E S I G N T R A I N I N G E X P O

    p

    Transportation

    62

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    63/82

    F D O T D E S I G N T R A I N I N G E X P O

    p

    Transportation

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    64/82

    F D O T D E S I G N T R A I N I N G E X P O

    p

    Transportation

    64

    Superstructure weight (ea. deck)= 54.2 klf 

    Equivalent concrete depth for girder = 3.4’

    Longitudinal Post-Tensioning= 11 psf  

    Transverse Post-Tensioning= 0.9 psf  

    Weight of stay cables= 3.5 psf  

    KEY BRIDGE PARAMETERS AND QUANTITIES

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    65/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Contract B1

    Contract Award:• April 2008

    Owner:

    • ConnDOT

    Contractor:

    • Cianbro/Middlesex JV III

    Designer:

    • URS

    Program Manager:

    • Parsons Brinckerhoff 

    CE&I:

    • Prime: Lochner

    • Sub: FIGG

    Original Contract Value:• $137,494,973

    Final Contract Value:

    • $136,385,903

    Final Completion Date

    • August 18, 2011

    • 34 days early

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    66/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Contract B

    Contract Award:

    • July 2009

    Owner:

    • ConnDOT

    Contractor:

    • Walsh/PCL JV II

    Designer:• URS

    Program Manager:

    • Parsons Brinckerhoff 

    CE&I:

    • Prime: Lochner

    • Sub: FIGG

    Original Contract Value:

    • $416,691,984

    Current Contract Value:

    • $416,805,470

    Current Completion Date

    • June 30, 2015

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    67/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    67

    Tower Foundations: Drilled Shafts

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    68/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Tower Foundations

    Florida

    Department of

  • 8/20/2019 Extra Dosed Bridges

    69/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Tower Construction

    Florida

    Department of

    T t ti

  • 8/20/2019 Extra Dosed Bridges

    70/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Bridge Bearings

    Florida

    Department of

    T t ti

  • 8/20/2019 Extra Dosed Bridges

    71/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Tower: Stay Anchor Box

    Florida

    Department of

    T t ti

  • 8/20/2019 Extra Dosed Bridges

    72/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Pier Table Construction

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    73/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Pier Table Construction

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    74/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Out-of-Balance Supports

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    75/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Balanced Cantilever Construction with Form Traveler 

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    76/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Balanced Cantilever Construction

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    77/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Side Span - Main Span Closure

    77

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    78/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Main Span Closure

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    79/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Northbound Bridge Opened 22June 2012

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    80/82

    F D O T D E S I G N T R A I N I N G E X P O

    Transportation

    Existing Bridge removed – Southbound Bridge

    Scheduled for June 2015 Completion

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    81/82

    F D O T D E S I G N T R A I N I N G E X P O

    a spo tat o

    Concluding Remarks –

    Extradosed Bridges

    • Extradosed Bridges are an Emerging Technology

    • Their practicality has been proven by numerous

    prototype bridges constructed in more than 25countries

    • Economical in the 200-900 foot span range

    •  Advantageous for Multi-span Bridges

    • Basic Proportioning Well Understood• Stay Criteria Included in Latest PTI Specifications

    • Have Opportunities for Unique Visual Presentations81

    Florida

    Department of

    Transportation

  • 8/20/2019 Extra Dosed Bridges

    82/82

    F D O T D E S I G N T R A I N I N G E X P O

    p

    QuestionsQuestions